SLRA - NRC Presubmittal Meeting Slides - 6-28-23
ML23173A047
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 06/28/2023
From: Mark Yoo
NRC/NRR/DNRL/NLRP
To:
References
Download: ML23173A047 (1)


Text

Dresden Nuclear Power Station, Units 2 and 3 Subsequent License Renewal Application (SLRA)

Safety Pre-Application Meeting June 28, 2023 Mark Yoo Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation

Meeting Agenda

Inputs into NRC Licensing Decision

  • Safety Review:

o Process Overview o Tentative Review Schedule for Dresden

  • NRC Contact Information
  • Conclusion / Questions 2

Subsequent License Renewal Review Process +

Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

NRC Renewal Decision (10 CFR 54.29)

Subsequent License Renewal Application (SLRA) Accepted Safety Review (10 CFR 54)

ACRS Recommendation (10 CFR 54.25)

Hearings*

10 CFR 2 3

Safety Review:

Process Overview Issue Safety Evaluation (SE)

Acceptance Review In-Office Technical Review Audit On-SiteAudit BreakoutAudit 4

Dresden: Tentative Safety Review Schedule 5

Activity Estimated Date Application Submission Date April 2024 Acceptance Date (Project Start Date)

May 2024 In-Office Technical Review Audit August 2024 On-Site Audit August 2024 Breakout Audit September 2024 Safety Evaluation Report July 2025 Advisory Committee on Reactor Safeguards (ACRS) Full Committee Meeting September 2025 Licensing Decision November 2025 Note: The review schedule below is tentative and subject tochange.

The schedule is only finalized once the application has been accepted forreview and docketing.

NRC Contact Information 6

Safety Project Manager Mark Yoo (Mark.Yoo@nrc.gov)

Safety Branch Chief Lauren Gibson (Lauren.Gibson@nrc.gov)

Environmental Project Manger Tam Tran (Tam.Tran@nrc.gov)

Environmental Branch Chief Ted Smith (Theodore.Smith@nrc.gov)

Questions?

7