ML20154H817
| ML20154H817 | |
| Person / Time | |
|---|---|
| Site: | Rancho Seco |
| Issue date: | 09/01/1988 |
| From: | Fish R, Prendergast K NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML20154H807 | List: |
| References | |
| 50-312-88-25, NUDOCS 8809220136 | |
| Download: ML20154H817 (5) | |
See also: IR 05000312/1988025
Text
___ __ _____ _ _ _
.
..
.
U. S. NUCLEAR REGULATORY COMMISSION
REGION V
Report No. 50-312/88-25
Licensee: Sacramento Municipal Utility District
14440 Twin Cities Road
Herald, California 9568-9799
,
l
Facility Name:
Rancho Seco Nuclear Generating Station
Inspection at: Clay Station, California
Inspection Conducted: July 19-21, 1988
Inspector:
[,,1 n
k1,4
9/4/e p
K. N. Prenderpast
0
Dat6 S'igned
,
Emergency Preparedness Analyst
j
Approved by:
[ ', ( . A . b, , < -
" $ 4/
(,y/ R. F. Fish, Chief
Date Signed
Emergency Preparedness Section
Sumary:
Areas Inspected:
Routine unannounced inspection of the licensee's emergency
preparedness program.
The inspection included an examination of emergency
facilities, equipment, and emergency preparedness training.
Inspection
Procedure 827^1 was covered.
Results:
One violation was identified for the failute to maintain the calibration of
dedicated emergency equipment,
in addition, declining performance was
observed in the licensee's drill and exercise program and the emergency
response surveillance program. These areas are discussed ir. Sections 2 and 6
of this report.
sh072 g h.h
'
h
O
_ - _ _ _ _ _
-
._-.
.
-.
-,
.
_.
-
,
.
-. -
y
!
i
..
i
DETAILS
!
>
1.
Persons Contacted:
i
- B. Croley, Assistant General Manager, Technical and Administrative
Services
-
i
- P. Lavely, Manager, Environmental Protection
- F. Thompson, Supervisor, Emergency Preparedness Training
i
D. Feighert, Supervisor, Emergency Preparedness Programs
!
i
J. Price Emergency Preparedness Specialist
t
B. Gwaltney, Radiation Protection Technician
!
4
j
- Indicates personnel attending the Exit Interview
2.
Emergency Facilities. Equipment Instrumentation, and Supplies (82701)
This area was inspected to verify that key facilities and equipment were
'
maintained and to determine whether changes made to facilities or
i
equipment were adequate to meet the NRC requirements and that the changes
j
did not adversely effect the licensee's capabilities to respond to an
j
emergency.
!
The inspector toured the Emergency Operations Facility (EOF 1 a.M
l
l
Technical Support Center (TSC), examined the Emergency Plan and
!
implementing procedures, examined records of inventories of emergency
.
equipment, and examined the emergency equipment located in Warehouse A
,
and the Auxiliary Building. The following observations were noted.
,
i
t
j
A.
The EOF and TSC appeared well maintained and in a state of
'
)
operational readiness. Communications systems and facsimile
'
machines were tested and found to be operational. Copies of the
Technical Specifications and plant procedures were also observed to
j
be available. The TSC and EOF facility layouts appeared as
!
j
described in the current version of the Emergency Plan, Revision 1.
!
There were no changes to the facilities observed that would appear
j
,
to decrease their effectiveness.
j
l
B.
The records of the quarterly Emergency Response Telephone Directory
number verifications required by EPIP 5660, were examinej and
!
considered adequate.
i
k
'
C.
The records of inventories of onsite and offsite emergency equipment
!
j
documented quarterly inventories had been made. However, both the
i
record review and a physical inspection identified that some
i
,
!
portable dose rate monitoring equipment were due for calibration.
2
A May 1, 1988 inventor of offsite assembly kits identified two
l
2
portable ion chambers Eberline R02s) that were due for calibration
!
i
on February 23, 1988. A physical inventory during this inspection
l
}
of the energency lockers in Warehouse A an' % Auxiliary Building
i
also identified two portable ion cha;nbers wat had exceeded their
i
j
cralibration due date. The R02 instruments, toentified as serial
!
4
numbers 1632 :nd 1410, were last calibrated on November 23, 1987 and
j
were due for calibration on February 23, 1988. Procedure AP-311,
,
f
i
I
!
'
.
.
.
.
-
. _ _
-
.-
,
,
!
'
l
2
,,
l
!
l
"Portable Radiological Instrumentation," requires quarterly
calibration of dose rate instrumentation. Based upon the
calibration dates it appears that instrument nos 1410 and 1632 were
l
the same instruments identified by the licensee on May 1, 1988.
.
!
Corrective action to recalibrate the two instruments had not yet
l
been taken. The Manager, Environmental Protection attributed the
'
reason the instruments were out of calibration to a misunderstanding
between Radiation Protection and Emergency Preparedness regarding
i
j
who was responsible for these calibrations.
In addition, numerous
other problems were observed which included the follom ng:
'
a)
EPIP-5660 requires records of inventories to be forwarded
)
to the Manager of Emergency Preparedness. This action was
not done,
b)
Some inventories were performed using an outdated
!
inventory fortn.
c)
There were numerous discrepancies between the contents of
+
emergency lockers / kits and the inventory fonns in EPIP
i
l
5660.
l
l
The failure to ensure instruments are calibrate.d in accordance with
i
!
plant procedures was identified as a violation and will be followed
as 88-25-01.
.
!
,
l
D.
The Emergency Plan, Section 6, references numerous support
l
agreements with offsite individuals, groups, and agencies that would
,
'
'
provide support during an emergency. Section 8.6.2 establishes the
responsibility for an annual review by the Manager of Environmentai
Protection and to record the status of agreements or ':ontracts.
Prior to an agreements expiration date the Manager of Environmental
,
'
Protection is to initiate an update and renewal of the agreement.
The licensee's files for agreements with offsite support agercies
!
were examined and two contracts with the Regents of the University
of California UC Medical Center were noted to heve expired on April
15, 1988. The contracts were identified as B-16 and B-17
It
appears the licensee had perfortned the required review, homver, the
actions to renew the contracts were not timely. A siellar finding
was also identified in a March 1988 audit perfonned to satisfy the
i
requirements of the 10 CFR 50.54(t).
I.i this audit, two other
contracts with offsite agencies were stated to have expired. The
l
licensee initiated corrective action to renew the expired co.. tracts
'
identified in this audit. However, their corrective action did not
preclude the expiration of the two contracts discussed above. The
licensee's actions regarding this matter will be followed as open
item 88-25-02.
Licensee performance in this program area appears to be declining
due to a lack of management involvement to insure emergency
capabilities are maintained.
I
l
,
. -
3
4
3.
Changes to the Emergency Plan (82701)
Since the last inspection, Revision 1 to the Rancho Seco Emergency Plan
has been received. The revised plan was avaluated and a finding made
that the revised plan continues to meet the standards contained in 10 CFR
-
50.47 and Appendix E.
No changes were observed that appeared to decrease the effectiveness of
the Emergency Preparedness Program.
10 CFR 50, Appendix E contains requirements that changes to the Emergency
Plan and implementing procedures be sent to the NRC within 30 days of
such changes. During this inspection it was observed that numerous
temporary changes had been made to the licensee's classification
procedure and to the Emergency Plan. The temporary changes observed
primarily dealt with classification of emergency events.
Procedural
interim change notice's (PICNs) 01, 02, 03, 04, to EPIP 5001,
"Classification of Emergency Events" were examined and appeared to be
primarily clarifications. These changes did not appear to represent a
subst'intiative change to the implementing precedures that would require a
record of the change be sent to the NRC. However, it was suggested to
the licensee that they examine their procedures to insure compliance with
I
this requirement.
,
'
No trends with regards to strengths or weaknesses were identified in the
t
review of this program area.
l
4.
Organization and Management Control (82701)
.
!
There have been anc' continue to be changes in the Plant organization and
}
to the emergency response organization (ER0). However, these changes do
'
"
not appear to impact the ERO. The responsibilities contained in the
i
Emergency Plan and implementing procedures continue to be filled with
!
qualified personnel that have received the training required by the
e
!
Eniergency Plan and implementing procedures.
!
No significant strengths or weaknesses were identified in this program
i
area.
l
C.
Training (82701)
2
Records of annual Emergency Plan training were examined for numerous key
.
'
i
individuals in the ERO including: the Emergency Coordinator, the
Emergency Manager, the Emergency tews Center Manager, and selected
radiation protection positions. The training data base utilized by the
emergency preparedness group was examined to determine what training had
been received.
Basea upon comparing the training requirements contained
in the Energency Plan and the implementing procedures with the records
observed, it appears required training was accomplished.
During the records review, the specific training required for the
Operations Technical Advisor (OTA), a position comparable to a Shift
Te:hnical Advisor (STA), was not observed in the ERO training
requirements. The STA typically supports the Shif t Supervisor by
.
h
i
.
.
.
.
.
.
.
.
.
.
_ _ _ _ _ _ _ _
.
4
.
..
evaluating plant conditions and providing technied assistance during an
emergency, which are the same responsibilities delegated to the OTA. The
training requirements for the OTA position need to be examined and
appropriate training included in the Emergency Plan implementing
procedures.
No significant strengths or weaknesses were identified in this program
area.
6.
Drills and Exercises
Records of drills and exercises required by the Emergency Plan and
implementing procedures were examined. The licensee s "Emergency
Preparedness Orill and Exercise Nnual" was also examined. The
examination showed that the licensee has established an acceptable
program for identifying areas, during drills and exercises that require
improvement in the response to an emergency. However, the timeframe for
closing items identified during drill and exercises appears unacceptably
long. A review of the open items for 1987 drills and exercises indicated
a significantly large number of open items still open from 1987 drills.
Excessive time for corrective action resulted in some items being
reidentified in the 1988 drill. At the exit interview, methods were
discussed which could improve the timeliness of corrective action, these
included:
Develop or utilize one of the existing management tracking
systems to insure management involvement is at a level to
insure priority items, dealing with errergency response or
safety, are corrected in timely manner.
'
Oevelop a means to close the large number of cpen items that
require a revision to the implementing procedures or Emergency
Plan. Approximately 40 items were still open from 1987.
l.icensee perfonnance in this program area appears to be declining since
the previous evaluation.
7.
Exit Interview
The scope and findings of the inspection were discussed with licensee
representatives at an exit interview conducted at the conclusion of the
inspection. 1.icensee personnel present at this meeting are denoted in
Paragraph 1 of this report. Mr. T. D' Angelo. Senior Resident Inspector
was also present as a Mpresentative of the NRC at this meeting. During
this meeting the license was informed of one apparent violation
identified in Sections 2 of this report. Other items specifically
discussed during this meeting are contained in Sections 2 through 6.
_ _ _ _ _ _ _ _ _ _ _ _