MONTHYEARML20069G7962020-03-0909 March 2020 Email to Wpadgett, LES Request for Additional Information Regarding Executed Financial Instruments (L-2019-DFA-0017) Project stage: RAI 2020-03-09
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24303A4052024-10-29029 October 2024 Email from Uusa Response to NRC Request for Further Clarification ML24292A1582024-10-17017 October 2024 Email from Uusa Response to NRC Request for Clarification ML24281A1402024-10-0707 October 2024 2024-004 Uusa NCS - OPS Document Request ML24249A1222024-08-28028 August 2024 Second Revised Completion Date for LES License Amendment Request (LAR) 23-01 ML24137A0202024-04-12012 April 2024 Incoming Email - 4-12-24 - Uusa Higher Enrichment Pre-Submittal Activities ML24060A0482024-02-28028 February 2024 Revised Completion Date for LES License Amendment Request (LAR) 23-01 ML24061A1602024-02-13013 February 2024 Acceptance of Executed Financial Assurance Instruments for 2024 Decommissioning Funding ML24043A1622024-02-12012 February 2024 Approval of Enrichment Technology Company-United States Information System Security Plan ML24051A2212024-02-0808 February 2024 Acceptance for Review of Urenco USA Revision to Information System Security Plans (LAR 23-10) ML24037A1902024-02-0505 February 2024 Acceptance of LAR 23-07 to Delete License Condition 14 ML24043A1132024-01-30030 January 2024 Approval of Interim Authority to Operate Classified Information Systems in Centrifuge Assembly Building ML23320A0622023-11-15015 November 2023 Email to Etc USA Regarding Issp Comments ML23265A1312023-09-21021 September 2023 Update on Schedule for Completion of Movement Plan ML23261B4682023-09-18018 September 2023 Document Request for Epx Inspection ML23249A1632023-09-0505 September 2023 Acceptance for Review of Uusa License Amendment Request LAR-23-01 ML23244A1932023-08-30030 August 2023 Acceptance for Review of Uusa Revision 14 to the Physical Security Plan ML23244A1952023-08-30030 August 2023 Acceptance for Review of the Etc USA Information System Security Plan (Issp) ML23220A3402023-08-0202 August 2023 Acceptance for Review of Request for Exemption from 24-Hour Reporting Requirement of 10 CFR 70.50(b)(1) ML23146A1902023-05-25025 May 2023 Acceptance of Revision 12 of the Movement Plan for Transportation of Classified Centrifuge Components/Materials Between Tripartite Countries and the Us ML22298A0912022-10-18018 October 2022 Summary of Call with Uusa Regarding Sppp Updates for Centrifuge Assembly Building and 32 CFR 117 ML22241A0942022-08-25025 August 2022 Notice of Administrative Adjustment of the Estimated Completion Date for the LES Risk Assessment Subject to Resolution of the Follow-up Request for Additional Information ML22206A0372022-07-19019 July 2022 Email - Status Update on the Uusa Risk Assessment Request for Additional Information ML22179A0332022-06-24024 June 2022 NRC Response to LES Request to Extend the Due Date for the Re Bi-Monthly Inventory ML22167A1582022-06-15015 June 2022 Approval of LES, D.B.A Urenco USA, Request for Extension of the RAI Response Date ML22041A3312022-02-0909 February 2022 NRC Staff Summary of January 27, 2022 Closed Call with LES Regarding Iato Conditions and the Definition of Substantive Vs. Non-substantive ML21281A2212021-09-22022 September 2021 LES Email Request to Postpone 2022-2024 Decommissioning Funding Estimate ML21141A1052021-05-20020 May 2021 E-mail to Wpadgett, LES Re Project Manager Change ML21091A0232021-03-31031 March 2021 Final Summary of 3/30/2021 Call W/Les Redundant IROFS ML21040A1132021-02-0808 February 2021 E-mail to Wpadgett, Urenco Receipt of Sppp Page Changes ML21034A1682021-02-0202 February 2021 Receipt of Urenco USA Emergency Plan, Revision 27a NRC-2020-0261, Urenco USA (Louisiana Energy Services) Response to Draft Enforcement Policy NRC-2020-02612021-01-25025 January 2021 Urenco USA (Louisiana Energy Services) Response to Draft Enforcement Policy NRC-2020-0261 ML21014A5162021-01-14014 January 2021 Louisiana Energy Services - RAI for Annual Decommissioning Fund Cost Estimate (Enterprise Project Identifier L-2020-DFA-0006) ML20356A0612020-12-16016 December 2020 E-mail from Abixenman Re Uusa Regulatory Relief Request ML20069G7962020-03-0909 March 2020 Email to Wpadgett, LES Request for Additional Information Regarding Executed Financial Instruments (L-2019-DFA-0017) ML19354A9662019-12-17017 December 2019 E-mail from Wpadgett, Urenco, Facility Modifications Since Last Decommissioning Cost Estimate Update (L-2019-DFA-0014) ML19337D4062019-12-0202 December 2019 Email to A. Bixenman, Urenco Receipt of Page Changes to Sppp ML19309F9132019-10-31031 October 2019 Final Summary of 10/29/2019 Call W/Les Exemption from 70.50(b)(2) ML19297G1802019-10-24024 October 2019 Email to Sdiggs, Urenco NMSS Reorganization and New Project Manager Assignments ML19297G1822019-10-24024 October 2019 NMSS Org Chart 2024-08-28
[Table view] |
Text
From:
Ramsey, Kevin To:
Padgett, Wyatt Cc:
Zimmerman, Jacob; Kline, Kenneth; Adkins, Brannen; Cooke, Lindsey
Subject:
Request for additional information regarding executed financial instruments (L-2019-DFA-0017)
Date:
Monday, March 09, 2020 1:29:00 PM We have reviewed your letter dated December 12, 2019, transmitting executed financial instruments for decommissioning financial assurance. The letter is available in the Agencywide Documents Access and Management System (ADAMS) under Accession Number ML19351C744. Our review of your application has identified that additional information is needed.
- 1. In the Standby Trust Agreement, there are references to both Amendment 11 and Amendment 10. We believe the references to Amendment 10 are erroneous. Please correct the amendment numbers or explain why they are correct.
- 2. In the Standby Trust Agreement, there are references to December 5, 2019, and December 5, 2018. We believe the 2018 dates are erroneous. Please correct the dates or explain why they are correct.
- 3. In Schedule B of the Standby Trust Agreement, the dollar amount listed in the first line does not match the sum of the financial instruments listed in the evidence section. We believe the dollar amount in the first line is erroneous. Please correct the dollar amount or explain why it is correct.
The additional information requested above should be provided within 30 days from the date of this message. This information is needed to verify compliance with 10 CFR 70.25, Financial assurance and recordkeeping for decommissioning.
Pending your response, we anticipate completing our review by July 2, 2020. This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any significant changes to this schedule.
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this message will be available for public inspection in the NRC Public Document Room or from ADAMS. The ADAMS database is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please let me know if you have any questions regarding this request for additional information.
Kevin M. Ramsey Senior Project Manager U.S. Nuclear Regulatory Commission 301-415-7506