IR 05000312/1988035

From kanterella
Jump to navigation Jump to search
Mgt Meeting Rept 50-312/88-35 on 881114.Major Areas Discussed:Licensee Operational Performance Since Restart in Mar 1988 & Progress Re Restart Commitments in Areas of Engineering,Procurement,Maint & Effluent Sys Areas
ML20196B872
Person / Time
Site: Rancho Seco
Issue date: 11/21/1988
From: Miller L, Zimmerman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20196B869 List:
References
50-312-88-35-MM, NUDOCS 8812070070
Download: ML20196B872 (68)


Text

- _ _ _

_ _

-

.

e-

,

. .

,.

.

U. S. NUCLEAR REGULATORY COMMISSION t

REGION Y p Report No.: 50-312/88-35 Docket No.: 50-312 License No.: DPR-54 Licensee: Sacramento Municipal Utility District 14440 Twin Cities Road Herald, California 95638-9799 Facility Name: Rancho Seco Management Meeting at: Clay Station, California Management Meeting Conducted: November 14, 1988 Inspector: fu W /ed d L. F. Miller, Chief Date Reactor ProjectsSection II Approved by: 19 n/pi///

Date '

R. P. Zirfpfman, Chief Reactor Pfejects Branch Meeting Sumary: A Management Meeting was held on November 14, 1988 at the licensee's facility to discuss the licensee's operational performance since restart in March,1988, and to discuss SMUD's progress regarding pre-restart comitments to perform various activities after restart. These comitments included efforts in the areas of engineering, procurement, the performance improvement program, maintenance, and radioactive effluent systems. The conclusion reached was that SMUD's operational performance since restart had been good. SMUD's progress on post-restart comitments was unclear, particularly with respect to design basis reconstruction, and perfonnance improvement program problem resolution.

< GG120700'70 881122 PDR ADOCK 05000312 O F'DC

_ .-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _

'

,

. -

  • ,. .

.

'

DETAILS f Management Meeting Participants NRC Participants ,

J. B. Martin, Regional Administrator G. P. Yuhae, Cnief, Radiological Protection and Emergency Preparedness Branch J. L. Crews, Senior Reactor Engineer D. Kirsch, Director, Division of Reactor Safety and Projects R. Zimmerman, Chief, Reactor Projects Branc L. F. Miller Jr., Chief, Reactor ProjectsSection II -

T. D' Angelo, Senior Resident Inspector C. Myers, Resident Inspector P. Qualls, Resident Inspector W. P. Ang, Project Inspector G. Kalman, NRR Project Manager G. W. Knighton, Director, NRR Project Directorate V G. N. Cook, Senior Public Affairs Officer l Licensee Participants D. A. Boggs, General Manager J. F. Firlit, Chief Executive Officer, Nuclear J. R. Shetler, Assistant General Manger (AGM), Support Services B. G. Croley, AGM, Technical Services R. S. DeWitt, Acting AGM, Nuclear Power Production B. Gibson, Acting Manager, Scheduling and Outage Management i D. Ferguson, Acting Manager, Nuclear Engineering

'

J. Vinquist. Director, Nuclear Quality D. Brock, Manager, Maintenance S. Crunk, Manager, Nuclear Licensing D. Yows, Manager, Environmental Monitoring and Emergency Praparedness T. Redican, Manager, Materials Management T. Telford, Project Manager l

S. Melancon, BCT, Project Manager of Effluent Management In addition to the above, other members of the licensee's staff were presen . Management Meeting Overview On November 14, 1988, a management meeting was held at the Rancho Seco Nuclear Generating Station, with the individuals listed in paragraph 1 above in attendanc !

. . . . . .. .

)

______ _

.

.

.

'. ,

. .

The NRC Regional Administrator stated that the purpose of the meeting was to review current issues with SMUD's operation of Rancho Seco. The meeting fcllowed the agenda in the "Status Update" viewgraf attached, with questions and discussion a:; they arose during 5 3's presentation. A brief presentation of the licensee's interim c od long term plan:, to reduce the volume and activity of secondary plant effluents was appended to the presentation at the NRC's request. Discussion of recent feedwater system history was not conducted due to time limitations, but will be discussed at a subsequent meetin b. Specific Issues Power Ascension Program Mr. Firlit gave a progress report on Rancho Seco's activities since restart, noting that SMUD's plans for completing the final power escalation from 92% to 100% were still being developed. Mr. Martin cautioned SMUD to fully discuss their intent with the NRC before changing the previously approved power ascensioa progra . Emergency Preparedness Mr. Firlit noted that the 1988 emergency exercise had been

"highly seccessful." Mr. Martin agreed that SMUD had imprnved substantially in this area in the last five years, but emphasized that emergency exercise results were highly sensitive to the training of the specific personnel involve He stressed that this is an area which, as at most plants, requires continuous management attention to ensure good results, including the maintenance of a strong working relationship with offsite authoritie . Quality Assurance Effectiveness Mr. Firlit discussed the increased numbers of audits conducted by the Quality department, and the improved results of the latest INP0 evaluation just completed. He noted that further l evaluations by the Nuclear Performance Comittee in December l 1988, and May 1989, were planned, as well as the completion of I twenty mot e system evaluations under the Expanded Augmented

'

System Review and Test Program (EASTRP) progra Mr. Miller noted that recent NRC inspection results indicated some reluctance by SMUD personnel to formally identify nonconformances due to a perception by some personnel that SMUD management was discouraging their use. A general I

discussion ensued, from which it was concluded that SMUD recognized that further management attention was necessary to ensure all SMUD personnel were encouraged to identify and document nonconforming conditions, rather than unintentionally discourage piant staff from doing s _

.

-

. 3 o e e Mr. Martin emphasized that SMUD's biggest challenges were to be highly self-critical, and to have the capacity to learn from mistakes. He noted that SMUD had the programs in place to meet these challenges, but the important task remaining was for management to ensure that everyone instinctively used these existing programs effectivel . Performance Improvement Program Comitments ("QCI-12 Process")

Mr. Shetler reviewed the changes since restart in SMUD's programs to find and remedy all significant problems at Rancho Seco. He then presented the current status of open problem The licensee recognized that follow-up of the non-hardware problems had slackened to the extent that the status and schedule for completion was not completely know Mr. Kirsch observed that during tne January 1987, SMUD presentation of this program to the NRC Commission, SMUD had stated that nesr term (also known as Priority 2) items would be completed during the next refueling outage. Mr. Shetler pointed out that in April 1987, and again since restart, SMUD had made significant changes to this program. However, SMUD agreed that the system for prioritizing corrective action of problems changed after restart rather than befor Mr. Martin stressed that the approval to restart Rancho Seco had not only been based on problems SMUD had corrected, but also on problems they agreed to correct after restart. He further emphasized that, until changed by mutual agreement of the NRC and SMUD, the connitments to resolve the near term (Priority 2) problems by the end of the next refueling outage remained in force. He noted, however, that some new issues could have developed since restart which could properly receive priority for completion before all of the Priority 2 problem He concluded by stressing that any diminishment of SMUD's level of effort on known existing problems, or change in the prioritization of problem resolution without agreement of the NRC was not acceptabl Mr. Boggs and Mr. Martin then agreed that a technical meeting in the near future, to clearly define SMUD's connitments in this area, is essential. Mr. Boggs affirmed that SMUD would meet its comitments to the NRC, even if additional resources, which had not been previously budgeted, were require . Maintenance Mr. Brock made a presen* Jtion of the nature and trend of SMUD's maintenance backlog since restart. He stated that SMUD's goal was to reduce the backlog to 600 items by mid-198 The principal reason offered for the backlog was the large number of discretionary preventive maintenance items, most of which were originated and done for the first time after restart. .

.

.

.

.. ,-

.

,

In this area, Mr. Martin observed that the number of control room annunciators which were unnecessarily alarming appeared to be excessive. Mr. Firlit responded that SMUD's goal was to reduce the number of such alarms to zer In response to an NRC question, Mr Brock stated that SMUD's intention was to replace or repair all valves in the plant which had been repaired by injection of a temporary sealan This effort is contingent on plant conditions and spare parts availability. He also noted that this effort included a search of equipment history records to determine which valves have been repaired with this techniqu . Engineering Action Plan Mr. Ferguson presented SMUD's plans for developing a comprehensive computer database configuration management system for Rancho Seco by 1991. Messrs. Miller and Crews asked when the first plant system would be incorporated into this database such that a complete design basis description l of the plant system existed. SMUD could not provide a i schedule for this milestone.

l Mr. Martin expressed concern that some of SMUD's comitments I as expressed in the Engineering Action Plan approved prior l to restart appeared to have changed significantly from that which had been agreed to prior to restart. SMUD representatives

'

were not prepared to address these questions directly. It was agreed that a meeting in the near future to clarify SMUD's comitments would be appropriat . Procurement Mr. Rediken presented the status of comitments made in the procurement program. There was a question between SMUD representatives regarding whether the environmentally qualified equipment parts evaluation had been completed by June 30, 1988 as comitted. This item will be discucsed further in the resident inspection report which includes this perio . Radioactive Effluent System Plans Mr. Melancon presented a description of the short and long tenn modifications SMUD intends to install to minimize waste water volume and activity from Rancho Seco. The short term modifications include: Recirculating the auxiliary feedwater pump bypass flow to the condensate storage tank rather than draining it to the hotwell as presently configured; u

'

..

. .

.

. 5

..,-

.. ,

. ~ Recirculating selected secondary sample lines to the hotwells rather than to secondary sumps; Installing a demineralizar and filter in the condensate polisher sluice water effluent line; and Installing a high capacity portable demineralizer between the regenerative holdup tanks and the retention basin These modifications are expected to improve normal operating efficiency and increase capacity factor. In addition, a major upgrade of the tank farm and a new waste water treatment facility are planned in the near future. Mr. Martin emphasi. ed that previous SMUD plans in the past few years have not progressed very far, and stronger SMUD comitment to folicuing through on the plans made is importan c. Conclusion Mr. Boggs sumarized his view that SMUD should clarify further with the NRC whether it is doing what the NRC expects in the areas of plant improvements, the QCl-12 process, and the Engineering Action Plan. He stressed that the CE', Nuclear, Mr. Firlit, has SMUD's

-

total support for meeting the NRC's-expectation Mr. Martin stated that Rancho Seco has clearly operated very well since restart, but the completion of the Engineering Action Plan and the near term Performance Improvement Program items is not clear, and further discussion between SMUD and the NRC to clarify and status existing commitments in these ares is necessar _ _ . . - . _- . . _ _ _ _ . . . _ _ . - _ .

f D RANCHO SECO I

NUCLEAR GENERATING STATIO N I

14 NOVEMBER 1988 NRC REGION V STATUS UPDATE i .-

=-

T 4-

-

!

I j

'

(r. C s ..

D Jfj !

.

'

.

'

,

0~:

H

'-.T*

.= r*?- -

. . .

C .: . .:4

.- ,

, .

. f '?

'

! ,

'

~

  • '

l e

{

-

.

j m.m .

,

..s

~

. ._ . .. ,

cj*

.

-e, ; sew r T{ :., - y.'.

.

-

. ' . .'

- j (1

_

gg "m; '(g i~4%fpi",E . T g L j 4gf-h his3;!L ' %

i

\

r e y;

, --MMywa ( 3_ p ..

- <-

M7m y ~j!

1

!

!

!

.

- - , _

.

- _ - .__ _- _- -,, ~ -

_ _ . _ __

- - 1 < -

(8397

[ n-o NRC REGION V AGENDA 1 6 MONTH STATUS UPDATE

-

.-

l s INTRODUCTION . . .. .. . . JOSEPH F. FIRLIT a PROGRESS REPOR ... . .. JOSEPH F. FIRLIT m LONG RANGE SCHEDULE COMMITMENTS. . . . JIM SHETLER m AREAS OF MANAGEMENT ATTENTION

- MAINTENANCE . . .... .......... DAVE BROCK

- ENGINEERING . . . . . . . . . . . . . . . . . . . . . . B O B C R OLEY

- M ATERI ALS M AN AGEMENT . . . . . . . .... . . . TOM REDICAN

- OUTAGE MANAGEMENT. . . . . . . . . . . . . . . . . . . BOB GIBSON

= CONCLUSION / QUESTIONS . . . . . . . . . . . . . . JOSEPH F. FIRLIT N ,

Y I

L_

I1 1 I

O TR J

O I

L E A RL I

F C U U

.N F

.

O H OE PC E

O S O

J m

m N

O m I T

C-r U D

m O R

T m N I

m m

-

L l

-

-

-

-

w

-

r TR A

t

-

L AE I

R L

-

r I

F C a U r .

N F ,

-

r H OE P

E C

m S O

J m

T-r R

O P

E

,

R m S S

E m R G

O R

P

-

_

m N

llll l l l l1ll. ll 1l 1ll l

<

< N RRS E AE L EC

< T LIV E CR HUE SNS

,T MMG R

- I J AOP P

- U S S T T

- N N E A L

- M P ET GI M

- N

<

AM ROC

_

G

_

NE L O

L U D

_ E H _

_

_ C S

-

_ '

_

u (

l l l

~

'Ye %

._

~,

,,

..

. ;g *

'/

CQ \

E o\\\\

-

'

\

OD O y

~ x

+-

t

x X~

g L .-

--: ; p , -

l

- --

l- '

CWND W -9 Q ~ H Av O

cn/

( J

~

l - -

E8363 l n-o l LONG RANGE SCHEDULE PROCESS ,

. l l

m EVOLUTION OF SCOPE CONTROL PROCESSES

<

a STATUS OF LONG RANGE SCOPE LIST (LRSL)

- PRIORITY 2 AND 3 ITEMS a STATUS OF LONG RANGE SCHEDULE (LRS)

t I

'

,

..

,

- . . _ . _ _ m ,, ~

.

- - - -- - - _ _ _ _

' esso

- * ..

EVOLUTION OF SCOPE CONTROL

_

1984-1986 LIVING SCHEDULE l PROCESS

\ NEED FOR: - Brooder /In-Depth Process

- Return to Basic issues

- Process That Could Handle Larger Volume 1986-1988 RESTART EFFORT NEED FOR: - Enhanced Task Evoluotion

- Improved Prioritization

- Return to Operating l '

Plant Environment l

1988-PRFSENY LONG RANGE LONG RANGE

'

SCOPE LIST SCHEDULE l

t

,

_

- __, c , , , , ,

- - - -

( UCD EVOLUTION OF SCOPE CONTROL

l m 1984-1986 l LIVING SCHEDULE = CAPITAL PROJECTS PROCESS l

- BENEFIT EVALUATION

- COST EVALUATION Y

- PRIORITIZED SCOPE BASED UPON RESOURCE LIMITATIONS a PROPOSED LICENSE AMENDMENT a SUSPENDED IN EARLY 1986 N ]

- - - - - - - , - o ,- , , , ,

= - -

O EVOLUTIOB! OF SCOPE CONTROL ,

a 1986-1988 RESTART = - OCl-12 PROCESS EFFORT - RSL/LRSL PROCESS (RSAP-0215) l

- HARDWARE / SOFTWARE ISSUES

- DEFINED CRITERIA

- SCOPE BASED UPON SAFETY /

RELIABILITY / ENHANCEMENT CRITERIA a PLANT PERFORMANCE AND MANAGEMENT IMPROVEMENT PROGRAM (QCI-12)

- DISCOVERY PROCESS

- 1986-1987 m RESTART SCOPE UST/LONG RANGE SCOPE LIST (RSAP-0215)

- CLOSURE / TRACKING PROCESS

- INSTITUTED 1987

- REPLACED OCl-12

- - - - - --

- _ - _ -

( "* %

a RESTART SCOPE LIST /LONG RANGE SCOPE LIST PRIORITIZATION CRITERIA - RSAP-0215 m PRIORITY 1 - RESTART ACTIONS TO BE COMPLETED PRIOR TO RESTART OR COMPLETION OF THE RESTART TEST PROGRAM

- Assure plant remains in Post-Trip Window

- Assure compliance with Technical Specifications

- Minimize the need for operator action outside the Control Room within the First Ten Minutes of an Event l m PRIORITY 2 - NEAR TERM f

ACTIONS TO BE SCHEDULED AS PROMPTLY AS PRACTICAPLE. SHEDULE DEVELOPED, RESOURCES ASSIGNED AND MAINTAINED ~. '~ .. .ETE (IT IS THE INTENT TO INITIATE THESE ACTIONS AS SOON AS PRIORITY ONE ACTION COMPLETIONS MAKE RESOURCES AVAILABLE.)

l - Enhance ability to remain in Post-Trip Window

- Reduce Reactor Trips

- Reduce challenges to Safety Systems l - Produce Near-Term Programmatic Benefits a PRIOR!TY 3 - LONG TERM ACTIONS TO BE SCHEDULED FOR THE LONGER TERM

- Improve Reliability

- Improve Availability

- Major Programmatic Enhancements

.

-

aa - - - - - - - - - - - __

( ' "i"" N EVOLUTION OF SCOPE CONTROL a 1988-PRESENT l

LONG RANGE LONG RANGE HARDWARE SCHEDULE SCOPE LIST =

PLANT / ORGANIZATIONAL PROCESS l

(RSAP-0215) ROLLOVERS BETTERMENT ITEMS (RSAP-1401)

- TRACK STATUS AND - BENEFIT EVALUATION (SAFETY /REUABILITY)

SCHEDULE OF LONG - COST EVALUABON RANGE RESTART COMMITMENTS

- COMMUNICATION - PRIORITIZED SCOPE BASED VEHlCLE UPON RESOURCE LIMITATIONS a LONG RANGE SCOPE UST CONBNUES UNBL RESTART COMMITMENTS ADDRESSED m LONG RANGE SCHEDULE CONTINUES AS CAPITAL PROJECTS SCOPE CONTROL k

I

[ a

[  !

A I

$

o

$

e

'

r

, .

5 E l R S l R A

E

'

J

- - - - -

_ _ _ _ _ _ _ . .

N

'

?

[  !

(  ! '

c !II /

I uJ e-(

~

y ,y

~

( V/

( h iB $

{ W E 5 5 (

d 8  ?

l s

l2  ? ~

I h 8

4

. _ _ _ _ _ _ _ . . . _ _ _ _ _ _

$

$

I

!

$ -

[

7 \. 4 i

. .. .

{ O P $ $

"

9 ?

I

!E S t ii i

-___.__ _

E -

5 !!

Il $,

8 S

H

'

l Il $ $

D n 8 l

a 1 i es S 8

- T

!

( EN 58 <

l ea /

'

.

(

, ,

~

.

I

.

i  !

E u

- - - - - - - - < ,> , , ,

tossa

_

LONG RANGE SCOPE LIST FUTURE a MAINTAIN AS TRACKING SYSTEM FOR ORIGINAL LONG RANGE SCOPE LIST UNTIL COMPLETION - STATUS AND SCHEDULE m COMPLETION

- PROPERLY CLOSED

- PROPERLY TRANSFERRED TO OTHER TRACKING SYSTEM

- PROPERLY INVAUDATED e PROCESS IS AUDITED BY QUALITY m PERIODIC UPDATE STATUS TO THE NRC N ,

]

. _

r "::: m LONG RANGE SCHEDULE STATUS a CURRENT IDENTIFIED SCOPE

- ~ 586 HARDWARE ITEMS TOTAL

- 213 ITEMS LRSL ROLLOVER

= CYCLE 7 SCOPE

- ~ 211 HARDWARE ITEMS TOTAL

- 52 ITEMS LRSL ROLLOVER ( 4

)

-

- - _ - - - - - - -

f "?b'

SCOPE FOR CYCLE 7 m LOW PRESSURE TURBINE ROTOR REPLACEMENT l

m REACTOR COOLANT PUMP UPGRADES a CONTAINMENT FIRE PROTECTION UPGRADES m MAIN FW PUMP LOVEJOY CONTROLS UPGRADES a REACTOR COOLANT LEVEL MEASUREMENT a AFW PUMP PACKING UPGRADE a AUXILIARY BOILER REUABlUTY IMPROVEMENTS a SMART AUTOMATIC SIGNAL SELECTION SYSTEM a CONTROL ROOM DESIGN REVIEW UPGRADES m FUEL HANDLING EQUIPMENT UPGRADES N ,

Y

-

e .

N " '

,

e *

g

- - - , ,

t - - - - - -. - - -

(~~ '*:0 LONG RANGE SCHEDULE EFFECTVENESS a EVALUATION IN PROGRESS

- COMPARISON TO OTHER PLANTS

- USER FRIENDLINESS  !

l - PROCESS FLOW l

, - PRIORITIZATION PROCESS

m UPDATE AS NECESSARY i

ll

%

l

- - - - - - , , ,

_ - _ -

,

r <"::: %

SUMMARY a LONG RANGE RESTART COMMITMENTS ARE BEING TRACKED a LONG RANGE SCOPE UST WILL BE MAINTAINED FOR I STATUS AND SCHEDULE  !

l m LONG RANGE SCHEDULE PROCESS IN PLACE / CURRENTLY UNDER EVALUATION FOR EFFECTIVENESS m PERIODIC UPDATES WILL BE PROVIDED a LONG RANGE SCHEDULE PROCESS SUBMITTAL WILL BE MADE

.

.

..

  • -,

'

O

.N . a

- - - - - .- <- , , , , ,

- - - _

,

PLANT PERFORMANCE DEPARTMENT STAFFING

<= 7 SOURCES OF CURRENT STAFF (TOTAL 44 PERSONNEL)

SRTP l 20 -

l 18 -

d 16 -

y- @ 14 -

m M 12 - MAINTENANCE E5 10 -

g R/S g 8-b z

6-CONTRACTOR 4-2- OTHER SITE

^

O ( .

J

.

KRE .

CEC .

O GN AA R NN A B AE E MTN V I A

A M D 4 W $

%

=

E

=

'

"

m

'

'

d C

N M A -

N m E T

N I

A M

%

,

@

1 ! l 11 i

,, - _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _

(

-

c _

A f v A

!b !! o

[ x 1 b m

!NN k-f D s

- -

'

<C b h\\\\

t w m

s :.

LtJ s ( _

D o -

"

-

,

( h e a l

x hk\kh\\\kkkkhN .

..

i l

i i i i i i

'

8 8 ? 8 R e S1S3nO38 'HBOM N3dC ,dC 838 LN nN ,

-

.

-

_ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ . _

_ - - - - - _ - - _ __

( '""" %

WORK REQUEST BACKLOG

= CURRENT BACKLOG IS ~1000 CORRECTIVE MAINTENANCE WORK REQUESTS l

l - FROM A POST-RESTART HIGH OF 1270

m AVERAGE MONTHLY COMPLETION RATE FOR MAINTENANCE l ACTIVITIES

- CORRECTIVE ~500

- PM'S ~700

- SURVEILLANCE ~100

- TOTAL ~1300/ MONTH ( ,

J

_

__---_---_-_m , ,

coa;>>-

,

BACKLOG REDUCBON

= MAINTENANCE GOAL FOR CORRECTIVE BACKLOG

~S00 WORK REQUESTS BY 1/1/89 m BACKLOG ACBON PLAN

= SHORT ltRM

'

- INCREASED THE AMOUNT OF PLANNERS

- INCREASED THE AMOUNT OF LABOR SUPPORT l

l m LONG TERM

- SUPPORT THE NEW QSS SCHEDULE

- ESTABLISH A NEW JOB FUNCTION WITHIN PLANNING; LONG RANGE PLANNERS

- DEVELOP PROCEDURES FOR REPEATED CM WORK REQUEST

- VISIT AND IMPLEMENT LESSONS LEARNED FROM THE THREE HIGHEST RATED PLANNING DEPARTMENTS IN THE INDUSTRY N ,

)

.

_

- Y,

'

- 0 o 8 -

3 n 9 8 8

' E I

/

- G A

L R 5 E 6 V 9

- A8 I

/

E 8 4 T / 1 9 A /

R

1

, 1 9 1 8 F I

/

N FO 3 OT 4

- O I

K R8 7 T O8 W/

1 9

A I

1 /

- N / 8

N I

O 8 2 .

M D 2 9 I E I 8 S /1 L A E B 3

- G 2 8 8 ,

I

/

O 7

1

- L 3 K 3 8 C I

/1

- A 1 B

. 8

, l

/

0 .

P .

_ 8 l

/ .

_ 6

6 8

- - /

~ - - - - 8 .

0 0 0 0 0 0 U -

0 0 0 0 0 0 7 5 4 3 2 1 l l l

_ - - - - - . , . , . ,

_ - - - -

f ' *:".' %

MAINTENANCE BACKLOG WORK REQUESTS .

PM'S s BACKLOG REDUCED SIGNIFICANTLY a AS OF 8/88 616 l

= AS OF 11/88 337 m NO E.O. P.M.s OVERVIEW l

= AVERAGE WORKOFF RATE PER MONTH 45 m TARGET FOR EUMINATION OF BACKLOG 5/1/89 L .

J

- - , , , , ,


-

f "$$

WORK REQUEST TRENDING PER MAP-009 m SYSTEM EVALUATES THE THREE SYSTEMS REFLECTING THE HIGHEST CORRECTIVE MAINTENANCE ACTIVITY m COMPONENT REVIEWS THE 10 EQUIPMENT 1.D.s THAT HAVE THE MOST CORRECTIVE MAINTENANCE PERFORMED e PREDICTIVE

- CURRENTLY UTILIZES - UNDER DEVELOPMENT LUBE CIL ANALYSIS THERMOGRAPHY VIBRATION ANALYSIS MOVATS ULTRASONICS a MAINTENANCE INTERVAL ROOT CAUSE EVALUATION TO ENSURE APPROPRIATE CORRECilVE ACTION IS TAKEN AND MEASURES TO PREVENT RECURRENCE ARE ESTABLISHED N .

]

v

- - - - - - - --

- - - -

( '$$

RESULTS OF PREDICTIVE TRENDING m BEARING REPLACEMENT IN DECAY HEAT REMOVAL PUMP e REPLACE FATIGUED BRAKE SHOES ON CRANE a REPAIRED LEAKING CHECK VALVES ON BACK UP AIR TO ADV's l

l m REPLACED DAMAGED WIRING ON HVAC UNIT a REPLACED WIRING ON HYPOCHLORITE PUMP N ,

Y

- ,- s , , ,


( ~::: m MAP -

0006 PRIORITIES a PRIORITY E SHIFT SUPERVISOR EMERGENCY a PRIORITY I IMMEDIATE ATTENTION l m PRIORITY 1 WORK TO BE PLANNED WITHIN 24 HOURS AND WORKED WHEN THE WORK PACKAGE IS READY AND MANPOWER IS AVAILABLE l

m PRIORITY 2 l

WORK TO BE PLANNED WITHIN SEVEN (7) DAYS AND WORKED i AS MANPOWER IS AVAILABLE a PRIORITY 3 WORK TO BE PLANNED WITHIN 30 DAYS AND WORKED AS MANPOWER IS AVAILABLE a PRIORITY 4 NON-POWER PLANT RELATED WORK OR MINOR PLANT WORK NOT AFFECTING PLANT OPERATIONS k ,

..

-.

.

_ _ - _ - - - _ _ __

( "$$

CURRENT WORK s ALL WORK JUSTIFIED NON-RESTART IS CONSIDERED PRIORITY 2 FROM Q.C.I. - 12, NOW RSAP-0215 l

- WORKED AS SCHEDULE AND AS PLANT CONDITIONS

'

ALLOW

- MAP-0006 PRIORITIES ARE IN EFFECT

! e OF THE 986 CORRECTIVE MAINTENANCE WORK REQUESTS

! JUSTIFIED FOR NON-RESTAFT, 341 REMAIN OPEN

- 177 ARE OUTAGE

- 51 ARE MATERIALS OR ENGINEER HOLD

- 113 ARE SCHEDULED N 5 A

a

ll; 1 1 YRS EAE L EC LI O CV R

RUE CNS B ,

L O M GC A B AI N

H C

E W T N

G N

I R

E E

N I

G N

E g

- - , ..

- - - - - - - - - -

f '$$

POST-RESTART NED ACTIVITIES a CREATE A MORE ORDERLY WORK ENVIRONMENT / ROUTINE a WORK OFF "BOW WAVE" OF ITEMS PUSHED AHEAD OF RESTART

- LRSLs, PDQs, CCTS, EARS, et APPROXIMATELY 3000 ITEMS COMPLETED e DEVELOP AND IMPLEMENT NEW NED PROCEDURES / PROCESSES

l m CONTINUE TO WORK ON ENGINEERING ACTION PLAN (EAP),

l REV.1 ACTIVITIES l l

m DEVELOP PLANS FOR FUTURE IMPROVEMENT

- EAP, REV. 2 AND >47 PROGRAM ACTION PLANS

- THIS INCLUDES "DESIGN BASES RECONSTITUTION" m PREPARE FOR UPCOMING OUTAGE

- FORECASTING OVER 200 DCPs BY END OF CYCLE 7

'

N .

Y

. .

- - - - - .

-

- - _ -

( "L".'D PLANNED NEAR-TERM NED ACTIVITIES a PROVIDE ENGINEERING SUPPORT OF PLANT OPERATION /

MAINTENANCE a CONTINUE PROCESSING DCPs (>200 BY END OF CYCLE 7) i l

a SUPPORT SIMULATOR DEVELOPMENT a TECH CENTER m IMPLEMENT PROGRAM TO MEET IND;VIDUAL PLANT EXAMINATION REQUIREMENT a IMPLEMENT CONFIGURATION BASELINE DEVELOPMENT PROGRAM N .

.1 i

N

)

)

7 o 7 -

I 3 n

(

, 1

,

T S

A -

C W E A 0 R h 9 O

W F E

F M m F I .

O T K

R O 9

W L

S R

L i l l ,I l 1 I l iil i I l n

-

T R

-

8 A

- 8 T S

0 0 0 0 E 0 0 0 R 6 4 2

$W _ lW$ _

.

-

(

l

_ - ,

- _ _ _ =- _ - _

f $?

POST-RESTART NED ACCOMPLISHMENTS m DEVELOPED AN ADDITIONAL 7 SYSTEM DESCRIPTION AND FUNCTIONAL REQUIREMENTS DOCUMENTS

- TOTAL 21 SYSTEMS NOW COMPLETE a COMPLETED AND ISSUED OVER 100 DESIGN CHANGES (ECNs AND DCPs)

m INCORPORATED OVER 6000 DRAWING CHANGE NOTICES a PROVIDED SUPPORT FOR 2 PLANNED AND 2 FORCED OUTAGES .

m INCORPORATED OVER 6000 MEL CHANGES a COMPLETED EASRTP REVIEW OF 19 "ADDITIONAL SYSTEMS" N .

]

-

- q

~~

_

  • .

,-- - , , _ _ , - , , ,

- - - - - ,-, - -

(3576A ( c-i ENGINEERING ACTION PLAN Cm nCURADON ECN CLOSURE CALCULATlON l PERIOOIC TECHNICAL AND BASEUNE CHECKUST PROCEDURE l l PROGRAMMATIC REMEWS PROCESS (2.2.u) (2.zi.4) REMS m g g (2.2.1.6)

z, _

CHANGES I I m 1 -

'

"

l 1 I DEScN oEScN CHANCE TECHNICAL l l l l ASSuRANT PACKAGE OVERSCHT g l l enc NEERS PROGRAM COWWITTEE g

(2.2.i.3) (2.2.1.2) (2.2.4.1) I I I I I CnC AcoED Suuo - -

1- --I - - J CURRENT ouAuTY I f -

REMEW SSR 1TEMS AUDITS '

l OUTAGE (2.2.2.i) (2.2.2.2) (2.2.4.2) 1 I l

WMK I I -

' '

AFW l !

POST RESTART SSR/ SIR WORK '

NRC NRC ASRTP FUNCDONAUTY ASRTP l l (2.2.2.3) REMST l l SYSTEM  ! l STATUS SYSTEM DESMPTION & FUNCTIONAL lyl REPORTS REQUIREMENTS DOCUMENTS g g SYSTEM DESIGN (2.2.3) (2.2.3.i) DESGN BASS VAUDATION l  !! ^*RN[w"";" _

l g ;

(2.2.3.i)

SYSTEMATIC SYSTEM ASSESSWCNT TESENG l f PRO * (2.2.3) S21-TYPE l l SSn-M (2.2.3, INSPECRONS l l INTECVONS

, _

~

i TEST WORKING (33 E b S)

(2.2.3.1) l I

l C'3 M")"

CROUP g g (2.2.3)

L _1 k ,

_

- - - - - - - - - - - - , - - > ,. ,

"

f DESIGN RECONSTITUTION OBJECTIVES a IMPROVED ACCURACY a INFORMATION EASILY ACCESSABLE TO MULTIPLE USERS e VALID / COMPLETE INFORMATION e CONTROLLED UPDATE PROCESS - INSURES ACCURACY a PROVIDES FOUNDATION FOR FUTURE ENHANCEMENTS l

I l

l ( ,

)

--

- _ _ - - , - - , , ,

- - - - - -

._,

DESIGN INFORMATION ENVIRONMENT l

/ / c - -" i I

./

CALC's

s@s p -~ L

/

STRESS

[/h I

/ / I jF__._______

I REPORTS l

'

-

s -

g; = g ,

!# " - J r- } r -~ ! O O O

' -' -

- -- - "

1 VENDOR I P & ID's DOCUMENTS I

- ___________J

-

/ Mgr / /

g

/wr -


 :

! / .

, , --

DESIGN El

~

-l BASIS RE '

,

-

q L f~ W

~

l  :

""! /

/m2esws / I OTHER DOC PER USERS ., RSAP 0302 DESIGN TECH PRO l INFORMATION DATA BASE l

l

.

- ~ - - - - - _ - ,-- ., , , ,

CF31srT)

R-G DESIGN BASIS DEVELOPMENT PROCESS 1988 1988 - = 1991 1991 SD & FRD

. _ _ _ _ _ _ _ _ _ _ VALIDATION AND SYSTEM 11 B&W AND RECONSTRUCTION DESIGN 16 BOP SYSTEMS OF DESIGN BASIS BASIS AVAILABLE l lNFORMATION DOCUMENTS l

i i l

l l PROMDES IMMEDIATELY AVAILABLE DESIGN BASIS INFORMATION

,

-

h

. .

l '

4 r

'

N O

8 -

r

R m O TS I

R

' NTE E GAL B S SM A U I

-

S ER DOI LL T FAL R NVA

- O I

A F _-

- F E

- N NL O OA I

NS D_ N

-

I t T OT T I

- U AIG TS AE AI CT E C DSAA I

n I FDJ T UE DB T DO I

N AR I

T AD E F P

- S V D O N I

- O ,

C = _~ = =

E

- R N

- G S L I

N E S O C N

A UE E

I T ND A A A

- D G L A R TI L

I SM E G E

G S E

V T DG P U SS sR C AN

_ N EN V i FUC E RI I UO S N I WSS R J G NTI N

Sl l M O PA O SU S

P E TS ES/N V

I S / R URT M E

_ G T NN I

L C I EO E EI DTI N P

G E DO D DIT PT R D D A -

N AS / N N .N U / BT NM E RS UR OE SSsO US PWT CE I

O LR RN0T E

I E LURCE P SLT A O S UITASOH SD ACDC E OAAXA PN - ERYRT AN EEPA D S ECEOI D B OVDSPO BA = = = e N E I R ===== C = = ====

_

k

! l

l l) Irllli1ll(l

,

,

,

T N

E t

  • F

,

N

- NG O L NET GI L

S

T L ORN I S t v

CN I I UE SE I ES D TTM ACf ED D

E D

,

TMM AEE U

A MEh S LE

-

P GT L

C I I g l l I l I i RTt F LARs

- RAS OI E SACAtt r ONY L .I FHV )' CI v HE FAS U NCE LI Sf T NM A I RD AGYRS I P A NOHAY ALPHS oooeo T E ET C M HR

- A 1 CO F P SP R R U / P

_ G C

E N

E T

S GU NS 3 G N T I

_ 3 W

E L

I C E

N NH

.

N N

ALN R C J AC EE E P LW t

_ C I

Y R

N O

R LE PT SS NOTO S 2EO 8 DR L A P OERTRSONB

_ G o oe CGI OI ECA SOACA) WL

_

_ S UHMSMAE L D E MGSE E A LLHL RI R T N - 3 E iLUCUMORR t

- N E

M I

L E R -

T C

L T

I I AI AI EHA L BPRPJCCD E S E 'w r ATG D 0 f N

O A

N BNA EN R

O

- 8

P J

O T

N N R G

- NMA A F - E I

T A

Z I

GM M

MA TP iI OPM I

TIA T AIC L

E T

-

-

-

-

B U

S P

T N

M I

G

S

I I

C S

E L

S ME AD I

S N

A CE ED RVE UEJ M

O

- D B

F M M%

N N ASI S R GG G J GD3 T - C T 4M PE EON

- R O

n K

I F P F

I - R A

L PE T EDNRRI RI OAPDE E

P N - P C S CUI W LV T O _ E D

NR I L

SGTTTI R AFNUU C C T OC I E

J

-

- R O _

I TS d

-

4P GUSO DNLOI BC

_ P rE / I DI C P . P

-

-

O AR LTI SLSTXM R I'

F

_

U S

~ oo F E&E ADEUU M%PDCESAP T

T C -

_ I L

Q

/

- -

p U

A Q

-

-

Ce o -

-

-

- _ E S F

C RE T A SS N OT N F LLRRON

_ NI T ONI A

T N

O S T R

E EEE f SE TTK0 RNE[

E H

~ -

I EI tsp W A o L

U S

I TIS A

O T O

C T

I N

U4NhIOL AU44 DST SSHHNNT NT G

I H RTC N R V S S EESSAAI ST

! UN O I I U R ' I l H E DD ML EI GET C G E H 8 E R YYK DW I MR I P C G U B9RRR8BD FEO T F U I NS A T OOAAA0OB GE NGS R N S R GT N C BBCGMBBT NC CAI E O I C A E T I A CNV P C SF M T N VF AD X EJ I f LR MA E DO T H M OE R C C F VT

_ DP f R G NN

_

M J A A N I I I O N O R NMA I TT I P OAM MT CS I L T OC Y E U TPf MLOE LT JM A C FART AI O MNR MC O CL RNT ROU EI LR I I POC OI O RROP NBS I E F TS UTR AAR DTJ NCE CCTE T AO f

HI E I AR OENRCCLH I MR RLOI SF F Tr RP oeo PECFI MI O MO

'. F D ANB EI C e

1l l-

l!

.

.

3 NRT

,

AEN C GE I

AM

-

, D NE E AG R MA

- N M A O M T S m

_ T N

E R

T L

A I

'

A .

- M M E

- G A

N

- A l M

- S L

A $

-

_

I E R

E

- T A

,

T M '

-

_

-

-

.

.

_

f -

_

Il l1l l!ll1Il

,

,

-

) )

,

)

s s o s a-

-

,

a c

- Y R

-

A M

M T

_ U N S E

_ S U M M T E

_ A A V R T O G TS S RR

_ R E OP O AT U F R S M -

_ TN S S I

P SE EM I

EM

_ T RT T VA I

N I N TR E TM E AG M SM C TO I

OO E R

.

I

_ -

E PC R NP -

R I U a a m

_ C O

_ R P -

-

-

_

_

_

_

_

_

_

_

_

[ k l l lLl ll

_ _ _ - - _ _ _ - - _ > < - , , - - - - -

f  ?!

PROCUREMENT PROGRAM SUMMARY POST RESTART COMMITMENT STATUS i PROCUREMENT PROJECT (ORIGIN ALLY PEAP)

COMPLETION ISSUE STATUS DATE i l

a EQ EQUIPMEfJT PIECE-OVER 1500 WR REVIEWED' 6/30/8S PARTS EVALUATION (CG:) 77 CGIDEs GENERATED

m POST EQ PIECE PARTS - ADDITIONAL WR SCOPE 12/30/88 SURVEILLANCE BY QA DISCOVERED / SCHEDULED FOR REVIEW l l

a LIKE-FOR-LIKE CGI -REVERIFIED 257 CGIDEs 6/30/88 )

DEDICATION VERIFICATION PERFORMED UNDER OLD PROCEDURES a RPS/CRD COMMERCIAL -EVALUATED 510 WRs/ 9/30/88 GRADE ITEM EVALUATION 19 CGIDEs PERFORMED a POST RPS/CRD - NEW SCOPE OF WRs 2/28/89 SURVEILLANCE j IDENTIFIEO/ SCHEDULED FOR REVIEW J

__ - . .

o / 6

' *

s .

-o

.g _

.

- - - - - , . .. ,

- - - _ -

orssn

[ a-o ,

PROCUREMENT PROGRAM SUMMARY POST RESTART COMMITMENT STATUS (CONTINUED)

PROCUREMENT PROJECT (ORIGINALLY PEAP)

COMPLETION ISSUE STATUS DATE E 10CFR21 VENDOR - 532 ASL VENDORS 8 / 31 /88 CONFIRMATIONS CONTACTED & PART 21 RESOLJTION ACHIEVED a EVALUATION OF - ALL 7.000 SERIES 8 /31 /8 8 AGASTAT RELAYS (CLASS 1) AGAST .TS I EVALUATED; 2 RE _AYS SCHEDULED FOR REPLACEMENT (8/89)

m EVALUATION OF - ALL FASTENERS IN 11/30/88 FOTENTIALLY STCRES EVALUATED DEFICIENT FASTENER (IN 87-02) - CLOSE INVOLVEMENT BY NRC

- ONE OPEN PDQ AWAITING CLOSURE l

- OVER 4,000 MHs EXPENDED TO RESOLVE N .

]

- - - - - - - - , . . . . .

( '":::%

PROCUREMENT PROGRAM SUMMARY POST RESTART COMMITMENT STATUS (CONTINUED)

COMPLETION ISSUE STATUS DATE aLER 85-14 - REVERIFIED ALL 9/30/88 CLASS 1 STOCK MATERIAL (17,000 i MHs AND OVER 2,100 STOCK ,

CODES) l

l

,

____-, , . ,

_ _ _ _

r ":M PROCUREMENT PROGRAM SUMMARY RECENT ISSUES l

COMPLETION ISSUE STATUS DATE aIN 88-05 - OVER 750 MHs PENDING RESEARCHING DIRECTION uIN 88-19 FLANGE MATERIALS IN 88-46 12/31/88 IEB-88-XX - EXTENSIVE RESEARCH INTO PMS AND PENDING PURCHASED CIRCUIT NRC/NUMARC BREAKERS

- OSER 2.000 MHs ANTICIPATED UPON ISSUANCE OF IEB 88-XX

,

,/

.

-

-

.

y .

.

.

. <

_

- .

- - - - - - -

- -

c e3si

[ n-o PROCUREMENT PROGRAM SUMMARY SELF-GENERATED INITIATIVES FOR PROGRAM IMPROVEMENT a MATERIALS ENGINEERING

- NEW GROUP UNDER MATERIALS MANAGEMENT DEPARTMENT

- PROVIDES FOCUSED ATTENTION, DECISION MAKING AND ACCOUNTABILITY FOR ALL MATERIAL PROCUREMENT AND USE AT RANCHO SECO

- STREAMLINED PROGRAMM ATIC AND TECHNICAL PROCEDURES IN DEVELOPMENT

- MAXIMlZES LESSONS LEARNED FROM RECENT NRR/ REGION V INSPECTIONS

= CRITICAL SPARE PARTS AVAILABILITY

- CRITICAL COMPONENTS IN 12 KEY SYSTEMS EVALUATED BY 12/31/88

- PHASE 11 - 44 SYSTEMS BY 6/30/89

- PHASE III - EQUIPMENT ANALYSIS BY 12/31/89

- CURRENTLY TECH SPEC LCO AND PLANT AVAILABILITY ORIENTED

= EXPANDED RECEIPT INSPECTION CAPABILITIES PLANNED

- STANDARDIZED RECEIPT INSPECTION PROGRAM

- ON-SITE TEST LABS INIBALLY FOR COMMERCIAL ITEMS; LA.TER FOR MORE COMPLEX ITEMS

,

. - .

. .

, _

~ ~

-

_

-

e . ma . -

.

1l l1

-

- NTG ONN S EIL B DU

.

.

.

ND

.

I

_

_

_

GE T E

_

H BIN C ORS B EP

_

U S

_

_

_

_

T N

E M

E -

G -

A

-

N

_

-

-

-

A

_

_

_

_

M E

G A

_

T

_ U O

_

_

_

ll

- - , .

- - - -

RANCHO SECO FOH-2 Recovery Schedule Oc t. 25, 1988 Oc tober 1988 2s - i .

e I 2 I e I r I e I ,, I , I , I s I , I , I ,, j Sofety Evoluoto O=ygen Level

& need for Scott Air Pocks

& Refill Air Bottles

.

i S

b ofety &

=O HP Survey Building

,-

! Building Wolkdown

HP. PP. Moint. Ops Evoluote Results

... . - . . . .

Repair j Mot,ilize Suspect Volve e Fer rniriit e LT 21SO3C g Reactor Rest or t C =O =O- Mg C-RCP l Sychronize vibration Anosysis i to Grid WORK ITEMS: (if Required)  ;

at 0400 g . .. ..-.. - .

-

l Mi P - Control Oil *

&d

& Filter Clean.in9 aHr Ho(ch WR 0160066 - Pocking C ,

OM Leak on HV20530 I&C SPs SP-406 A-D sec 6.14 SP-431 A&B SP-432 A&B

. , _ _ SP-2OO.OS 8- 109C

<.-> <s u m 32se ___ __ _.____ ._ ____

- n - - - - - - ,__, . .

RANCHO SECO FOH-2 Recovery Schedule Oct 25, 1988 October 1988 25 - T* 26 - wed 9 I 3 I s I 'I e I ,, I , I J I 3 I * I e I e, i , I m I s y I e I ,, I ,

I I 3 I , I , I ,I ,,

Safety Evoluote Onygen Level i

& need for Scott Air Pocks

& Refill Air Bottles N

p Sofety & HP Survey Building ""'"'""'"""'"5"'

.=,-em- ..uu o c u =

co

-:os . ,vss

-

.

Building Wolkdo n U N.s...

-

NA.Y*=rCU Yu sts s. u. , % ,c son s H P, P P. fA c.ont. Ops

.

-p .. e= v v .. .si .m . -- c.omc ce sm .u w =1

. . s ..s e c

.

c aa .w.ssw w= 6c wo } .cI ( Evoluote Results O- REPAIR valve !

RCS-SIO WR 145083! *

PDO 88- 1798 Reac t or Re stort L RP' .A m ,k c~ e h T T O ' C* Re pair"v'al ve

-

"g M ot,.h e HV-21510 WR 145085 '

-

Syc h roniz e

'

LEAK R E P A,R PDO 88- 1800 l to Gr d i h ;m

- w

.

'

. a

' Gt 1600 C - t< C P l V b.otion Anolysis l i (if Required) l G . - . .'

I O

R-isiOO TRouettsuoor l WR 14L192 PDO 88- 1797 l WD -- -;

t s

. s .o.c .. . . . &C SPs . LLRT Hotc h .'** **

, w

gy 345j43 = e s.s . .. ewa . r .

IC 8001105 l

e t L - _ . .. _ _ _ _ Mw s'~se*w%

_ _ _ _ - . - ,- . , , ,

_ _ _ - -

RANCHO SECO FOH-2 RECOVERY SCHEDULE O c t. 25, 1988 October 1988 2S T e,.

26 - Thu

"B3 I s I *I p I**I .I iI s I e I , F.; , T I 2 Is I I e I..I . I >I >I v I . .I >I s I - I , I .. I , I 3 I TI ,I .] Z Cofety Evoluot e Oeygen Level

& need for Scott Asr Pocks

& Refill Air Bottles POIENT6AL wOHK 41[us SCOPE ufP - Control Oet & f elter Cseos eerg wa i<, ooc 6 - PAcrir4G t cAx on Hv- 20530

.

-p Poa na-175=,

Sof ety & HP Survey Buildin9 wR 149129.A.B.C - HCP CHECx ost a cWLs

$-$ wa 145 9 s - usa cot 4 Hot Tc-3o;25 wR 14si90 - coo woo 3 2 ce 4 r ast Twansr En Guildin9 Wolk down wn 14*,oe4 - Arou. sTu Hrc c-360 (uu)

-p H P. PP.Mo.snt. Ops wa 3 4Soe4A- ATou. stu Htc c-3co (eC)

an 34 ,335 . p.e ,s4 ocPt4cc poup g-$ wR 139236 - CCiv s3 wR 137222 348023. 153330 two coratuot vAtvrs

p Evoluote Results t.1E ASURE FOR ttJCAPSULATIOfJ RCS-510 WR 145083 vE r 4 DOR PRLPARE REuovE IRECT PDO US-1793 E r 4 CAPSUL A T sGrJ SCAFFOLOtrJG REAC IOR REST ARI LCAITOLD ;C ;O  ;

M E r JC APSULAT E O c t.g o t,.liz e Repair Volse t iv- 21 *.,10 .

LEAK HE PAIR to C, TEAK REPAIR WR 145085 PDO HS- 1800 j o, i t,og g-c zu

,

- l

C-RCP * I

Vat,r atic,n Anotyr es p 1. L R T tiotcri C Corm usus

,

=O - -

1 i IC 600110S H - 1 *,100 T40001 f SHOOT  !

WH 14 *,192 l'bO 68 - 1797 *

. . . . . - . . - - - -

h t esc ss

s,. . . . o ._ . . . . .. , . ox .o

.

-

sa- 4 3 n aa n noa s s o ?.e

  • p - 4 5 2 ma te nao s e v s o I?cC LPs ,

f m,oS,ng ,go ,o, O-y ' 's r

  • -

Fee 3 4 14*39 hw S*(M.) MM 1 Tie 6 ie ee f* _ _ _ _

~

_ _ - - ~ , , ,

RANCHO SECO FOH-2 54ECOVERY SCHEDULE Oc t. 26, 1988 October 1988 25 T .,.e 26 - Wed 27 - Trou Mfs I e I _~ p Iee I *I J I s I *I y I,,j l l iI z I * I ,I**I *I 2 I z I v I e I*e iI 2 I s I , I _, I ** I * I 2 I s I r I eyn Sofety Evoluote O-ygen Level g

& need for Scott Air Pocks

& Refill Air Sottles wown scoet ( 4.32 mR 1S'#717 139642 - uf P CTL Ost CL t4 stag 61 WR 360066 - PACFsteG LfAM oen HV 20L30 PDO 85- 17L5 64 WR S 45315 - P-858A REFWE Puun

.

33 wR 137222 148023 153380 [HO PCV

p Safety & HP Survey Buildir*9 64 wR 149362 - Auto stos Ost c or41 Rot VAtvts g-g 6, wn 14Soo4 . ATou stu ncc c-360 (uu)

r.2 = = 14Lossa- arou. svu n[c c.360 (sc)

Ouilding Wolkdown si =R 145891 . usa coe4Tuos. IC-302 *S

p HP,PP. Maint. Ops t. 2 = R i 4si9o - Cuo s.oo i2 cp 4 rA THAresf [H h*4 6 mse 149 : 29.A.B.c - NCP CHECe( C4. t[vfts ET:

61 mR 13sp238 - CCTV # 3

.p Evoluote Results O MEASURE FOR Ef JCAPSULATIOtJ RCS-SIO WR 1450 VEr4 DOR PREPARE R E *.s OV E REACTOR LRECT PDO SS- 1798 E f 4CAPSULATIOrJ SCAFFOLDirJG HCSTANT SC AFFOLD $-M- ;C OC N

Et 4CAPSULAT E '.

M o t,iliz e Repair weve HV- 21 "> 10 LEAK R EP AIR I

LEAK REPAIR WR 145085 PDO 88- 1800 .

%

D)

'

i g-$

V)

( @ --

l . s u s ><o C-RCP ou 3 3,.c vibration Anolysis ac nooiio, C 20 -- --

R- 15100 TROUBLESHOOT WR 145192 PDO 88-1797 I h4 .e c - . ,

e n r m e - o < <. . e. r u.s. l V 439 A& ts n00 914, P 8 o'O I&C SPs C " w* * U ^^ "o,u ' ce' *< c i n .

x.o ,.os,,.,,,.en i ,e ,,,,

Q-----------r----_-_-r------,---------__---

_

,,3,.

r.. . m m.mmm

'

'

% e .

%

i

-

- - - , . _

RANCHO SECO FOH-2 RECOVERY SCHEDU LE O c t. 26, 1988 October 1988 25 - Two 2 6 - wed 2 7 - This 28 - Fri

. I 3 I s I r I e I,.I , I 3 I 3 I , I e I ...

TT3 D Ie13 I .. I = I s I s I v I e I,. ? I s I s i , I e I . I s I s I * I e I * R 2 I s I * I e I,* I e I s I m I , I e I ..

Sofety Evoluoto Onygen Level

& need f or Scott' Air Pocks

& Refill Air Bottles work scoPC MtA:

e 73.S9 WR 1",9717, 1S9642 - a,sf P CTL Ost CLN8PdG 61 WR 360066 - PACKateC LEAK o< M 2O530 POO eS-1755 64 WR 145315 - P-OSSA REPLACE PUuP

. .

11 wR 13u22. 14 8023 1s32eo 04o Pcv-p >o f e ty & HP Survey Duildin9

,_ 64 we 3 49362 - Auto sTop om. cor4Twot valves

& C wR - RLPNR LLAK LT-21503C

.

64 wu 145191 - wMe CONTROL 'C- 30225'  !

Building Wolkdowr' 62 wR $ 45190 - CRD FOD 12 GP 4 FML TRANSTER !

HP 64 wR 14si aa - ea- Poo ss-1796

}g , PP, tAoint. Ops E nd:

64 WR 149129.A.B.C - RCP CHECK Ort LEVELS ET:

64 wR 139236 - CCTV # 3 p Evoluoto Results

, g tJEASURE FOR l EtJCAPSU AT40N RCS-510 WR , 50S3 vEtJDOR PREPARE E tJC APSULATE ERECT PDO 88-1798 ErJCAPSULATION LEAK REPAIR SCAFFOLD M b-- 0O >

Mobai2e MCSILIZE WELD VALVE It4 JECT ' RE REACTOR ,

LEAK RE P A!R CLEAN i RCS- 510 RCS,510 SCAFF RESTART H PREP Gv :D& ---- ----- C C-RCP ERECT trJJECT , . - - - - <' :

vibration I.noty sis . SCAFF LT-21503C t_LRT Hotch

$- - m$ j t tAta 145148

'

R E IC 6001105 R 11,100 TPOUBLESHOOT c r-WR 14 *,192 PDO 88- 1797  %

Rep;dprpofvo O'4 y 145085

-'

PDO 88- 1800 Ac ws R&C SPs CPL sp-406 4-0 s.c 6.14 1497s6.e. h-.

_- -- v----- ;h SP-431 Mb 800110 CPL SP-432 A&8 8001109.1 O SP-200 O*, . s- t o9C M001106

[ p . ;g "Wa*lh's s

. - * ,

  • g 8

4

- -

_

.

RANCIIO SECO FOH-2 RECOVERY SCHEDULE O c t. 27 I088 October 1988 2 *., T 26 ** .d 27 - i tsea 28 - ;Hj fddG * I * IaJ Is I * I e I * * ,I s I J .L P **I *I 2I M M t I** * I 2 I s I * I e I * * I * I 2 I m I * I e GTTT ETJ I*Iph I* Isis.JM ,J.] ]

Sofety Evoluote O ygen Level g

& reced for Scott Aar Pocks * T

  • -

" RCfill Air Octtle* as e.e . 73.o s wu tL97:7 s S96e 2 - nas e ;tt ont Ct un e 54 145663 - HLPA84 LEAM HCS S t O ST)Q OP3 - t 793 09 Jn 6s 14LC65 . HLPAnk afAM H4-21Sto PDO 88-1800 09 mu s60066 - eacM t tw on we - 2v So Poo es . i 7 S 69 mR 345395 - P-SLMA #d[PLACL PuemP y Sofc1y & HP Survey Builde ** *R 837222. 14s023.153300 (no eCv 04 ws< 149 362 - Auto stop ost Cotaspa v4vts 24 mR 14398MO- HI PAsp tfAM L T - 21 SO SC Ptr3 85- 1008 23 wu 147Lb9 - preAsu afan secs 602 e wu 14S19s - sesse Con t ou C - 30 Guelden9 Wols do.vn 62 mR 14Ss90 - CHO NOO 12 GP 4 r aat Tswass tH p 6 4 P, PP, fJoint. Ops

.

o. .a i. Sis, u. 3,4 roo 33 3796 g ( DA L wH I 4 9129.A.f4.C - S*C P C H( C M DEL t [Vf LS 64 m14 1392.56 - CCTV #3 p fvoluote Results O fJE ASURE f OR Etcct [f JC APStr.AllOf J VE f JD. tR PREPARE [f JC AF'5ULAT E Rc a, 510 RCS ",10 Ef 4C A8'SUL AT IOf J tCAK R E P AIR Scof f ofd M " ^ - - " " ^ ' " -

$ -- --- - $ ".1t O BeLI.*E O'M u u t,.a r e Cl EAf3 WEL D vat _Vf StiJLCT IIEACIOR l

Hl:PA:n y Pkt i P C S 'r1 0 U S-510 RLSTART e t :-e:

H H -toREPAIR CL E Af J

=> Q,g

>

l C PCP ERECT LT - 21 SO3C LT - 21 SO 3C 2CAff v.t .e o t . .r. Ae.oif ,is SC AiT 2nd OFT 2nd OFF ttRT n o t I W M LOO ;O :O REM 6> .ioi i 4 *> i 4 es IC 0001105

!

R-15100 T rot tHL t Se 4001 af ASPECT SCAT WR 14 *,1 C ? I>DO BS 1797 a RCS-602 M D 4 Repair Vot <e uv-21510 _ _ _ . .

'

s .g c sp., ar c ss %

x. g .. CPt. SP 406 A D se t, 14 8 4 9 70-t. H. .

g ___________ _____ .-_____. --_________

_ _

c n ss>-43i Au. sm i i m."

C Pt. SP 4 3 2 A O m *O ' 8 ' " . 8 0 SP- 2OG O's $ I O1*C t%A118 D6

~~

-~~

    • "*

. ._ *'f v ! . _ . _ _ .

_ _

RANCHO SECO FOH-2 RECOVERY SCHEDULE Oc t. 27, 1988 October 1988 25 - tw 26 - ne ed 27 - T hu 28 - r ] gsTe% 7..I,IJIsI*Ie ,I2 I _p I * I e I , * I * i s I s I * I e f * *

  • I3I2IF IeI**IeIJ I sa I * I e I * * ] , I 3 I s I e I e IesI e I 3 I s I eIeI**]

Sofety Evoluote Oeygen t. ev el

& rece d for Scott Air Pocks o wR 14*,os30- plus mut. 9Cs.Sio

& Refill Air Bottles uu: e 3.61 we 159717 159642 - adrP cTL os cts t c e 64 mR 145083 - REPAR LEAM HCS 510 POO 88 1795 73 WR 1 eSOSS - REPAJR LEAM Hv-21510 PDO 88- 1800 69 WR 160066 - PACS ( LfMC on *W 20S30 POQ BS- 17*.S 73 WR 3 45315 - P-858A HLPLACE PuedP

.'p Sofety & HP Surve*y Busedsn9 11 PR 137222. 148023. 1533So EHO PCV C4 WR 149362 - AUTO STOP Out CONT *FCq, VALy[$

g 61 WM 14395S5- REPAse LEAM LT 21SO3C Poo eS-iooS 61 WR 14 7S69 - REPAs4 LEAst C-4,02 PDQ 58-1803 Duilding Walk down e mR 14S101 - uSR CONTROL 1C-3022S HP, PP. tAoint. Ops 62 wR 14S190 . cHo Roo 12 c.P 4 r A4. TRusSTER 4, 6* "R **Sina - un eaa as-1796 E s mR 149129.A.D.C - RCP CHECM ost ([vtts 69 WR tfAX)otA- uGTOR LOAD do CUH84L N T LT: 64 *R 139236* CCTV #3

'A Evoluote Results O

MOBILIZE Erect CL EAf J WELD VALVE ITJJECT RCS-510 PREP RCS- 510 RCS-510 Sc of f old M $4 - - - [( ;(

f Ao b.h 2" RE SCAFF REAC TOR LEAK REPAIR ry RESTART H 0 CLEArJ REPAIR I l C-RCP ERECT LT - 21503C LT-21503C .

V t, rot ion AnotySis SCAF F 2nd OFF- 2nd OFF V LLRT tiotCh W M 4 ^ ^ ___- ---._ 4 ; Q ..

-

($ MM 145148 l REPA IC 8001105 I R- 1 L 100 TROUBLED 400T Repoir Volve trJSPECT SCAFF WR 14 *,192 POO 66- 179 7 tiv-21510 RCS-632 i

$-4 $ --- $ --

Oh!NJECT VALVE I RCS - 602 s&C SPs s&C SP's j

$-- -

-- -- ---

~- w CPL SP-406 A-D sec 6.14 14 9 7 56.0. i CPL SP-4 31 A&B 800110 l CPL SP-4 32 A&B 8001109.10 CPL SP-2OO OS s-109C 8001106 j 8: " ..*t u . ""__.1_W_ :r'2"_1 ' tee _ er

  1. s

"

,

{- O s

/

_

a m . _

- - - - - - - - - ,

- - - - .

R NCHO SECO

'

FOH-2 RECOVERY S C H E- _- O c t. 28, 1988 October 1988 26 - wed 27 - T h., 2a .

M J]sI?IeI,I,IJIsIyIeI,,

79 9

,Im IsI ,I ,I..I ,I 3I s I eIe I., .I 3I3 I ,IeI,,I I3.3I ,IeI..',y3I ,y ,g ,y,,g ,y3y ,j ,y ,y g tou: 61 mR 14"sO5 30- 5tEPLACC eNSUL. 5tC5.*s 10 ww: 8 3.f,4 wR 1",9717. 159642 - MfP C1L Oel CLtd*dG 64 wM 14L08?,- REPAsR LEAM WCS S10 PDO B5- 1798 73 wR 145085 WLPAan LfAM Hv-21510 PDO 88- 1800 73 WM 160006 - PACM LLAst ces HV-20L30 PDO 88- 17L5 73 ww 14 s s i s - P esaA *E PtACC Pt*P WELO VALVE it wn 13n22. i4so23.1:,s3so [no ecv 64 wM 149 *42 - AUTO STOP Ott COedf ROL vat v[S RCS-SIO C

61 wM 14 3'ASSO- RCPAtM LIAM LT-21">O.30 PDO 55- 1005 61 WM 147*/.9 - REPAsR LEAM WCS-602 PDO 88 1803 O 29 aC; 85 ava 145191 - MSR CONT 5tOL TC .30225 62 wp 145190 - CRO NOD 12 GP 4 Fasl TRAed*> [ R .

  • ,t JJ EC T 64 wH 14*s189 - Ne- PDQ 65-1796 RCS-510 L vt M 14 9129.A.Hi. - RCP Ce<0CM Ost LEVELS g.9 wu 1600664- MOTOR LCAO & CupMENT

[T: e5 ask 139234 + CCTV p3

,

RCirJSTALL If JSULATIOrJ REM SCAFF

)

REACTOR g RESTART t

U< EC T CLEAR 4 LT-21 SO3C REPA R LT - 21503C (I

-

SC AI r 2 rid Off 2nd OFF .

HotC h

' pg. . _ - -- - - ; . . g _. . ._. . . .._ ..

. __ _ . . . . .. ..-._ . . _ . .

@Q uMLLRT145146 Repo;r Volw e REPA IC 8001105 S C A FI" HV - 217.810

.

M __ _ _ . . . . . _ _ _ . . . _ . . _ . . _ _ . .

srJSPECT IPJJECT VALVE RElfJJECT VALVE RCS-602 RCS-602 RCS-602

.

t 4 *

V *b Y m,

. * I w

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _

)

RANCHO SECO FO H - 2 GECOVERY SCHEDULE O c t. 28, 1988

__

20 med 27 - Tow, Oc t ober 1988 3 23 - F ri ;9 . sog

[iHfd*_] g ILt] LJ 2 I s I e I e I to e I 2 I s I f I_e I , I * I 312 I ' I F I ' *I3I2 I ? I e I * * I e I J I 2 I * I e I,,: * I 2 T s I e I . I ,1, I , I n I . I e s IssA t1 mR 3 4 508 3fs- 88[ PLAC C aNSUt_ . StCS $50 pea S 3. (-4 WW Dt 1S9717, 1 %(,4 2 - uf P C TL Ost Ct teer G 64 WM 14 S6e 3 . saEPAsp t (Asa #CS 510 PDO S S- 17'+S 7S wM 14* 095 - REPA*R LEAM *W-21510 PDO 55- 1800

.

7S w68 f f,0064> - PAC 8( L LAs< est tw 20330 PDO c5 17*,5 7*.a WPt 14 * 315 . P- BSSA ft( Pt. ACE PtsuP . VELD VALVE c. 4 WM 149*c2 - AUTO STOP Ost CotstPOL VAtytS t.9 Ws4 14 39ee8- HEPA#ft i tAaC ( T- 21 ? 03C iT)O e5- 100'5 m RCS-510 A

a t,4 wH 14 75tba 84LPAsR L EA*C NCS-(,02 PL,Q nn- I tsO3 WW f S w54 14S191 . MS84 CON 18eOL TC-30225 C1 w*e 14 SOS 3A- PLACf" FT+ 2102 7 A eq * .tRveCE *

o4 wu 14 S i es - ese 3.4 PDO 85- 1796 INJECT

= 7S wa :4 9129.A.te.C - 8<CP CHECst Ost. lev 0LS ,;C$.$10 73 w*t 14.,004, t,A - MOTOM 10AD Ar CuteME NT L T: eS wit 139236 CCTV #3

.

RElf JSTALL

~

if JCUL ATIOr 4 RE SCAFF

^

. p(k l

.

REACTOR

-'s 2 RESTART l co--9

'

Ct E Ard REPAsi PLACE FT-21027A ER[ C T L T - 21 *,0 3C L T - 21 '.,0 3C trJ SE RVIC C SCAFF 2 rid OFF 2nd OFF 6 Lt H ot c h _ gg

.

. . _ . _ . . . . . . _ _ _ . . . . _ _

(b uu.R14S14SY

.

REM C 8001105 Fe po.r vo t v e SCAFF HV-21510 A KA . . A

.._ Q4 .. I ar4?ECT IN 8'rCT VALVE REIN JECT VALVE HCL-GD2 HC S- 6Cr2 RCS- 602

....,..,,.... _

_. ,_ _1hatitusam

_ _ _

,

.

-

RANCHO SECO OUTAGE MANAGEMENT ORGANIZATION (OUTAGE WORK ITEMS OtJLY)

CEO NUCLEAR DIRECTOR QUALITY ACM tJUCLEAR POWER PRODUCTION TECHuic[SuwORT l

'

l l

MAtJAGER '

SCHEO. & OUTACE i I

MAtJACEMEtJT l

. . . . . . .

..7......

.

.

mat 4AGER MANAGER ^ I M, 'tJTENANCE CHEMISTRY

.

PERFO MANCE .

ENG r EER NG

.

.

_

MArJACER ^"^

^ SHIFT MANAGER MANAGER OPERATIONS MATJACER pg LICENSING MATERIALS

. . . . . . . . . . . . . . . . -

SHaf T H.P. SHIFT " ' '"

SUPE RVISOR L OUALITY SUPERVISOR . ,ffpORT CONTROL

-

THESE RELATsorJSHsPS ARE MAINTEf4ArJCE EST ABLsSM[D FOR OUTAGE SYSTF i SH3f7 MATERIALS WORM SCOPC. woHM PRIO R- EtJGINE SUPERv SOR sisC S, AND SCHEDtA E cw PER M N E * E C uisON

.

_ ________ _ _ _ _ - - - ------ ---

y m

l 1!i 1

, J TR L AE I

R L I

F C U

.

N F ,

H OE PC E

S O

J S

N O

I T

S E

U Q

/

N O

I S

U L

C N

~ O C

-

r ,