MONTHYEARML23220A3402023-08-0202 August 2023 Acceptance for Review of Request for Exemption from 24-Hour Reporting Requirement of 10 CFR 70.50(b)(1) Project stage: Acceptance Review ML23263A2652023-09-25025 September 2023 Request for Additional Information for Request for Exemption from 24-Hour Reporting Requirement of Title 10 of the Code of Federal Regulations Section 70.50(b)(1) Project stage: RAI ML23321A2412023-12-26026 December 2023 Transmittal Letter - Uusa 24 HR Exemption Request Approval Project stage: Other ML23321A2402023-12-26026 December 2023 Enclosure 1 - Safety Evaluation Report for Uusa 24 HR Exemption Request Project stage: Approval ML23321A2382023-12-26026 December 2023 Enclosure 3 - LES Amendment 100 - 24 Hour Reporting Requirements Exemption Request (Public) Project stage: Other 2023-08-02
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24037A1902024-02-0505 February 2024 Acceptance of LAR 23-07 to Delete License Condition 14 ML23320A0622023-11-15015 November 2023 Email to Etc USA Regarding Issp Comments ML23265A1312023-09-21021 September 2023 Update on Schedule for Completion of Movement Plan ML23261B4682023-09-18018 September 2023 Document Request for Epx Inspection ML23249A1632023-09-0505 September 2023 Acceptance for Review of Uusa License Amendment Request LAR-23-01 ML23244A1932023-08-30030 August 2023 Acceptance for Review of Uusa Revision 14 to the Physical Security Plan ML23244A1952023-08-30030 August 2023 Acceptance for Review of the Etc USA Information System Security Plan (Issp) ML23220A3402023-08-0202 August 2023 Acceptance for Review of Request for Exemption from 24-Hour Reporting Requirement of 10 CFR 70.50(b)(1) ML23146A1902023-05-25025 May 2023 Acceptance of Revision 12 of the Movement Plan for Transportation of Classified Centrifuge Components/Materials Between Tripartite Countries and the Us ML22298A0912022-10-18018 October 2022 Summary of Call with Uusa Regarding Sppp Updates for Centrifuge Assembly Building and 32 CFR 117 ML22241A0942022-08-25025 August 2022 Notice of Administrative Adjustment of the Estimated Completion Date for the LES Risk Assessment Subject to Resolution of the Follow-up Request for Additional Information ML22206A0372022-07-19019 July 2022 Email - Status Update on the Uusa Risk Assessment Request for Additional Information ML22179A0332022-06-24024 June 2022 NRC Response to LES Request to Extend the Due Date for the Re Bi-Monthly Inventory ML22167A1582022-06-15015 June 2022 Approval of LES, D.B.A Urenco USA, Request for Extension of the RAI Response Date ML22041A3312022-02-0909 February 2022 NRC Staff Summary of January 27, 2022 Closed Call with LES Regarding Iato Conditions and the Definition of Substantive Vs. Non-substantive ML21281A2212021-09-22022 September 2021 LES Email Request to Postpone 2022-2024 Decommissioning Funding Estimate ML21141A1052021-05-20020 May 2021 E-mail to Wpadgett, LES Re Project Manager Change ML21091A0232021-03-31031 March 2021 Final Summary of 3/30/2021 Call W/Les Redundant IROFS ML21040A1132021-02-0808 February 2021 E-mail to Wpadgett, Urenco Receipt of Sppp Page Changes ML21034A1682021-02-0202 February 2021 Receipt of Urenco USA Emergency Plan, Revision 27a NRC-2020-0261, Urenco USA (Louisiana Energy Services) Response to Draft Enforcement Policy NRC-2020-02612021-01-25025 January 2021 Urenco USA (Louisiana Energy Services) Response to Draft Enforcement Policy NRC-2020-0261 ML21014A5162021-01-14014 January 2021 Louisiana Energy Services - RAI for Annual Decommissioning Fund Cost Estimate (Enterprise Project Identifier L-2020-DFA-0006) ML20356A0612020-12-16016 December 2020 E-mail from Abixenman Re Uusa Regulatory Relief Request ML20069G7962020-03-0909 March 2020 Email to Wpadgett, LES Request for Additional Information Regarding Executed Financial Instruments (L-2019-DFA-0017) ML19337D4062019-12-0202 December 2019 Email to A. Bixenman, Urenco Receipt of Page Changes to Sppp ML19309F9132019-10-31031 October 2019 Final Summary of 10/29/2019 Call W/Les Exemption from 70.50(b)(2) ML19297G1822019-10-24024 October 2019 NMSS Org Chart ML19297G1802019-10-24024 October 2019 Email to Sdiggs, Urenco NMSS Reorganization and New Project Manager Assignments 2024-02-05
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
From: Jonathan Rowley To: Schwarz, Chris; Love, Barry Cc: Samantha Lav (She/Her/Hers)
Subject:
Acceptance for review of Request for Exemption from 24-Hour Reporting Requirement of 10 CFR 70.50(b)(1)
Date: Wednesday, August 2, 2023 11:53:00 AM
Dear Chris Schwarz:
The U.S. Nuclear Regulatory Commission (NRC) staff has received your submittal dated July 6, 2023 (Agencywide Documents Access and Management System (ADAMS)
Accession Number ML23), pertaining to Louisiana Energy Services (LES), doing business as Urenco USA (UUSA) request for exemption from 24-hour reporting requirement of Title 10 of the Code of Federal Regulations 70.50(b)(1).
We have completed our acceptance review of the submittal. We have identified no administrative omissions or deficiencies that would prevent us from proceeding with a detailed review. Your submittal has been assigned Enterprise Project Identification Number (EPID) L-2023-LLE-0019. Please reference this EPID number and Docket Number 07003103 in any future correspondence associated with this request.
Please note that the NRC staffs technical review of your submittal may identify issues that require additional information. Based on our preliminary evaluation and projection of current review schedules, we anticipate completing our formal review by November 30, 2023. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule. In addition, the NRC staff estimates that completing the review of your submittal will require approximately 40 staff hours which corresponds to about $11,600.00 (current rate of
$290.00/hr, which will change once the Fiscal Year 2023 Fee Rule is implemented).
Jonathan Rowley, Project Manager U.S. Nuclear Regulatory Commission (NRC)
Office of Nuclear Material Safety and Safeguards (NMSS)
Division of Fuel Management (DFM)
Fuel Facilities Licensing Branch (FFLB)
Phone: 301-415-4053 Email: jonathan.rowley@nrc.gov