ML20059F625

From kanterella
Jump to navigation Jump to search
Insp Rept 50-219/93-22 on 930920-24.No Violations Noted. Major Areas Inspected:Addressed Open Items Associated W/Eop & Reviewed Licensee Actions in Response to Violations Associated W/Recirculation Loop Isolation Event
ML20059F625
Person / Time
Site: Oyster Creek
Issue date: 10/28/1993
From: Conte R, Walker T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20059F613 List:
References
50-219-93-22, NUDOCS 9311050018
Download: ML20059F625 (13)


See also: IR 05000219/1993022

Text

.

i

.

1

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

REPORT NO:

93-22

.1

FACILITY DOCKET NO: 50-219

t

FACILITY LICENSE NO: DPR-16

LICENSEE:

GPU Nuclear Corporation

P. O. Box 388

Forked River, New Jersey 08731

FACILITY:

Oyster Creek Nuclear Generating Station

INSPECTION AT:

Forked River, New Jersey

INSPECTION DATES:

September 20-24,1993

INSPECTORS:

D. Florek, Senior Operations Engineer

/

f

'

!M

/s/2 M G

'

LEAD INSPECTOR:

/T'. WalkkSenior' Operations Engineer

Date '

BWR Section, Operations Branch

Division of Reactor Safety

/#k/h3

APPROVED BY:

'

' Richard J. Conte,[hief

_

Date

.BWR Section, Operations Branch

Division of Reactor Safety

'

1

4

.

.

9311050018 931029

l

PDR

ADOCK 05000219

,

O

PDR

-

.

.

.

. -

. .

--

-

--

.

. .

1

.

i

a

2

Inspection Summarv (50-219/93-22J:

This was a special announced inspection of the Oyster Creek Emergency Operating

Procedure (EOP) program and other open issues. The objectives of the inspection were to:

(1) address the open items associated with the EOPs and nonlicensed operator (NLO) training

identified in Inspection Report No. 50-219/92-02; (2) to review the licensee's actions in

response to violations associated with the recirculation loop isolation event identified in

Inspection Report No. 50-219/91-29; and (3) to review an unresolved item related to reactor

water level instrumentation mismatch identified in Inspection Report 50-219/92-18.

The licensee has significantly improved the program for development, implementation, and

maintenance of the EOPs and support procedures. They have developed complete and

detailed procedures for control of the EOP program. The EOP Committee and initiatives

that they have undertaken indicate strong management involvement in the program and

commitment to maintenance of high quality procedures. No significant problems were

identified with the EOPs or the verification and validation that was performed on the latest

revisions; however, some potential shortcomings were identified with the licensee's practices.

The operators performed well on the EOP simulator exercises and no technical concerns

were identified with the EOPs. The inspector questioned whether the procedures and

.

training provided to the operators could be improved to provide more timely implementation

of radiation release mitigation actions. A formal procedure for NLO on-the-job training has

been developed and is being implemented. Training is provided to the NLOs on tasks that

they are responsible for during emergencies. The unresolved items related to the EOP

program and NLO training are closed (Paragraphs 2.0,3.0, and 4.0).

The licensee is making an ongoing effort to improve procedure compliance with training,

focus on human performance, and a procedure upgrade program. The licensee clarified the

procedural guidance for conducting a plant cooldown with the MSIVs closed by developing a

,

new procedure and revising system operating procedures. These procedures are adequate;

however, the inspector was concerned that there were still some aspects of the procedures

that could cause confusion. There were no concerns with the licensee's review of the event

and specific corrective actions; however, no corrective actions were taken to improve the

process for tracking internal corrective actions and commitments to preclude conditions

'

adverse to quality (Paragraph 5.0).

The licensee completed the actions recommended by General Electric SIL No. 470 to address

,

the mismatch in reactor water level instruments. The unresolved item related to completiori

of these actions is closed (Paragraph 6.0).

>

C

_

_

'

,

.

DETAILS

1.0

INTRODUCTION

During an Emergency Operating Procedure (EOP) followup inspection in January 1992,

NRC inspectors determined that the licensee's programmatic approach for development,

implementation, and maintenance of the EOPs was weak. The inspectors also noted

deficiencies in the nonlicensed operator (NLO) training program. Similar deficiencies had

been noted in two previous EOP inspections. The results of the January 1992 inspection

were documented in Inspection Report No. 50-219/92-02. The licensee responded to these

items in a letter dated April 24,1992, and indicated improvements that had been made or-

were planned for the EOP program and NLO training. Many of the licensee's actions were

dependent on the plant-specific simulator, which was not available for use onsite until early

1993. A meeting was held at the NRC Region I office on May 5,1993, to discuss the status

of the EOP program. The licensee indicated that the improvements and corrective actions

had been implemented. One of the purposes of this inspection was to address the unresolved

items identified in the January 1992 EOP inspection related to the EOP program and NLO

training. An additional objective of this inspection was to evaluate the technical adequacy of

the EOPs and the operators' ability to use the EOPs in a dynamic setting on the plant-specific

simulator.

A followup inspection of a recirc loop discharge valve isolation event in September 1991

identified violations of NRC requirements and an unresolved item related to correcting

problems prior to plant restart. The results of the inspection were documented in Inspection

Report No. 50-219/91-29. The licensee was asked to address the repetitive nature of the

recirculation loop isolation event and the repetitive nonadherence to facility procedures. The

licensee responded in a letter dated January 31,1992, and indicated that personnel error was

the dominant cause in the three recirculation loop isolation events with procedural problems

as a contributing cause. The licensee cited a continuing effort to reduce the frequency of

^

procedural noncompliance and had a differing viewpoint on several of the procedure

noncompliances noted by the NRC. A meeting was held in the NRC Region I office on

March 23,1992, to discuss the licensee's position. As a result of the meeting, the NRC

retracted one violation and portions of another violation. One of the purposes of this

inspectior was to review the licensee's actions in response to the remaining violations related

to the recuc loop isolation event and to review the unresolved item related to review of the

event.

I

During an inspection in August 1992, an NRC inspector reviewed the licensee's response to

industry information related to reactor water level instrumentation. The review focused on

the site specific problem of the B GEMAC reactor water level indicator reading 5 to 10

inches higher than other reactor water level instruments. An unresolved item was identified

<

related to the licensee's response to General Electric (GE) Information Letter, SIL No. 470.

The results of the inspection were documented in Inspection Report No. 50-219/92-18. One

i

-

,

.

4

of the purposes of this inspection was to review the licensee's actions on GE SIL 470 to

resolve the unresolved item related to reactor water level instrumentation mismatch identified

in Inspection Report No. 219/92-18.

2.0

EMERGENCY OPERATING PROCEDURES PROGRAM

Scope

The inspectors reviewed the licensee's procedures for EOP program control and for

verification and validation (V&V) of EOP program documents. The EOP program and the

V&V process were discussed with licensee personnel responsible for the activities, including

a human factors specialist. The results of the V&V for the two latest revisions to the EOPs

were reviewed along with selected EOP flowcharts, EOP support procedures, and portions of-

the Plant Specific Technical Guidelines (PSTGs) and differences documentation.

Findings

Closed (219/92-02-02): The programmatic approach taken to develoo. implement. and

maintain high ouality EOPs and sunoort nrocedures is weak.

During the EOP inspection in January 1992, the NRC inspectors noted that the V&V

program requirements and EOP Writers' Guide had not been approved by plant management

and that a formal V&V of all EOP flowcharts and support procedures had not been

,

completed. They also noted that previously-identified procedure deficiencies had not been

corrected. Plant modifications were not evaluated using a programmatic approach for impact

on the EOPs, and a multidiscipline team approach was not clearly defined in development of

EOP program documents.

At the time of the September 1993 inspection, the licensee had approved procedures for EOP

program control, for verification and validation of EOP program documents, and an EOP

Writers' Guide that applies to flowchart and text procedures. The EOP program control'and

V&V procedures are very detailed and complete. They clearly define the responsibilities and

requirements for maintenance of the EOP program documents. The definitions provided in

the procedures were noted as a particular strength.

The licensee has established an EOP Committee to oversee the administration of the EOP

Program. The committee is chaired by the EOP Coordinator and includes representatives

j

from Operations, Engineering, Training, Human Engineering, and Safety Analysis / Plant

i

Control. The committee also interfaces with Quality Assurance, Emergency Preparedness,

and Licensing. The responsibilities of the EOP_ Committee are defined in the EOP program

control procedure and include: (1) evaluating operational concerns for impact on the EOPs;

)

~

'

(2) maintenance of the EOP Program documents; (3) approval of change requests and

resolutions of EOP Program discrepancies; and (4) ensuring that the EOPs are technically

correct, correctly written, and can be used during emergency conditions. The EOP

- . . .

-.

__ -

.

- -

._

--

. . ~ .

.

-.-

!

.

.

5

Committee provides a team approach for control of the EOP program. Additionally, the

procedures for verification and validation specify a multidisciplined team for conducting

V&V.

The EOP Coordinator is responsible far coordinating the activities of the EOP Committee,

all requests for change to the EOP Program, and all changes to the EOP program documents.

Logs are used to track EOP change requests, performance of verifications and validations,

and discrepancies identified during V&V. The inspector was concerned that the procedure

for resolving verification discrepancies specified that the completion date be documented

when the corrective action was initiated rather than when the action was completed. The

EOP Coordinator uses an informal tracking system, the EOP Action Item List, to track all

outstanding EOP actions including actions identified as a result of V&V. Additionally, the

documentation for the V&V that was performed for a revision to the EOPs following the 14R

outage had not been closed out because some action items were outstanding. Items on the

EOP Action item List are assigned a priority and responsibility for completion. However,

because the list is an informal tracking system, there are no specifications for assigning

priority or assuring accountability. Only seven of the thirty-seven items on the list at the

time of the inspection had due dates specified.

At the time of this inspection, the verification for the latest revision to the EOP flowcharts

and support procedures had not been completed. Validation was completed prior to

implementation of the revised procedures, but the verification was delayed because the

revisions to the PSTGs were not complete. The EOP program control procedure requires

that technical changes to the EOPs be evaluated against and incorporated into the PSTGs

prior to changing the EOPs. Changes to the PSTGs can only be postponed for expedited

EOP changes. Review of selected EOPs, support procedures, and the PSTGs did not

indicate any significant discrepancies that would have been identified during verification.

However, if technical problems are identified during the verification process, another

procedure revision could be required. Licensee representatives understood the inspector's

concern with implementation of revised procedures prior to completion of the V&V process

and agreed to review the practice.

The EOP Coordinator is responsible for determining the V&V requirements for changes to

EOP program documents. The V&V procedures provide specific instructions for

determining the V&V requirements; however, the scope of verification for minor revisions is

at the discretion of the EOP Coordinator, and there is no independent review of the EOP

Coordinator's decisions. The inspector identified three changes from the latest revision to

,

the EOPs that the EOP Coordinator had determined did not require verification that appeared

to need verification. For example, the wording of a step in EMG-3200.01B, "RPV Control

with ATWS," was changed from " boron injection is required" to " boron is being injected"

due to a request from the licensed operators. The EOP Coordinator determined that this was

a minor revision to reword for clarity that did not require verification. However, the two

phrases do not necessarily have the same meaning in all situations, which could result in an

incorrect action.

_

~

.

.

6

The EOP program control procedure requires that plant modifications potentially affecting

the mitigation strategy for emergencies be evaluated against the PSTOs and BWR Owners

"

Group (BWROG) Emergency Procedure Guidelines (EPGs) prior to incorporation into the

EOPs. Currently, the licensee relies on using knowledgeable personnel to review plant

modifications for impact on the EOPs. However, a revision to the modification process will

be implemented in the near future that incorporates review for impact on the EOPs into the

beginning of the rnodincation process. They are also developing a li',t of systems and

components that don't affect the EOPs that should help to streamline the modification

evaluation process.

The licensee is working on a number of initiatives to improve their EOP program. Some of

these include technical upgrade of the documentation of their deviations from the BWROG

EPGs and EOP calculations, development of a plant specific bases document similar to

Appendix B of the BWROG EPGs, development of a PSTG to EOP crossreference

document, and performance of a general verincation on all the EOP support procedures. All

of these initiatives are being tracked on the EOP Action Item List.

Conclusion

The licensee has significantly improved their program for development, implementation, and

maintenance of the EOPs and support procedures. They have developed complete and

detailed procedures for control of the EOP program and performance of V&V. The EOP

Committee and initiatives that they have undertaken indicate strong management involvement

in the program and commitment to maintenance of high quality procedures. No signincant

problems were identined with the EOPs or the V&V that was performed on the latest

revisions; however, some potential shortcomings were identified with the licensee's practices.

Implementation of revised procedures prior to completion of V&V could result in technically

incorrect procedures. Lack of independent review of EOP Coordinator decisions for V&V

requirements could allow incomplete verification or validation. Informal tracking of EOP

program action items does not assure accountability for completion of items and appropriate

prioritization of action items. These potential shortcomings did not have a negative impact

on the quality of the latest revisions to the EOPs; therefore, the unresolved item related to

the weaknesses in the EOP program is closed (219/92-02-02).

3.0

W '1ULATOR EXERCISES

Two operating crews participated in three dynamic exercises using the plant-specific

simulator. The purpose of the simulator exercises was to evaluate whether the EOPs could

be used effectively and ef6ciently in the plant in an emergency. The scenarios were

designed solely to test the procedures and the training provided to the operators. Discussions

were held with the operators and the EOP Coordinator following the scenarios.

_

_

.

.

..

-

-

-

.

.

.

4

7

Findines

Overall, the operators had no difnculty using the procedures, and no technical problems were

identified in the EOPs. However, a number of problems were noted associated with a

scenario that exercised EMG-3200.ll, " Secondary Containment Control," and EMG-

3200.12, " Radioactivity Release Control." During the scenario, the Scram Discharge

Volume (SDV) failed to isolate following a reactor scram with fuel failure, resulting in a leak

in secondary containment. Additionally, an unisolable Isolation Condenser (IC) tube leak

caused an offsite release. The following problems were noted:

-

Both crews had difficulty resetting the scram signal to isolate the SDV. Neither crew

referred to the abnormal procedure that could have provided assistance in resetting the

scram.

,

-

EMG-3200.12 is entered with an offsite release rate above the ALERT Emergency

Action Level (EAL) classification. Field readings and dose projection information are

required to make an EAL classification. Both crews identified the tube leak and

failure of the IC to isolate, but were slow to initiate action to evaluate the significance

of the offsite release. This appeared to be due to focusing their attention on isolation

of the SDV. Additionally, neither crew used the information that the IC vent

radiation monitor high level alarms were annunciating to assist in the evaluation of the

significance of the offsite release.

-

EMG-3200.12 contains a " wait" step that directs the SRO to wait until the actual or

projected offsite dose approaches or exceeds the dose that requires a GENERA'L

EMERGENCY (GE) classification prior to emergency depressurization (ED) of the

'

RPV. One of the SROs did not take action to ED when given dose information

approaching the GE level. In followup discussions, he indicated that he read the step

as wait until the dose exceeds the GE level.

-

One of the radiation monitors and some of the temperature indications needed for

implementation of EMG-3200.ll are not available on SPDS. Therefore, operators

must obtain the information from back panels. The licensee has developed laminated

forms to keep track of this information, but these forms were not used consistently

during the simulator exercises. The licensee is considering modifications to SPDS to

,

improve monitoring capabilities for secondary containment.

-

-

The reactor building drain tank radiation monitor is not used for entry into or

i

implementation of EMG-3200.12. The inspectors questioned whether this monitor

covered any areas that were not covered by other radiation monitors and, if so, why it

was not included in the EOP.

The plant-specific simulator was capable of modeling all of the conditions required for the

simulator exercises that tested almost all legs of the EOPs. The simulator operators' ability

-

-

-

.

.

_.

. .

-

-

..

.

.

8

to use the machine allowed two of the exercises to be used on two crews because validation

time was minimized. Time compression was used to transition between two of the exercises

and the use of a previously developed initial condition allowed for evaluation of a complex

exercise in a dynamic setting. No simulator fidelity problems were noted during the

exercises.

Conclusion

With the exception of timeliness in response to the offsite release, the operators performed

well using the procedures. The inspectors questioned whether the procedures and training

provided to the operators could be improved to provide more timely implementation of

radiation release mitigation actions. There were no other significant problems identified with

the EOPs. The operators demonstrated that the EOPs could be used in an emergency and the

SROs had a thorough understanding of the procedures. The simulator had the capability to

model all of the conditions requested by the NRC, and no simulator modeling problems were

noted.

4.0

NONLICENSED OPERATOR TRAINING

S&QLM

The inspector reviewed the procedure for nonlicensed operator on-the-job (OJT) training, the

job performance measures (JPMs) used in NLO training, and an EOP lesson plan used in

NLO training. The inspector also discussed the NLO training program with training

personnel, the Operations Training Coordinator, and a nonlicensed operator.

Findings

Closed (219/92-02-Olh Programmatic weakness in the implementation of the systems

approach to trainine for nonlicensed operators.

During an EOP followup inspection in January 1992, the NRC inspectors noted that the

licensee had failed to develop and implement a formal OJT program and formal EOP training

for NLOs.

At the time of this inspection, the training department had developec a formal procedure for

NLO OJT and was in the process of revising the equipment operator (EO) qualification card.

The NLOs are trained and evaluated with JPMs. NLOs are trained on all in-plant tasks that

ROs are trained on with the exception of tasks that require reactivity manipulations. These

tasks include all of the in-plant tasks required to support the EOPs. TSe only tasks that are

not included in the training are frequent evolutions for radwaste operators. Periodically,

NLOs participate in simulator training on the EOPs by walking through the procedures with

instructors in tre control booth during EOP scenarios.

r

-

c

-


--

T

<

w

w

-

1

.

.

9

The EOP program control procedure does not require training for NLOs on applicable EOP

revisions. Licensee representatives indicated that this was an oversight and would be

corrected.

Conclusion

A formal procedure for NLO OJT has been developed and is being implemented. Training is

provided to the NLOs on tasks that they are responsible for during emergencies. The

unresolved item related to NLO training is closed based on the actions taken by the licensee

(219/92-02-01).

5.0

RECIRC LOOP DISCHARGE VALVE ISOLATION EVENT

Scope

The inspector reviewed the licensee's corrective actions taken in response to two violations

of NRC requirements during a recirculation loop discharge valve isolation event in

August 1991. This review included a review of procedures and event review documentation.

The inspector also discussed the procedures and the event with licensee personnel.

Findings

Closed (219/91-29-04): Failure to take adequate corrective actions to preclude the repetition

nf a significant condition adverse to quality.

Following the recirc loop isolation event, an NRC inspector noted that the licensee had failed

to revise plant procedures to address possible difficulties in achieving cold shutdown with the

MSIVs closed and recirculation pumps off. Additionally, the licensee had not updated

placards in the control room following a Technical Specification amendment associated with

the recirc pump discharge valves. The licensee developed Procedure 203.4, " Plant

Cooldown Following Reactor Scram," to provide direction for cooldown with the main

condenser available or unavailable (MSIVs closed). Procedure 305, " Shutdown Cooling

System Operation," and Procedure 307, " Isolation Condenser System," were also revised to

clarify the direction for operating the shutdown cooling (SDC) system and the ICs during a

plant cooldown. The placards in the control room have been revised to be consistent with

the Technical Specification and procedural requirements for recirc discharge valve operation.

The violation for failure to take adequate corrective actions is closed based on the actions

taken by the licensee (219/91-29-04).

ClasnLL219/91-29-02): Failure to adhere to multiple ooerating and administrative

procedures in clostire of all five recirculation discharge valves.

The licensee determined that confusing procedural guidance was a contributing factor in the

failure to adhere to procedures. Procedure 203.4 was developed and Procedures 305 and 307

_

_

_

i

}

.

.

1

10

were revised to clarify the direction for cooldown with the MSIVs closed. Discussions with

operations personnel and a licensed operator indicated that the procedures could be followed;

i

!

however, the inspector was concerned that there were still some aspects of the procedures

that could cause confusion. Procedure 203.4 was intended to coordinate the use of

Procedures 305 and 307, but it is not the controlling procedure for the entire cooldown. For

example, 203.4 directs actions for control of RPV water level while using the ICs, but

direction for RPV water level control is transferred to 305 when SDC is placed in service.

Coordination of actions between multiple procedures could result in missed or incorrect

actions. For example, an SRO indicated that he would not have referred to Procedure 307

after placing SDC in service and isolating the ICs. As a result, he would have missed the

'

direction in 307 to cycle the IC vent valves to maintain the ICs within 50 psig of reactor

pressure. Additionally, several inconsistencies were noted between the three procedures,

j

The violation for failure to adhere to procedures is closed based on the licensee's ongoing

actions to improve procedure compliance and the observation that the procedures for

cooldown with the MSIVs closed could be followed by plant personnel (219/91-29-02). The

clarity of the procedures will continue to be evaluated during future routine inspections.

Procedure 305 was recently revised to provide specific direction for SDC system operation to

prevent temperature stratification and maintain circulation within the core. The inspector

was concerned that Procedure 2000-OPS-3024.27, " Shutdown Cooling System - Diagnostic

and Restoration Actions," does not provide clear guidance for restoration of shutdown

cooling if SDC is lost based on the revised requirements for maintaining core circulation.

Procedure 2000-OPS-3024.27 directs actions based on the adequacy of SDC and circulation

flow. It is not clear what is considered adequate flow based on the revised requirements.

L.icensee representatives acknowledged the inspector's observations.

'

,

Closed (219/91-29-03t Adequacy of the cost-transient review crocess to take corrective

actions orior to restarl.

't

In 1991, an NRC inspector noted that the licensee's Post-Transient Review (PTR) did not

evaluate problems noted during a plant cooldown following the reactor scram and isolation

event. However, a critique of the recirc loop isolation event performed by the operations

department determined the root cause of the event and identified that incomplete procedural

guidance was a contributing factor to the problems encountered during the cooldown. No

written guidance was provided to the operators prior to restart of the plant; however, the

operators were briefed on the recire loop isolation event, informed of the procedure

problems, and directed to consult with operations management prior to placing shutdown

cooling in service in the event of a plant cooldown with an MSIV closure. This verbal

guidance was provided in a memorandum to operations personnel after the NRC raised the

concern that no written guidance had been provided. The unresolved item related to the

adequacy of the post-transient review process is closed based on the observation that the

critique process adequately evaluated the event and identified corrective actions prior to

restart (219/91-29-03).

- -

.-

-

. _ - .

-.

.

--

-

0

.

.

I1

No concerns were noted with the licensee's review of the recirc loop isolation event and the

specific corrective actions taken; however, the inspector noted that no specific actions were

taken to address the failure to complete an identified corrective action prior to the event. It

was not apparent that any improvements had been made to the process for tracking internal

corrective actions and commitments that would ensure that actions are completed. The

inspector identified an example that demonstrated that the licensee's processes for tracking

actions may not assure that corrective actions designed to preclude conditions adverse to

quality are completed. One of the recommendations from the Independent Offsite Safety

Review Group (IOSRG) following the recire loop isolation event was to provide a training

scenario on a full isolation shutdown following a plant scram. This recommendation was

accepted, but then was closed without being completed because of the delays in obtaining the

plant-specific simulator.

Conclusion

The licensee is making an ongoing effort to improve procedure compliance with training,

focus on human performance, and a procedure upgrade program. The licensee clarified the

procedural guidance for conducting a plant cooldown with the MSIVs closed by developing a

new procedure and revising system operating procedures. These procedures are adequate;

however, the inspector was concerned that there were still some aspects of the procedures

that could cause confusion. There were no concerns with the licensee's review of the event

i

and specific corrective actions; however, no corrective actions were taken to improve the

process for tracking intemal corrective actions and commitments to preclude conditions

adverse to quality.

3

6.0

REACTOR WATER LEVEL, INSTRUMENTATION

l

S10IN

,

The inspectors reviewed the licensee's actions taken to address previous NRC concerns

related to the licensee's response to GE SIL 470 for " Reactor Water Level Mismatches."

This review included a review of a memorandum documenting licensee actions and

discussions with licensee personnel concerning the reactor water level instrumentation

mismatch.

Findings

t

!

I

Closed (219/92-18-Olk Incomplete response to GE SIL 470. " Reactor Water Level

Mismatches."

During a previous inspection of reactor water level instrumentation issues, an NRC inspector

l

noted that the licensee did not measure the slope from the reference leg steam condensing

chamber to the reactor vessel penetration or take into account the effect of RPV expansion on

the reference leg slope during plant heatup. During the last refueling outage, the licensee

'

--.

.

-

- - - - - .

- - .

>

.

.

12

measured the slope of the cold reference leg reactor water level instrumentation and verified

that the slope is in compliance with the recommendations of GE SIL 470 with and without

thermal expansion. The licensee also verified that the thermocouple bracket on the B

GEMAC sensing line does not interfere with condensing chamber movement. The

unresolved item related to the licensee's response to GE SIL 470 is closed based on these

actions (219/92-18-01).

The licensee has concluded that the level instrument mismatch is due to the relative

difference in the location of the referenced leg nozzles to the corresponding main steam

nozzles. The licensee has no additional plans to evaluate the niismatch between the B

GEMAC level instrument and other water level instruments. They have accounted for the

mismatch in the digital feedwater control modification planned for the next refueling outage

and the mismatch is modeled in the plant-specific simulator. When the modification

addressing the noncondensible gas effects on level instrumentation modification is completed,

the licensee will reevaluate the condition if their explanation for the condition proves to be

incorrect.

Conclusion

The licensee completed the actions recommended by GE SIL 470 to address the mismatch in

reactor water level instruments. The licensec has evaluated the condition and has determined

an explanation for the cause of the mismatch. The mismatch does not appear to have any

adverse effect on operator performance and is modeled in the simulator.

7.0

EXIT MEETING

Management was informed of the purpose and scope of the inspection at the entrance

interview on September 20,1903. The findings of the inspection were summarized at the

exit meeting on September 24,1993. Licensee representatives were informed that the

unresolved items and violations related to the EOPs, recirc loop isolation event, and reactor

water level instrumentation would be closed. The concerns related to the radioactivity

release EOP were discussed and licensee representatives committed to review the areas of

concern.

Persons contacted and attendecs at the exii meeting are listed below:

GPU Nuclear Corporation

i

S. Levin, Director, Operations and Maintenance

,

P. Scallon, Manager, Plant Operations

i

C. Gaydos, Supervisor, Operations Support Engineering

W. Behrle, Director, Plant Engineering

M. Godknecht, Plant Engineering

T. Corcoran, Plant Operations Engineer

.-

. - . -

-

.

.

.

-

-

- .

. .

13

GPU Nuclear Corocration (Cont'd.)

G. Jaffa, Human Factors Specialist

J. Kowalski, Manager, Plant Training

G. Cropper, Operations Training Manager

H. Tritt, Lead Instructor, Operations Training

J. Sims, Operations Training Coordinator

B. DeMerchant, Licensing Engineer

T. Sensue, Licensing Engineer

J. Rogers, Licensing Engineer

The inspectors also held discussions with training instructors and licensed and

nonlicensed operators during the inspection.

Nuclear Regulatory Commission

D. Vito, Senior Resident Inspector

,

'

S. Pindale, Resident Inspector

Denotes those present for the exit meeting on September 24,1993.

a

I

--'

-

--

---

-

,, ,

_,

_

, . . ,