Advises That 13 of 23 Transcripts of 840403-0503 Interviews w/11 Witnesses Available to Board in Camera Upon Request. Board Notification Recommended
ML20214T182
Person / Time
Site: Diablo Canyon, 05000000
Issue date: 06/01/1984
From: Hayes B
NRC OFFICE OF INVESTIGATIONS (OI)
To: Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML20213E738 List:
References
FOIA-86-197 NUDOCS 8706100153
Download: ML20214T182 (1)


Text

'

3.& ' ;' q'o*

UNITED STATES ->(-  !@) R<t Q f*'f

[*"

/*)c NUCLEAR REGULATORY COMMISSION

, .g, WASHINGTON, D. C. 20555 e, b, .. /c/

~

g'.*,

June 1, 1984 MEEORANDU!i FOR: Darrell G. Eisenhut, Director Division of Licensing Of.fice of Auclear Reactop Regulation FROM: B!n $a e D dhor/

Office of Investigatidn's EUBJECT: PROPOSED BOARD NOTIFICATION Eetween April 3 and May 3, 1984 the Office of Investigations (01) and Region V Staff conducted interviews of 11 witnesses who furnished testimony concerning the Diablo Canyon Nuclear Power Plant. These individuals were T.ade available by the Government Accountability Project (GAP) and were represented by GAP during the interviews. The interviews were transcribed by court recorders and documented in 23 transcripts.

A review of the transcripts has been conducted by 01 and an open Board Notification is recommended for the enclosed 10 transcripts representing testir:ony of the following witnesses:

Harold 0. Hudson (April 7, 11 and May 2, 1984)

Steven Lockert ( April 6, 9, and May 1,1984)

Charles Stokes ( April 3, 26, 27,'and 30,1984)

OI is holding 13 of the 23 transcripts containing additional information ,

provided by eight witnesses.who have requested and been granted confidential-ity. These transcripts will be made available to the Board in camera upon recuest.

En-l os u re s : As stated cc w/c enclosures:

.. J. Chandler, ELD H. E. Schierling, LS 3

0. C. Shackleton, 01:RV L. Schollenberger, RV 0706100153 G70604 PDR FOIA HOLMESU6-197 PDR I '; 't