ML20217F664
ML20217F664 | |
Person / Time | |
---|---|
Site: | Oyster Creek |
Issue date: | 04/22/1998 |
From: | Eugene Kelly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
To: | |
Shared Package | |
ML20217F631 | List: |
References | |
50-219-98-80, NUDOCS 9804280228 | |
Download: ML20217F664 (28) | |
See also: IR 05000219/1998080
Text
.
U. S. NUCLEAR REGULATORY COMMISSION
REGION I
Report No: 98-80 !
Docket No: 50-219
License No: DPR-16
Licensee: GPU Nuclear incorporated
1 Upper Pond Road
Parsippany, New Jersey 07054
Facility Name: Oyster Creek Nuclear Generating Station
Location: Forked River, New Jersey
l
l
Inspection Periods: February 23,1998 - March 13,1998
March 30,1998- April 2,1998
Inspectors: Jimi Yerokun, DRS, Team Leader
Ram Bhatia, DRS
Carl Sisco, DRS
l
l Ron Eaton, NRR
Don Haverkamp, DRP
Tom Elsasser, Contractor i
!
Approved By: Eugene M. Kelly, Chief,
Systems Engineering Branch
Division of Reactor Safety
9004280228 980422
PDR ADOCK 05000219
G PDR
1
1
I
EXECUTIVE SUMMARY
Oyster Creek Nuclear Generating Station
Report No. 98-80
A regional engineering team inspection was performed at Oyster Creek Nuclear Generating
Station (OCNGS) during the periods of February 23,1998 to March 13,1998, and March
30 to April 2,1998. The inspection consisted of Safety System Engineering Inspection
(SSEI); Safety Evaluation Program Inspection; and evaluation of the Effectiveness of
OCNGS at identifying, Resolving, and Preventing Problems.
In the systems area, the team selected the Automatic Depressurization System (ADS) and
the Containment Spray System (CSS). The CSS also included its heat sink, the Emergency
Service Water System (ESWS). The purpose of the inspection was to evaluate the
capability of the systems to perform safety functions required by their design bases, the
adherence to the design and licensing bases, and the consistency of the as-built
configuration with the updated final safety analysis report (UFSAR).
In the programmatic area, the team reviewed and assessed the processes in place for the
implementation of the requirements of 10 CFR 50.59 for proposed changes, tests and
experiments and the processes for implementation of the Corrective Action Program
including: Root Cause Analysis; Safety and Independent Oversight; Self Assessment; and
Operating Experience Feedback.
A significant concern was identified with the ADS system involving the DC voltage that
would be available to the EMRV solenoids during a small break loss of coolant accident
(SBLOCA) concurrent with a loss of offsite power and a failure of emergency diesel
generator #2. In this scenario, three of the five EMRVs would not have functioned as
required to depressurize the reactor because the voltage available to their solenoids would
not have been enough to operate the solenoids. This concern resulted in three apparent
violations as follows:
! * Failure to establish adequate design control measures to verify or check the
l adequacy of design voltage required for the ADS EMRV solenoid valves as required
by 10 CFR 50, Appendix B, criterion Ill, Design Control. (section E2.1)
- Failure to verify that the field installation of the EMRV solenoid voltage was
I representative of tb EQ documentation as required by 10 CFR 50.49,
Environmental Qualification. Further, when the NRC identified discrepancies with
the EQ program, GPUN was untimely at performing the program required
determination of operability. (section E2.1)
Specification 3.4.B.1, ADS. (section E2.1)
!
ii
l
There were also some weaknesses with the methods established to ensure compliance
with some Technical Specification requirements associated with the ADS. While the ADS
functionality was not affected, an instance that resulted in a violation of Technical l
Specification was identified. The instance involved the failure, on October 6,1996, to
ensure that ADS was operable during the reactor pressure vessel test as required by
Technical Specification 3.4.B.1, ADS. (E2.1)
Apart from the issues discussed above, the ADS was maintained well. System
modifications were properly implemented. The discharge piping vacuum breakers were
adequately tested to the IST requirements and the acceptance criteria was consistent with
the design basis. Instrumentation and control design for the ADS and pressure relief
function was consistent with the design basis and licensing documents. l
The Containment Spray and Emergency Service Water Systems were maintained operable
and capable of performing their safety functions including during a loss of offsite power i
and a single active failure. Surveillance testing of system components were conducted in
accordance with existing procedures. The CSS and ESWS instruments were properly
calibrated and maintained. While initial conditions and the basis for some assumptions
were not always obvious, calculations and safety analysis adequately supported
implemented modifications. The team identified that some pertinent design information in
the UFSAR required updating. The licensee was aware of this and already had efforts
ongoing to update the UFSAR. However, witn regard to the resolution of seismic
deficiencies, there was untimely follow up and reporting to the NRC the status of SOUG
outliers. Also, two discrepancies that resulted in violations were identified as follows:
- Failure to adequately correct a seismic deficiency with a containment spray heat
exchanger as of February 26,1998, as required by 10 CFR 50, Appendix B,
Criterion XVI, Corrective Actions. (section E2.2)
- Failure to verify design calculations that supported the seismic adequacy of safety
related equipment as required by procedure EP-06 and 10 CFR 50, Appendix B,
Criterion V, instructions, Procedures, and Drawings. (section E2.2)
In the 10 CFR 50.59 program area, procedures were found to be comprehensive and
detailed in providing guidance and assigning responsibility for implementing the
requirements of 10 CFR 50.53 and updating the UFSAR. The procedures were also up to
date in incorporating revised industry and NRC 10 CFR 50.59 guidance and GPUN self
assessment findings.
10 CFR 50.59 Safety Evaluations (SEs) were of good quality and performed in accordance
with the requirements of 10 CFR 50.59 and the applicable procedures by qualified and
certified personnel. However, some SEs exhibited a lack of thoroughness and attention to
detail that was expected by the facility procedures. Two violations were identified as
follows:
i
- Failure to submit the required changes, test, and experiments reports in 1983,
1986, and 1998 as required by 10 CFR 50.59(b) and 10 CFR 50.71(e). (section
l
,
E3.2)
1
l
l
i
!
\
- Failure to comply with procedure EP-016 for Safety Evaluations on several
occasions as of February 26,1998, as required by 10 CFR 50, Appendix B,
Criterion V, Instructions, Procedures, and Drawings. (section E3.2)
Overall, the quality of the 10 CFR 50.59 training program for certification of RTR and ISR
was excellent. The contents of the training were appropriate and supported the OCNGS
review process that is being implemented. Safety evaluations were prepared and reviewed
by individuals who had received training regarding the preparation and review of SEs in
accordance with the facility procedure.
In the Correction Action Program area, Deviation Reports (DVR) reflected appropriate
operability determinations, and management attention necessary to identify causes and put
into place effective corrective actions. The Corrective Action training process was
acceptable and staff members were generally knowledgeable of the corrective action
process. The trending of DVRs was adequate and provided meaningfulinformation to
management. Although not all management expectations were met concerning the
program issues, industry operating experience was adequately used at the plant.
The assessments and evaluations of the Independent Safety Oversight Review Group, the
General Office Review Group, and Nuclear Safety Assessment staff were effective in
providing independent oversight of safety significant activities at OCNGS. The experience
of the Independent Safety Oversight members, both industry-wide and site-specific, was a
significant contributor to the value of their products. Management appeared to be full
supportive of the oversight groups and were responsive to their recommendations.
The corrective action and safety review audits were of high quality. Audit findings
received appropriate division management attention. The May 1997 safety review process
I
assessment was self-critical and probing. The NSA audit and assessment reports were
effective in providing GPU Nuclear management independent identification of significant
findings and appropriate recommendations for process improvements.
l
f
l
,
l
iv
1
l
l
l
l
.
TABLE OF CONTENTS
PAGE
EX ECUTIV E S U M M A RY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii
il l . Engi n e e ri ng . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
E2 Engineering Support of Facilities and Equipment ....................... 1
E2.1 Automatic Depressurization System . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
E2.2 Containment Spray and Emergency Service Water . . . . . . . . . . . . . . . . . 8
E3 Engineering Procedures and Documentation . . . . . . . . . . . . . . . . . . . . . . . . . 12
E3.1 10 CFR 50.59 Safety Evaluation Program . . . . . . . . . . . . . . . . . . . . . . 12
E3.2 Implementation of 10 CFR 50.59 Program .....................13
E7 Quality Assurance in Engineering Activities . . . . . . . . . . . . . . . . . . . . . . . . . . 16
E7.1 Problem Identification, Resolution, Prevention, and Corrective Actions . . 16
V. Management Meetings .........................................20
X1 Exit Meeting Summ ary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 ;
!
l
i
1
i
I
l
1
I
t
v
Reoort Details
Ill. Enaineerina .
i
E2 Engineering Support of Facilities and Equipment
E2.1 Automatic Deoressurization System
a. Insoection Scope (IP 93809)
The team reviewe.d and assessed the operation, testing and mai' tenance of the
automatic depressurization system (ADS). The review included related sections of
the Updated Safety Analysis Report (UFSAR) and Technical Specifications (TS), the
System Design Basis Document, flow diagrams and other system drawings,
calculations, operating (normal and emergency) procedures, and in service and
surveillance test procedures and results.
The review was multi-disciplinary (mechanical, electrical and instrument & control)
and included a review of analysis that support system performance during normal
and accident conditions, walkdown of accessible portions of the system, and
discussions with cognizant system and design engineers. The review slso included: l
'
verification of the appropriateness and correctness of design assumpicens;
confirmation that design bases were consistent with the licensing bar,3s; and
- verification of the adequacy of testing requirements.
b. Observations and Findinos
Mechanich_pesian l
The ADS consists of five electromatic relief valves (EMRVs), NR 108A, B, C, D, and
E, that actuate to rapidly reduce reactor coolant system pressure. There are two
discharge piping systems; one for valves A, B and E on the south header and one
for valves C and D on the north header. Two vacuum breakers are connected to
each EMRV discharge line. Their function is to prevent excessive water slugs in the
I discharge piping, which could lead to piping damage on a subsequent EMRV
actuation. Surveillance test 602.1.013, revision 4, ADS Downcomer Line Vacuum
f
l Breaker Operability Test satisfied the requirements of the in-service Test Program
for the vacuum breakers. The acceptance criterion opening force of less than or
equal to 4.4 pounds was adequately supported by design calculations and test
methodology.
There are two modes of operation for the EMRVs. In the pressure actuation mode,
the EMRVs open when reactor pressure reaches the EMRV setpoint. In the
automatic depressurization mode, the valves open to depressurize the reactor vessel
when ADS logic channels sense high drywell pressure, low-low-low reactor water
level and a Core Spray booster pump running.
- _-_ ______________-_____________________-___________________________ ___________ -
I
t
l
2
The team reviewed a modification made to the system in 1994 that increased the
EMRV pressure relief function setpoints by 15 psig to 1085 psig and 1105 psig. l
The revised setpoints had been properly reflected in the EMRV pressure sensor test ;
and calibration procedures. The procedure for operational guidance on the diagnosis
of EMRV system abnormalities and subsequent restorative actions also correctly
documented the changes. The calculations for the Core Spray Booster pump i
differential pressure switches were found to adequately support the existing
setpoints specified in the surveillance procedures and Standing Orders for
instrumentation setpoints.
The team reviewed surveillance test for the ADS and found that it adequately
verified EMRV operability. The team noted that System Engineering personnel were
cognizant of Information Notice 96-02. This Notice described an event where the
main disc of a power operated relief valve had not been repositioning during an
actuation signal. However the condition had been masked to the operators because
the acoustic monitoring system was identifying flow conditions. The team found
that the valve test at Oyster Creek provided operations personnel with alternate
methods of verification of main valve opening such as the requirement to trend
discharge piping temperatures. GPUN's surveillance test was found to have a valve
opening time acceptance criterion of 2.5 seconds. GPUN stated that this value was
consistent with paragraph 4.2.1.4(b) of OM-10, which required stroke times for all
power operated valves to be measured to at least the nearest second. However,
the team indicated that the 2.5 seconds criterion was technically unacceptable,
l since the ASME Code required a 2 second limit for rapid acting valves, and
therefore the intent of Position 6 of GL 89-04 was to establish a maximum struke
time limit of 2 seconds. After further review, GPUN initiated a procedure revision to
change the acceptance criterion to a maximum allowed value of 2 seconds. The
team reviewed the results of valve testing for the past 6 years and noted that in all
cases, the times were found to be below 2 seconds. Therefore, no significant
safety consequence was associated with this discrepancy.
TS 3.4.B.1 established the requirement for all five electromatic relief valves to be
operable whenever reactor water temperature is above 212*F and reactor pressure
is above 110 psig. The specification permits only the relief function of the EMRVs
to be bypassed during Reactor Vessel Pressure Tests. These conditions existed
during the reactor pressure vessel test performed during the period of October 5
through October 10,1996. TS Table 3.1.1, item G1 required high drywell
instruments to be operable to support ADS operability. TS 4.1.1, item 9 required
the high drywell pressure instruments to be channel checked ence per day. The
channel check is satisfied by documenting instrument log readings. However, the
required log readings were not performed during the October 1996 test. The team
noted that although the ADS function was required to be operable during the
pressure vessel tests, there existed no requirement to maintain primary containment
operable. Therefore the high drywell pressure permissive may not have been
achievab;e. Prior to the end of the inspection period, GPUN initiated a Technical
Specification Change Request (TSCR 255), to evaluate deleting the requirement for
ADS to be operable during vessel pressure testing. However, the failure to verify
ADS operability was contrary to the requirement of TS 3.4.B.1 and, therefore, a
violation of NRC requirements. (VIO 50-219/IIS-80-01)
l
,
.
3
TS Table 3.1.1, permits the bypass of only one electromatic relief valve controller at
a time. The TS indicated that the amount of time that relief valve controllers may
be bypassed is limited to 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> total for all controllers in any 30 day period. This
specification established limits on EMRV bypass configurations, to permit testing,
calibration and repair without significant loss of protection. When the team
questioned GPUN about how they ensured compliance with this requirement, they
did not have any established administrative controls to track the amount of time the
controllers had been historically bypassed. However, GPUN was able to provide
nominal times when the controllers were bypassed recently by a review of the
control room log book from January 1997 to January 1998. Procedure 602.3.004,
Electromatic Relief Valve Pressure Sensor Test and Calibration, had been performed
14 times with the test durations logged. The team concurred that based on the
provided documentation, compliance with the requirement had been demonstrated.
GPUN stated that procedure 602.3.004 would be revised to include controls
required to satisfy TS Table 3.1.1 requirements. Upon further investigation, GPUN
discovered that the T.S. limit should be eight hours and not three hours. it
appeared that during the processing of TS Amendment No. 75, a typographical error
had occurred and the number eight became cut off and appeared to be a three. The
team reviewed this information and concurred with the licensee's determination.
However, this was a weakness on the licensee's part at establishing formal controls
for assuring compliance with the requirements of the TS.
The team reviewed the UFSAR steam flow assumptions and noted that GPUN had
recognized inconsistencies in various sections of the UFSAR concerning EMRV flow
rates. Deviation Report (DVR) 97-01 had been previously initiated to address this
issue. Otherwise, the team found that ADS system design was consistent with the
UFSAR design basis requirements.
The team conducted a walkdown of the accessible areas of the ADS including the
panels and controls in the control room, and the EMRVs in the drywell, and
identified no discrepancy.
(
Electrical Desian
The team reviewed the ADS logic, schematic and electrical drawings, and identified
no discrepancy. The team reviewed the available voltage at the terminal point of
the EMRV solenoid valves versus the acceptable minimum voltage required for the
valves to perform their intended design function and noted some discrepancies.
The licensee was unable to provide an appropriate calculation reflecting the voltage
at the terminal point of the valves nor test results to show the minimum voltage
required to operate the valves. As a result, GPUN issued a deviation report (DVR
98-0211)to evaluate the concern. The licensee then conducted a bench test on a
spare unit to determine the minimum voltage at which the EMRV pilot solenoid
valve could operate. The test was conducted at an ambient temperature of 69'F
under a simulated process condition. The EMRV pilot solenoid operated at a
minimum voltage of 70 volt dc. In addition, the licensee also performed a
preliminary voltage drop calculation that indicated that the minimum voltage at the
EMRV coil terminal points would be approximately 80 volts assuming an initial
.. .. - _ _ _ _ - _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ _ _
4
voltage of 116 Volts at the battery bus instead of the nominal 125 Vdc. Based on
this test result and calculation that showed that the available voltage would always
be more than the minimum required to operate, the licensee considered the EMRVs
operable at that Fme.
The team reviewed the licensee's analysis and noted that while the licensee had
assumed a conservative system voltage to calculate the available voltage (116 volts
instead of 119.4 volts that was obtained during the last end of the service test
performed in 1996 on B battery bank), there were still some discrepancies with their
l determination. For example, it was not clear that the ten conditions properly
simulated the expected plant conditions of the solenoids in an accident situation.
l Also, the assumptions and uncertainties used in the voltage drop calculations were
l not clear. The licensee indicated that their analysis and testing would further be
l confirmed by more testing at the solenoid vendor's laboratory.
The team reviewed the Environmental Qualification (EQ) of ADS components (EQ
file EQ-OC-301, Revision 2), and noted that the EMRVs solenoid valves were
qualified at a minimum voltage level of 105 volt de to perform their intended design
! function. This minimum voltage was, however, inconsistent with the licensee's
determination of 70 volts minimum voltage required and of the worst case 86 volts
- available. The licensee indicated that their EQ documentation (Westec Report
i
Project #6035 and GE PEP report # 42963) was very conservative. They stated that
the functionality of GE tests conducted as a part of the EQ tests (GE PEP report #
42963) included in their EQ documentation was overly conservative because of the
overconservative force assurned and that the recent test conducted indicating 65
Vdc (lowest) voltage was more representative of actual conditions for operation of
the EMRVs. Therefore, the EMRVs were determined to be operable with the
estimated 80 Vdc available at the terminal of the EMRV coil of the actuators. This
determination was documented in deviation report (DVR) 98-0250.
Upon further questioning by the team, the licensee reverted to equipment
qualification procedure, 5000-ADM-7317.01,(EP-031), Revision 7, Conduct of
Determination of Operability (DOO) to develop a justification for continued operation
(JCO) as required for all discoveries where EQ components or sub-components are
in nonconforming condition. The procedure required that a DOO must be developed
to document that the equipment in question was operable prior to discovery and to
justify continued operation until the planned corrective action can be implemented.
The licensee issued DOO-OC 119 on March 11,1998, and concluded that the
EMRV solenoids were qualifiable and would remain functional during accident
conditions and capable of performing their intended design function. To further
address the deficiency, the licensee developed a test plan for an EMRV/ solenoid .
operator and sent a spare valve to Wyle Laboratories for testing. However, the
team found that the licensee's EQ program implementation was weak, specifically in
validating the assumed critical parameters for their plant conditions in the
established EQ documentation. The team also identified a weakness with the
licensee staff not readily invoking the requirements of their established EQ program
procedure (EP-031) to justify the nonconformaning EQ component conditions until
further questioning by the team.
5
Upon the completion of engineering analysis of the test results obtained from Wyle
testing, the licensee determined that the ADS would have not met its design basis
requirements. This was based on the fact that three of the five EMRVs would not
have functioned as required to depressurize the reactor during a small break loss of
coolant accident (SBLOCA) concurrent with a loss of offsite power and a single
failure of emergency diesel generator # 2. In that scenario, the three solenoid
valves (A, C and E) would have approximately 77.7; 73.7; and 74.2 volts de
respectively available at their terminals points. A minimum required voltage of 80
. volts had been established in the recent Wyle laboratory testing in harsh
environmental conditions. When this design deficiency was confirmed on
March 30,1998, the unit was already shutdown due to a condenser vacuum
problem which occurred on March 20,1998. This design deficiency was reported
to the NRC on March 30,1998, via a 10 CFR 50.72 (b) (2) (I) notification stating
that the ADS would not have met its design basis requirements. The licensee's
failure to establish adequate design control measures to verify or check the
adequacy of the required design voltage for the ADS solenoid which left the
solenoids with inadequate voltage until questioned by the NRC is an apparent
violation of 10 CFR 50, Appendix B, Design Control (eel 50-219/98-80-02).
l
To address this concern, GPUN management assembled five teams to each
conduct root cause analysis; calculation ar.f testing; modification; extent of issues
review; and independent reviews. The licensee root cause analysis team
determined that this deficiency was attributed due to: (1) lack of engineering
process which did not force voltage analysis information into the EQ process; (2)
GPUN not treating voltage considerations as rigorously as other EQ parameters
(Radiation, heat, humidity); and (3) lack of clear ownership of determination that
l
l
qualification criteria meet the installed configuration.
The GPUN modification team developed and implemented a modification that
involved adding cables and using spare conductors to reduce the circuit resistance
to improve voltage drop. A #4 cable was added between power panel DC-D and
'
relay panel ER-18A to decrease the voltage drop in the EMRVs power supply circuit
to improve the available voltage at the terminals of the deficient solenoid valves.
Subsequent voltage drop calculations (C-1302-735-E320-037and 38 issued on
April 2,1998), considering the improved circuit resistances due to the above
modification, revealed that a worst-case minimum voltage of 84.6 Vdc would be
available at the terminal of EMRV "E" solenoid coil. Since the minimum
requirement, based on Wyle laboratory test, was 80 Vdc during the worst case
environmental conditions (281 degree F) and at 70 Vdc during normal operational
conditions (150 F), the NRC team determined that the licensee adequately resolved
the design basis deficient condition.
The team noted that the licensee's extent of issue team had also completed a
sample review of safety related AC and DC components for adequacy of voltage
drop calculations under their design basis conditions. The licensee stated that these
components were selected based on PRA consideration and that no significant or
similar concerns were identified. At the conclusion of this inspection, the GPUN
independent review team was reviewing all the licensee's team findings and
l
l
!
6
recommendations to develop additionallong term corrective actions to address the
inadequacies. The GPUN EQ staff had revised the existing DOO to justify continued
operation based on the new test results, completed modification, and adequacy of
available voltage to all EMRVs solenoid valves.
The team found the weakness identified in the EQ program was significant because
it raised a question with the operability of the ADS valves.10 CFR 50.49(f)
requires each item of electrical equipment important to safety to be qualified.10
CFR 50.49(k) allows certain electrical equipment to be qualified in accordance wi9
" Guidelines for Evaluating Environmental Qualification of Class 1E Electrical
Equipment in Operating Reactors," November 1979 (DOR Guidelines). DOR
Guidelines, Section 5.2, Qualification by Type Testing, item 5, requires that
operational modes tested should be representative of the actual application
requirements (e.g. motor and electrical cable loading during the test should be
representative of actual operating conditions). In addition, item 6, requires that the
equipment qualification program should include an as-built inspection in the field to
verify that equipment was installed as it was tested.
Contrary to the above, from November 1984 through March 12,1998, the actual
application for the five ADS system electromatic relief solenoid valves in the
equipment qualification documentation (EQ-OC-301 dated 8/1/1989) was not
representative of the installed condition at Oyster Creek Station. The licensee also
did not perform analysis to validate the acceptability for the EQ established
qualification (a minimum of 105 Volt dc ) Specifically, the voltage requirement for
the EMRVs solenoid valves was not validated in the installed condition. This :
absence of as-installed validation was contrary to the requirement of 10 CFR 50.49 l
and therefore, an apparent violation. (eel 50-219/98 80-03)
Also, as of March 19,1998, when the unit was in power operation mode, the ADS
was not operable as required by the TS because it was not capable of functioning
during a small break loss of coolant accident, concurrent with a loss of offsite
power and a worst case single failure. Specifically, TS 3.4.B.1, ADS, requires five
EMRVs to be operable when reactor water temperature is greater than 212 degrees
F, and pressurized above 110 psig. This is an apparent violation of TS 3.4.8.1.
(eel 50-219/98-80-04)
Updated Final Safety Analysis Reoort
Existing surveillance tests for the EMRV Acoustic Monitoring components and the
thermocouples adequately tested the functional capability of the system.
Preventive maintenance frequencies were conservative with respect to thermal
aging calculations found in the EQ files for the EMRV acoustic monitoring
l
accelerometers and preamplifiers located in the primary containment. Section
! 7.6.1.1.8 (Relief Valve / Safety Valve Acoustical Monitoring System (VMS),
described an alarm on main control room panel 1F/2F which annunciates after a 2.2
second time delay to indicate that the valves have opened. The team found this to
be incorrect because, the system actually incorporates a 2.2 second time constant,
which is dependent on the magnitude of the signal. GPUN acknowledged this and
stated that they~ will clarify the UFSAR.
.__
=
.
7
c. Conclusion
A significant concern was identified with the ADS system involving the DC voltage
that would be available to the EMRV solenoids during a small break loss of coolant
accident (SBLOCA) concurrent with a loss of offsite power and a failure of
emergency diesel generator #2. In this scenario, three of the five EMRVs would not
have functioned as required to depressurize the reactor because the voltage
available to their solenoids would not have been enough to operate the solenoids.
This concern resulted in three apparent violations as follows:
- Failure to establish adequate design control measures to verify or check the
adequacy of design voltage required for the ADS EMRV solenoid valves as
required by 10 CFR 50, Appendix B, criterion ill, Design Control. (section E2.1)
e Failure to verify that the field installation of the EMRV solenoid voltage was
representative of the EQ documentation as required by 10 CFR 50.49,
Environmental Qualification. Further, when the NRC identified discrepancies
with the EQ program, GPUN was untimely at performing the program required
determination of operability. (section E2.1)
Technical Specification 3.4.B.1, ADS. (section E2.1)
There were also some weaknesses with the methods established to ensure
compliance with some Technical Specification requirements associated with the
ADS. While the ADS functionality was not affected, an instance that resulted in a
violation of Technical Specification was identified. The instance involved the
failure, on October 6,1996, to ensure that ADS was operable during the reactor
pressure vessel test as required by Technical Specification 3.4.B.1, ADS. (E2.1)
'
Apart from the issues discussed above, the ADS was maintained well. System
modifications were properly implemented. The discharge piping vacuum breakers
were adequately tested to the IST requirements and the acceptance criteria was
consistent with the design basis, instrumentation and control design for the ADS
and pressure relief function was consistent with the design basis and licensing
documents.
I E2.2 Containment Sorav and Emeraency Service Water
a. Inspection Scope (IP 03809)
l The team reviewed and assessed the operation, testing and maintenance of the
Containment Spray / Emergency Service Water System (CSS /ESW). The review
included related sections of the UFSAR and Technical Specifications, the System
Design Basis Documents, flow diagrams and other system drawings, calculations,
operating (normal and emergency) procedures, and in service and surveillance test
l
procedures and results.
l
l
,
l
8 i
The review was multi-disciplinary (mechanical, electrical and instrument & control)
and included review of analysis that support system performance during normal and
accident conditions, walkdown of accessible portions of the system, and
discussions with cognizant system and design engineers. The review also included:
verification of the appropriateness and correctness of design assumptions;
confirmation that design bases were consistent with the licensing bases; and
verification of the adequacy of testing requirements.
b. Observations and Findinas
Mechanical and Electrical Desian
1
The team reviewed some calculations and safety analyses that support the CSS and
ESW system functions and found them generally thorough and accurate, although in
some instances, the reasons for selecting assumed values or initial conditions were
not always cbvious. In those instances, amplification by engineering department
personnel was necessary to fully understand the approach taken in analysis and
why the values used were correct and conservative. For example, the original
design flow assumed for analysis of the CSS was 3,000 gpm. Since initial
construction, system modification and procedural change have increased the actual
flow to rubstantially higher values. In the surveillance procedure, if CSS flow is
below~4,100 gpm, action is required to investigate and to increase system flow, in
various analysis of the CSS system, assumed flows ranged from 3,000 gpm to
4,100, gpm depending on the situation being analyzed. Generally, the reason for
the value assumed for analysis or calculation was not always fully developed. In
response to this, the licensee issued a deviation report regarding potential
inconsistencies between existing calculations that support the CSS and ESW
systems. DVR 98-0191, issued on February 25,1998, seeks to resolve the fact
that several active calculations covering the CSS and ESW systems have
discrepancies with each other and with the FSAR. These calculations were
reviewed by the licensee with applicability to correct design basis information and
found not to impact plant safety. The team independentlyi did not identify any
impact on plant safety either.
.
i
1
1
9
CSS and ESW system pump motors and applicable valves were found to be
appropriately powered from vital 460 volt motor control centers (MCCs) and
provided with backup power from their respective emergency diesel generators
(EDG). The team verified that associated motor load requirements and manual
starting sequence time were adequately reflected in the EDG loading calculation.
The team reviewed the system logic and identified no discrepancy. The team
verified that all the applicable system components associated with the CSS and
ESW pumps were consistent with the UFSAR requirements.
A significant modification was accomplished in 1993, that changed CSS from
automatic to manualinitiation. The team reviewed this modification and found that
it was properly analyzed, implemented and documented. The UFSAR, operating
procedures and emergency operating procedures were all revised appropriately to
reflect the changes in system operation. Instrumentation and controls were
provided to enable operators to manually initiate and trip the system as required.
As a follow up to seismic concerns addressed in NRC GL 87-02, Verification of
Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors,
and USl A-46, Seismic Evaluation Report, the licensee conducted system
walkdowns in 1994. During the walkdowns, the licensee identified a number of
seismic outliers associated with safe shutdown equipment including the
containment spray heat exchangers. In late March 1996, the licensee submitted to
the NRC, " Oyster Creek Nuclear Generating Station USl A-46 Seismic Evaluation
Report (Report #42112-R-001). This report (the summary report) was in response
to NRC Generic Letter 87-02 that encouraged utilities to participate in a generic
program to resolve the seismic verification issues associated with USl A-46. The
purpose of the report was to describe the results of the seismic reviews performed
to resolve USl A-46. The licensee's summary report indicated that the CSS heat
exchanger outlier had been resolved. However, the resolution of this outlier was
based on a preliminary licensee calculation which had not been design verified as
required by the licensee's procedure, EP-06. The initial calculation in the design
verification process to resolve this issue was completed in January 1997. From
January 1997 to February 1998, a number of administrative and technical issues
delayed the completion of the design verification process. A new analysis was
begun on February 2,1998 to resolve this issue, and is expected to be completed
by the end of June 1998. At the time of this inspection, the NRC had not been
notified of the change in the status of this outlier. As a result of the NRC Team
identifying this discrepancy, the licensee agreed to review the SOUG summary
j report to determine which other outliers have incomplete documentation and to
( revise the summary report accordingly. The failure to properly perform a design
verification of the CSS heat exchanger seismic calculation as required by Procedure
EP-06,is a violation of 10 CFR 50, Appendix B, Criterion V. (VIO S0-219/98-80-
05)
l
l
l
L. .
10
l- System Walkdown
,
The team performed walkdowns of selected portions of the CSS and ESW systems.
'
Piping and mechanical components, piping interfaces with the service water system
and installation of instrumentation and electrical components were examined to
verify consistency with plant drawings. The team also examined the control room
instrumentation for monitoring CSS and ESW systems operation. The material
condition of the system and general housekeeping were good. Some discrepancies
that presented seismic concerns were noted involving: Chain hoists inadequately
stored on or in the vicinity of the CSS heat exchangers; and a neutron shield located
l
about one-inch from the CSS supply piping at the vicinity of drywell penetration
X66 for the CSS system.
i
!
Regarding the neutron shield, the licensee stated that it had been in place since
initial plant construction; however, the licensee was unable to identify any
documentation that describes the seismic adequacy of the shield. During the course
of the inspection, the licensee performed calculation SQ-OC-153-001 and concluded
l
that the shield support will not displace and that the containment spray piping and
! the support will remain intact during a postulated seismic event at Oyster Creek.
The team reviewed this analysis and identified no discrepancy, and accepted the
l resolution of the concern with the neutron shield. However, the team noted that
l the licensee's configuration control process was weak since the licensee had not
assessed the adequacy of the configuration until questioned by the team.
With respect to the chain hoist near the heat exchanger, the licensee stated that a
walkdown was scheduled to closeout the item, but had not been completed.
Shortly thereafter, a walkdown was completed by a structural engineer and it was
!
determined that the actions specified in Job Order 61509 were not adequate to
resolve the discrepancy. Further reviews by the team revealed that CSS walkdowns
,
conducted in August 1994 by the licensee utilizing SOUG methodology identified
! outlier conditions with respect to suspended chain hoists in the vicinity of the CSS
heat exchangers. This condition was documented in SOUG packages SQ-OC-H-21-
l 001 A and B, dated August 17,1994, wherein the outlier condition was described
l as " chain hoists in the vicinity of the heat exchangers need to be restrained due to
impact concerns." The proposed method of outlier resolution was to " modify chain
I
hoists or remove." in response to this condition, job order 61509 was issued on
i July 16,1996 and completed on December 6,1996; however, the corrective action
!
. was not verified as completed. Accordingly, on March 5,1998,the licensee then
l issued and completed another work request (776527)that corrected the improper
storage of the chain hoists.
l '
l- The team noted that seismic outliers continued to exist with respect to the
l containment spray system heat exchangers, storage of chain hoists on or around
the heat exchangers and the containment spray pumps. The initial work order
issued to correct the condition of the improperly stored chain hoists was not
adequate to correct the nonconforming condition. Further, the action to verify the
adequacy of the corrective action completed in December 1996 was not adequate.
This failure to implement prompt and adequate corrective action to resolve concerns
with seismic adequacy of safety related components is a violation of 10 CFR 50,
Appendix B, Criterion XVI. (VIO 50-219/98-80-06)
.
!
11
Updated Final Safety Analysis Reoort
The team reviewed the applicable FSAR sections for the CSS and ESW systems,
interf acing systems, and the associated electrical and instrumentation and controls
l sections, to verify consistency between the UFSAR, TS descriptions, and design
documentation. The following discrepancies were identified:
j * The UFSAR contained no discussions of the fact that 5% containment spray is
l diverted to torus spray during system activation, although this 5% diverted
l flow is taken into account during accident analysis and analytical calculations.
The licensee stated that a discussion of the 5% torus spray flow will be
l
included in a subsequent UFSAR revision.
- Section 1.2.2.2 of the UFSAR has not been updated to reflect the deletion of
the dynamic test mode from the containment spray system.
!
l * Table 6.2-7, " Containment Spray Heat Exchangers," has not been updated to
l reflect a 95*F tube side inlet temperature. The table footnote indicates that the
listed value of 85*F was derived from the vendor's heat exchanger
specification sheet; however, maximum inlet temperature has been revised
upward to 95*F.
The licensee indicated that they had a major effort ongoing to review and update
the UFSAR. None of these discrepancies presented an unreviewed safety question
and the team did not identify any immediate safety concerns with them, and was
satisfied with the licensee's ongoing efforts to resolve the issues.
c. Conclusion
The Containment Spray and Emergency Service Water Systems were maintained
operable and capable of performing their safety functions including during a loss of
offsite power and a single active failure. Surveillance testing of system cornponents
were conducted in accordance with existing procedures. The CSS and ESWS
instruments were properly calibrated and maintained. While initial conditions and
the basis for some assumptions were not always obvious, calculations and safety
analysis adequately supported implemented modifications. The team identified that
some pertinent design information in the UFSAR required updating. The licensee
was aware of this and already had efforts ongoing to update the UFSAR. However,
with regard to the resolution of seismic deficiencies, there was untimely follow up
and reporting to the NRC the status of SQUG outliers. Also, two discrepancies that
resulted in violations were identified as follows:
- Failure to adequately correct a seismic deficiency with a containment spray
heat exchanger as of February 26,1998, as required by 10 CFR 50, Appendix
B, Criterion XVI, Corrective Actions. (section E2.2)
)
.
l
12 l
e Failure to verify design calculations that supported the seismic adequacy of
safety related equipment as required by procedure EP-06 and 10 CFR 50,
Appendix B, Criterion V, Instructions, Procedures, and Drawings. (section
E2.2)
,
E3 Engineering Procedures and Documentation
!
E3.1 10 CFR 50.59 Safety Evaluation Proaram
l
l
'
a. Insoection Scone (37001)
The team reviewed selected procedures and held discussions with GPUN
representatives to Mermine: (1) if proper procedural guidance has been
established for implementing the requirements of 10 CFR 50.59 for proposed
changes, tests and experiments (CTEs); and (2) if proper procedural guidance has
been established for updating the Final Safety Analysis Report (UFSAR), as required
by 10 CFR 50.71(e).
b. Observations and Findinas
The inspectors reviewed several corporate and division procedures which provide
guidance and responsibilities related to 10 CFR 50.59 and 10 CFR 50.71(e) J
requirements for OCNGS. The three administrative procedures defining the 10 CFR
'
50.59 program at OCNGS are corporate procedure,1000-ADM-1291.01, l
engineering division procedure,5000-ADM-1291.01(EP-016) and Oyster Creek !
division procedure,130. Procedure 1000-ADM-1291.01 implements and controls
the GPU Nuclear Safety review and approval process and applies to all divisions of
GPU Nuclear. The procedure was up to date in incorporating revised industry and
NRC 10 CFR 50.59 guidance and GPUN self assessment findings. Procedure 5000-
ADM-1291-01 provides the Engineering Division basis and method for determining
whether a proposed change to TMI-1, TMI-2 or OC nuclear facility activities or
documents would adversely effect existing safety or environmental conditions,
including those governed by the site's Final Safety Analysis Report or Technical
Specifications. In addition, the procedure provides guidelines for complying with
10 CFR 50.59 and is used in evaluating acceptability of existing plant conditions.
Procedure 130 implements the GPU nuclear safety review and approval process for
the Oyster Creek Division and provides guidance for personnel involved in the
preparation and review of documents covered by the procedure. The procedures
contain appropriate requirements on the performance of 10 CFR 50.59 safety
reviews.
However, the team identified two weaknesses in the program as follows: In one
instance, most of the corporate procedure enhancements had not been reflected in
the Oyster Creek and Engineering Division 10 CFR 50.59 implementing procedure.
In the other instance, no GPU Nuclear corporate or division procedure provided
, guidance for formally reporting to the NRC the CTEs made in accordance with
Section 50.59 as required by 10 CFR 50.59(b)(2). The licensee indicated that
efforts were ongoing to improve the program. The team identified no other
significant discrepancy.
13
c. Conclusions
in the 10 CFR 50.59 program area, procedures were found to be comprehensive
and detailed in providing guidance and assigning responsibility for implementing the
requirements of 10 CFR 50.59 and updating the UFSAR. The procedures were also
up to date in incorporating revised industry and NRC 10 CFR 50.59 guidance and
GPUN self assessment findings.
, ,
L
E3.2 Imolementation of 10 CFR 50.59 Proaram
a. Insoection Scope (37001)
The team reviewed some safety evaluations (SEs) performed by OCNGS in
accordance with 10 CFR 50.59 to determine if the SEs for plant permanent and
temporary modifications, and procedure changes addressed all safety issues
pertinent to the associated modifications or changes, and did not involve an
unreviewed safety question (USO).
b. Observation and Findinas
The team reviewed some Safety Evaluations involving the Automatic
Depressurization System, Core Spray, Emergency Service Water, and Containment-
Spray Systems. The team also reviewed selected CTEs for which the licensee had
determined that 50.59 safety evaluations were not required to verify that the
applicability determinations for these CTEs were made in conformance with the
50.59 procedures and controls. The team reviewed a sample of procedure changes
and determined that the evaluations were in accordance with OCNGS procedures in
that they reached the appropriate conclusions. Appropriate 50.59 applicability
determinations were made.
The team reviewed the training and qualification program for personnel involved
with the safety evaluation process to determine the quality of trainir.g and evaluate
the certification status of licensee's responsible technical reviewers (RTR) and
independent safety reviewers (ISR). Training and certification requirements have
been consistent with the commitments established in GPUN corporate plan 1000-
PLN-7200.01, GPU Nuclear Quality Assurance Plan. The inspector reviewed initial
and refresher training materials for some RTR and ISR and founce that they had been
trained in accordance with the program requirements to perform safety
determinations and safety evaluations. GPUN kept abreast of industry safety
evaluation guidance and participated in industry wide Nuclear Energy Institute (NEl)
licensing issues. Safety evaluations were prepared and reviewed by individuals who
had received training regarding the preparation and review of SEs in accordance
with the facility procedure.
. .
. _ _ _ _ _ _ _ _ _ _ _ _ _ _ -
.
.
.
14
The inspector noted in a few case that while the evaluations met the requirements
of the facility procedures, there were weakness in the thoroughness and
documentation by the preparer and/or reviewers. For example:
o Safety evaluation SE-402140-OO1, evaluated a modification to install additional
monitoring equipment, differential pressure gauges, in the Emergency Service
Water (ESW) System. The SE was completed on July 22,1983. During a
licensee assessment of the ESW system using NRC Temporary Instruction
2515/118, Rev 1, the licensee identified that the fittings used during the
modification did not meet the design pressure specifications for the ESC
system. As a result, the licensee issued a revision (Rev.1) to the SE justifying
the use of the fittings. The inspector pointed out some mistakes in the revised
SE regarding the design and maximum pressures of the fittings. As a result the
licensee issued a deviation report, DR 98-0210,to resolve the issue.
e Safety Evaluation SE OOO531-021, evaluated the replacement of the ESW keep
full throttle valves. The original SE was revised (Rev.1) in response to
deviationJeport, DO 97-1029,which recognized that the SE did not address
the possiole malfunction of a different type or possible reduction in a margin to
safety. This was licensee identified and corrected, however, the original
package contained a memorandum from Environmental Affairs identifying the
need for the Chemistry Department to review the proposed change to ensure
the discharge limit for total residual chlorine in the service water /ESW was not
exceeded. The licensee provided some meeting notes and e-mail that indicated
that some discussion of the chlorination flow took place, however, they did not
have an evaluation or calculation to ensure that they will not exceed the
applicable limit.
The team identified a discrepancy in the program implementation that, although
minor, was widespread. In several instances, the RTR and/or ISR did not make a
complete and appropriate Mtry in the signature block of the SE forms by printing
their name, in addition to signing their name, as required by Engineering Division
Procedure, EP-016, Nuclear Safety / Environmental Determination and Evaluation.
Interviews with some of the individuals conducting the reviews revealed that there
was not a consistent application of procedure (s) by the reviewer. This lack of
consistency in implementation of the procedure resulted in several instances of
failure to follow procedure. Procedure EP-016 prescribes the requirement for
implementing activities affecting quality as required by 10 CFR 50, Appendix B,
Criterion V, Instructions Procedures and Drawings. These instances of failure to
follow procedures represented another example of a violation of NRC requirement.
(VIO 50-219/98-80-05)
. .
.. . .
. _ _ _ _ _ _ _
. _ _ _ _ _ _ .
._ . ..
.
15
10 CFR 50.59 Reoortina Reauirements
The team reviewed the facility submittals pursuant to 10 CFR 50.59(b) from
November 1982 to present. The licensee, in a letter dated November 5,1982,
submitted a report covering calendar years 1980 and 1981. In the report, the-
licensee acknowledged the untimeliness of the report and attributed it to the
transfer of reporting responsibilities from Jersey Central Power to GPU Nuclear
Corporation. No report was submitted in 1983 as required by 50.59(b) and the
" annual" report filed on March 1,1985, covere J calendar year 1983. There was no
report filed in 1986 as required by 10 CFR 50.59(b). The March 30,1987, report
covered calendar year 1984, and the reports filed on June 30,1987, and
October 30,1987, covered calendar years 1985 and 1986, respectively. Annual
reports were filed thereafter that covered the preceding year through 1993. The
annual report filed on February 16,1998, covered the period April 1993 to March
1995. This report did not meet the reporting requirements of 10 CFR 50.59(b). To
address all these discrepancies, the licensee plans to make an additional report this
summer to bring them current with the reporting requirements of 10 CFR 50.59(b)
and put them on a reporting schedule consistent with 10 CFR 50.71(e) as permitted
by 50.59(b). However, the repetitive nature of this issue as shown by the
licensee's failure to submit CTE reports for 1983 and 1986 and failure to submit
timely reports for 1993 through 1996, constitutes a more than minor f ailure to
adhere to the requirements of 10 CFR 50.59(b)(2). (VIO 50-219/98-80-07)
c. Conclusions
10 CFR 50.59 Safety Evaluations (SEs) were of good quality and performed in
accordance with the requirements of 10 CFR 50.59 and the applicable procedures
by qualified and certified personnel. However, some SEs exhibited a lack of
thoroughness and attention to detail that was expected by the f acility procedures.
Two violations were identified as follows:
e Failure to submit the required changes, test, and experiments reports in 1983,
1986, and 1998 as required by 10 CFR 50.59(b) and 10 CFR 50.71(e).
(section E3.2)
e Failure to comply with procedure EP-016 for Safety Evaluations on several
occasions as of February 26,1998, as required by 10 CFR 50, Appendix B,
Criterion V, Instructions, Procedures, and Drawings. (section E3.2)
Overall, the quality of the 10 CFR 50.59 training program for certification of RTR
and ISR was excellent. The contents of the training were appropriate and supported
the OCNGS review process that is being implemented. Safety evaluations were
prepared and reviewed by individuals who had received training regarding the
preparation and review of SEs in accordance with the facility procedure.
.. ..
_ _ _ _ _ _ .
.
'
i
16
E7 Quality Assurance in Engineering Activities
>
' E7.1 Problem Identification, Resolution Prevention, and Corrective Actions
a. insoection Scoos (IP 40500)
The team evaluated the effectiveness of OCNGS controls in identifying, resolving,
and preventing issues that could affect the quality of plant operations or safety.
The controls included: corrective action programr; root cauae analysis programs;
independent onsite and offsite safety review grou,u; independent safety oversight; ,
self assessment activities; and the process that provides for the incorporation of
operating experience feedback.
b. Observations and Findinas
Corrective Action Proaram
)
Plant Procedure 104 " Control of Non-Conformance and Corrective Actions" Rev. 25
dated 11/17/97 provided the overall purpose and responsibilities of the deviation
report (DR) process. This process was to ensure events and situations which may
require further review, reporting, or corrective actions were identified, controlled, l
documented and evaluated. And also, to ensure that deviations which could affect
operability were identified and operability determinations made and documented.
The team reviewed the procedure and found that it adequately described the
deviation report process requirements.
The team reviewed, on a sampling basis, DVRs that had been generated during the
period January 1996 through early March 1998. Based on this review, the team
determined that appropriate operability determinations had been made. In addition,
each of the issues identified in the DVR had received an acceptable management i
review with respect to safety and the appropriate level of attention needed to I
identify causes and put into place effective corrective actions. In one instance,
when the team questioned the acceptability of the placement of electrical jumpers in !
the reactor protection system (RPS) to bypass the scram function of the mode
switch in shutdown, the licensee prepared a DVR addressing the issue and promptly
- made a notification to the NRC in accordance with 10 CFR 50.72. The DR was
given the appropriate level of management review in accordance with the corrective
action program requirements. In addition, a plant review group (PRG) meeting was ;
promptly scheduled to discuss this issue. Individual team members attended this
meeting and observed the licensee personnel discuss the issue in detail. The
licensee was able to determine that their practice was acceptable via a 1977 SER
(and TS Amendment) that had been approved by the NRC. However, this was not
properly reflected in the current technical specification. The licensee indicated that
the TS will be clarified to properly reflect the acceptability of the practice. The -
licensee properly followed their corrective action program requirements and
adequately evaluated, and documented this issue. The licensee subsequently
retracted the 10 CFR 50.72 notification.
.
.
17
The team determined; based on discussions with the training manager, that
corrective action training was conducted as part of general employee and licensed
operator training. Based on discussions with licensee staff, the team determined
the various staff members were generally knowledgeable of the corrective action
process.
Root Cause Analysis Prooram
The tea [n reviewed the process for ensuring that appropriate root cause
determinations are perfumed for identified problems. While the individuals making
root cause determinations were not required to be trained in root cause
determinations, all root cause determinations that were reviewed by the team
indicated that the determination were made correctly by trained personnel.' In
addition, based on discussions with licensee personnel, it was determined that there
was a management expectation that a person trained in root cause determinations
be on the team that makes such determinations.
Trendina of Deviation Reports
l
The status of DVRs are trended by the safety review group from a computerized
! data base. A periodic trending report is distributed to management. The team
l reviewed several of these reports and found they provided important and meaningful
information concerning the status of the corrective action program. Those DVRs
with extended required due dates are also tracked, and this information is
specifically provided to senior plant management. The safety review group also
provides a listing of all open DVRs to department heads on a routine basis. These
reports are discussed at the routine deWation report meetings and the routine
trending group meetings. The trending group conclusions are made part of the
routine trending reports. In addition, the system engineers are given a report of
each DR written on their system (s) and are requested to evaluate these DVRs and
advise the safety review group of any developing negative trends. The team
sampled several of the system engineer reports, including the associated DVRs, and
found the reports to be detailed.
The team reviewed the DR report status from January 1997 to January 1998. The
periodic trending report listed the number of DVRs that were issued and closed for
each month. As of January 1998, a total of 331 DVRs were still open. Of these,
50% were from the engineering department,12% from operations,14% from the
maintenance department,7% from the logistical support group and the other
stations groups accounted for 17% of the open DVRs. Also,84 of the open DVRs
were significant and had elapsed due dates. The team conducted a review on a
sampling basis of those DVRs and determined that adequate management attention
had been directed to track, trend and close them. No significant discrepancies were
identified.
.
4
18
Indeoendent Safetv Oversicht
There are three elements of oversight at OCNGS: (1) the independent Safety !
Oversight Review Group (ISORG): (2) Nuclear Safety Assurance (NSA); and (3) l
General Office Review Board (GORB). The ISORG has no line responsibilities or line
functions, and is devoted solely to safety matters. It is independent of the plant
staff and reports offsite to the Director - Nuclear Safety Assessment. The Nuclear
Safety Assurance (NSA) audits, monitor and assess aspects of GPUN activities
within the scope of the GPUN Operating Quality Assurance Pisn or relating to
safety. This process provides for an overview of activities affecting or pctantia!!y
affecting safety. The GORB reports to and takes general direction from the GPUN
President, but has direct access to the Chairman of the Board and Board of
Directors. Its charter is broadly defined to encompass all matters potential affecting i
nuclear safety and radiation problems. NSA provides staff support to the GORB. l
l
The ISORG assessment topics were appropriately selected based on ongoing review l
and prioritization of site, industry and NRC safety concerns that could potentially
impact OC performance. The assessment reports clearly described the assessment
purpose and scope, the results of in-depth technical reviews of the selected topics,
and recommendations that were being tracked via the station action item tracking
system.
1
The inspectors reviewed the minutes of GORB meeting numbers 163 through 167,
which were conducted between February 1997 and February 1998. The meetings ;
included appropriate briefings by GPUN directors and OC department manager of
the plant status and issues since the prior GORB meeting and detailed discussions l
of major activities and projects that were receiving senior management attention.
GORB reports contained detailed descriptions of the topics discussed and
recommendations resulting from GORB oversight reviews. The meetings included
appropriate discussions of diverse topics related to operations, maintenance,
engineering and plant support issues and concerns. )
i
The reports and activities were focused and appropriately critical. Both positive and
negative performance was emphasized for a balanced picture of OC strengths and
weaknesses. Issues that were identified by the ISO organizations were responded
to by plant management and evaluated for propor action depending upon the nature l
of the concern.
Self Assessment
The inspectors reviewed completed audits performed by the NSA department
addressing the corrective action program (Audits O-COM-96-03,0-COM-97-01, and
S-COM-97-07) and the safety review program (Audit S-OC-97-07). The audits were
performed at the proper frequency, and addressed performance as well as
compliance-related issues. The corrective action and safety review audits were of
good quality and the audits were properly implemented in accordance with
corporate policy 1000-PLN-72OO.1,GPU Nuclear Operational Quality Assurance
Plan, Rev.10, and adrninistrative procedure 1110-ADM 7218.01, Nuclear Safety
. . .- . . . .
.
.
.
19
Assessment Audit Program, Rev. 2. The audits reviewed pertinent procedures,
records and departmental performance and included review of corrective actions
and management requested items. Significant findings were documented in
deviation reports for departmental response and corrective action development.
Audit findings received appropriate division management attention.
.The inspectors reviewed GPU Nuclear Assessment Report No. 6750-97-001,
OCNGS Safety Review Process implementation, May 1997. The report documented
1 special self-assessment conducted to review the effectiveness of the safety
review process with specific focus on the safety determination (SD) element of the
process at OCNGS, in response to SD inadequacies described in four recent NRC-
identified findings (unresolved item 96-07-04 and violations 96-09-02,96-11-01
and 96-12-01).
The initial procedure for implementing the self-assessment program, which became
effective on February 16,1998, provides detailed guidance and instructions and
appropriate responsibilities, based on extensive review of current industry and
consultant documents and input from other nuclear generating stations and
companies. The formal program implementation was determined to be too new to
assess the quality of self-assessments by line organizations.
Operatina Exoerience Review Prooram
Plant procedure 2OOO-ADM-12OO.02" Operating Experience Review Program" Rev 0
dated 3/20/95 provided the overall purpose and responsibilities for the operating
experience review program. This program was to establish a consistent method for
screening, evaluating and distributing industry and plant information to the
appropriate staff members. Also, pertinent information was to be tracked and
trended for management review and action as appropriate.
The team noted that a NSA audit had correctly identified that this program was not
implemented in such a manner that all managements expectations were met.
However, based on a review of records and interviews with personnel, the team
determined that the licensee actively participated in the sharing of pertinent
operating experience information using the nuclear network. Also, the operating
experience computer data base was used to enter both NRC and industry
organizations operating experience information and personnel interviewed were
aware of recent industry events. The team concluded that although not all
management expectations were met concerning the program issues, industry
operating experience was adequately used at the plant.
.
.
20
c. Conclusions
in the Correction Action Program area, Deviation Reports (DVR) reflected
appropriate operability determinations, and management attention necessary to
identify causes and put into place effective corrective actions. The Corrective
' Action training process was acceptable and staff members were generally
knowledgeable of the corrective action process. The trending of DVRs was
adequate and provided meaningfulinformation to management. Although not all
management expectations were met concerning the program issues, industry
operating experience was adequately used at the plant.
The assessments and evaluations of the independent Safety Oversight Review
Group, the General Office Review Group, and Nuclear Safety Assessment staff were
effective in providing independent oversight of safety significant activities at
OCNGS. The experience of the Independent Safety Oversight members, both
industry-wide and site-specific, was a significant contributor to the value of their
products. Management appeared to be full supportive of the oversight groups and
were responsive to their recommendations.
The corrective action and safety review audits were of high quality. Audit findings
received appropriate division management attention. The May 1997 safety review
process assessment was self-critical and probing. The NSA audit and assessment
reports were effective in providing GPU Nuclear management independent ~
identification of significant findings and appropriate recommendations for process
improvements.
V. Mananoment Meetinas
X1 Exit Meeting Summary
On March 20,1998, the NRC held an exit meeting with members of GPUN at the Oyster
creek Nuclear Generating Station to discuss the findings of this inspection. The licensee
acknowledged the inspection findings. A list of those present at the exit is shown below.
Following additional inspection conducted between March 30 and April 2,1998, another
exit meeting was held via a telephone conference call on April 8,1998.
!
i
.
.
21
PARTIAL LIST OF PERSONS CONTACTED
.
Licensee
- + G. Busch, Manager, Nuclear Safety & Licensing
M. Roche, Director, Oyster Creek
- + D. Slear, Director, Configuration Control
- + R. Tilton, Manager, Assessment
. P. Scallon, Manager, Safety Review
R. Baron, Safety Review Engineer
- + B. DeMerchant, Licensing Engineer
T. Corcoran, Plant Operations Engineer
K. Mulligan, Plant operations Director .
D. Croneberger, Director, Equipment Reliability
- + S. Schwartz, System Engineer
- J. Frank, System Engineer
- + D. Meisiero, Manager, Technical Support
- T. Wiggins, Media Relations
- + D. Kelly, Licensing
- + M. Godknecht, Engineering
- P. Burke, MTCE
J. Logatto, Engineering '
- + S. Levin, Director, Operations & Maintenance
+ A. Agarwal, Manager, EP&l
+ D. McMillan
NRC
S. Pindale, Resident inspector
"J. Schoppy, Senior Resident inspector
- E. Kelly, Branch Chief, DRS
- W. Axelson, Deputy Regional Administrator
+ N. Perry, Project Engineer
Others
R. Pinney, Nuclear Engineer, New Jersey DEP
- Denotes those present at the March 20,1998 Exit Meeting.
.
+ Denotes those present on the April 8,1998 telephone conference call.
INSPECTION PROCEDURES USED
Procedure No. .Tji. tin
37001 10 CFR 50.59 Safety Evaluation Program
40500 Effectiveness of Licensee Controls in Identifying, Resolving, and
Preventing Problems
93809 Safety System Engineering Inspection
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - - _ _ _ - _ _ _ _ _ _ _ . _ - _ _ _ _ _ _ _ _ _
,
.
.
i 22
l ITEMS OPENED, CLOSED AND DISCUSSED
Ooened
Number Tvoe Descriotion
50-219/98-80-01 VIO Failure to verify ADS operability as required by TS 3.4.B.1. (Section E2.1)
1
50-219/98-80-02 eel Failure to ensure adequacy of the voltage for the EMRV l
solenoid as required by 10 CFR 50, Appendix B,
Criterion 111, Design Control. (section E2.1)
50-219/98-80-03 eel Failure to verify that the EMRV solenoid voltage was in
accordance with the EQ documentation as required by
10 CFR 50.49, EQ. (section E2.1)
50-219/98-80-04 eel Failure to maintain ADS operable as of March 19,1998,
l as required by Technical Specification 3.4.B.1, ADS.
l
50-219/98-03-05 VIO (1) Failure to perform a design verification of the CSS heat 1
exchanger required by EP-06 (10 CFR 50, Appendix B, l
Criterion V). (Section E2.2)
,
(2) Failure to follow procedure EP-016 as required by
10 CFR 50, Appendix B, Criterion V. (Section E3.2)
50-219/98-80-06 VIO Failure to implement adequate corrective actions for
l improperly stored chain hoist around a CSS heat
l
exchanger as required by 10 CFR 50, Appendix B,
Criterion XVI. (Section E2.2)
50-219/98-80-07 VIO Failure to submit CTE reports for 1983 and 1986 as
required by 10 CFR 50.59(b)(2). (Section E3.2)
l
l
l
! .
i
.
4
I
,
.
23
LIST OF ACRONYMS USED
ADS Automatic Depressurization System
CFR Code of Federal Regulations
CTE Changes, Tests and Experiments
DOO Determination of Operability
DRP Division of Reactor Projects
DRS Division of Reactor Safety
DVR Deviation Report
EDG Emergency Diesel Generator
EMRV Electromatic Relief Valve
EQ Environmental Qualification
ESW Emergency Service Water
GORB General Office Review board
GPUN General Public Utilities (GPU) Nuclear
l&C Instrumentation and Control
IP inspection Procedure
ISORG Independent Safety Oversight Review Group
ISR Independent Safety Reviewer
IST Integrated System Test
MCC Motor Control Center
NEl Nuclear Energy Institute
NRC U.S. Nuclear Regulatory Commission
NRR Office of Nuclear Reactor Regulation
NSA Nuclear Safety Assessment
OCNGS Oyster Creek Nuclear Generating Station
PDR Public Document Room
PRG Plant Review Group
RTR Responsible Technical Reviewer
SE Safety Evaluations
SQUG Seismic Quality Utility Group
TSCR Technical Specification Change Request
UFSAR Updated Final Safety Analysis Report
USl Unresolved Safety issue
USQ Unresolved Safety Question
VMS Valve Acoustical Monitoring System
i