Rev 1 to ISAP:I.b.3,Conduit to Cable Tray Separation, Comanche Peak Response Team Results Rept
ML20155B122
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 03/26/1986
From: Beck J, Bizzak R, Mallanda J
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
Shared Package
ML20155B118 List:
References
PROC-860326, NUDOCS 8604100247
Download: ML20155B122 (14)


Text

l i

l .

l .

O COMANCHE PEAK RESPONSE TEAM RESULTS REPORT ISAP: 1.b.3

Title:

Conduit to Cable Tray Separation REVISION 1 O

WWAb h Y$anbJ f$d/ =Sb l Sh Issue Coordinit%r // Date M1. )11aAAA 3/ze/gG Date I RJviewI m Lea' der Qw- 4). k Joh6/ W. Beck, Chairman CFRI-SRT 3 /2 <. h t.

Date O

8604100247 860404 PDR ,

A ADOCK 05000445 PDR

R; vision; 1 J

Page 1 of J3 t

(,,/ RESULTS REPORT ISAP I.b.3 Conduit to Cable Tray Separation

1.0 DESCRIPTION

OF ISSUE IDENTIFIED BY NRC (NUREG-0797, Supplement No.

7, Page J-42)

"The TRT found no evidence that the existing GLH analysis for establishing the criteria for a 1-inch separation between rigid conduits and cable trays, as stated in G&H Electrical Erection Specification 2323-ES-100, had been evaluated by the NRC staff for Co:anche Peak. This analysis should have been referenced in the FSAR."

2.0 ACTION IDENTIFIED BY NRC (NUREG 0797, Supplement No. 7. Item 6(e),

Page J-44)

"TUEC shall accomplish the following actions prior to fuel load:

Submit to the NRC the analysis substantiating the acceptability of the criteria stated in G5H electrical erection specification governing the separation between separate conduits and cable trays.

s

' This analysis shall be supported with the necessary documentation in sufficient detail to perform an independent evaluation of how these criteria were established based on the analysis."

3.0 BACKGROUND

Raceway separation criteria utilized in Gibbs & Hill electrical drawings and specifications were based upon the requirements of IEEE 384-1974, "IEEE Trial-Use Standard Criteria for Separation of Class 1E Equip =ent and Circuits", and Regulatory Guide 1.75, Revision 1. January 1975, " Physical Independence of Electric Syste=s". Although very specific criteria are provided in the standard and regulatory guide for separation between redundant

  • cable trays, the same degree of specificity is not provided for separation between conduits and cable trays.

All separation requirements in this report are for redundant cable trays and/or conduits. The word " redundant" as used herein means that the cable trays and/or conduits requiring separation belong to different trains, i.e., Class 1E train A, Class 1E train B, or non-Class 1E train C. Note that cable trays and/or conduits of the f~')/

s_- same train require no separation.

t

1 Revision: 1 i

Page 2 of 13 i

O V

REST'LTS REPORT ISAP I.b.3 )

(Cont'd)

I 1

3.0 BACKGROUND

(Cont'd) l Since Regulatory Guide 1.75. Revision 1, January 1975, and l j

IEEE 384-1974 do not specifically provide criteria for conduit-to-cable tray separation, Gibbs & Hill originally interpreted these documents tp require a one-inch minimum '

separation between a safety-related conduit and an g cable tray when the conduit is below the top of the side rails of the cable i tray. This interpretation was included in a Gibbs & Hill document entitled " Criteria for Separation of Class 1E Equipcent and Circuits". This document was transmitted to tha TUCCO project for i their information and use via letter GTN-2'+41, dated February 19, 1975. The above criterion, along with separation requirepents for safety-related conduits above cable trays, was added to Electrical Erection Specification 2323-ES-100 in the form of Design Change Authorization (DCA) 6132, dated November 16, 1979. This DCA also included all separation criteria for non-safety related cenduit.

Specification 2323-ES-100, Revision 2, dated January 1981, which O incorporates DCA-6132, states in Section 4.11.1 that the Engineering drawings showing the plant layout utilized the separation criteria transmitted via Gibbs & Hill lettar GTN-2441.

The separation criteria, as stated in 2323-ES-100, are to provide "the necessary information for assisting the contractor in field routing the conduit . . . ."

During the Gibbs & Hill review of DCA-15917, which authorized a reduction in the separation criterion for a conduit above an enclosed' raceway from four inches to one inch, the adequacy of the existing one-inch separation criterion for safety-related conduits and open cable trays was questioned. Tnis issue was resolved by Gibbs & Hill memo EE-863, dated January 17, 1964, which included the Gibbs & Hill report and simplified analysis that the NEC-TET reviewed on site (See Section 1.0). The purpcse pf the memo was to establish the engineering interpretation of required separation between conduits and cable trays in accordance with established criteria in the standard and regulatory guide. This supporting documentation was not submitted to the NRC staf f f cr review because the interpretation was not considered a deviation to the standard or regulatory guide, but was considered documentation supporting the implementation of these requirements.

n v

, , Revisicnr 1 Pag 2 3 of 13 RESULTS REPORT ISAP-I.b.3 i (Cont'd) i 4.0 CPRT ACTION Pl.AN 4,1 Scope and Methodology The objective of this action plan was to wbstantiate the j acceptability of the criteria governing the separation between conduits and cable trays and to submit the evaluation and supporting documentation to the NRC.

To achieve this objective, the following tasks were )

implemented:  !

- Gibbs & Hill prepared a report compiling criteria and supporting analyses

- The Electrical Review Team reviewed the report substantiating the separation critaria The TUCCO Coordinator initiated the submittal of the report to the NRC J

4.1.1 Report Preparation Gibbs & Hill prepared a report for TUGC0 presenting the methodology and criteria used in applying IEEE 384-1974 and Regulatory Guide 1.75, Revision 1, January 1975, to cor.duits requiring separation fro cable trays. Included was a copy of a Sandia Report

(" Cable Tray fire Tests", SAND 77-1125C), which documents a series of tests funded "by,the Nuclear Regulatory Co:=ission to provide data needed for confination of the suitability of current design stendards and regulatory guides for fire protection and control in water (cooled) reactor power plants".

4.1.2 Report Review The above report was submitted to the Electrical Review Team for review.

4.1.3 Report Submittal to NRC The TUGC0 Coordinator submitted an FSAR Change Request to TUGCO Nuclear Engineering for submittal to the NRC l . for review. The FSAR Change Request provides a description of the existing conduit-to-cable tray separation criteria. Supporting docurents are attached to the TSAR Change Request.

l

R3 vision: 1 i Page 4 of 13.

~f) s~-

RESULTS REPORT i

ISAP I.b.3

(Cont'd) i 4.0 CPRT ACTION PLAN (Cont'd) 4.2 Participants Roles and Responsibilities The organizations and personnel that participated in this effort are described below with their respective work scope.

4.2.1 TUCCO Comanche Peak Project 4.2.1.1 Assisted the Electrical Review Team in reviewing the report coepiling the Gibbs &

j Hill criteria.

J

! 4.2.1.2 Will submit, upon approval, the FSAR Change i Request and supporting documents to the NRC.

4.2.1.3 Personnel Mr. W. I. Vogelsang, TUGC0 Coordinator

~

4,2.2 Electrical Review Team 4.2.2.1 Reviewed the report compiling the Gibbs &

Hill criteria.

4.2.2.2 Personnel (prior to October 18, 1985)  ;

Mr. M. B. Jones, Jr., Review Te am Leader Mr. E. F. Stroupe, Issue Coordinator  !

4.2.2.3 Personnel (starting October 18, 1985)  :

Mr. J. J. M411anda, Review Team Leader ,

Mr. R. J. Bittak, Issue Coordinator Mr. M. B. Jones, Jr., Third-Party Adviser I Mr. E. P. Stroupe Third-Party Adviser 4.2.3 Gibbs & Hill r

4.2.3.1 Prepared a report compiling the criteria used

in confirming the adequacy of conduit-to-j cable tray separation.
  • j

Rsviciga-: 1 Page 5 of 13

(}

\J RESULTS REPORT ISAP I.b.3 (Cont'd) 4.0 CPRT ACTION PLAN (Cont'd) 4.2.3.2 Personnel Mr. S. P. Martinovich Principal Enginect-Electrical 4.2.4 Third-Party Adviser (prior to Octobet 18, 1985) 4.2.4.1 Feviewed the report compiling the Gibbs &

Hill criterla.

4.2.4.2 Personnel Mr. L. D. Pates, Third-Party Adviser 4.3 Oualification of Personnel /

Third-party participants in the trplementation of this action plan met the personnel qualification and objectivity

\ require-ents of the CPRT Program Plan and its impleeenting procedures, Other participants were qualified to the requiremente of the CPEES Quality Assurance Program or to ete specific requirements of the CPRT Pregran Plan. A:tivities perforced by other than third-party personnel were governed by the applicable principles of See: ton III,K, " Assurance of CPRT Trogram Quality", of the CPRT Program Plan.

4.4 Procedures Not appifcable.

4.5 Acceptance Criteria The acceptance criterion f or the report was thet it demonstrate that the conduit-to-cable tray separation criteria meet the intent of IEEE 384-1974 and Regulatory Guide 1.15 Revision 1. January 1975. This was met as discussed in Section 5.0.

4.6 Decision Criteria If compliance with IEEE 384-1974 and Regulatory cuide 1.75 Revision 1 January 1975 could not be adequately demonstrated, the conduits and cable trays would have to be modified, ao appropriate, to achieve compliance. This was not necescary as diaeussed in Section 5.0.

1

Rsvisient 1 j . _ .

Peg 2 6 cf 13 4

!p RESULTS REPORT I ISAP I.b.3 (Cont'd)

]

j i 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS k 5.1 Sunna rv I A report based on the informacion contained in Gibbs & Hill memo EE-663 was prepared by Gibbs and Hill. This report i addressed those separation distances between a conduit and an open cable tray which did not meet the criteria given in IEEE

384-1974 for open esble trays. The primary' reference used to

-l substantiate the conduit-to-cable tray separation criteria was

a Sandia report documenting a series of electrically initiated 4 cable tray fires. One case which is not directly evaluated in j the Sandia report-is the case of a safety related conduit one inch beside or beloW an open cable tray, The justification

! presented in the Gibbs & Hill report for the one inch  ;

separation case mentioned above was a simplified analysis from 4 i EE.863 which utilized cold vall heat flux values from the "

Sandia report.

l]

The above Gibbs 6 hill repert, originally issued in September '

! 1984, was reviewed by the Electrical Review Tasm daring the late 1984/early 1985 time frane and revised seve'ral times to

! incurporate corsnts. Subsequent to the above review tycle, ,

i' questions temsined on the simplified analysis presented in the repart. To alleviate these concerns, Gibbs & Hill performed .

1 computer analyses in the summer cf 1995, using an alternate J

methodolc.gy, to substantiate the simplified analyses.

j Although :*.he computer analyses were in agreement with the results cf the simplified analysis, a subsequent' review of the '

report and analyses in the last quarter of 1995 by the i Elsetrical Keview Tea:n identified inconsistent a ssumptions in
the simplified analysis which req 21 red rubsequent j justifications. A final report utilizing a revised computer analysis was completed and issued to TUG 00 by Gibbs & Hill.

The final report and analyses have been reviewed by the ,

j Elecerscal Review Team Leader and Issue Coordinator. The 4

conclusion is that the above documents provide adequate jus:f fication of the existing conduit-to-cable tray separation; therefore, no plant modifications are required. A l

1 su:n.tary of the report is given in the following section.

1 i 1

5.2 _ Conduit / Cable Tray separation Criteria l 1

The separation criteria in Gitbs & Hill Elettrical Erection i 4

p Specificatien 2323-25-100 are graphically Fresented on Drawing )

t / 2323-El-1702-02, Revision 2, " Cable and Raceway Sep.aration l l

Typical Details". l l

i l

_ . _ _ . , _ . _ . , _ .- ,,_ . ,_ , - . _ _ - _ . . _ . . . - . . - - , - _ . , - , . _ ~ - - , , - . . __ --

~_ __m.-

Rsvision: 1 Page 7 of 13 (j

\

RESULTS REPORT ISAP I.b.3 (Cont'd)

I 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS (Cont'd) l The separation criteria shown on Gibbs & Hill Drawing 2323-El-1702-02 apply only when hazards are limited to electrically-initiated fires due to failures or faults internal to electrical equipment or raceways. This is consistent with the definitions given in IEEE 384-1974 for the cable spreading area and general plant areas.

The criteria given in IEEE 384-1974 for separation of redundant cable trays for the above areas are:

Cable Spreading Area - Both I foot horizontally cable trays are open ventilated 3 feet vertically trays.

General Plant Areas - Both 3 feet horizontally cable trays are open ventilated 5 feet vertically /

trays.

Cable Spreading Area and 1 inch horizontally General Plant. Areas - Both 1 inch vertically l cable trays are enclosed.

The IEEE standard also allows the separation distances to be alternatively escablished by analyses / testing "to determine i the flame retardant characteriscita of the proposed cable installation, . . ."

Although the above specific criteria for redundant, open cable trays are provided in IEEE 384-197~4 and Regulatory Guide 1.75 Revision 1, January 1975, the same degree of specificity is not provided for separation between cenduits and cable trays.

Hewever, the above ceparation distances for open cable trays could be reduced when one train of circuits is in conduit since a barrier

  • now exists between the two redundant trains.

The current CPSES conduit-to-cable tray separation criteria are depicted in Details 45 thru 49, 52 thru 5$. and $7 of Drawing 2323-El-1702-02. A su m ary of these criteria follows:

i The IEEE 364-1974 definition of a barrier is "a device or structure interposed between Class IE equipment or circuits and a potential source cf damage to limit damage to Class IE rystems to an acceptable level."

R2visien: 1 Pcgs 8 of 13

-~ RESULTS REPORT N'

ISAP I.b.3 (Cont'd) i 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS (Cont'd)

Cable Spreading i foot horizontally When conduit .

Area 2 feet vertically elevation

  • is above the top of the cable tray side rails or when the cable tray is vertical.

General Plant 3 feet horizontally When conduit j Area 3 feet vertically elevation

  • is above the top of the cable tray side rails or when the cable tray is vertical.

1 Cable Spreading 1 inch horizontally When conduit Area and General 1 inch vertically elevation

  • is below i Plant Areas the top of the cable tray side rails 4

O\_ /

(cable tray horizontal), conduit is non-safety related, or cable tray is enclosed.

In comparing the conduit-to-cable tray separation criteria given above te the criteria provided in IEEE 384-1974 for open cable trays, the following three categories of differences are noted:

Category 1 - !;on-Safety Related Cenduit Separation between conduit and cable tray is one inch when conduit is non-safety-related.

Category 2 - Safety-Pelated Conduit Above Cable Trays Vertical distances are 2 feet /3 feet for safety-related conduits over open cable trays in the cable spreadinF/ general plant areas, respectively.

Category 3 - Safety-Related Conduit Below the Top of the Cable Tray Side Rails Separation between conduit and cable tray is one inch t

\-

when conduit elevation is below the top of the cable tray side rails.

  • Conduit elevation is top of cceduit.

Revision: 1 Pcg2 9 of 13 RESULTS REPORT 7s k ISAP I.b.3 (Cont'd) 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS (Cont'd)

Category 1 - Non-Safety-Related Conduit The CPSES minimum separation for non-safety-related conduits adjacent to safety-related cable trays is one inch, regardless of orientation. The non-Class 1E circuits in the conduit do not have to be protected from a cable fire in the cable tray since the non-Class 1E circuits do not provide a safety function. However, the Class 1E cables in the cable tray do have to be protected from a fire in the conduit. The conduit in combination with a one inch air space will provide adequate protection to the safety-related cable tray. This configuration is similar to Figure 5 of IEEE 384-1974.

It should be noted that a fire in a conduit represents a less severe source of damage than a fire in an enclosed cable tray since:

- Conduit size is limited to five inches thus limiting the volume of cables contained.

Threaded connections provide an essentially air-tight medium which inhibits internal combustion and effectively isolates internal events from the surroundings.

The curved surface of the conduit provides a radial distribution of radiant heat and, therefore, less favorable heat transfer characteristics to or from an adjacent cable tray than a fist surface of equivalent area.

Category 2 - Safety-Related Conduit Above Cable Trays The basis for the adequacy of vertical separations given in this category is electrically initiated fire tests conducted i by Sandia Laboratories and presented in Report SAND 77-1125C,

" Cable Tray Fire Tests." One of the objectives of these tests was to use cables representative of those used in the nuclear industry. An industry survey of 13 leading architect-engineering firms, 13 utility companies, and 13 cable manufacturers was performed. Twenty (20) different cable types were screened on the basis of popularity of use, small scale electrically initiated cable insulation fire tests, UL FR-1 flame test, and pyrolyzer and thermal chromatograph testing (which measured insulation outgassing as a function of s- / temperature). The cable constructions tested are

Ravision: 1 Page 10 of 13

/9 RESULTS REPORT )

D ISAP I.b.3 (Cont'd) 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS (Cont'd) representative of those used at CPSES. The cables used at l CPSES comply with IEEE 383-1974, " Standard for Type Test of Class IE Electrical Cables, Field Splices, and Connections for Nuclear Power Generating Stations". The cables used in the <

Sandia tests "were capable of passing IEEE Standard 383-74". I Therefore, the Class 1E cables at CPSES and the cables used in the Sandia tests have similar flame-retardant chiracteristics.

The Sandia testing showed that, for an electrically initiated cable tray fire, cables in an open tray located 10.5 inches vertically above the tray with the fire did not burn. All circuits in the cables above the fire remained functional. As noted above, the CPSES criteria for safety-related conduits located above cable trays is a minimum of two feet. It should be emphasized that the Sandia tests were performed using exposed cable; therefore, the CPSES criteria are even more conservative since the cables at CPSES are enclosed in a barrier.

Some of the more significant observations of the nature of electrically initiated fires noted in the Sandia Report are:

- The fire characteristics do not vary greatly from one cable fire to another.

The intense period of the fire at a particular location lasts between 40 and 240 seconds before die-out begins l

to occur.

The luminous zone of the fire is optically thin which means that the major heat transfer mechanism is convection versus radiation.

Based on the above, given a specified separation, the worst configuration is conduit over the cable tray since the conduit will be exposed to both convective as well as radiation heat transfer. Since the exposed cable 10.5 inches above the fire remained functional, any cable enclosed in a conduit (which provides additional heat protection for the cable) 10.5 inches or more from an electrically initiated fire will also remain functional.

o i

I l

.

  • R2 vision: 1  :

Pcge 11 of 13 fh RESULTS REPORT ISAP I.b.3 (Cont'd) 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS (Cont'd)

Category 3 - Safety-Related Conduit Below the Top of the Cable Tray Side Rails The only case where a safety-related conduit at CPSES can be less than 10.5 inches from an open cable tray is when the conduit elevation is below the top of the cable tray side rails. The major heat transfer mechanism for this configuration is radiation. Based on the above noted characteristic of the Sandia test fires (i.e. the luminous zone of the fire is optically thin), radiation is a minor part of the heat transferred from the fire to objects immersed in the flame.

In order to quantify the response of a conduit beside or below a cable tray, a computer analysis was performed by Gibbs &

Hill for the case of a conduit one inch directly below the fire. (Note that conduits alongside cable trays are partially p blocked from the radiation from the flame by the cable tray side rails.) Cable fire parameters taken from the Sandia Report were used as inputs to this analysis.

The above analysis included the following conservatisms:

- The fire data used in the analysis was for the October 5, 1976, fire test, one of the most intense and longest duration fires studied.

The radiation heat flux applied to the conduit was taken just slightly above the burning tray (1,e., in the flame) rather than one inch away from the flame.

- The radiation heat flux, based on the maximum flame temperature, was held constant from 30 seconds to 240 seconds. The test data showed that temperatures measured by a thermocouple in the flame varied from 1150*F to 700'F during this period.

- The flame diameter was held constant at eight inches.

- No blockage was assumed by other cables in the cable tray with the fire.

The cable enclosed in the conduit was assumed to be at O

'd the same temperature as the conduit. No credit was taken for the cable acting as a heat sink.

.

  • Ravicion: 1 Page 12 of 13 I' \ RESULTS REPORT ISAP I.b.3 (Cont'd) i 1

l 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS (Cont'd)

The results of the analysis showed that the conduit exceeded 1 302*F (150*C) for approximately 4-1/4 minutes with a maximum .

temperature of 357'F (181*C), assuming an ambient temperature of 122*F (50*C).

The Electrical Review Team reviewed the manufacturers' data for the cables used at CPSES. All cables are qualified for 302*F (150*C) for a minimum period of one week. Additionally, the cables with silicone insulation were tested at a minimum temperature of 392*F (200*C) for seven days and remained functional. Anaconda FR-EP cables were qualified for a LOCA environment by testing at 385'F (196*C) for two twelve-minute j periods. The remaining cables were LOCA tested at a minimum of 345'F (174*C) for a minimum of four hours. The cables subjected to the above tests to simulate LOCA environmental conditions remained functional.

Additional evidence which supports the adequacy of CPSES O conduit separation one inch below cable trays is provided in the results of the propane-fueled exposure fire tests also conducted by Sandia in which conduits and trays were included.

In these tests, fourteen (14) trays were stacked seven (7) high by two (2) wide separated vertically 10.5 inches.

Directly below each tray (except for the bottom tray exposed i to the propane-fueled source) was a conduit containing I additional cables. Although all circuits in the conduits l above the third tray failed during the exposure fire (the 1 higher conduits experiencing heat input from all fires below I them), circuits in the lower two (2) conduits maintained circuit integrity throughout the duration of the fire. ,

I Considering that the fire in the lower two (2) trays was more severe than in an electrically initiated fire, being larger in size and of lorger duration, the results provide'an indicatio'.1 j of the adequacy of protection offered by conduits installed i with an air gap of one inch during the less severe electrical l fire. I 5.3 FSAR Change Request Submittal The TUCCO Coordinator submitted an FSAR Change Request to TUGC0 Nuclear Engineering for submittal to the NRC for review.

The FSAR Change Request provides a description of the existing

[

conduit-to-cable tray separation criteria. Supporting documents were attached to the FSAR Change Request.

Ravision: 1 Page 13 of 13 m

I RESULTS REPORT ISAP I.b.3 (Cont'd) 5.0 IMPLEMENTATION OF ACTION PLAN AND DISCUSSION OF RESULTS (Cont'd) 5.4 Classification and Evaluation of Discrepancies No design deviations were noted in the implementation of this action plan. However, two design observations were noted.

The first observation was that analyses did not exist at the time that the criteria for conduit-to-cable tray separation were placed in design and construction documents. The basis for the criteria appeared to have been engineering judgment based on experience with other nuclear projects. The second observation was that inconsistent assumptions used in the Gibbs & Hill simplified analysis verifying the one-inch separation criteria were not discovered during the design verification process.

Since no deviatione were found, no root cause analysis was performed. The observations were too few in number and too limited in scope to identify a trend. Therefore, the facts Ih relating to these observations were transmitted to the Design

\-s/ Adequacy heview Team Leader in accordance with Appendix A,

" Design Adequacy Program Plan", to be included in the collective evaluations of that plan.

6.0 CONCLUSION

S The established conduit-to-cable tray separation criteria meet the intent of IEEE 384-1974 and Regulatory Guide 1.75, Revision 1 January 1975. No corrective acticns are required.

7.0 ONGOING ACTIVITIES The FSAR Change Request and supporting documents have been issued to TUGC0 Nuclear Engineering (TNE) by the TUGC0 Coordinator. TNE will transmit the information to TUCCO Licensing, whi:h is the formal channel for submitting information to the NRC.

The design observations noted in Section 5.4 were forwarded to the DAP RTL in accordance with Appendix A, " Design Adequacy Program Plan", to be included in the collective evaluations of that plan.

8.0 ACTION TO PRECLUDE OCCURRENCE IN THE FUTURE p]3

\~- Since no design deviations were found, no corrective actions were required.

_ . . . _ _ __ _ - . - .