ML20214T707

From kanterella
Jump to navigation Jump to search
Forwards Summary Rept for Regional Evaluation of Diablo Canyon Unit 2. Previous Schedule for Operations Not Achievable.Updated Evaluation of Licensee Work on Outstanding Items Will Be Done by Jan 1985 If Warranted
ML20214T707
Person / Time
Site: Diablo Canyon, 05000000
Issue date: 12/05/1984
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20213E738 List:
References
FOIA-86-197 NUDOCS 8706100387
Download: ML20214T707 (2)


Text

' ~ l

..m__.. - . _ . . . . _ _ . _ _ _ _ _ _ _ _ _ . . _ . . .. _ _ _ _ . . _ _ _ _ _ . . _ _ _ . _ . .

s .e i p uc f* ' ?[,

[g e UNITED STATES

(

}

.. p, NUCLEAR REGULATORY COMMISSION t

.3 # 'g%g(/c [* REGION V

  • . O, 2h~ 1450 MARIA LANE,su1TE 210 I

,o WALNUT CREEK, CALIFORNIA 94596 -

.  %, . .%/

? DEC 051984 MEMORANDUM FOR: Harold R. Denton, Director .

Office of Nuclear Reactor Regulation FROM: John B. Martin, Regional Administrator

SUBJECT:

DIABLO CANYON UNIT 2 OPERATIONAL READINESS REPORT (MC 94300)

This letter transmits the first Region V report summarizing the readiness of Diablo Canyon Unit 2 for issuance of an Operating License. The licensee has

. informed the Region that the schedule for operations as previously stated is not achievable. The fuel load date is now set for mid February. The attached report reflects the expected schedule changes.

It is anticipated that by mid January 1985, sufficient work will have been accomplished by the licensee and reviewed by the staff to significantly reduce the number of outstanding items. At that time, if warranted, a recommendation and updated evaluation will be provided.

AA0 f}

f u Joh'n . Mar't'in Regional Administrator

Enclosure:

As Stated cc (w/ attachment)

W. J. Dircks, EDO R. C. DeYoung, IE J. Davis, NMSS D. Eisenhut, NRR f T. Novak. NRR

.- G. Knighton,jNRR 3 l

1 l

1 0706100387 870604 PDR FOIA HOLMES86-197 PDR j

- - - - -a - . , . . - .

-. . .- . .L . .. l :. . . . -- - . . .~ ..:. . - . .

e l' .

? .

. , Schedule as of November 30, 1984:

I j Complete Hot Functional Tests - December 20, 1984 Implement Security System in Unit 2 - January 15, 1985 j Load Fuel - February 15, 1985

! Initial Criticality - April 1985 l

1 Power Ascension - May 1985 Commercial Operation - August 1985 5

t 6

4 1

2 i

l

]