MONTHYEARNL-13-043, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2013-02-27027 February 2013 Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation ML13169A1272013-06-25025 June 2013 Request for Additional Information Regarding Reliable Spent Fuel Pool Instrumentation, Order No. EA-12-051 NL-13-103, Response to Request for Additional Information (RAI) Regarding Reliable Spent Fuel Pool (SFP) Instrumentation (Order No, EA-12-051) (TAC Nos. MF0737 and MF0738)2013-08-20020 August 2013 Response to Request for Additional Information (RAI) Regarding Reliable Spent Fuel Pool (SFP) Instrumentation (Order No, EA-12-051) (TAC Nos. MF0737 and MF0738) NL-13-109, First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation2013-08-27027 August 2013 First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation NL-13-110, First Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-27027 August 2013 First Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML13298A8052013-11-0808 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0737 and ML14010A3312014-01-14014 January 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Indian Point Energy Center, Units 2 and 3, TAC Nos.: MF0744 and MF0745 ML13337A5942014-01-24024 January 2014 Interim Staff Evaluation and Audit Report Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) NL-14-031, Center'S Second Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-02-27027 February 2014 Center'S Second Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events NL-14-029, Second Six-Month Status Report for the Implementation of Order EA-12-051, Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2014-02-27027 February 2014 Second Six-Month Status Report for the Implementation of Order EA-12-051, Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation NL-14-109, Third Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation2014-08-27027 August 2014 Third Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation NL-14-110, Third Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-08-27027 August 2014 Third Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events NL-14-132, Response to 03/12/2012, Request for Information Pursuant to Title 10 of the Code of Federal Regulation 50.54(f) Regarding Recommendations of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dia-ichi.2014-11-0303 November 2014 Response to 03/12/2012, Request for Information Pursuant to Title 10 of the Code of Federal Regulation 50.54(f) Regarding Recommendations of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dia-ichi. ML14335A6422014-12-0909 December 2014 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 NL-15-012, Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-01-28028 January 2015 Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events NL-15-025, Fourth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-02-27027 February 2015 Fourth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events NL-15-026, Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2015-02-27027 February 2015 Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation NL-15-036, Retraction of Entergy'S Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-03-16016 March 2015 Retraction of Entergy'S Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML15079A3542015-03-24024 March 2015 Withdrawal of Request for Relaxation of the Schedule Requirements for Order EA-12-049,Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Events NL-15-059, Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard..2015-05-20020 May 2015 Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard.. NL-15-112, Fifth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-08-28028 August 2015 Fifth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events NL-15-111, Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation2015-08-28028 August 2015 Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation ML15301A0932015-10-30030 October 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 NL-16-024, Center'S Sixth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-02-29029 February 2016 Center'S Sixth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML16155A0842016-04-29029 April 2016 APS Response to Request for Additional Information Regarding Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Lnstrumentation NL-16-089, Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard ...2016-08-12012 August 2016 Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard ... NL-16-115, Response to Request for Additional Information Regarding Review of Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,.2016-12-0202 December 2016 Response to Request for Additional Information Regarding Review of Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,. 2014-08-27
[table view] |