EPID:L-2024-LRM-0009, Constellations Pre-Submittal Meeting Presentation About Peach Bottom ECCS Compensated Level System Replacement Project - July 22, 2024 (Open) |
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML24134A2032024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment - Rev 0 Project stage: Other ML24131A1282024-05-14014 May 2024 Lessons Learned for ECCS Digital I&C License Amendment Project stage: Other ML24121A1862024-05-14014 May 2024 Attachment 3: Peach Bottom ECCS Compensated Level System Replacement Project Presentation Material (Non-Proprietary Information) Project stage: Request PMNS20240898, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-07-0808 July 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24200A2312024-07-22022 July 2024 Constellations Pre-Submittal Meeting Presentation About Peach Bottom ECCS Compensated Level System Replacement Project - July 22, 2024 Project stage: Request ML24206A1782024-07-29029 July 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System Project stage: Meeting ML24270A2612024-10-17017 October 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Concerning Peach Bottom, Units Nos. 2 and 3 Digital Upgrade of the ECCS Compensated Level System Project stage: Meeting PMNS20241330, Meeting with Constellation Energy Generation, LLC to Discuss a Planned Licenseamendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-10-18018 October 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned Licenseamendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24302A2422024-10-29029 October 2024 ECCS Compensated Level System Replacement Project Pre-Submittal Meeting Slides Project stage: Meeting ML24305A0952024-10-29029 October 2024 Constellation Slides - ECCS Compensated Level System Replacement Project NRC Pre-submittal Meeting on October 29, 2024 Project stage: Request ML24325A5532024-11-21021 November 2024 Summary of October 29, 2024, Public Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System EPID L- Project stage: Meeting ML24325A5702024-11-22022 November 2024 ECCS Compensated Level System Replacement Project, Constellation Pre-submittal Meeting Slides November 22, 2024 (EPID L-2024-LRM-0009) Public Project stage: Meeting PMNS20241466, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32024-12-11011 December 2024 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML24366A0502024-12-12012 December 2024 Non-Proprietary Slides for 12/12/24 Meeting with Constellation - ECCS Compensated Level System Replacement Project Project stage: Meeting ML24344A2272024-12-12012 December 2024 Summary of Partially Closed Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 and 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System Project stage: Meeting ML25014A0552025-01-13013 January 2025 December 12, 2024, Summary of Closed Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System (EPID L-2024-LRM-0009) Non-Proprietary Project stage: Meeting PMNS20250143, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32025-01-31031 January 2025 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML25051A2332025-02-16016 February 2025 Constellations Affidavit for Proprietary 2-21-25 Presubmittal Meeting Materials Project stage: Meeting ML25051A2292025-02-21021 February 2025 Constellations Non-Proprietary Slides for 2-21-25 Presubmittal Meeting Project stage: Meeting ML25083A0722025-04-0808 April 2025 Summary of February 21, 2025, Partially Closed Observation Meeting with Constellation Energy Generation, LLC Peach Bottom, Units 2 & 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System EPID L-2024-LRM-0009 Non-Pr Project stage: Meeting PMNS20250476, Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 32025-04-28028 April 2025 Meeting with Constellation Energy Generation, LLC to Discuss a Planned License Amendment Request for a Digital Instrumentation and Controls Upgrade at Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Meeting ML25118A0372025-05-0101 May 2025 NRC Public Meeting - Peach Bottom Atomic Power Station ECCS Compensated Level System Replacement Project Project stage: Meeting ML25118A0362025-05-0101 May 2025 NRC Slides Peach Bottom Pre-Application 5.1.25 Meeting - Radics Topical Report Safety Evaluation Conclusions on Internal Diversity Project stage: Approval ML25122A1722025-05-0505 May 2025 Summary of Public Observation Meeting with Constellation Energy Generation, LLC Regarding Peach Bottom Atomic Power Station, Units 2 and 3 Digital Upgrade of the Emergency Core Cooling System Compensated Level System Project stage: Meeting 2024-07-29
[Table View] |
Text
NRC Pre-submittal Meeting October 29, 2024
Meeting Purpose
- Gain alignment on the basis of the additional NRC requested documents from DI&C-ISG-06 Rev 2 Enclosure B.
Agenda
- Introductions - Project Team
- Requested DI&C-ISG-06 Rev 2 Enclosure B documents
- NRC to provide regulatory basis for the requested documents 1
Constellation Energy
- Pablo Guardado, Principal PM, PEA Project Management
- Steve Flickinger, Prin. Reg. Specialist, Corporate Licensing Sargent & Lundy
- Pareez Golub - Project Director, Digital Licensing SME 2
Items submitted as part of the ARP
- 1.3 Approved Topical Report Safety Evaluation
- 1.7 (Unified Compliance/Conformance Matrix for) IEEE
[Institute of Electrical and Electronics Engineers] Stds 603-1991 and 7-4.3.2-2003
- 1.8 (Changes to) Technical Specifications
- 1.9 Setpoint Methodology and Calculations
- 1.10 Secure Development and Operational Environment 3
Additional documents requested by the NRC
- 1.6 (Summary of) Hardware Equipment Qualification
- 1.11 Software Requirements Specification
- 1.12 Software Design Specification
- 1.13 Design Analysis Reports for Platform Changes
- 1.14 System Response Time Analysis Report
- 1.17 Quality Assurance Plan for Hardware
- 1.18 (Summary of) Hardware Development Process
- 2.2 As-Manufactured, System Configuration Documentation
- 2.6 System-Level Failure Modes and Effects Analysis
- 2.9 (Summary of) Electromagnetic Interface, Temperature, Humidity, and Seismic Testing Results
- The project team needs to understand the basis of the additional NRC requests to ensure that what we provide in the submittal meets the necessary basis.
4