Slides - Constellation - Pre-Application EP 2/23/2023 Meeting SlidesML23052A175 |
Person / Time |
---|
Site: |
Calvert Cliffs, Dresden, Peach Bottom, Nine Mile Point, Byron, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle |
---|
Issue date: |
02/21/2023 |
---|
From: |
Rhoades D Constellation Energy Generation |
---|
To: |
Scott Wall Plant Licensing Branch III |
---|
Wall, SP |
References |
---|
EPID L-2023-LRM-0009, NEI 99-01, Rev 7 |
Download: ML23052A175 (1) |
|
Similar Documents at Calvert Cliffs, Dresden, Peach Bottom, Nine Mile Point, Byron, Braidwood, Limerick, Ginna, Clinton, Quad Cities, FitzPatrick, LaSalle |
---|
Category:Slides and Viewgraphs
MONTHYEARML24325A5702024-11-22022 November 2024 ECCS Compensated Level System Replacement Project, Constellation Pre-submittal Meeting Slides November 22, 2024 (EPID L-2024-LRM-0009) Public ML24310A2602024-11-0808 November 2024 Constellations Presentation on Proposed License Condition for Limerick DMP (EPID L-2022-LLA-0140) (Non-Proprietary) ML24310A0672024-11-0505 November 2024 Constellation NRC Pre-Submittal Meeting Slides - Proposed Alternative for Reactor Vessel Closure Stud Exam Optimization ML24302A2422024-10-29029 October 2024 ECCS Compensated Level System Replacement Project Pre-Submittal Meeting Slides RS-24-116, Attachment: GE-Hitachi Affidavit / Pre-Application Meeting Presentation2024-10-25025 October 2024 Attachment: GE-Hitachi Affidavit / Pre-Application Meeting Presentation ML24270A0042024-10-0202 October 2024 Fitpatrick Pre-submittal Meeting Slides, October 2, 2024 ML24267A0522024-09-24024 September 2024 Standby Gas Treatment Planned Amendment Preapplication Meeting Presentation ML24249A3092024-09-0606 September 2024 September 6, 2024, Public Meeting Related to Digital Instrumentation and Control Amendment Slides ML24232A2052024-08-12012 August 2024 Presentation Slides for Dresden End-of-Cycle Meeting ML24172A1092024-08-0707 August 2024 Scoping Power Point Presentation ML24200A2312024-07-22022 July 2024 Constellations Pre-Submittal Meeting Presentation About Peach Bottom ECCS Compensated Level System Replacement Project - July 22, 2024 ML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML24134A2032024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment - Rev 0 ML24131A1282024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment ML24121A1862024-05-14014 May 2024 Attachment 3: Peach Bottom ECCS Compensated Level System Replacement Project Presentation Material (Non-Proprietary Information) ML24127A0952024-05-0606 May 2024 License Renewal Public Scoping Meeting May 2024 ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24060A1692024-03-0707 March 2024 NRC Slides for March 7, 2024 Regulatory Conference with Constellation Nuclear Regarding Braidwood ML24057A3032024-02-26026 February 2024 Attachment 1: Braidwood Station Regulatory Conference Information ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML24003A1812024-01-0808 January 2024 Handout - Byron-Braidwood Core Monitoring and Support System LAR Pre-Submittal Meeting January 8,2024 ML23345A0362023-12-11011 December 2023 ATWS Uet December 11, 2023 Pre-submittal Meeting Slides ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML24051A0462023-10-31031 October 2023 UFSAR Revision 17, Chapter 6, Figure 6.3-35-6.4-1, Redacted (2) ML24051A0472023-10-31031 October 2023 UFSAR Revision 17, Chapter 6, Figure 6.3-4-6.3-34, Redacted (1) ML23272A0622023-09-29029 September 2023 Ultimate Heat Sink Temperature Tech Spec Limit Change ML23262B2602023-09-19019 September 2023 Slides - Constellation - Pre-Application EP 9/25/2023 Meeting Handout ML23251A0782023-09-0606 September 2023 DRE1 Decom Pre-Submittal Slides ML23229A4832023-08-17017 August 2023 RR 20-Year ISI Pre-Submittal NRC Meeting Handout ML23229A1722023-08-17017 August 2023 RR Pen-75 Pre-Submittal NRC Meeting Handout ML23229A0132023-08-17017 August 2023 Relief Request for Alternative Requirements for Byron Unit 1 Reactor Pressure Vessel Inservice Inspection Intervals NRC Meeting Handout ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23170A0082023-06-29029 June 2023 Decommissioning Presentation for NRC Pre-submittal Meeting, June 29, 2023 ML23172A2102023-06-28028 June 2023 CPS Lr Pre-Submittal Meeting Presentation ML23173A0472023-06-28028 June 2023 SLRA - NRC Presubmittal Meeting Slides - 6-28-23 ML23172A2092023-06-28028 June 2023 LRA - NRC Pre-Submittal Meeting Slides ML23173A0462023-06-28028 June 2023 DNPS SLR Pre-submittal Meeting Presentation Rev. 1 ML23145A1322023-06-27027 June 2023 June 27, 2023, Dresden Nuclear Power Station Subsequent License Renewal Environmental Pre-application Public Meeting - Constellation Slides ML23165A0242023-06-27027 June 2023 June 27, 2023, Dresden Nuclear Power Station Subsequent License Renewal Environmental Pre-application Public Meeting - NRC Slides ML23174A0012023-06-23023 June 2023 Pre-submittal Meeting Slides Regarding Update to the FitzPatrick Fuel Handling Accident Analysis with Impacts to Technical Specifications, June 26, 2023 ML23165A0162023-06-14014 June 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting - NRC Slides ML23145A1342023-06-14014 June 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting - Constellation Slides ML23163A1642023-06-12012 June 2023 2022 Braidwood/Byron End-of-Cycle Meeting Presentation ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23103A4072023-04-13013 April 2023 Presentation Slides for Information Call on 4/13/23 N2E Recirc Discharge Nozzle Weld Repair 2nd Request for Alternative ML23094A1492023-04-11011 April 2023 Licensee Presentation on Whr Exemption Request for Public Meeting on April 11, 2023 ML23080A2972023-03-21021 March 2023 Presentation Slides for Information Call on 3/21/23 N2E Recirc Discharge Nozzle Weld Repair Request for Alternative ML23076A0442023-03-16016 March 2023 Pb U2 Scram Barrier Presentation KT Session ML23055A2712023-03-0202 March 2023 March 2, 2023, Preapplication Meeting to Discuss Planned Amendments to Adopt TSTF-505 and 10 CFR 50.69 (EPID L-2023-LRM-0007) - Slides 2024-09-06
[Table view] |
Text
NEI 99-01 Rev. 7 Implementation:
NRC Pre-submittal Meeting February 23, 2023
Constellation plants EALs are currently based on NEI 99-01, Revision 6 guidance NEI and NRC are working through final development of Revision 7 to the NEI 99-01 guidance NRC endorsement of the NEI 99-01, Revision 7 guidance is currently anticipated about June 2023
Background
1
EPFAQs written against NEI-99-01, Revision 6, guidance were reviewed Current EALs for correct level of event classification and necessity were reviewed References to permanently shutdown conditions were removed NEI 99-01 Rev. 7 - Development Considerations 2
- Expect no deviations from the guidance in NEI 99-01 Rev. 7
- Expect fleet drafts and fleet internal reviews to be completed by June of 2023
- Anticipate NRC endorsement about June of 2023
- Will reconcile any differences between NEI 99-01 Rev. 7 draft and what is endorsed by the NRC
- Will coordinate submittal of License Amendment Request with final NRC-endorsement of NEI 99-01, Revision 7, guidance (late July 2023)
- Request 12-month NRC review period (July 2024) with final site implementation occurring by late 1Q25 o Extended implementation period is needed to facilitate and coordinate necessary training with established training cycles for the Operations' personnel and other Emergency Response Organization (ERO) personnel and allows time to complete the training around outage schedules.
- All calculated thresholds have been previously docketed Approximate Timeline and Schedule 3