Letter Sequence Acceptance Review |
---|
EPID:L-2023-DFA-0010, Louisiana Energy Services, LLC, Dba Urenco USA, Executed Financial Assurance Instruments for 2024 Decommissioning Funding (Open) |
|
MONTHYEARML23348A2712023-12-14014 December 2023 Louisiana Energy Services, LLC, Dba Urenco USA, Executed Financial Assurance Instruments for 2024 Decommissioning Funding Project stage: Request ML24061A1602024-02-13013 February 2024 Acceptance of Executed Financial Assurance Instruments for 2024 Decommissioning Funding Project stage: Acceptance Review ML24177A3062024-07-26026 July 2024 Enclosure 3 - Louisiana Energy Services, LLC Amendment 102, Special Nuclear Material-2010 (Public) Project stage: Other ML24177A3042024-07-26026 July 2024 Cover Letter - Louisiana Energy Services, LLC, - Amendment 102, Approval of Urenco USA Executed Financial Assurance Instruments for 2024 Decommissioning Funding Project stage: Other 2024-02-13
[Table View] |
|
---|
Category:Acceptance Review Letter
MONTHYEARML24061A1602024-02-13013 February 2024 Acceptance of Executed Financial Assurance Instruments for 2024 Decommissioning Funding ML24051A2212024-02-0808 February 2024 Acceptance for Review of Urenco USA Revision to Information System Security Plans (LAR 23-10) ML24037A1902024-02-0505 February 2024 Acceptance of LAR 23-07 to Delete License Condition 14 ML23249A1632023-09-0505 September 2023 Acceptance for Review of Uusa License Amendment Request LAR-23-01 ML23244A1952023-08-30030 August 2023 Acceptance for Review of the Etc USA Information System Security Plan (Issp) ML23244A1932023-08-30030 August 2023 Acceptance for Review of Uusa Revision 14 to the Physical Security Plan ML22038A2882022-02-17017 February 2022 Louisiana Energy Services, LLC - NRC Acceptance of the LES Submittal of the 2022 Through 2024 Decommissioning Cost Estimate (LES-21-07 4-NRC) ML21298A2642021-11-0808 November 2021 NRC Acceptance Review for Louisiana Energy Services, LLC (LES) Dba Urenco USA Revisions to the Physical Security Plan ML21048A0552021-02-22022 February 2021 Louisiana Energy Services, LLC - Acceptance for Review of Classified Network Change (L-2021-LLA-0008) ML20301A7972020-11-0303 November 2020 Louisiana Energy Services - Acceptance Letter for Updated Decommissioning Cost Estimate Amount (Enterprise Project Identifier L-2020-DFA-0006) ML19354B1552019-12-23023 December 2019 Louisiana Energy Services - Accept for Review Change to Enrichment Limit (L-2019-LLA-0264) 2024-02-08
[Table view] Category:E-Mail
MONTHYEARML24303A4052024-10-29029 October 2024 Email from Uusa Response to NRC Request for Further Clarification ML24292A1582024-10-17017 October 2024 Email from Uusa Response to NRC Request for Clarification ML24281A1402024-10-0707 October 2024 2024-004 Uusa NCS - OPS Document Request ML24249A1222024-08-28028 August 2024 Second Revised Completion Date for LES License Amendment Request (LAR) 23-01 ML24137A0202024-04-12012 April 2024 Incoming Email - 4-12-24 - Uusa Higher Enrichment Pre-Submittal Activities ML24060A0482024-02-28028 February 2024 Revised Completion Date for LES License Amendment Request (LAR) 23-01 ML24061A1602024-02-13013 February 2024 Acceptance of Executed Financial Assurance Instruments for 2024 Decommissioning Funding ML24043A1622024-02-12012 February 2024 Approval of Enrichment Technology Company-United States Information System Security Plan ML24051A2212024-02-0808 February 2024 Acceptance for Review of Urenco USA Revision to Information System Security Plans (LAR 23-10) ML24037A1902024-02-0505 February 2024 Acceptance of LAR 23-07 to Delete License Condition 14 ML24043A1132024-01-30030 January 2024 Approval of Interim Authority to Operate Classified Information Systems in Centrifuge Assembly Building ML23320A0622023-11-15015 November 2023 Email to Etc USA Regarding Issp Comments ML23265A1312023-09-21021 September 2023 Update on Schedule for Completion of Movement Plan ML23261B4682023-09-18018 September 2023 Document Request for Epx Inspection ML23249A1632023-09-0505 September 2023 Acceptance for Review of Uusa License Amendment Request LAR-23-01 ML23244A1932023-08-30030 August 2023 Acceptance for Review of Uusa Revision 14 to the Physical Security Plan ML23244A1952023-08-30030 August 2023 Acceptance for Review of the Etc USA Information System Security Plan (Issp) ML23220A3402023-08-0202 August 2023 Acceptance for Review of Request for Exemption from 24-Hour Reporting Requirement of 10 CFR 70.50(b)(1) ML23146A1902023-05-25025 May 2023 Acceptance of Revision 12 of the Movement Plan for Transportation of Classified Centrifuge Components/Materials Between Tripartite Countries and the Us ML22298A0912022-10-18018 October 2022 Summary of Call with Uusa Regarding Sppp Updates for Centrifuge Assembly Building and 32 CFR 117 ML22241A0942022-08-25025 August 2022 Notice of Administrative Adjustment of the Estimated Completion Date for the LES Risk Assessment Subject to Resolution of the Follow-up Request for Additional Information ML22206A0372022-07-19019 July 2022 Email - Status Update on the Uusa Risk Assessment Request for Additional Information ML22179A0332022-06-24024 June 2022 NRC Response to LES Request to Extend the Due Date for the Re Bi-Monthly Inventory ML22167A1582022-06-15015 June 2022 Approval of LES, D.B.A Urenco USA, Request for Extension of the RAI Response Date ML22041A3312022-02-0909 February 2022 NRC Staff Summary of January 27, 2022 Closed Call with LES Regarding Iato Conditions and the Definition of Substantive Vs. Non-substantive ML21281A2212021-09-22022 September 2021 LES Email Request to Postpone 2022-2024 Decommissioning Funding Estimate ML21141A1052021-05-20020 May 2021 E-mail to Wpadgett, LES Re Project Manager Change ML21091A0232021-03-31031 March 2021 Final Summary of 3/30/2021 Call W/Les Redundant IROFS ML21040A1132021-02-0808 February 2021 E-mail to Wpadgett, Urenco Receipt of Sppp Page Changes ML21034A1682021-02-0202 February 2021 Receipt of Urenco USA Emergency Plan, Revision 27a NRC-2020-0261, Urenco USA (Louisiana Energy Services) Response to Draft Enforcement Policy NRC-2020-02612021-01-25025 January 2021 Urenco USA (Louisiana Energy Services) Response to Draft Enforcement Policy NRC-2020-0261 ML21014A5162021-01-14014 January 2021 Louisiana Energy Services - RAI for Annual Decommissioning Fund Cost Estimate (Enterprise Project Identifier L-2020-DFA-0006) ML20356A0612020-12-16016 December 2020 E-mail from Abixenman Re Uusa Regulatory Relief Request ML20069G7962020-03-0909 March 2020 Email to Wpadgett, LES Request for Additional Information Regarding Executed Financial Instruments (L-2019-DFA-0017) ML19337D4062019-12-0202 December 2019 Email to A. Bixenman, Urenco Receipt of Page Changes to Sppp ML19309F9132019-10-31031 October 2019 Final Summary of 10/29/2019 Call W/Les Exemption from 70.50(b)(2) ML19297G1822019-10-24024 October 2019 NMSS Org Chart ML19297G1802019-10-24024 October 2019 Email to Sdiggs, Urenco NMSS Reorganization and New Project Manager Assignments 2024-08-28
[Table view] |
Text
From: Jonathan Rowley To: Schwarz, Chris; Pfabe, John Cc: Samantha Lav (She/Her/Hers)
Subject:
Acceptance of Executed Financial Assurance Instruments for 2024 Decommissioning Funding Date: Tuesday, February 13, 2024 1:28:00 PM
Dear Chris Schwarz:
The U.S. Nuclear Regulatory Commission (NRC) staff has received your submittal dated December 14, 2023 (Agencywide Documents Access and Management System (ADAMS)
Accession Number ML23348A271), pertaining to Louisiana Energy Services (LES), doing business as Urenco USA (UUSA), newly executed financial assurance instruments for the 2024 decommissioning funding.
We have completed our acceptance review of the submittal. We have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identification Number (EPID) L-2023-DFA-0010. Please reference this EPID number and Docket Number 07003103 in any future correspondence associated with this request.
Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by July 12, 2024. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require approximately 80 staff hours which corresponds to about $24,000.00 (current rate of
$300.00/hr).
Jonathan Rowley, Project Manager U.S. Nuclear Regulatory Commission (NRC)
Office of Nuclear Material Safety and Safeguards (NMSS)
Division of Fuel Management (DFM)
Fuel Facility Licensing Branch (FFLB)
Phone: 301-415-4053 Email:jonathan.rowley@nrc.gov