Clinton Power Station Unit 1 License Renewal Application (LRA)

Safety Pre-Application Meeting June 28, 2023 Chris Tyree Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation 1

Audio Issues

  • Call into bridgeline:

(301) 576-2978 Passcode:89874471#

Conference ID:898 744 71#

  • In Teams, check your devise settings:

1)

Click More 2)

Choose settings 3)

Choose Device Settings 2

Meeting Agenda

  • Safety Review:

o Process Overview o Tentative Review Schedule for Dresden

  • NRC Contact Information
  • Conclusion / Questions 3

License Renewal Review Process DSEIS Public Meeting Draft Supplement To GEIS Issued**

Final Supplement To GEIS Issued**

NRC Decision On Application**

Advisory Committee on Reactor Safeguards (ACRS)

Subcommittee Review**

Hearings*

Safety Evaluation Audit & Review Inspection Report(s)

Issued**

ACRS Full Committee Review**

Onsite Inspection(s)

Safety Review Environmental Review Safety Evaluation Report Issued**

Safety Evaluation Report with Open Item(s) Issued**

License Renewal Application**

Submitted To NRC ACRS Letter Issued**

Site Environmental Audit License Renewal Process &

Environmental Scoping Meetings Opportunities for Public Interaction

  • If a Request for Hearing is Granted
    • Available at www.nrc.gov Safety Evaluation Audit & Review AMR Review AMP Review AMP Audit 4

Safety Review:

Process Overview Issue Safety Evaluation Report (SER)

Acceptance Review In-Office Technical Review Audit On-SiteAudit BreakoutAudit 5

Tentative Safety Review Schedule 6

Activity Estimated Time Application Submission Date February 2024 Acceptance Date (Project Start Date)

March 2024 In-Office Technical Review Audit June 2024 On-Site Audit June 2024 Breakout Audit August 2024 Safety Evaluation Report May 2025 Advisory Committee on Reactor Safeguards (ACRS) Sub-Committee Meeting July 2025 ACRS Full Committee Meeting November 2025 Licensing Decision January 2026 Note: The review schedule below is tentative and subject tochange.

The schedule is only finalized once the application has been accepted forreview and is docketed.

NRC Contact Information 7

Safety Project Manager Chris Tyree (Christopher.Tyree@nrc.gov)

Safety Branch Chief Lauren Gibson (Lauren.Gibson@nrc.gov)

Environmental Project Manger Lance Rakovan (Lance.Rakovan@nrc.gov)

Environmental Branch Chief Ted Smith (Theodore.Smith@nrc.gov)

Questions?