ML23055A271
| ML23055A271 | |
| Person / Time | |
|---|---|
| Site: | Quad Cities |
| Issue date: | 03/02/2023 |
| From: | Constellation Energy Generation |
| To: | Robert Kuntz NRC/NRR/DORL/LPL3 |
| Kuntz R | |
| References | |
| EPID L-2023-LRM-0007 | |
| Download: ML23055A271 (1) | |
Text
QuadCities NuclearPower Station RICTand50.69LARs NRCPreSubmittalMeeting March2,2023
- Meeting Objectives
- QCNPS Design Features of Note
- Overview of License Amendment Requests (LARs)
- Probabilistic Risk Assessment (PRA) Models
- FLEX Equipment Use
- External Hazards
- Submittal Timeline
- Key Takeaways Agenda Topics QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING 1
- Provide NRC a clear understanding of the planned site-specific LARs
- Obtain NRC feedback on the proposed LARs to aid the acceptance review and minimize the need for RAIs
- Discuss proposed submittal schedule and corresponding need by date in order to allow NRC resource planning Meeting Objectives QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING 2
- Pre-General Design Criteria (GDC) plant
- Safe-Shutdown Makeup Pump (SSMP) is a common unit system designed to supply makeup water to the reactor core at the same capacity as the Reactor Core Isolation Cooling (RCIC) system
- Three emergency diesel-driven generators (EDGs) - one dedicated per unit plus one that can be utilized by either unit
- Two station blackout diesel-driven generator sets, each having a continuous rating of 4350 kW
- FLEX equipment, including the Hardened Containment Vent System (HCVS) and use of BlackStarTechTM carts, for Extended Loss of AC Power (ELAP) conditions QCNPS Design Features of Note QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING 3
QCNPS meets the EPRI 3002017583 Tier 1 criteria for a "Low Seismic Hazard/High Seismic Margin" site
- RICT LAR based on TSTF-505-A, Rev. 2 BWR/3 reactor design with a Mark 1 containment TS markups follow TSTF for BWR/4 (NUREG-1433 basis)
No clean page revisions included in the LAR Submittal intended to allow use of the model Safety Evaluation (SE)
- Considering including content of TSTF-591, which alters the RICT Program description wording and adopts RG 1.200 Rev. 3 (impacted by timing of final approval of the Traveler)
Overview of License Amendment Requests 4
QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
- Mostly nomenclature, section numbering or title wording differences, or driven by plant design
- TSTF-505 LCOs/Conditions not in QCNPS TS 3.3.4.1 "End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation" 3.3.6.3 "Low-Low-Set (LLS) Instrumentation" 3.6.3.1 "Drywell Cooling System Fans" 3.7.2 "Plant Service Water (PSW) System and Ultimate Heat Sink (UHS)"
3.8.7 "Inverters - Operating"
- RICT added to plant-specific LCOs not included in TSTF-505 3.3.6.3 "Relief Valve Instrumentation" 3.6.2.6 "Residual Heat Removal (RHR) Drywell Spray" 3.7.9 "Safe Shutdown Makeup Pump (SSMP) System"
- RICT not added to LCOs included in TSTF-505 3.6.2.4 "Residual Heat Removal (RHR) Suppression Pool Spray" Variances from TSTF-505 (identified in Attachment 1 and Enclosure 4) 5 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
- Full Power Internal Events (FPIE) PRA - Peer Reviewed to RG 1.200 Rev. 2 Fact & Observation (F&O) Closure review performed No Open Finding F&Os
- Fire PRA - Peer Reviewed to RG 1.200 Rev. 2 F&O Closure review performed No Open Finding F&Os PRA Models Technical Acceptability 6
QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
QCNPS RICT and 50.69 LAR submittals will follow the process defined in NUREG-1855 Rev. 1, and the guidance in EPRI 1016737 and EPRI 1026511, including:
Identification of internal events/internal flooding PRA model plant-specific and generic sources of uncertainties per EPRI 1016737 Identification of internal fire PRA model plant-specific and generic sources of uncertainty per Appendix B of EPRI 1026511 Consideration of generic Level 2 model sources of uncertainty per Appendix E of EPRI 1026511, as applicable to large early release frequency (LERF)
Assessment of potential sources of uncertainties that are key to the respective applications, and associated disposition or treatment Consideration of parameter and completeness uncertainties Evaluation of PRA Uncertainties and Assumptions 7
QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
Three portable diesel-driven pumps One deep well motor-driven FLEX pump and associated diesel generator Four separate portable generators and associated piping, valves, and instrumentation Hardened Containment Vent System (HCVS)
- Only used during ELAP conditions per QCNPS plant procedures Thus, only credited in PRA for ELAP FLEX Equipment Use 8
QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
- BlackStarTechTM was incorporated into the QCNPS PRA models and is used in sample RICT calculations Multiple portable carts with equipment capable of providing backup power to specific equipment Located near equipment intended to be served RCIC flow controller Automatic Depressurization System (ADS) valves and logic instrumentation HCVS FLEX Equipment Use-BlackStarTechTM 9
QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
External Hazards 10 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
- IPEEE Initial Screening
- Reviewed current hazard information
- Updated analysis using Part 6 screening criteria of ASME/ANS PRA Standard RA-Sa-2009
- Performed conservative or bounding analyses where appropriate RICT - Incorporates NEI 06-09 guidance Justify exclusion of external risk sources from the PRA models based on their insignificance to the calculation of configuration risk 50.69 - Incorporates NEI 00-04 guidance Figure 5-6, Other External Hazards Seismic will use EPRI alternative approach (TR 3002017583) for Tier 1 plants
Two flood causing mechanisms to be screened Local Intense Precipitation
- Intense rainfall is monitored by the station in accordance with LIP Procedures
- Following a consequential rainfall event, the procedure directs the installation of six flood barriers
- In combination with permanently installed features (such as exterior doors), the station does not lose any key SSCs or safety functions during the event
- Time Validation performed to ensure all actions can be accomplished in the time window
- Operators are trained on the installation of the temporary barriers QCNPS External Hazards - External Flooding 11 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
Two flood causing mechanisms to be screened Local Intense Precipitation
- Station response to LIP was presented in Integrated Assessment letter RS-18-045 (ML18180A033)
- NRC assessment issued August 29, 2019 (ML19168A196)
- Initial Preliminary Screening Criterion C1, "Event damage potential is less than events for which the plant is designed" QCNPS External Hazards - External Flooding 12 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
Two flood causing mechanisms to be screened PMF (River Flood with Hydrologic Dam Failure)
Current Strategy:
- Station strategy includes shutting down reactors well in advance of flood, cooling down, disassembling, flooding up and refilling with river water over the long duration event
- Building doors are opened to allow water pressure to equalize on both sides of the walls
- This strategy will remain in place for the most extreme floods QCNPS External Hazards - External Flooding 13 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
QCNPS External Hazards - External Flooding 14 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING PMF (River Flood with Hydrologic Dam Failure)
- Station performed a Probabilistic Flood Hazard Assessment for the river flood mechanism Utilized stochastic weather modeling and continuous simulation hydrologic model accounting for uncertainties
- Study showed that flood waters exceeding:
Site Grade (@595.5) ~ 2E-6/yr LIP Barriers (@599.0) ~ 5E-8/yr
QCNPS External Hazards - External Flooding 15 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING PMF XF MEAN HAZARD CURVE
QCNPS External Hazards - External Flooding 16 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING PMF (River Flood with Hydrologic Dam Failure)
Proposed Strategy:
- Upon receipt of river flood warning, operators close LIP Barriers in accordance with the station LIP Procedures
- Follow normal procedures to shutdown, cooldown, and dissemble for long term make up in extreme flood situations Revised Analysis:
- Structural capability of LIP Barriers and Building walls to sustain hydrologic forces to an elevation of 599
- Modifications of some LIP barriers to protect to 599
- Revision to procedures to include step of closing six LIP barriers prior to the flood waters arriving
QCNPS External Hazards - External Flooding 17 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING PMF (River Flood with Hydrologic Dam Failure)
Bounding mean CDF evaluation - conservative assumptions, inputs and methods Anticipated CDF will be estimated an order of magnitude lower than the threshold No credit for mitigation capabilities once water tops barriers Screen utilizing Progressive Screening Criterion PS4 where the bounding mean CDF is less than 1E-6/yr
- Wind pressure effects from high winds and tornados screen
- Although the Tornado Missile design and licensing bases are met, tornado risk is evaluated due to risk-significant SSCs vulnerable to missiles RICT Although average CDF is expected to be < 1E-6/yr, a penalty factor will be needed to account for configuration risk 50.69 Expect to screen with CDF < 1E-6/yr (PS4)
External Hazards - Extreme Winds / Tornados QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING 18
RICT Seismic penalty value QCNPS seismic risk contribution was included in overall risk 50.69 EPRI Seismic Alternative Tier 1 Methodology Tier 1 definition: (1) GMRS peak acceleration derived from the seismic hazard is at or below 0.2g or (2) where the GMRS is below or equal to the SSE between 1.0 Hz and 10 Hz QCNPS meets second criterion since GMRS is bounded by a combination of 2 SSE curves (next slide) (ML15309A493)
External Hazards - Seismic 19 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
External Hazards - 50.69 Seismic 20 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
- All external hazards, except for seismic and tornado missiles, screened for applicability to QCNPS in accordance with GL 88-20
- Screening criteria in ASME PRA Standard RA-Sa-2009 used for both the TSTF-505 and 50.69 applications External Hazards - Other 21 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
- A primary goal of presubmittal meetings is to understand what site-specific issues the NRC may be interested in prior to docketing the submittal
- QCNPS submittal will address common themes in past NRC Requests for Additional Information (RAIs), including the NEI published generic set of TSTF-505 RAIs
- Proactively incorporating RAI insights reduces burden on both the NRC and CEG during the review Lessons Learned 22 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
- Submitted as two separate requests on same day (or close to same day)
Common assessment approach of PRA technical adequacy and sources of uncertainty Common screening approach of external hazards Same technical teams reviewing PRA risk information Submittal Timeline 23 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING Submit May 2023 Acceptance June 2023 Audit Approve June 2024
- QCNPS submittals similar to prior CEG BWR submittals Template variations administrative in nature or to accommodate plant-specific design Primary plant-specific differences are SSMP and available alternative power sources
- Seismic & tornado missile use penalty factor
- External flood strategy capitalizes on current licensing basis by providing physical barriers to increase time to flood plant equipment, but otherwise generally same strategy Key Takeaways 24 QUADCITIESNUCLEARPOWERSTATIONNRCPRESUBMITTALMEETING
Feedback