From:
Norma Garcia Santos To:
Mike Rose; CLARK Gary (EXTERNAL ORANO)
Cc:
Joseph Borowsky; Bharatkumar Patel; Yoira Diaz Sanabria
Subject:
Follow Up on RSI and Observations Discussion with the Applicant of the Model No. IR-100ST (71-9385)
Date:
Thursday, November 7, 2024 5:18:00 PM Good afternoon,
As a follow up of todays meeting, in terms of a response to the RSIs, the staff explained that a narrative responding to the questions may be an approach to supplement the application, given that all answers are acceptable. As part of your responses to the staffs questions provided in the RSI letter, based on todays discussion, provide the following information:
- 1. Provide and explain the basis for all the assumptions (e.g., temperatures)
- 2. Explain impacts of the thermal load and materials of construction of the batteries on the performance of the package under HAC and NCT.
- 3. Provide manufacturers specifications for the batteries, including thermal load, dimensions, materials of construction, voltage, etc.
- 4. Explain if a runway reaction due to battery failure or overheating is possible; are there any gases generated during NCT or HAC that can ignite?
- 5. Describe the characteristics of the special source (material of construction, melting temperature, etc.)
- 6. Explain the meaning of ignition of vented gases in section 2.7.4.
Per discussion with the staff, even though a narrative may be a way to respond to the RSI and supplement the application, the staff may have additional questions or request additional analyses after performing a more detailed technical review of the application.
I will follow up with you if there is additional information that may facilitate your response.
Thanks in advance, Norma Garcia Santos Project Manager (Preferred pronouns: she, her, hers)
Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards WAH: M, Th, and F Chat with me in Teams