ML20154E995
ML20154E995 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 03/31/1988 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
To: | |
Shared Package | |
ML20154E975 | List: |
References | |
50-482-88-14, NUDOCS 8809190212 | |
Download: ML20154E995 (70) | |
See also: IR 05000482/1988014
Text
_ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
!
. .
[
1
,
G
FINAL SALP REPORT
l
U,$. NUCLEAR REGULATORY COMMISSION ;
REGION !Y
l
SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE
i
NRC Inspection Report 50-482/88-14
Wolf Creek Nuclear Operating Corporation
'
Wolf Creek Generating Station
March 1,1987, through March 31,1988
i
8809190212 000912
i
'
ADOCK 05000482
O pg
I
(
, '.
. '.
,
1. INTRODUCTION
The Systematic Assessment of Licensee Performance (SALP) program is an
integrated NRC staff effort to collect available observations and data on
a periodic basis and to evaluate licensee performance based upon this
information. SALP is supplemental to normal regulatory processes,used to
ensure compliance with NRC rules and regulatiens. SALP is intended to be
i
sufficiently diagnostic to provide a rational basis for allocating NRC
resources and to provide meaningful guidance to the licensee's management
to promote quality and safety of plant operation.
1 An NRC SALP Board, composed of the staff members listed below, yet on
May 17, 1988, to review the collection of performance observations and
data, and to assess licensee performance in accordance with the guidance
in NRC Manual Chapter 0516, "Systematic Assessment of Licensee
Performance." A summar
provided in Section !! ofy of thereport.
this guidance and evaluation criteria is
1
l T'his report is the SALP Board's assessment of the licensee's safety
performance at Wolf Creek Generating Station for the period March 1, 1987,
through March 31, 1988.
SALP Board for Wolf Creek Generating Station:
L. J. Callan, Director, Division of Reactor Projects, Region IV (chairman)
J. L. Milhoan, Director, Division of Reactor Safety, Region IV
M. R. Knapp, Acting Director, Division of Reactor Safety and
Safeguards, Region IV
D. D. Chamberlain, Chief, Reactor Project Section A. Region IV
B. L. Bartlett, Senior Resident Reactor Inspector, WCGS, Region IV
P. W. O'Connor, Project Manager, Nuclear Reactor Regulation
The following personnel also participated in the SALp board meeting:
i
J. M. Montgomery, Deputy Regional Administrator, Region IV
A. B. Beach, Deputy Director, Disision of Reactor Projects Region IV
J. P. Jaudon, Deputy Director, Division of Reactor Safety Region IV
R. E. Hall, Deputy Director, Division of Reactor Safety and Safeguards,
Region IV
J. B. Baird, Technical Assistant, Division of Reactor Projects, Region IV ,
C. A. Hackney, Emergency Preparedness Analyst, Region IV
J. L. Pellet, Chief, Operator Licensing Section i
'
R. J. Everett, Chief. Emergency Preparedness and Safeguards Programs
Section, Region IV
R. E. Baer, Chief, Facilities Radiological Protection Section, Region IV
W. M. McNeill, Reactor Engineer, Materials and Quality Programs Section,
Region IV ,
!
!!. CRITERIA
Licensee performance was assessed in 11 selected functional areas.
Functional areas normally represent areas significant to nuclear safety
and the environment. Some functional areas may not be assessed because of
1
l
l
l
_ _ _ _ _ _ _ _ _ _ _ _ __ _ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ - _ _ _ _ _ __
'O a
l
'. .
2
.
- little or no licensee activities or lack of meaningful observations.
'
Special areas may be added to highlight significant observations.
l One or more of the following evaluation criteria were used to assess each
I functional area:
1
1. Management involvement and control in assuring quality.
2. Approach to the resolution of technical issues from a safety
standpoint,
3. Responsiveness to NRC initiatives.
4. Enforcement history.
5. Operational events (including response to, analysis of, and
corrective actions for).
6. Staffing (including management).
However, the SALP Board is not limited to these criteria and others may
have been used where appropriate.
Based upon the SALP Board assessment, each functional area evaluated is
classified into one of three performance categories. The definitions of
these performance categories are:
Category 1. Reduced NRC attention may be appropriate. Licensee
management attention and involvement are aggressive and oriented toward
nuclear safety; licensee resources are ample and effectively used so that
l
a high level of performance with respect to operational safety and
construction quality is being achieved.
Category 2. NRC attention should be maintained at normal levels.
Licensee management attention and involvement are evident and are
concerned with nuclear safety; licensee resources are adequate and are
reasonably effective so that satisfactory performance with respect to
operational safety and construction quality is being achieved.
Category 3. Both NRC and licensee attention should be increased.
Licensee management attention or involvement is acceptable and considers
nuclear safety, but weaknesses are evident; licensee resources appear to
be strained or not effectively used so that minimally satisfactory
performance with respect to operational safety and construction quality is
being achieved,
,
1
l
,
. .
. .
3
.
!!I. SUMMARY OF RESULTS
The SALP Board review revealed areas of strength in fire protecti*on and
security with an increase in performance from the previous SALP period.
Performance in the areas of emergency preparedness and surveillance
remained consistent with the previous SALP period. All other areas
revealed a decline in performance or a declining trend from the previous
SALP period. The overall decrease in performance is due, in part, to the
failureoflicenseemanagementtomaintaineffectivecontrolofmajor
ottages.
The licensee's performance is summarized in the table below, along with
the performance categories from the previous SALP evaluation period.
Previous Present
ory
Functional Performance Category) Performance
(02/1/86 to 02/28/87 Categ/88)
(03/1/87 to 03/31
A. Plant Operations 2 2
B. Radiological Control 2 2
C. Maintenance 1 2
D. Surveillance 2 2
E. Fire Protection 2 1
F. Emergency Preparedness 2 2
G. Security 2 1
H. Outages 2 3
!. Quality Programs and 2 3
Administrative Controls
Affecting Quality
J. Licensing Activities 1 2
K. Training and Qualification 1 2
Effectiveness
IV. PERFORMANCE ANALYS!$
A. Plant Operations
1. Analysis
i
i The assessment of this area consists chiefly of the activities
j of the licensee's operational staff (e.g., licensed operators
-
and nuclear station operators). It is intended to be limited to
i
i
- _ _ - . _ - _ _ _ - _ _ -_ - - _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ - _ .
- o a
'
.i
'
4
j -
t
.
I
] operating activities such as: plant startup, power operation. L
plant shutdown, and system lineups. Thus, it includes f
- I activities such as reading and logging plant conditions', .
'
responding to off-normal conditions, manipulating the reactor
'
'
and auxiliary controls, plant-wide housekeeping, and control ;
room professionalism.
This area has been inspected on a continuing basis by,the NRC ,
resident inspectors and on several occasions by NRC regional !
4 impectors. Specific areas inspected included operational l
'
se,ety verifications, safety system walkdowns, follow up on ,
significant events / problems, and review of licensee event ;
4
reports (LERs), t
i One violation was identified in this functional area and, while !
! it indicated additional management controls were needed, i
i corrective action was promptly initiated by the licensee. Also, l
j one of the escalated enforcement violations listed in the outage !
functional area included three examples of problems relating to !
the operations functional area. Four LERs were issued by the
i licensee in this functional area. These four LERs had no major ;
i effect on plint safety. One of the LERs concerned the one i
i violation that was identified in this area. The remaining three l
- LERs were all perscnnel errors and were indicative of a failure ;
) to pay attention to detail. ;
l Corrective actions initiated by licensee management included
- requiring the use of procedures in additional areas in !
I operations. At the end of the SALP period the use of procedures
in operations was much improved. j
,
! Operational events and NRC observations showed that operations !
'
interface with other departments is lacking. There has been an j
apparent failure of operations to make effective use of i
technical support groups. In some cases even when technical ;
l support groups became aware of problems and provided input to i
) operations, the input was ignored or was lost. There are two ,
examples. The first was when operations was not responsive to i
Nuclear Safety Engineering's information and advice concerning ;
'
. the essential service water (ESW) pipe-wall thinning issue. As ,
a result, timely corrective action was needlessly delayed. The ;
! second was when engineering provided disposition to repair a i
- section of thinwall safety-related pipe and the disposition was l
l misplaced for approximately 3 months. j
i l
In general, operator performance, as observed by the NRC 1
i inspectors, has been good. Control room professionalise has l
1 been maintained and good operator morale exhibited. At times,
- however, the operators failed to pay attention to detail. Two
examples of this are given below:
l
l
,
-
_____ _-__ _ _ ___ __________-__ - _ ____ ___ _ _ _ _ _ _ _ _ _ _ _ _ _ _
"
.. .
'
. .
, 5 i
. t
),
i
- The first example occurred when vital batteries were
allowed to be depleted over a 30-hour time span wi,thout a
procedure being available to provide alternate AC power to -
'
a the battery chargers, and without bus voltage being
observed carefully or without periodically observing ,
i current readings and comparing them to expected values. ,
j ' The second example was the uncontrolled use of operator
. aids, When ESF actuations occurred as a result of the ;
' degraded batteries, the operators relied on the l
l uncontrolled aids in determining that certain manual !
I isolation valves were shut. The valves were, in fact l
j open. Whenthevalveshadbeenopened,theuncontroIIed s
J
.
aid had been forgotten. This resulted in the undesirable
placing of lake water in each of the steam generators.
!
! The licensee continues to give strong management support to the :
l college degree program for operations personnel. The number of i
'
operators with engineering degrees or working toward degrees is !
i considered to be a plus, t
i :
l The number of operators with senior reactor operator licenses !
i exceed the number of operators with reactor operator licenses by !
1 more than 2 to 1. This allows the licensee mo'e versatility in :
the use of the operators, while at the same time giving !
operators additional training and mobility.
l In general, the licensee maintains a 6-shift rotation of their !
<
operating crews. This allows for a better utilization of the j
crews, less overtime, and increased training.
- 2. Conclusions j
< i
i The overall assessment of this area indicates that improvements
2
need to be made. As stated in the previous SALP report, !
licensee attention to detail in this area can be improved. The
, use of procedures in operations was noted to improve; however, ,
I
this occurred only after the situation had been a110wed to '
I deteriorate to an unacceptable level,
l The examples of inattention to detail and the lack of effective
'
operations interface with other departments reflects an
d
ineffective management oversight in this functional area,
i
! Staffing in this area is considered a strength, along with good
control room professionalism during power operations.
I The licen m is considered to be in Performance Category 2 in
i this area, with a declining trend.
l
!
i
i
. _ . _ _ _ - _ _ _ _ _ - ----
- . - - _ . _ - . - -- - - _ . - _ . . -
"
i. 4
i
h l
I
i
l.
6 I
i
! !
i
f 3. Board Recommendations '
!
I
a. Recommended NRC Actions j
]
The level of NRC inspection in this functional area should !
be consistent with the basic inspection program, t
i Supplemental inspections should be performed to. focus on l
I
! operations interface with other departments.
I
J b. Recommended Licensee Actions
- I
i Licensee management should ensure that there is an adequate I
'
and prompt QA, NSE, and engineering involvement in !
-
operational events and in the technical resolution to !
safety issues. l
^
B. Radioloalcal Controls }
i
1. Analysis I
1 l
-
The assessment of this functional area includes the following l
l areas of activity which are evaluated as separate subareas to !
l arrive at a consensus rating for this functional area: l
- (a) occupational radiation safety, which includes controls by [
J licensees and contractors for occupational radiation protection, f
j radioactive materials and contasination controls, radiological l
1 surveys and monitoring, and ALARA programs; (b) radioactive I
i waste management which includes processing and onsite storage l
- ofgaseous, liquid,andsolidwaste;(c)radiologicaleffluent j
controls, which includes gaseous and liquid effluent controls
'
L
and monitoring, offsite dose calculations and dose limits, i
j radiological environmental monitoring, and the results of the !
NRC's confirmatory measurements program; (d) transportation of l
radioactive materials, which includes procurement and selection i
'
of packages, preparation for shipment, selection and control of
i shippers, delivery to carriers, receipt / acceptance of shipments
- by receiving facility, M riodic maintenance of pa
- kagings and, ;
,
for shipment of spent fuel, point of origin of safeguards
I activitiest and (e) water chemistry controls, which includes
! primary and secondary systems affecting plant water chemistry,
I water chemistry control program and program implementation, j
i chemistry facilities, equipment and procedures, and chemical i
j analysis quality assurance.
Nine inspectiet.s were performed in the area of radiological
controls during the assessment period by Region-based radiation
specialist inspectors.
l There were five violations and one deviation identified in this
j functional area.
1
4
. - - _ ._ _
. .
,
I- f
1 . *
[
!
I
.
I
a. Occupational Radiation Safety f
i The licensee's programs for occupational radiation ;
. protection, radioactive material and contamination :
i controls, radiological surveys and monitoring, and ALARA l
4
programs were inspected four times during the assessment !
,
period. Two inspections were conducted during normal d ant l
operations, one inspection during a scheduled refueling ;
outage, and one special inspection after the release e.f (
radioactive material to the local county landfill. t
)
The licensee's exposure for 1986 was 142 person-rem r
I
compared to the national PWR average of 3)2 person-rem.
I
During 1987, the licensee's person-rem exposure was 124 _
compared to a national PWR of 376 person rem.
(
l
The size of the radiation protection staff was dequate to l
! support olant operations. A low personnel turnon t rate t
I within the radiation protection group was experiened
i during the assessment period. The licensee's approach i
i concerning the resolution of technical issues indicated ;
their understanding of issues was generally apparent.
!
Acceptable resolutions were generally proposed in response !
l to NRC initiatives. [
Those violations identified in the radiation protection f
program were an indication of a lack of management l
involvement in assuring quality and worker training. The [
two concerns noted during the previous assessment period ;
,
which included: (1) lack of steam generator mockup ;
- training and (2) lack of health physics supervisory i
- personnel presence in the plant to oversee and evaluate i
i
ongoing radiation protection activities, had not been fully [
) resolved. l
t
'
The licensee had made changes in the position of radiation
protection manager, an individual with limited emperience [
,
and not qualified in accordance with Regulatory Guide 1.8 l
1 was appointed to the position. The licensee recently [
- contracted a qualified indiv8 dual to oversee and provide
- direction to the radiation protection program, j
1
b. Radioactive Waste Manage ent
]
! >
j The licensee's program involving processing and onsite !
,
storage of solid waste was inspected twice during the f
J assessment period. One violation was identified. The !
] licensee released radioactive material as trash which was !
l found thd recovered froa the local county sanitary t
i landfill. The licensee had reduced the volume of !
-
solidified waste generated by use of a portable l
l
< i
I I
- .
. .
'
.
.
8
demineralizer skid for liquids and processing spent resins
by dewatering methods. The licensee had identified key
positions and defined their responsibilities,
c. Radiolooical Effluent Con _tro_1_ and_Monitorina
This area includes gaseous and liquid effluent controls and
monitoring, offsite dose calculations and dose limits,
radiological environmental monitoring, radiochemistry ,
program, and radiochemistry confirmatory measurement
esults. Three inspections were conducted during the
assessment period, together they encompassed the complete
program area.
.
The licensee has established a program concerning the
cor, trol and release of gaseous and liquid effluents.
Liquid and gaseous effluent release permit procedures have
been developed to assure that planned releases receive
proper review and approval prior to releases. A review of
gaseous and liquid releases indicates that offsite doses
were well below Technical Specification limits. Three
concerns were identified relating to: (1) liquid effluent
monitor setpoints, (2) condensate storage tank analyses,
and (3) radiation monitor calibration data.
The offsite radiological environmental tronitoring program
was inspected once during the assessment period. No
violations were identified. The adiological environmental
monitoring program is effectively managed from the
licensee's corporate office and implemented by station
personnel. The working relationship between the two groups
has been exc911ent.
The radiochemistry anri water chemistry program which
, included onsite confirmatory measurements with the NRC
Region IV sobile laboratory w4s inspected once during the
assessment period. No violaHons or deviations were
identified. The results of ;re confirmatory measurements
indicated 97 percent agreemtn',, a slightly higher value
from the previous assessment period.
d. Transportation of Radioactive Materials
This area was inspected twice during the assessment period
in conjunction with the solid radioactive waste management
program. Two violations were identified; one violation
involved the lack of proper storage and control of quality
assurance records of radioactive material shipments, and ;
the second related to the lack of training provided to the
health physics supervisor radwaste. Corrective action
- - _ _ _ - _ _ - _ _
_ _
'
. .
'
. .
.
9
taken by the licensee has generally been timely and *
effective in this area.
Transportation activities at the site usually involve the
support and guidance from the corporate offices. The
,
licensee has established an adequate quality
control / quality assurance program for low-level. radioactive
material shipments. Transportation activity records are
complete.
e. Water Chemistry Controls
This area was inspected once during the assessment period.
-
The inspection involved the initial use of prepared water
chemistry standards for confirmatory measurement
'
evaluations. The results of the water chemistry
confirmatory measurements indicated 84 parcent agreement
between the licensee and the NRC's reference laboratory.
These results are considered within expected industry
performtnce levels. The inspection also identified four
concerns involving instrument calibration and the quality
control aspect of the water chemistry analysis program.
2. Conclusions
, The licensee's overall performance indicated a decrease in
effectiveness over the previous assessment period. Seven
violations and one deviation were identified during this
assessment period, as compared to no violations or deviations
being identified during the previous assessment period.
Inadequate management attention to NRC concerns is demonstrated
by the lack of resolution to the concerns noted during the
previous assessment period, which were: (1) lack of steam
generator mockup training and (2) lack of health physics
supervisory personnel presence in the plant to oversee and
evaluate ongoing radiation protection activities. Improvements
were noted regarding the implementation of the ALARA program.
The licensee's personnel radiation exposure history has been
better than (less than one half) the national everage for PWRs.
l
No significant problems were identified in the functional areas
of transportation of radioactive material, and radiological
. effluent control and monitoring. The licensee's program for
these areas appeared adequate regarding management oversight,
.
resolution of technical issues, training, procedures, and
J staffing.
The licensee is considered to be in Performance Category 2 in
this area. However, during the SALP period, performance was
4
__.__s_.________________________________.__________
. ,.
'. .
10
.
decreasing. Recent changes in management have not yet had time
to be effective. .
3. Board Recommendations
a. Recommended NRC Actions
The NRC inspection effort in this area should be consistent
with the basic inspection program with increased emphasis
on management involvement to assure quality.
b. Recommended Licensee Actions
,
Hesith physics supervisory personnel should spend more time
in the radiologically controlled areas evaluating and
observing or. going radiation protection work activities to
ensure compliance with station procedures. Management
should take action to provide training to technicians to
enhance procedural compliance.
C. Maintenance
1. Analysis
The assessment of this area includes all licensee and contractor
activities associated with preventive or corrective maintenance
l of instrumentation and control equipment and mechanical and
electrical systems.
This area was inspected on a continuing basis by the NRC
resider +. inspectors and periodically by NRC regional inspectors.
There were two violations identified in this area. These
violations involved the failure of the licensee to request a
code exemption when required and three examples of a failure to
follow procedures. There were 11 LERs issued by the licensee in
this functional area. One LER was due to inadequate
post-maintenance testing on a containment isolation valve,
another LER was due to an accidental mispositioning of a breaker
switch.
The escalated enforcement action that was taken due to the
problems which occurred during the fall refueling lutage
revealed significant problems within the mainterar.e
organization. These problems consisted of workers failing to
follow procedures, inadequate procedures, inadequate control
,
over special processes, and an overall breakdown of management
oversite of maintenance activities during the refueling outage.
i,
One of the major causes for the problems which occurred this
SALP period was workers failing to follow procedures.
_ _ __ _
. ..
.
0 .
11
.
Three of the findings in the escalated enforcement package were
workers failing to follow procedures. These included ipsuance
of the wrong weld rod material, use of the wrong weld rod
material, and failure to check for an energized circuit. There
have been multiple occurrences of Wolf Creek event reports
written for failure to follow procedures. The failure to follow
procedures was pervasive at the Wolf Creek site. This could
only exist if it was allowed to sicwly build up over a period of
months or years. Licensee management was not effectiva in
correcting the problem.
During the last quarter of the SALP eriod, the maintenance
management organization underwent si nificant changes.
Maintenance was combined with facili ies and modifications to
form maintenance and modifications. This change combines all
maintenance activities under a single manager. The
superintendent of maintenance transferred to the outage planning
group and the manager of facilities modifications became the
manager of maintenance and modifications. In addition, some
lower level managers were transferred and some positions were
eliminated. These changes appear te have significantly
strengthened the maintenance area.
2. Conclusions
The NRC found evidence of upper management support for a strong
maintenance program. However, the implementation of this
program was not adequately carried out. Management oversight of
the day-to-day activities in the area of maintenance declined
significantly during the assessment period. Several examples of
the results of this decline were identified. Towards the end of
theSALPperiod,majormanagementchangeswereimplemented.
These changes appear to have significantly strengthened
management oversight of maintenance activities.
The licensee is considered to be in Performance Category 2 in
this functional area.
3. Board Recommendations
a. Recommended NRP Actions
The NRC inspeccion effort in this area should be consistent
with the basic inspection program. The resident inspectors
should increase their inspection activities in this area
b. Recommended Licensee Actions
The licensee should follow through and assess the
effectiveness of their corrective actions. The licensee
!
l
l
l
.
.. .-
.
. .
,
)
"
12
should continue the increased emphasis on procedural
compliance.
D. Surveillance
1. Analysis
The assessment of this functional area includes all surveillance
testing and inservice inspections and testing activities.
Examples of activities included are: instrument calibrations,
equipment operability tests, special tests, inservice inspection
and performance tests of pumps and valves, and all otrer
.
inservice inspection activities.
This functional area was inspected on a routine basis by the NRC
resident inspectors and periodically by NRC regional inspectors.
The enforcement history in this functional area identified two
violations during this assessment period. Also, several LERs
were issued by the licensee during this assessment period.
Personnel errors and inadequate procedures were the predominant
causes of the violations and reportable events during this
assessment period. This resulted in examples of missed
surveillances, late performance of surveillances, inadequate
post-test review, and undesirable engineered safety feature
actuations which are similiar to problems which occurred during
tM previous SALP period.
During the previous SALP per'od, the licensee was rated a SALP
-
'
Category 2 in this functior.al area with a decreasing trend. ,
Although the enforcement and reporting history indi G te
improvement, as noted above, similar procedural and personnel
errors are being repea',ed during this SALP period. 1
2. Conclusions
The overall asse sment for this functional area indicates a
.
program for scheduling and tracking of surveillance activities
that appears adequate. Procedures in some cases did not address
I
all Technical Specification surveillance requirements
adequately. The repeat procedural and persornel errors indicate ;
that additional management involvement is needed.
The licensee is considered to be in Performance Category 2 in l
this functional area. l
l
l
. ,
i
- - - - - - - - - -
- - - - _ . . - - . , - , , -- ,--.--- ~ ..
-
, , ,
. _ _ _
.. ..
. .
13
.
3. Board Recommendations
a. Recommended NRC Action
The level of NRC inspection in this functional area should
be consistent with the basic inspection program.
b. Recommended Licensee Actions .
The licensee is encouraged to perform an indepth review of
the Technical Specification surveillance requirements and
ensure that the surveillance procedures address these
requirements. Also, additional management involvemen.'. with
surveillance activities is encouraged.
E. Fire Protection
1. Analysis
The assessment of this area includes routine housekeeping
(combustibles, etc.) and fire protection / prevention program
activities. Thus, it includes the storage of combustible I
material; fire brigade staffing and training; fire suppression I
system maintenance and operation; and those fire protection '
features provided for structures, systems, and components
important to safe shutdown.
This area was inspected by a Region-based inspector and on a
continuing basis by the NRC resident inspectors. During this
assessment period the fire protection group went through some
organizational changes. One change was the transfer of the fire
protection training duties from the supervision of the fire
protection engineer to the training department. The other
change was the transfer of the fire protection group from the
plant support organization to the operations organization.
The following observations were made:
. The licensee has made significant improvement in the area l
of administrative controls for fire barrier penetrations
and openings. Especially significant has been the
reduction of missed fire watch patrols.
. Control of transient combustibles has been effective.
However, housekeeping could be improved in the area where
trash is being deposited in other than approved containers
(example: openings in tube steel).
. Fire brigade / watch training continued to be 9utstanding.
The transfer of the fire training group to the t : inh.:
department has shown no adverse effects.
..
_
a
-
.-
. .
14
.
The licensee instituted a program to identify all fire barrier
penetration seals that were either never sealed or removed and
not resealed. This was an extensive program which the licensee t
aggressively pursued and completed.
2. Conclusions
The licensee has shown significant improvement in their fire
protection / prevention program. Management involvement, both in
the program as well as training, was evident. The mayor reason
i
for the improvement in this area has been the continu ng
dedication and hard work of the well qualified fire protection
engineer and training instructor.
.
The licensee is considered to be in Performance Category 1 in
t this area.
,
3. Board Recommendations
a. Recommended NRC Actions
' The level of NRC inspection in this functional area should
be consistent with the minimum inspection program.
b. Recommended Licensee Actions
The licensee should assure that the recent organizational
changes that have the fire protection engineer reporting to
a different group and at a lower management level does not
result in a reduction of management support.
1. Analysis
The assessment of this area includes the licensee's preparation
for radiological emergencies and response to simulated
emergencies (exercises). Thus, it includes emergency plan and
implementing procedures; emergency facilities, equipment,
instrumentation, and supplies; organization and management
control; training; independent reviews / audits; and the
licensee's ability to implement the emergency plan.
During the assessment period, four emergency preparedness
inspections were conducted by Region-based and NRC contractor
insper. tors. One of these inspections was the observation and
evaluation of an annual emergency response exercise by a team of
NRC and contractor inspectors. During the exercise, four
deficiencies from a previous exercise were closed and one new
deficiency was identified. The deficiency identified during the
exercise involved incorrect classification of the emergency as
l
l
. . ..
.
. .
,
15
an unusual event rather than an alert. The licensee's overall
performance during the exercise was evaluated as good. .The NRC
staff concluded that licen% = emergency response personnel
demonstrated their ability 'a protect the health and safety of
the public.
Three routine inspections resulted in identification of three
violations. One violation inicivcd failure to document required
communication tests of the emergency response facilities. The
other two violations, one of which was a repeat violation,
involved failure to determine availability of required emergency
preparedness personnel in the event of an accident. Training
was identified during the previous SALP period report as an area
. needing management attention. The licensee has developed lesson
plans, revised training requirements, and implemented a more
efficient record management system.
The 1987 SALP report stated, "However, several changes were made
to the onsite emergency planning administrator (EPA) position,
and the replacement EPAs have had little previous experience in
this area " Due to attrition, new inexperienced personnel have
been assigned the onsite emergency planning and preparedness
responsibilities. Discussions held with onsite management
l
revealed a difference of opinion as to what the functions of the
onsite emergency preparedness coordinator were and would be in
the future. The offsite emergency preparedness administrator is
located in Wichita, Kansas. The licensee has recently added
another level of supervision above the EPA, removing the EPA
further away from plant management. (This reorganization
presently is awaiting NRR approval.) The emergency preparedness
program appears to be in a transition phase with the shift in '
lead responsibility for emergency program to the corporate I
office. .
2. Conclusions
The violations issued in shift staffing and augmentation
indicate that the personnel notification method and procedure
requires additional improvement. Management attention should be
devoted to meeting regulatory requirements and licensee
commitments.
Licensee management attention and involvement are evident; ,
licensee resources are adequate and reasonably effective so that i
I
satisfactory performance with respect to operational safety and
construction quality is being achieved.
4
i
.. ..
.
. .
16
.
The inspection findings for this evaluation period indicate,
overall, that the licensee's einergency preparedness program is
adequate to protect the health and safety of the public.
The licensee is considered to be in Performance Category 2 in
this area.
3. Board Recommendations -
a. Recommended NRC Actions
NRC attention should be maintained at riormal levels.
Attention should be directed to licensee action taken
toward correcting the call-out drill response and shift
augmentation response times.
b. Recommended Licensee Actions
The level of management attention to the implementation of
the emergency preparedness program should be increased to
ensure proper response to NRC identified concerns relating
to call-out drill response and shift augmentation response
times. The licensee should expedite correction of the
call-out drill response and shif t augmentation concern.
Management should review the distribution of onsite and
offsite emergency program areas of authority and
responsibilities.
G. Security
1. Analysis
The category of security relates to all activities whose purpose
it is to ensure the protection of the plant. Specifically, it !
covers all aspects of the security program including ancillary
'
efforts such as fitness for duty and access authorization
programs. Examples are: the licensee's overall management
involvement in establishing protective policies; designing
physical security systems; submitting the security plan and ,
implementing associated procedures; selecting, training,
equipping, and supervising personnel maintaining the hardware
thatsupportstheprogram;andauditIngandmeasuringthe
performance of the security program.
This area was inspected on a continuing basis by the NRC
resident inspectors and on a periodic basis by the NRC
Region-based inspectors. Four inspections were conducted by
Region-based NRC physical security inspectors during the
assessment period. Four violations were identified, two by the )
licensee. 1
I
. -_.
,
- '
17
htcre was evidence of prior planning and assignment of
p iorities. Policies and procedures are wil stated,
ap repriately disseminated, and understandable. Decisionmaking
was sually at a level that ensured adequate management review.
The , w corporate structure, which includes a repositioning of
'
the Qu lity Assurance Department, is committed to continuing an
,
indepen ent and effective oversight of security related matters.
Manageme t reviews of identif: 4d security matters were timely,
thorough, nd technically sound. The initial review of security
incidents s improved and further examination for generic ,
significance has been enhanced. Records were generally
complete, wel maintained, and available. Rarely were
procedures and olicies violated. However, some cases of
l personnel failu have occurred and these appear to be
j associated with mporary employee hiring practices. Corrective
action on licensee identified violations was generally
effective.
f
4 A clear understanding security issues was demonstrated and
subsequent decisions r ected reasonable and prudent judgement
on the part of man . These kinds of judgements were also
demonstrated in the - in' nd Human Relations Departments
-
where security's a y forts, such as fitness for duty,
continual observation o m e's behavior, and the access
authorization programs we . ed.
_ There has been a major organiz on 1 restructuring of the
-
QualityAssurance(QA)Depar n. e changes have been too
recent to evaluate their impa e heretofore strong
'
-
security oversight.' effort. Th . e concern that these
l
-
changes will not provide the le 1, audit expertise previously <
h
provided. A review of these cha nd the quality of the ,
audits performed will be necessar he future. <
The licensee has been usually respon .e o NRC initiatives, but ,
there continues to be two long standing r ulatory issues i
attributable to the licensee. These are co trol room access and
alarm assessment capability. Technically so nd and acceptable
resolutions were proposed initially in most c ses, but
timeliness of resolution for these outstanding issues is slow. !
t
After considerable discussion, the licensee agr d that their
CCTV system had degraded and proposed proper cor ctive actions.
- One major violation concerning security personnel a tentiveness
'
was directly attributable to a member of the securit {
organization. It was promptly and effectively correc d. A few
- minor procedural mistakes by security personnel have o urred,
but were not repetitive. These mistakes appear to be in icative i
4
of a need to enhance the selection process for temporary l
l security personnel and to be persistent in programmatic
- training.
i
l
._ _ _. _ _ - _ _
_-- --._ _ __ _ _ - _ __ _ _ _ _ __ __ _ _ _ -
. .
17
There was evidence of prior planning and assignment of
priorities. Policies and procedures are well stated,
appropriately disseminated, and understandable. Decisionmaking
was usually at a level that ensured adequate management
review. The new corporate structure, which includes a
repositioning of the Quality Assurance Department, is connitted
to continuing an independent and effective oversight of
security-related matters. Management reviews of identified
- secu.*ity matters were timely, thorough, and technically sound. ;
The initial review of security incidents has improved and i
further examination for generic significance has been
enhanced. Records were generally complete, well maintained,
and available. Rarely were procedures and policies violated.
However, some cases of personnel failure have occurred and
these appear to be associated with temporary employee hiring
practices. Corrective action on licensee identified violations
was generally effective.
A clear understanding of security issues was demonstrated and
subsequent decisions reflected reasonable and prudent judgement
on the part of management. These kinds of judgements were also
demonstrated in the Training and Human Relations Departments
where security's ancillary. efforts, such as fitness for duty,
continual observation of employee's behavior, and the access
authorization programs were managed.
There has been a major organizational restructuring of the
Quality Assurance (QA) Department. The changes have been too
recent to evaluate their impact on the heretofore strong
security oversight effort. There is some concern that these
changes will not provide the level of audit expertise
previously provided. A review of these changes and the quality
of the audits performed will be necessary in the future.
The licensee has been usually responsive to NRC initiatives,
but there continues to be two long-standing regulatory issues
i in need of resolution. These are control room access and alarm
- assessment capability. Technically sound and acceptable
resolutions were proposed initially in most cases, but
timeliness of resolution for these outstanding issues is slow,
s After considerable discussion, the licensee agreed that their
CCTV system had degraded and proposed proper corrective actions.
- One major violation concerning security personnel attentiveness
J was directly attributable to a member of the security
organization. It was promptly and effectively corrected. A
!
few minor procedural mistakes by security personnel have
occurred, but were not repetitive. These mistakes appear to be
- indicative of a need to enhance the selection process for
) temporary security personnel and to be persistent in
} progranmcic training.
l
. .
. .
18
Occasional computer outage related events, construction / outage
worker misunderstandings of security requirements, and*
maintenance related activities were attributable causes to
violations. These events were identified and reported in a
timely manner.
Security organization positions were clearly identified.
Authority and responsibility was clearly defined. This included
the relationship with the rest of the corporate organization. A
new squad manning structure has allowed for training and
practice in squad response tactics. Temporary contract
personnel, while not meeting anticipated standards, have been
utilized to staff appropriate watchperson billets. However, the
employment practices used for these temporary watchpersons,
combined with their lower experience levels and abbreviated
training, appear to have had some adverse impact on the security
operation. It did accomplish the overall goal of providing
relief for the more experienced officers and to make them
available for more critical tasks.
2. Conclusions
The licensee appears to have an ample number of supervisors,
fully qualified security officers, and support personnel
assigned to the security department to comply with the several
security plans. With the exception of a few minor procedural
errors, the security force had operated at a high level of
performance. The licensee manroement's attention and
involvement with nuclear securt y is evident. Licensee
resources were appropriate and effective so that there was very '
good performance with respect to site physical and personnel
security.
i
The licensee is considered to be in Performance Categorf 1 in
this area. i
i 3. Board Recommendations
I
'
a. Recommended NRC Actions
The NRC inspection level of the security program should be
consistent with the minimum inspection program, with some
exceptions. Exceptions where a more expanded inspection
effort is recommended include: licensee measures to
enhance and maintain physical security systems; methods for
i
selecting, training, equipping, posting and supervising
security personnel; and changes to the QA function where
audits are performed to measure the performance of the
i security program rid its ancillary efforts.
l
-
-
.
.
19
b. Recommended Licensee Actions
.
The licensee should continue to probe the causative factors
of security events for broader implications and adjust
programs, training, disciplinary actions, maintenance, and
n ineering responses appropriately. The organizational
a ustments made in the QA area should be closely monitored
to nsure that the high quality of the security oversight
pro am continues.
H. Outage
1. Analysis
The assessment this area includes all licensee and contractor
activities associ ted with major outages. It includes
refueling, outage ment,majorplantmodifications, repairs
or restoration to m. components and all post-outage startup
testing of systems p r to return to service.
This area was inspecte n a continuing basis by the NRC
resident inspectors riodically by NRC regional
inspectors. In addit n, spection was performed by a
safety system outa if ion inspection (SSOMI) team. The
inspections included r el g activities, outage management,
-
planning and scheduling, ta majorcomponents/ systems
repairs and modifi, cation, up testing.
~ '
~
The licensee had two major o ring this SALP period.
There was a refueling outage c lasted approximately 101 days
and an outage to replace leaki r ctor vessel 0-rings which
lasted approximately 16 days. fU ing outage activities
included replacement of Raychem s '
s, replacement of eroded
essential service water pipe, annu , spection of the diesel
generators, removal of heaters from torque valve operators,
' umber one seal,
replacement of reactor coolant pump
replacement of the trip mechanism sha s the reactor trip
breakers, replacement of the tube bundle i thejacketwater
heat exchanger for diesel generator "A", re rk of Valcor valve
operators, cleaning of condenser tubes and in ections for thin
wall pipes. There were numerous significant o erational events
which were attributable to causes under the lic see's control
in this functional area.
There were four violations identified in this funct onal area.
Two of the violations involved escalated enforcement action and
a proposed imposition of Civil Penalty. There were t o LERs
issued by the licensee in this functional area. The t LERs
were on events that resulted in violations being issued.
- . . - - -
, . .._
. .
.,
19
.
k
b. Recommended Licensee Actions
d
The licensae should continue to probe the causative i
factors of security events for broader implications and
adjust programs, training, disciplinary actions, ,
maintenance, and engineering responses appropriately. The L
< organizational adjustments made in the QA area should be _'
1 closely monitored to ensure that the high quality of the '
security oversight program continues, i
!
j H. Outage [
a 1. Analysis !
4
The assessment of this area. includes all licensee and
f contractor activities associated with major outages. It i
includes refueling, outage ' management, major plant
'
,
!
modifications, repairs or restoration to major components, and
! all post-outage startup testing of systems prior to return to j
service.
'
I l
4 i.
J This area was inspected'on a continuing basis by the NRC
i
resident inspectors, and periodically by NRC regional
inspectors. In addition, an inspection was performed by a
safety system outage modification inspection (550HI) team. The
4 inspections included refueling activities, outage management,
- planning and scheduling, staffing, major components / systems
- repairs and modification, and startup testing. '
! The licensee had three major outages during this SALP period.
- There was a refueling outage which lasted approximately ;
j 101 days, an outage to replace leaking reactor vessel 0-rings l
) which lasted approximately 10 days, and a generator / exciter
outage which lasted 16 days. Refueling outage activities ,
j included replacement of Raychem splices, replacement of eroded
essential service water pipe, annual inspection of the diesel I
i generators, removal of heaters from Limitorque valve operators, l
l replacement of reactor coolant pump "B" number one seal,
j replacement of the trip mechanism shafts on the reactor trip j
i breakers, replacement of the tube bundle in the jacket water 4
j heat exchanger for diesel generator "A", rework of Valcor valve l
operators, cleaning of condenser tubes, and inspections for !
] thin wall pipes. There were numerous significant operational i
events which were attributable to causes under the licensee's j
control in this functional area,
j i
j There were four violations identified in this functional area,
i Two of the violations involved escalated enforcement action and
i a proposed imposition of Civil Penalty. There were two LERs
4
issued by the licensee in this functional area. The two LERs
l
were on events that resulted in violations being issued. l
i
I l
,. .. l
-
. . !
20
i
The two violations that resulted in escalated enforcement
involved examples of procedural control weaknesses that the NRC ,
considered significant. These weaknesses indicate mantgement
failed to provide an appropriate level of .unagement oversight
of safety-related activities. This is evidenced by the examples
sited below as well as other areas in this report. Management
oversight of outage activities was less than adequate as pointed
',
out by the six examples of failure to follow proceduras and foi
examples of inadequate procedures listed in the escalated
enforcement package. The NRC staff was concerned with the
licensee's lack of indepth analysis of these events. The
licensee's ability to perform root cause analysis and implement
timely and appropriate correr'.ive actions was a noted weakness.
-
During repair efforts on thin vall pipe due to erosion / corrosion
the licensee experienced some 'ifficulty. The licensee had on
site a contractor workforce knr..iledgeable and experienced in the
forming, fitting, rigging, and aligning uf heavy pipe. The
licensee decided to repair the thin wall pipe with their '
permanent maintenance workforce. The maintenance workforce was
not as experienced in this area as the contractor workforce.
1 This resulted in significant problems due to failure to follow
procedures, failure to follow work instructions, and failure to
, accomplish work activities by appropriately qualified personnel.
Maintenance management failed to realize the scope of work was
beyond their expertise. !
!
The licensee was generally responsive to NRC concerns, however,
there was a lack of aggressive response to identified problens
prior to NRC involvement. The licensee's investigation of
outage related events indicated a less than aggressive approach
to the resolution of technical issues. The 0-ring outage, which
was the second major outage of the year, indicated that the
- licensee failed to control the 0-ring cleanliness. The licensee
decided to restart the plant after the first outage with known
inner 0-ring leakage. ,
t
2. Conclusions c
. The licensee's ability to plan, manage, and maintain control over ;
4
complex outage evolutions was inadequate and resulted in escalated !
) enforcement action. The licensee apparently failed to believe in and
enforce strict procedural compliance. Aggressive management
4
involvement to address problems that occurred during the outage was ,
i
lacking, i
!
The licensee is considered to be in Performance Category 3 in this
I area.
!
a l
1
,
J
4
4
<
,
, .
.-
^ '
. .
'
21
.
3. Board Recommendations
.
a. Recommended NRC Actions
Supplemental NRC inspections should be performed prior to
and during the next major outage.
b. Recommended Licensee Actions
The licensee should ensure that lessons learned from the
previous outages are identified and reviewed for program
improvements. The results of this review should be
incorporated into outage planning and control.
I. Quality Programs and Administrative Controls Affecting Quality
1. Analysis
The assessment of this area includes all management control,
verification and oversight activities which affect or assure the
- quality of plant activities, structures, systems, and
components. This area may be viewed as a comprehensive
management system for controlling the quality of verification
activities that confirm that the work was performed correctly.
The evaluation of the effectiveness of the quality assurance
system is based on the results of management actions to ensure
that necessary people, procedures, facilities, and materials are
provided and used during the operation of the nuclear power ,
plant. Principal emphasis is given to evaluation of the ,
'
effectiveness and involvement of management in establishing and
assuring the effective implementation of the quality assurarce
program along with evaluation of the history of licensee
performance in the key areas of: committee activities, design
and procurement control, control of design change processes,
inspections, audits, corrective action systems, and records.
In order to more clearly define the specific strengths and
weaknesses noted in this functional area, the analysis is
divided into three areas, as discussed below:
a. Engineering
,
'
'
This crea has been inspected on a routine basis by the NRC
J residerd inspecurs and by a SSOHI team inspection during
the assessseni, period.
'
i
'
The staffing in the engineering urea is generally adequate
in terms of numbers, but it is weak in experience and
j training. Further, the weaknesses identified by the SSOMI
l
Inspection are indications that the communications between
the plant operating staff and the engineering organizations
t
. .
'
. .
22
.
were poor. In one case, engineering made a change to the
cooling system for an electrical equipment room, @ich
required manual adjustment of a flow control valve to
adjust the temperature. Since the temperature in this room
was required to be maintained within a relatively narrow
range, a surveillance program to verify the temperature
should have been instituted but was not. As a consequence,
the qualified life or performance of the equipment may have
been affected.
In another instance, it appeared that the operating staff
failed to ask for engineering guidance when performing a
maintenance activity that resulted in a deep discharge of
the safety-related station batteries and disablement of the
vital AC buses at the same time. This in turn led to the
,
i
introduction of lake water into the secondary side of the
The 550MI report includes a concern that appears to be
largely attributable to engineering since it involved a ,
failure to properly evaluate the effect of a temporary
modification. The modification involved application of a
l
clamp to keep a safety-related damper in the control room
emergency ventilation system open. Had actuation of the
'
damper been required, an operator would have had to remove
the clamp. The application of the clamp in such a manner
violated the intent of the Technical Specification for
system operability. There were also three LERs that were
at least in part attributable to engineering activities.
In each case, the LERs became necessary because there were
errors in design documents such as drawings,
specifications, and instrument set point data,
i b. Quality Assurance
This area has been inspected by both the NRC resident
inspectors and regional inspectors. In addition, the 550MI ;
team inspected the areas of procurement, material storage,
and audit activities.
There were two violations in the areas of procurement and
of material receipt. Additionally, some of the problems in ;
the management of the outage were related to QA. '
The licensee had received, accepted, and installed a
noncode part which formed a portion of the reactor coolant
system boundary. An audit after the plant restarted
disclosed this, and subsequent waiver to the code was
granted,
i
$
i
- ,.
- ~- . , , , . - - - -. -., - . - - . . . - - - . - , - . - - , - - _ , -
.
. ..
'
. .
23
The reactor vessel head 0-ring seals were not correctly
inspected prior to installation. Although this wa's not the
major contributor to the 0-ring leak, it showed a tendency '
for quality performance to be at pro forma level.
During the outage, there were problems with the weld
repairs to the essential service water systems. .These
problems included the issue of inappropriate welding
materials and welders making welds for which they were not
qualified. These problems were uncovered by quality
checks, but the investigation revealed that QA had missed
several opportunities to identify the problems earliec.
The licensee's vendor audit program did identify a problem
with the certification of fuses purchased from a supplier.
The licensee reported the facts to the NRC. Follow up
action by the NRC resulted in the issue of an Information
Notice.
The licensee had not conducted training in root cause
determination. Corrective actions tended to be focused on
specific events and did not often probe for the underlying
causes. For example, when a four-way valve on the MSIV
actuator failed, the original root cause determination was
not correct. The redesigned valve subsequently failed.
'
When incorrect fasteners were found in the charging pump
check valve, they were replaced. No determination was made
as to whether the problem was the fault of the fastener or '
the valve manufacturer.
c. Management and Administrative Controls
'
This area has been inspected on a routine basis by NRC
resident inspectors and regional inspectors.
During this SALP period, the licensee realized the ,
existence of problems with safety-related pipe wall !
,
thinning. NRC had two basic concerns with this issue. The
first concern was that the short term operability
determination of the thin wall pipe was not technically J
sound in that it was made by plant management without input ,
from engineering. Management did not reassess system !
- '
operability even after engineering made the determination ,
that the pipe did not meet code requirements. Plant '
'
management comunications with engineering was not )
adequate. The second concern was with long term corrective i
actions. Plant management's narrow focus on the issue of l
short-term operability showed that their understanding of '
the issue was lacking. The question of generic application
'
of one thin wall pipe to other areas in the plant was not
addressed in a timely manner. It was not until these
!
- . -- - - .
.
. . .
24
issues were raised by Nuclear Safety Engineering and the
Nuclear Safety Review Committee that appropriate corrective
tions were begun. The operational response to this
p blem was not timely and lacked thoroughness, The above
is ne example of a lack of management involvement in
- ass ing quality. Other examples have been cited in other
SALP reas. !
- The enf rcement history in the area includes seven .
I violatio and no deviations. Four violations were related
to the ens ronmental qualification of equipment. Ten LERs !
were issue by the licensee in this area. Eight of these '
LERs were re ated to control room ventilation isolation i
system (CRVIS actuations. Six of these were due to .
problems with e chlorine monitors. The licensee has made l
great strides i reducing the number of reportable events i
, due to CRVIS act ; however, the reliability of the [
>
chlorine monitors still low. The improvement effort in ,
this area has be otracted. This has resulted in the ;
! control room ope o longer trusting their chlorine l
! monitors. !
r
2. Conclusions p
i
1
The assessment of this func n ea indicates that management l
j has not been effective in ti y lution of important issues. ;
!
. Corporate management oversigh f t activities does not
always ensure adequate involve .t he quality and ;
engineering or.gantiations in pla erations. When problems '
i .
- -
are identified by the quality and n neering organizations they
are not always acted upon in a tim anner, i
,
} The licensee is considered to be in Perf rmance Category 3 for
"
an overall rating of the SALP area of qua ity programs and l
administrative controls affecting quality.
.
i
- l
f
, 3. Board Recommendations j
!
L
i
a Recommended NRC Actions ;
L
- Supplemental inspection effort should be dev ed to this
- area. !
i b. Recommended Licensee Actions !
Increased corporate management involvement in site l
activities is recommended. In particular, addition l
corporate management involvement is needed to ensure hat 1
1
proper engineering and QA involvement is maintained in all '
{ activities.
I
i
l
i
' ,. .. .
O O
24
,
'l
issues were raised by Nuclear Safety Engineering snd the
Nuclear Safety Review Committee that appropriate
corrective actions were begun. The operational response
to this problem was not timely and lacked thoroughness. l
The above is one example of a lack of management i
involvement in assuring quality. Other examples have been
cited in other SALP areas. 1
- The enforcement history in the area includes seven .
violations and no deviations. Four violations were '
related to the environmental qualification of equipment. l
Thirteen LERs were issued by the licensee in this area. ,
, Eleven of these LERs were related to control room
ventilation isolation system (CRVIS) actuations. Nine of
,
these were due to problems with the chlorine monitors.
- The licensee has made great strides in reducing the number
- of reportable events due to CRVIS actuations; however, the
'
reliability of the chlorine monitors is still low. The
i
improvement effort in this area has been protracted. This '
has resulted in the control room operators no longer
l trusting their chlorine monitors.- ,
t
2. Conclusions
The assessment of this functional area indicates that
, management has not been effective in timely resolution of
important issues. Corporate management oversight of plant '
activities does not always ensure adequate involvement of the
quality and engineering organizations in plant operations.
When problems are identified by the quality and engineering
. organizations they are not always acted upon in a timely '
1 manner.
l
l'
The licensee is considered to be in Performance Category 3 for
an overall rating of the SALP area of quality programs and
administrative controls affecting quality.
,
3. Board Recomendations
- a. Recomended NRC Actions
a
<
Supplemental inspection effort should be devoted to this
l area.
! b. Recomended Licensee Actions
1
a
Increased corporate management involvement in site I
4
activities is recomended. In particular, additional
- corporate management involvement is needed to ensure that ,
I proper engineering and QA involvement is naintained in all l
l activities. I
i l
l l
!
--
.. . o. ,
' -
. .
t
25
J. Licensing Activities . .
1. Analysis
During the present rating peri 6d, the 1(censee'5 Panagement
participated effectively in assuring the quality of submittals ,
forlicensingactionsandinresponsestoNRCstaffrequests.
The licensee s reviews were generally timely, thorough, and
technically sound. The licensee's participation was evident in
the ATWS Rule (10 CFR 50.62) submittal which demonstrated that .
'
l
the licensee appeared to adequately understand staff policies
! and be able to make decisions based on adequate management
l involvement. The licensee's submittal contained all of the
~
information that the staff requested for its review. An
appropriate level of management was present and significantly
involved at the review meeting held with the licensee, and the ;
licensee's technical presentations were technically sound.
!
The licensee management was involved and responsive during the
staff's review of WCNOC's request to remove the fire protection ;
program from the Technical Specifications. This licensing
-
action was the lead cause for generic technical specification
,
improvements and involved rapidly evolving staff requirements.
i
Because WCNOC involved its management in this review, they were
l
able to respond promptly to staff concerns to bring the review
'
to ccmpletion.
The WCNOC management has generally exhibited an adequate
understanding of the approach needed to resolve complex
technical issues involved in licensing activities. WCNOC's
June 16, 1987, submittal supporting analysis related to relaxed
i
outage time and increased surveillance intervals demonstrated a l
'
l clearunderstandingofthelicensingissuesinvolvedand
! followed the staff s guidance exactly as provided in the related
generic documentation. ;
i
,
!
The quality
evaluation and levelsubmitted
summaries of detailpursuant
of the licensee's safety )(2)
to 10 CFR 50.59(b !
I are not always adequate to permit the staff to conclude their
acceptability. In some cases these summaries only provide a ,
brief description of the change followed by a conclusive
statement that the change does not generate an unreviewed safety i
or environmental question; they do not provide a summary of the '
WCNOC safety evaluation that was prepared to support the change.
In review of WCNOC's submittal related to their inservice
testing program for pumps and valves, the staff met with the
,
licensee on September 8 and 9. During the meetings the licensee l
l agreed to revise their IST program in specific areas. However,
WCNOC did not make a number of revisions in their March 2, 1987,
Revision 6 resubmittal, as agreed to in the earlier meeting.
l
- . .__ _ _ - . . .
.- . ,
.
I
.
, ,
26
.
The failure to follow up on the agreed upon technical rasolution !
delayed the completion of the licensing action on the itservice l
testing program. l
The licensee had been generally responsive to NRC initiative -
during this rating period, with few longstanaing regulatory '
issues being attributable to the licensee. . l
<
On occasion, the licensee's response had not been adequate to
permit the staff to resolve the technical issue without the need
for additional interaction with the licensee. The staff's [
>
review of WCNOC's submittal related to the main steam line break :
j outside of containment issue required multiple requests for
additional information, and the licensee's responses to these
requests were not expeditious.
P
j The licensee reported 53 nonsecurity events to the NRC
1 operations center pursuant to 10 CFR 50.72. These events were
j almost always reported in a timely manner.
I
The licensee also submitted 49 nonsecurity Licensee Event ,
. Reports (LERs) during the reporting period, ihe LERs were well !
'
written and almost always timely.
I
'
There have been 8 LERs during this reporting period that have '
been caused by malfunctions or spurious actuations of the ;
chlorine monitors. These LERs follow up on 18 previous LERs
that have occurred since Wolf Creek was initially licensed.
This continuing series of LERs is indicative of a failure to
!j identify the root cause of these failures and an ineffectual
corrective action program for the chlorine monitor problems.
1 The plant has experienced seven unplanned scrams during this '
rating period. All of the scrams occurred during Cycle 2 which
ended in September 1987. There were three Safety System l
Actuations, no Sign'ficant Events and five Safety System ;
I
Failures during this rating period, i
2. Conclusion
l
..
The licensee continues to maintain a competent, knowledgeable l
j licensing staff; however during this rating period there were '
'
i occasionalinstancesofIackoftimelyresponsetostaff ;
requests and a decline in content of summaries of safety -
1 evaluations submitted by the licensee in response to l
{ 10 CFR 50.59. The licensee is considered to be in Performance i
Category 2 in this area. ;
i
- l
l
i l
t
i -
i
,
- - _- . -- -
9
. .
27
i
'
Board Recommendation
a. Recommended NRC Actions
hone l
.
b. Recommended Licensee Actions !
e licensee should improve the quality of the safety l
e luation summaries submitted pursuant to 10 CFR 50.59 and
'
r
i sho ld improve the content of licensing submittals to :
prec ude the need for staff requests for additional
infor tion that could have been foreseen by the licensee. ,
,
,
K. Training and Qual ication Effectiveness :
1. Analysis
i
i
The assessment of s functional area includes all activities
f relating to the eff tiveness of the training / retraining and
-
qualifications progr ucted by the licensee's staff. This ;
I area was inspectede ontinuing basis by the resident ,
,
inspectors. This a 150 the subject of an inspection ;
-
which was performed i appraisal period to look into the ;
, training of both the e d and nonlicensed staff. During the ,
4
appraisal period, lice ing nations were administered by
, the NRC to seven (7) rea r ator (RO) candidates and to
j seven (7) senior reactor candidates. Five (5) of the
.
!
) RO candidates ,and fix (6) candidates passed the
,.
-
examinations and were subseg n.t issued licenses. The !
! licensee currently has 36 ind is who hold an SR0 license !
j
and 15 individuals who have an cense. During the l
l
administration of the above exam ons, the examiners found i
i that the trainees had been adequa 1 informed of the I
- significant events that had occurred d ing the week of
j October 18, 1987. The trainees had als been schooled on the
lessons learned from these events.
l
l The inspections in the operator requalifica on training area l
-
indicate that the management oversight in thi area h&s not been
sufficiently thorough. This is evidenced by: '
)
'
j The section of the procedure (ADM 06-224) o licensed
j operator requalification training which relax d a
, requirement of 10 CFR 55 without Commission ap oval.
l *
4
An operator who had failed the annual requalific ion !'
examination and was therefore required to enter in o an
} accelerated requalification program was allowed to ntinue
,
to stand watch and perform watch standing duties pri to
{ his completion of the accelerated training.
!
l l
1
. .
27
3. Board Reconnendation
a. Recomended NRC Actions
None
b. Reconinended Licensee Actions
The licensee should improve the quality of the safety
evaluation sunnaries submitted pursuant to 10 CFR 50.59
and should improve the content of licensing submittals to
preclude the need for staff requests for additional
information that could have been foreseen by the licensee.
K. Training and Qualification Effectiveness
1. Analysis
~
The assessment of this functional area includes all activities
relating to the effectiveness of the training / retraining and
qualifications program conducted by the licensee's staff. This
area was inspected on a continuing basis by the resident
inspectors. This area was also the subject of an inspection
which was performed during the appraisal period to look into
the training of both the licensed and nonlicensed staff.
During the appraisal period, licensing examinations were
administered by the NRC to six (6) reactor operator (RO)
candidates and to seven (7) senior reactor operator
candidates. Four(4)oftheR0candidatesandseven(7)ofthe
SRO candidates passed the examinations and were subsequently
issued licent 1. The licensee currently has 34 individuals who
hold an SRO cense and 17 individuals who have an R0 license.
During the aaministration of the above examinations, the
examiners found that the trainees had been adequately informed
of the significant events that had occurred during the week of
October 18, 1987. The trainees had also baen schooled on the
lessons learned from these events.
The inspections in the operator requalification training area
indicate that the management oversight in this area has not
been sufficiently thorough. This is evidenced by:
- The section of the procedure (ADM 06-224) on licensed
operator requalification training which relaxed a
requirement of 10 CFR 55 without Coninission approval.
An operator who had failed the annual requalification
examination and was therefore required to enter into an
accelerated requalification program was allowed to
continue to stend watch and perform watchstanding duties
prior to his completion of the accelerated training.
. .
. .
28
The required reactivity manipulations had not been
completed in the 1985-1986 requalification cycle for at
least six licensed individuals. The correction of this
i problem had not been formally addressed, but an informal
effort by the simulator instructors is to track the ,
performance of the manipulations by each licensed ;
individual.
4
'
During 1986, at least nine licensed individuals had failed
, to review all of the errergency and off-normal procedures as
a required by the requalification program. The licensee ,
revised the appropriate procedure to specify the off-normal
and emergency procedures to be reviewed. The procedures
i
-
requested after the revision were also incomplete and the
procedure had to be further revised at the prompting of the i
NRC inspector.
The licensee had not provided procedures for implementing
the 10 CFR 55 rule change issued by the NRC on May 27,
1987.
j The above examples are indicators that the training department
i
'
arrangement had not provided the attention to detail necessary
to assure adequate oversight of this area.
There has also been evidence of inattention to detail on the
part of the training staff. Examples of this are:
minor uncorrected errors in the lesson plans that were
reviewed;
' *
failure to have lectures scheduled for 10 CFR Parts 2, 21,
50, and 55 in the operator requalification program;
a
failure to revise a procedure tc reflect a new requirement I
,
instituted by a rule change; and ,
-
- '
4
failure to delete a procedure requirement which was dropped
i by a rule change.
No deficiencies were identified in the area of training of the i
j nonlicensed staff. The procedures and policies in this area ;
were adequately stated and understood. Training records in this
area were generally complete and well maintained. ,
I t
l 2. Conclusions
l
The initial training of licensed operators and the training of I
the nonlicensed staff is effectively controlled and the 1
- licensee's performance in licensing examinations has been good. l
The area of requalification training for licensed operators has
, :
i
!
'
\
- . '
.
_
i . .
29
.
suffered from an apparent lack of management oversight and
inattention to detail on the part of the training staff, The
licensee is considered to be in Perforniance Category 2 in this
area.
l 3. Board Recommendations
-
! a. Recommended NRC Actions
The NRC inspection effort in this area should continue at
the level prescribed by the basic inspection program,
b. Recommended Licensee Action
The licensee should further emphasize the need for
oversight of operator requalification training and the need
for the training staff to be more attentive to details in
the performance of their activities. Licensee management
should continue their oversight and support of the training
of the nonlicensed staff.
,
V. Supporting Data and Summaries
A. Licensee Activitiej
Major Outages
l
. The unit was shut down on April 19, 1987. The cause was an
'
inadvertent trip due to control rod logic card failures. The
l outage duration was 13.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
. The unit was shut down on April 23, 1987. The cause was an
I inadvertent trip due to control rod logic card failures. The
outage duration was 33 hours3.819444e-4 days <br />0.00917 hours <br />5.456349e-5 weeks <br />1.25565e-5 months <br />.
. The unit was shut down on May 28, 1987. The cause was an
inadvertent trip due to a loss of power to the main turbine l
electro-hydraulic controi system. The outage duration was
22.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.
. The unit was shut down on June 29, 1987. The cause was an
inadvertent trip due to a loss of a main feedwater pump. The ;
outage duration was 38 hours4.398148e-4 days <br />0.0106 hours <br />6.283069e-5 weeks <br />1.4459e-5 months <br />. l
. The unit was shut down from July 20, 1987, to July 26, 1987. '
The cause was an inadvertent trip due to a loss of a main
feedwater pump. The outage was extended to repair a containment I
cooling fan. The outage duration was 129.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.
.I i
l 1
. _ -. _. .
.
. .
I
30 l
1
The unit was shut down on September 10, 1987. The cause was an :
inadvertent trip due to a failure of a main transmission line, j
The outage duration was 33.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />.
. e unit was shut down on September 27, 1987. The cause was an !
ii dvertent trip due to a mispositioned rod control switch. The ;
lic see decided to remain down and enter refueling o.utage II i
i earl The outage duration due to the inadvertent trip was !
> 93.5 h urs. The refueling outage duration was 2,418.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />, j
'
i
. The unit s shut down on January 21, 1988. The cause was a ;
j. manual shu own to replace failed reactor vessel 0-rings. The !
t outage durat on was 379.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. During startup following this !
4 -
outage, two t bine trips without reactor trips occurred. The i
duration of eac of se two outages was 9.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. l
t
Inspection Activities
) B.
NRC inspection activity his SALP evaluation period included l
] 49 inspections performe i 31 direct inspection aanhours
expended. These inspe s ed team inspections of the
,
equipment qualification p ra d a SSONI. This inspection effort I
i represents an approximate 5 r increase over the previous SALP i
j period. l
J
l
Table 1 provides a tabulation of RC, nforcement activity for each i
'
-
functional area evaluated. Table pt vides a listing of inspection
i findings in each P LP category.
'
~
InvestigationsandAllebationsReview
'
-
C.
) There was one investigative activity conducte during this assessment
period. The results have not been formally iss d yet.
!
.
'
!
D. Escalated Enforcement Actions
j 1. Civil Penalties !
1 l
1 A Notice of Violation and Proposed Imposition of Ci il Penalty '
i was issued on March 17, 1988. A $100,000 civil pena ty was
.
proposed for two Severity III violations involving a failure to t
i follow procedure and a failure to have appropriate proc ures. !
2. Enforcement Orders
i '
'
None
I
!
I
i
1
4
-_ . - _ _ _ _ _ _ . _ - - _ _ _ _ _ - _ _ _ _ _ _ - _ - _ _ _ _ - _ _ _ _
.-
.
L
, .
,
30
i
'
. The unit was shut down on September 10, 1987. The cause was an
inadvertent trip due to a failure of a main transmission line. ,
. The outage duration was 33.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />.
. The unit was shut down on September 27, 1987. The cause was an ;
inadvertent trip due to a mispositioned rod control switch. l
3
The licensee decided to remain down and enter refueling I
outage II early. The outage duration due to the inadvertent
j trip was 93.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. The refueling outage duration was
, 2,418.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />. ,
L ;
-
. The unit was shut down on January 21, 1988. The cause was a -
. manual shutdown to replace failed reactor vessel 0-rings.
l During startup following this outage, generator / exciter
'
problems were experienced and two turbine trips without reactor
i trips occurred.
.
I
l B. Inspection Activities
e
j NRC inspection activity during this SALP evaluation period included
49 inspections perforned with 6031 direct inspection manhours
expended. These inspections included team inspections of the
j equipment qualification program and a SSOMI. This inspection effort
. represer.ts an approximate 50 percent increaso over the previous SALP
period.
l
'
Table 1 provides a tabulation of NRC enforcement activity for each
functional area evaluated. Table 2 provides a listing of inspection ,
j findings in each SALP category. ;
,
! C. Investigations and Allegations Review ,
i
j There was one investigative activity conducted during this
assessrmnt period. The results have not been formally issued yet. t
1
0. Escalated Enforcement Actions
1. Civil Penalties
l l
l A Notice of Violation and Proposed Imposition of Civil Penalty l
j was issued on March 17, 1988. A $100,000 civil penalty was i
proposed for two Severity III violations involving a failure to
i
follow procedure and a failure to have appropriate procedures. [
] i
j 2. Enforcement Orders
i
3
j None j
1
)
.
1 !
4 !
i l
!
'
-
.. .
'
. .
'
. .
31
E. Manaaecent Conferences Held During Assessment Period
.
1. Conf.rences
i
'
A management meeting was held on October 21 1987, to discuss
theeventswhichoccurredduringtherefuelIngoutage. An :
enforcement conference was held on January 11, 1988, to discuss
violations which had occurred during the refueling outage,
i 2. Confirmation of Action Letters
Nont
i., Review of Licensee Event Reports and 10 CFR Part 21 Reports
Submitted By the Licensee
]
I
1. Licensee Event Reports
i
'
The SALP Board reviewed the LERs for the periori March 1,1987,
through March 31, 1988. This review included the LERs listed by
.i SALP category in Table 3.
2. Part 21 Reports
[
There were no 10 CFR Part 21 reports submitted by the licansee j
during this SALP assessment period. ;
- l
.
4 I
j !
!
i
'
4
i
i !
}
. .
I
f
i
,
i
'
i
j
.
!
'
!
l' !
. .
Table 1
Enforcament Activity
FUNCTIONAL AREAS NUMBER OF VIOLAT.10NS
IN E>'.CH LEVEL
\ DEFICIENCIES / DEVIATIONS V IV III
A. Plant Operations 1
B. Ra ological Controls 0/1 1 4
C. Mainte ce 2
D. Surveillanc 2
E. Fire Protection 1
F. Emergency Preparedne 1/0 2 1
G. Security - 4
'
H. Outages 1 1 2
I. Quality Programt and
Administrative
h, g 1 9
'
Controls Affecting
Quality
J. L-icensing Activities
'
K, Training and -
'." 2
-
Qualification
Effectiveness
Total 1/1 7 25 2
i
l
4
i
l
l
. .
l
Table I
Enforcement Activity-
l
FUNCTIONAL AREAS NUMBER OF VIOLATIONS
'
IN EACH LEVEL
l
l DEFICIENCIES / DEVIATIONS V IV III
1
1
'
A. Plant Operations 1
B. Radiological Controis 0/1 1 4
i
C. Maintenance 2
D. Surveillance 2 '
E. Fire Protection 1
F. Emergency Preparedness 1/0 2 1
G. Security 4
t
H. Outages 1 1 2
I, Quality Programs and 1 7
Administrative
Controls Affecting
Quality
J. Licensing Activities
1
K. Training and Qualification 2
Effectiveness :
,
TOTAL 1/1 7 23 2
l
l
1
c
. .
'
. .
Table 2
ENFORCEMENT ACTIVITY
= i
TABULATION OF VIOLATIONS, DEVIATIONS, AND
EMERGENCY PREPAREDNESS DEFICIENIES t
PERFORMAN CATEGORY
'
A. Plant Operations
Violations
. Failure to enter Technical Specification 3.0.3 when both trains
of CRVIS were inoperable. (Severity Level IV, 8720-01) ,
.
Deviations
>
. None
B. Ra.hological Controls
Violations f
!
. Failure to properly control, store and protect quality records. ;
(Severity Level V, 8708-01) l
. Radiation Protection Manager not fully qualified. (Severity
Level IV, 6712-01)
. Failure to properly evaluate radiologichl surveys of two !
contaminated persons. (Severity Level IV, 8728-01) {
. Unauthorized disposal of contaminated material.- (Severity l
Level IV, 8736-01) ;
. Failure to lock high radiation door. (Severity level IV, f
8809-01)
Deviations
. Repeated failure to implement a continuous airborne monitoring
program. (8712-02)
C. Maintenance
Violations
, Failure to comply with TS 4.0.5 by not obtaining a relief request
from NRC, (Severity Level IV, 8715-01)
. Three examples of failure to follow procedure. (Severity
Level IV, 8807-38)
. -- - . . . -_ - _ __ - -_ -. . - -._ .
,
-
. . !
-
. -
l
2
f
-
i
a !
Deviations j
- !
.
j None
.
f
I ;
i D. Surveillance t
,
.
,
Violations
i . Failure to demonstrate automatic isolation of the containment
i purge pathway. (Severity Level IV, 8715-02)
i
. Failure to alternate starting locations for the motor driven fire [
pump. (Severity Level IV, 8722-01) ;
i
Deviations l
l None
.
(
! t Fire Protsetion
l Violations !
. ;
) . Fire door inoperable by being blocked open. (Severity Level IV, l
j 8706-01) ;
l i
, . ,
4 :
j Deviations !
!
. None l
- i
l F. Emergency Preparedness ;
! >
l Violations l
i ,
'
l . Failure to document a communication test. (Severity Level V,
l 8714-01)
.
l . During an unannounced call-out drill, the communicators could not
j be reached. (Severity Level IV, 8714-02) !
t i
i
. Repeat violation of a failure to meet call-out time limits. l
i (Severity Level V, 8812-01)
1
l Deviations -
i {
j . None
[
I
!
i
I -
I
.
I
- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ __-_____--__________
_ _ _ _ _ _ _ _ _ _ __
. ..
-
. .
3
.
Deficiencies
. During an emergency plan exercise, an incorrect classification
was made. (8721-01)
G. Security
Violations *
. Failure to follow compensatory procedures. (Severity Level IV,
8716-01)
. Inadequate compensatory measures. (Severity Level IV, 8723-01)
.' Failure to maintain assessment aids. (Severity Level IV,
8734-01)
. Failure to maintain control of security badge. (Severity
Level IV, 8805-01) ,
Deviations ;
i
. None
l
H. Outages
Violations
. Six examples of failure to follow procedures. (Severity
Level III, 8731-A)
. Four examples of failure to have appropriate procedures.
(Severity Level III, 8731-B)
. Two examples of inadequate procedures. (Severity Level IV,
8806-01)
{
. Failure to make inservice test log entri'ss. (Severity Level V,
8811-02)
Deviations
. None
I. Quality Programs
Violations
. Failure to have qualified electrical splices. (Severity
Level IV, 8724-01)
_
, . . _ - - .. . . _ . - - _ . - - - _ . . . . .-.
.
j i .
4
l
i t
,
a
I Connection boxes mounted below post-accident containment water .
l level. (Severity Level IV, 8724-02) .
l
- . pace heaters operating in motor operated valves. (Severity f
vel-IV,8724-03) !
.
a
1 . Use f unqualified terminal blocks. (Severity Level IV, 8724-04) l
l }
.
Failur to evaluate temporary modification. (Severity Level V, j
8801-01 :
,
!i . Inadequate cceptance criteria for reactor vessel 0 rings. :
1 (Severity Le el IV, 8804-01) ;
,
i
. .
Purchase order alle to specify code requirements. (Severity ;
4
Level IV, 8815-0 ;
i
f
. . Purchase request di document Spec levels. (Severity i
Level IV,8815-02) !
!
t l
Unqualified code a t. (Severity Level IV, 8815-03) ;
l .
{ Deviations f
j i
q
, None j
.
.
4
l J. Licensing Activities .
I
!
'
. .
Violations .
-
-
l
,
l
. None ;
'
i
- Deviations ;
- i
. None j
j K. Training and Qualification Effectiveness
! Violations
j
. Failure to provide health physics retraining. (ieve ty Level V, ,
B
8717-01) l
Failuit tt, maintain health physics training records. (Se erity
l .
Level V, 9717-02)
4
I l
Deviations I
l
. None j
l
'
i
!
!
l I
- !
'
I
! !
. .
4
. Connection boxes mounted below postaccident containtnent water
level. (Severity Level IV, 8724-02)
. Space heaters operating in motor operated valves. (Saverity
Level IV, 8724-03)
! . Use of unqualified terminal blocks. (Severity Level V, 8801-01) i
- Failure to evaluate temporary modification. (Severity Level V.
8801-01)
,
. Inadequate acceptance criteria for reactor vestel 0-rings.
3
Severity Level IV, 8804-01) ,
. Failure of procurement program with three examples. (Severity
Level IV, 8815-01)
I Deviations
4 . None
. J. Licensing Activities
, Violations
. Noiie
I
i Deviations
. None
. 1
I K. Training an'. Qualification Effectiveness
Violattens
~
l
. Fai' e to provide health physics retraining. (Severity l
Level V, 8717-01)
!
. Failure to maintain health physics training records. (Severity !
,
Level V, 8717-02) !
Deviations l
. None
1
.
_ _ _ _ _ _ _ _ _ _ -_ .___ ___ - - _ _ _ _ _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _
. *<
-
. .
,
Table 3
OPERATIONAL EVENTS
TABULATION OF LICEN5EE EVENT REPORTS
=
PERFORMAN CATEGORY
A. Plant Operations
. Error while placing block switch in ' permit' results in aux,
feedwater actuation. (87-018) .
. Failure to communicate allowed an open door creating a pressure
boundary breach. (87-034)
. Errors result in loss of power to control rod moveable gripper
coils which causes a reactor trip. (87-041)
. Error leads to Hi-Hi 5/G 1evel resulting in feed isolation
signal. (87-042)
B. Radiological Controls
.
Inadvertent
without release of secondary)
prior sampling. (87-036 liquid waste monitor tank
. Inadequate control results in loss of licensed material.
(87-056)
C. Maintenance
. Logic cabinet cards overheated causing reactor trip. (87-017)
. Containment purge isolation due to signal spike on radiation
monitor. (87-019)
. Reactor trip caused by loss of power to main turbine
electro-hydraulic control system. (87-022) l
!
. Reactor trip resulting from personnel error in not correctly ,
tightening instrument sensing lines. (87-027) l
!
. Potential transformer failure causes partial loss of offsite ,
power and reactor trip. (87-030)
. Inoperable containment isolation valve due to incomplete
retesting following maintenance. (87-033)
. High Voltage transmission line failure causes generator
trip / reactor trip. (87-037)
. Accidental mispositioning of breaker switch causes inoperability
of one power operated relief valve. (87-039)
. .
..- . -_ -
, .. i
. .
l 2
!
l
. Omission of snubber from inspection procedure. (87-044) ;
.
. Inadequate hydrostatic pressure tests due to procedural
inadequacy. (87-045) j
. Containment purge isolation caused by moisture induced corrosion i
of an electrical connector. (87-054) ,
'
D. Surveillance
. TS violation caused by missed surveillance procedure. (87-014) !
. Shaft seal on containment air lock failed during testing causing ,
, total leakage above allowable. (87-023) l
t
Containment purge isolation due to personnel error during
'
.
,
I radiation monitor testing. (87-025)
>
. Late performance of spent fuel building vent tritium analysis. !
(87-026) j
. Inoperable Class 1E batteries dLe to inadequate post-test review C
of surveillance test. (87-028) !
I
. Required testing deleted from sureeillance procedures. (87-029)
. Failure to properly verify operability of fire pumps due to
procedural inadequacy. (87-038) ;
,
. Nonconservative error in containment purge radiation monitoring I
setpoint. (87-040) !
!
. Surveillance of power range low setpoint & P 8, P-9, and P-10 l
interlocks not performed properly. (87-043) {
. Containment isolation valve failed during testing causing total
path leakage to be above allowable. (87-050) g
i
. Procedural deficiency causes two feedwater isolations & an an aux !
feed actuation. (87-051) {
t
. Procedural inadequacy resulting in TS violation. (87-060) l
E. Fire Protection f
i
. Four fire dampers not actuated due to drawing error. (87 013) ,
r
Failure to maintain fire watch as required by TS. (87-016)
l
.
. Hourly fire watch performed late due to personnel I
error / individual overlooked one impairment. (87-021) j
i
. . - . ,- . - - - - - , , - - , . , , _ . . . ,
-_ _ . .-
. .* a
o , ,
I &
3
i
.
Spent fuel pool heat exchanger room doors not 3-hour fire rg,ted.
> (87-031)
.
Failure to fully understand the requirements causes TS violation
l
for hourly rather than continuous fire watches. (87 057)
! . Wired glass insert discovered in fire door causes loss of 3-hour
- fire rating. (87-059
. None
G. Security
j
j .
Unauthorized vital area entry. (87-046)
i . Vital door unsecured. (87-047)
j . Security officer inattentive to duty. (87-055)
H. Outages
j
. Improper maintenance causes fatality. (87-048)
l . Low battery bus voltage. (87-049)
I, Quality Programs and Administrative Controls Affecting Quality
I
i . CRVIS caused by chlorine monitor spike. (87-012)
l
CRVIS caused by paper tape bunching up on chlorine monitor,
l .
j (87-015)
l . CRVIS caused by paper tape breaking on chlorine monitor.
(87-020)
)
.
. FA-CRVIS caused by loss of power to chlorine monitor because of
- faulty sample pump. (87-024)
J
) . CRVIS caused by paper tape breaking on chlorine monitor.
4 (87-032)
1
j .
CRVIS - two events caused by malfunctions of the chlorine
!, monitors. (87-035)
I .
Instrument termination splices installed which fail to meet
environmental qualification requirements. (87-052)
l
CRVIS caused by paper tape bunching up on chlorine monitor.
)j
.
.
(87-053)
I
l
)
_ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ __________ _________ __- _ ___ ______________ _ _ . . ______________ - __ __________________ _
.
.'
.' . .
4
.
.
'
,' . TS Violation, due to error in design document. (87-058)
. Radiation monitor spike causes fuel building ventilation
isolation. (88-001)
. Probable transient in power supply for radiation monitor causes
containment purge isolation. (88-002) i
. CRVIS from chloriria monitor spike. (88-003)
. CRVIS from chlorine monitor spike. (88-005)
l
4
i
'
1
>
,
'
l
.
l
l
l
1
' l
l
,
'
I
i
.
,.I
!
. .
SALP MEETING SUMMARY
Date: July 20, 1988
Licensee: Wolf Creek Nuclear Operating Corporation (WCNOC)
Facility: Wolf Creek Generating Station (WCGS)
License: NPF-42
Docket: 50-482
"
On July 20, 1988, the Regional Administrator, NRC Region IV, members of the
Region IV staff, and NRR representatives met with representatives in an open
meeting at WCGS to discuss the SALP Board Report covering the period March 1,
1987, through March 31, 1988. The NRC material presented at the meeting and a
list of attendees are attached. The meeting was held at the request of NRC
Region IV.
,
! After opening remarks by the Regional Administrator, the Director, Division of
Reactor projects, presented each of the functional areas evaluated in the SALP
Board Report using Attachment 1 as an outline. The WCNOC Senior Vice
President and other licensee representatives discussed planned actions to
improve performance and/or respond to NRC recommendations in each of the SALP ;
categories. [
,
Attachments: (
, 1. NRC Material Presented at Meeting
- 2. Attendance List .
'
l
t
1
,
l ,
1
1
'
'
g. g f
- ' ' ATTACHMENT 1 ,
!
!
,
2 .
1 ,
i
I '
I
>
l
i i
I
i
i }
INTRODUCTION
ROBERT D. MARTIN, EGIONAL
} f
ADMINISTRATOR NRC EGION IV
a
h
-
.
I
SALP PESENTATION J0E CALLAN, DIECTOR, DIVISION OF
i i
,
1
i
EACTOR PROJECTS, NRC EGION IV !
i !
1 j
!
,
'
i WOLF CEEK NUCLEAR OERATING LICENSEE MANAGEENT AND STAFF l,
t
- CORKRATION ESKitSE AND l
' !
COtENTS !
!
4l l
,
'
[
i
1 CLOSING PEXARKS ROBERT D. MARTIN !
I
1
'
i'
i
1
h I
3
I
- ,.
5
- !
j !
'
i
f
l !
' !
f
)
1
,
,
4 h
! l
. . . _ - . _ -. . - _ - _ - - . . . - . _
.
- , ,
,
. .
,, .
! i
..
.
'
i
!
<
[
l !
l I
j LNilED STATES NUCLEAR EGULATORY C0ft!SS10fi l
i
i
i SYSTRATIC ASSES 9ENT OF LICENSEE PERF0WANCE l
,
! EETING l
4 L
I !
'
WDLF CREEK NUCLEAR OPERATING CORPORA 110N l
r
r
WOLF CEEK GEERATING STATION
!
i
j MARCH 1, 1987 - MARCH 31, 1988
,
i
.
W)LF CEEK GEERAT!?$ STATION
JULY 20, 1988
9 A.M. l
1
i ;
A \
l f
! '
i l
i
!
i }
,
l !
!.
I
f l
!
i
iI
l
1
l
!
l
!
'
t 1
.. .
.
l
l
\
,
SALP PROGRAM OPJECTI\ES
j
IMPROVE LICENSEE PERFORMANCE
-
PROVIDE A PASIS FOR ALLOCATION OF
NRC ESOURCES
l
IMPROVE NRC EGULATORY PROC.W1
1
I
I
'
,
l
l
l
l
!
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _ - _ - _ _ _
q I
.
j . . !
i
!
. .
i
,
'
i ERFORMANT ANALYSIS AREAS FOR WOLF CRFFK EERATING STATION
i !
- A. PLANTOERATIONS l
4
i
t
i B. RADIOLOGICAL CONTROLS :
I [
l C. MAINTENANCE !
!
!
. :
i D. SURWILLANCE !
! !
I E. FIRE PROTECTION !
! !
F. EERGENCY PREPAREDESS
(
.
i
- G. SECURITY l
4
j
I H. OUTAGES !
>
r
i 1. QUALITY PROGRAMS AND ;
i
ADMINISTRATl W CONTROLS !
AFFECTING QUALITY
j J. LICENSINGACTIVITIES !
i
K. TRAINING AND OUALIFICATION
f
! EFFECTlWESS !
!
i
i
!
1
1
j
_ .___ ___ _ _____ ,_ _ ___ _ ..____. _ ._ _ _ _ _ _ _ _ _ _ _ . _ __. _ _ , _ _ _ _
- - - - - - _ _ _ _ _ _ - - - - - - - _ - . - - - - - _ _ _ _ - - - _-- ---_-
, - ,
. .
.
FUNCTIONAL AEA KRF0mANCE CATEGORY
CATEGORY 1
EDUCED NRC ATTENTION PAY E APPROPRIATE, LICENSEE
MANACDENT ATTENTION AND INVOL\9ENT AE AGGRESSIVE AND
,
ORIENTED TOWARD NUCLEAR SAETY: LIENSEE ESOURCES AE #ftE
AND EFFECTlWLY USED S0 THAT A HIGH LEWL OF ERFOR%NE
WITH ESECT TO OPERATIONAL SAFETY IS EING ACHIEVED.
.
1
4 5 o .
l- . . ;
l
.
!
,
.
A
- i
d
!
! i
l l
1
!
. !
-
!
2
!
! !
i !
!
l !
} CATEGORY 2 [
I i
l
- NRC ATTENTION SHOULD E MAINTAIED AT NORMAL LEWLS,
i
- AND AE CONCERNED WITH NUCLEAR SAFETY, LICENEE ESCORCES
,
-
l
) AE AECUATE AND AE EASONABLY EFFECTlW SO THAT l
I !
j SATISFACTORY ERF0W#CE WITH ESECT TO OERATIONAL SAFETY l
l IS EING ACHIEED, [
i f
4 f
i
>
i !
.
i .
) !
i l
l
J
!
i
i
l l
'
!
, !
l !
i
t
I !
i {
~
J
!
1
,
>
_ _ _ - _ _ - - - _ _ _ _ _ _ - _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ - _ - _ _ - _ _ _ _ - - _ _ - _ _ _ _ _ - _ - _ - _ _ _ _ _ _ _
l s s . !
.. .
i
'
,
l i
5
l I
!
i
!
,
!
l
CATEGORY 3 l
t
!
BOTH NRC AND LICENSEE ATTENTION SHOULD E INCEASED. LIENSEE !
MANAGDENT ATTENTION OR ltWOLWeiT IS ACCEPTABLE AND CONSIDERS
NUCLEAR SAFETY, BUT EAKESSES AE EVIDENT: LICENSEE ES00RES
.
APEAR TO E STRAltED OR NOT EFFECTlWLY USED S0 THAT MINIMALLY
SATISFACTORY ERF0WAE WITH ESPECT TO OERATIONAL SAFETY IS [
EING ACHIEWD. !
!
l
!
s
!
1 ;
!
'
l
I
i !
!
.
{
i
,
I
i
f
I
_--
_ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _
,.
) +. * '
!
.
>
!
1 i
! i
i !
'
I
J !
!
q
1
i
i
,
EVALllt. TION CRITERIA l
J !
1
l
)
i
1. MANAGEENT INVOL\ DENT AND CONTROL IN ASSURING QUALITY
.!
J
l 2. APPROACH TO ESOLUTION OF TECHNICAL ISSLES Ff01 A SAFETY j
l STANDPOINT !
!
3. ESPONSl\0ESS TO NRC INITI ATlWS
!
-
i
,
} !
i '4 . ENFORCDENT HISTORY
i l
i i
5. OPERATIONAL EWNTS (INCLUDING ESPONSE T0, ANALYSIS OF, ;
j
j AND CORECTlW ACTIONS FOR) f
I 6. STAFFING (INCLUDING f%%GEENT) l
< t
!
i
1 !
'
)
{
i
- .
l
I
1 i
I !
l t
!
J l
<
1
l l
1 !
! l
4
i
I
i
1
l !
.
_ _ ____ _ __- ___ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _
l
, . - .
1 .
. . >
l .
l
l .
!
1
i :
1
,
l
l
.t
.SIBENES !
l
!
FIE PROTECTION AND SECLRITY AE STRONG AEAS j
i
i
(EE OF PROCEDURES IN OPERAi!0NS WAS MIH IPPROVED TOWARD TE
l
i
END OF ERIOD
f
i
'
ERSONEL RADIATION EXPOSURE HISTORY HAS BEEN ETTER
.
THAN TE NATIONAL AVERAGE FOR FHRs (LESS THAN 50% OF AWRAE)
,
.
PAJOR MANAGEENT CHANGES MADE IN TE MAINTENANCE AEA APPEAR :
.
TO E POSITlW ,
i
[
!
!
,
!
i
i
I
i
f
t
-_ - - - _ _- .- - .- -- . - . .-
. - o
. .
.
l
!
!
'
EAKESSES i
I
ACTUAL OERALL DECLIE OR DECLINING TEND IN TE
ERF0 WANCE FOR T E FOLLOWING FUNCTIONAL AREAS: !
!
PLANTOKRATIONS I
RADIOLOGICALCONTROLS
PAINTENANCE ;
Ll&NSING ACTIVITIES
l
TRAINING AND QUALIFICATION EFFECTlW. NESS l
t
MIN! PALLY SATISFACTORY ERF0WANCE IN TE i
t
AREAS OF QUAllTY F90 GRAMS AND OUTA T S l
i
LACK OF EFFECTlW C00 ERAT 10N AND COORDINATION j
ETEEN TE PLANT OPERATIONS STAFF AND TE l
vARiOUS TtcaCAt sum cR0ueS !
TRA!NING IN ROOT CAUSE DETEmlNATIONS
r !
l ?
!
i
l
I
c
l
l
r
._ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __- _ _ _ _ .
O d O
,,
,.. .
,
I k
-
i !
'
\
-
i
l
l^
PLANT OKRATIONS
!
' ;
CATEGORY 2
l I
'
!
TERE IS CONTINtED STRONG MANAGDENT SUPPORT FOR
!
4
TE COLLEGE DEGEE PROGRAM FOR OPERATIONS PERSONNEL !
,
1 !
l USE OF PROCEDUES IN OEPATIONS WAS MUCH IEROWD I
TOWARD TK END OF TE SALP KRIOD l
i
j OKRATIONS INTERFACE WITH OTER DEPARTENTS IS A l
1 TOTED EAKtESS !
i :
)
. .
AT TIES, OKRATORS Fall TO PAY ATTENTION TO DETAIL !
]
,
3
l
REC 0tENDFD LIEfM A{llg l
t
I 6
I !
! LICENSEE MANACBENT SHOULD ENSURE THAT TEE IS AN
i :
.' ADEQUATE AND PROPT 00AllTY ASSURANCE, NUCLEAR SAFETY i
1
, ENGlEERING, AND ENGlEERING INVOLWENT IN OPERATIONAL !
,
- BENTS AND IN DE ECmlCAL WET!0N TO SAFETY ISSLES, ;
i
f
y (
, (
1 I
I !
1 i
I !
I
i
i
j l
1 l
_ _ _ _ _ _ _ _ _ _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
, . o .
.
. .
L
l
RADIOLOGICAL CONTROLS
CATEGORY 2
,
TE LICEfEE'S KRSON'EL RADIATION EXPOSUE HISTORY HAS BEEN BETTER
!
l.
.
(LESS THAN OE-RALF) THAN TK NATIONAL AW. RAGE FOR FVRS
i OERALL KRFORMANCE INDICATED A DECEASE IN EFFECTIESS OWR TE ;
-
4
PEVIOUS ASSES 9ENT KR100
f
i !
f INADEQUATE F#iAGEENT ATTENTION TO NRC CONCERNS IS DOONSTRATED BY (
TE LACK OF ESOLUTION TO TE CONCERNS NOTED DURING TE PEVIOUS !
)! -
i
ASSES 9fNT KRIOD: l
]
l
I * !
LACK OF STE#4 EfERATOR MDCX UP TRAINING
f
,
LACK OF EALTH PHYSICS SUKRVISORY KRS0ffEL PESENCE IN !
! wm
!
EC0tENnFT) LIERTF ACTION .
i
- EALTH FWSICS SLFERVISORY KRS0ffEL SHOULD SEND M)E TIE IN TE
RAD 10 LOGICALLY CONTROLLED AEAS EVALUATING #0 OBSERVING ONGOING !
i
RADIATION PROTECTION WORK ACTIVITIES TO ENSUE C&PLIANCE WITH
]
j STATION PFOCEDUES,
i l
i
l PANAGEENT SHOULD TAKE ACTION TO PROVIDE TRAINING TO TEONICIANS TO
)
,
ENHANCE PROCEDURAL C&PLIME.
?
! - - _ _ _ _ - _ _ _ _ _ _ - _ - _ _
_ _ .- . _ - -
S
.
- .
- O O
"
'
!
,
, ,
PAINTENANCE l
!
.
GE@RY 2
4
i
I
TOWARD TE END OF TE SALP KRIOD, PAJOR MANAGDENT CHANGES HAVE EEN l
} IWLEEfffED, AND APEAR TO HAW SIGNIFICANTLY STENGTEED TE !
PAINTENM AREA
1 :
.
3 FANACHENT HAS SHOWN STRONG SUPPORT FOR TE PAINTENANCE PROGRM, BUT !
' '
IWLEE? RATION OF THIS PROGRAM WAS NOT ALWAYS ADEQUATELY CARRIED OUT
\ 1
L
i ESCALATED ENFORCEENT ACTION REWALED SIGNIFICANT PROBLEMS WITHIN TK
-
PAINTENANCEORGANIZATION, INCLUDING: l
l
1
WOFERS FAILING TO FOLLOW PROCEDUES
l ,
- !
1 *
l
INAKCUATE PROCEDUES !
J
i
l !
l If&DE00 ATE C0hTROL OWR SECIAL PROCESSES j
i,
'
j CfdRALL BEAKDOWN OF PANAGEENT OWRSIGHT OF MAINTENANCE
I
ACTIVITIES DURING TE FALL EFLEllNG OUTAGE
l
1 i
EC0tEhTFD LIERW ACTION
i I
< i
j TK LIENSEE SHOULD FOLLOW THROUGH AND ASSESS TE EFFECTlWESS OF (
l !
TEIR CORECTIVd ACTICtG. AND CONTlhE TE INCEASED EMEASIS ON
- I
!
PFOCEDURALCOPPLIANCE.
! i
- -_-_ -_ __--- _ ----- - - - _ _ _ _ _
_ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - __- _ _-___________ ___
.. ;
i=. * j
.,
j
,
,
!
i i
!
SURVEILLANT l
l
l CATEGORY 2 i
1 l
t
l
j ADE00 ATE PROGRNi EXISTS FOR SCEDULING At0 TRACKit4G OF SURWILLMEE
l
! ACTIVITIES !
- :
t ;
,
i
ENFORCDENT AND EPORTING HISTORY INDICATE ITRO\9ENT OVER TE !
l !
i PEVIOUS ASSES 9ENT ERIOD, RTT ERAT PROCEDURAL AND ERSONNEL j
ERRORS INDICATE THAT ADDITIONAL PANAGDENT INVOLN9ENT IS EEIED !
) I
PROCEDURES IN SCPE CASES DID NOT ADDESS ALL TECHNICAL SKCIFICATION j
l
i -
SURVE!LLANCE EQUIRDENTS l
I !
l ECCitENrrn LIENTF ACTIONS ,
t
1
1
1
TE LIENTE IS ENC 00RAED TO KRFORM INDEPTH EVIEW OF TE TECmlCAL
, SKCIFICATION SURNEILLANE EQUIRDENTS MD ENSUE THAT TE :
1
'
i
SUR\EILLA'CE PROEDURES ADDESS TESE EQUIEENTS, j
i
a
- ADDITIONAL PAVEENT lit.0LMENT WITH SURWILLANCE ACTIVITIES IS
a ,
'
EN000 RAGED,
1
I
i ,
1
]
i
i
l
I
i
2
-,_ - - . - - _ , . - . _ , _.-
. . .
. . .
f
- L
1
1
4
,
, FIFE PROTECTI@ ,
- ,
J CATEGORY 1 ;
4
- ;
'
SIGNIFICANT IPPROMENT IN TE FIE PROTECTION, PEWNTION PROGRAM
i HAS BEEN ACCGftlSKD i
'
i :
] FIE BRIGADE / WATCH TRAINING IS OUTSTANDING
I .
I !
l CONTROL OF TRANSIENT CCNBUSTIELES HAS BEEN EFie .E '
I l
'
! i
l TEE HAS BEEN A SIGNIFICA?U PEDUCTION IN TE NtNEER OF MISSED FIE !
'
l
j WATCES
l
1
1 ,
! EQMENDED LICENSEE ACTIONS !
I
I ;
TE LIENSEE SHXJLD ASSURE THAT TE EENT ORGANIZATIONAL 0%NGES
I
- THAT HAW TE FIE PROTECTION EN31EER EPORTING TO A DIFFEENT
i .
! GROUP AND AT A L0ER LEWL DOES NOT ESttT IN A REDUCTION OF
J .
i MAVGEENT SUPPORT. !
! ;
i !
l !
-
i
i
- ! '
1
'
l
-
.
1 I
l
i
4
., . .
. .
.
.
EMERGENCY PREPAPEDNESS
l
fATEGORY2
! TE ANNUAL EERGENCY ESPONSE EXERCISE WAS VIEWED BY TE EVALVATICH
TEAM AS GOOD
PERSONNEL NOTIFICATION ETHOD AND PROCEDURE REQUIES ADDITIONAL
IEROVEENT FOR CALL-0UT AND SHIFT AlRENTATION RESPONSE TlWS
l
EC0 WENDED LICENSEE ACTION
TE LEVEL OF MANAGEENT ATTENTION TO TE IELEENTATION OF TE
^
l EERGENCY PREPAREDNESS PROGRAM SHOULD BE INCREASED TO ENSURE PROPER
l ESPONSE TO NRC IDENTIFIED CONCERNS ELATING TO CALL-0UT DRILL
RESPONSE AND SHIFT AUGENTATION ESPONSE TIE.
TE LICENSEE SHOULD EXEDITE CORRECTION OF TE CALL-0UT DRILL
'
RESPONSE AND SHIFT AUGENTATION CONCERN,
1
MANAGEENT SHOULD REVIEW TE DISTRIBUTION OF ONSITE AND OFFSITE
EERGENCY PROGRAM AEAS OF AUTHORITY AND ESPONSIBILITIES,
1
l
l
l
_ _ _ _ _ _ _ _ - _ - _ _ _ _ - - _ .
,..
.. .
.
SECURIT(
CATEGORY 1
.
FOLICIES AND PROCEDURES ARE WELL STATED, APPROPRIATELY DISSEMINATED
AND UNDERSTANDABLE
A NEW SOUAD MANNING STRUCTURE HAS ALL0kED FOR TRAINING AND PRACTICE
IN SOUAD RESPONSE TACTICS
MINOR PROCEDURAL MISTAKES INDICATE A NEED TO ENHANCE TE SELECTION
PROCESS FOR TEFPORARY SECURITY PERSONNEL AND TO E 5RSISTENT IN
PROGPMATIC TRAINING
REC 0 WENDED LICENSEE ACTION
M LICENSEE SHOULD CONTINUE TO PROE TE CAUSATIVE FACTORS OF
SECURITY EVENTS FOR BROADER IMPLICATIONS AND ADJUST PROGRAMS,
TRAINING, DISCIPLINARY ACTIONS, MAINTENANCE, AND ENGINEERING
RESPONSES APPROPRIATELY,
TE ORGANIZATIONAL ADJUSTENTS MADE IN TE 0A AREA SHOULD E CLOSELY
MONITORED TO ENSURE THAT THE HIGH QUAllTY OF TE SECURIT( OVERS!Giff
PROGRAM CONTINUES,
,.,
,. .
.
DUTAGES
CATEGORY 3
SIGNIFICANT WEAMESSES WERE IDENTIFIED IN TE LICENSEE'S ABILITY TO
PLAN, MANAGE, AND MAINTAIN CONTROL OVER COMPLEX OUTAGE' EVOLUTIONS
AND ESULTED IN ESCALAiED ENFORCEENT
TE LICENSEE'S INWSTIGATION OF OUTAE-RELATED EVENTS INDICATED A
LESS THAN AGGESSIVE APPROACH TO TE ESOLUTION OF TECHNICAL ISSUES
WEAKNESSES WEE IDENTIFIED IN PROCEDURAL COMPLIANCE
.
RECCitENDED LICENSEE ACTION
TE LICENSEE SHOULD ENSURE THAT LESSONS LEARNED FROM TE PEVIOUS
OUTAGES AE IDENTIFIED AND REVIEWED FOR PROGRAM IMPROV9ENTS TE
ESULTS OF THIS REVIEW SHOULD E INCORPORATED INTO OUTAGE PLANNING
AND CONTROL.
. .' * ."
.
QUALITY PROGRAPS AND A mlNIS"RATIVE CONTROLS
AFFECTING G_AL TY
CATEGORY 3
FANAGEENT HAS NOT BEEN EFFECTIVE IN CONSISTENTLY ENSURING TIELY
RESOLUTION OF IDENTIFIED SAFETY PROBLEMS
TE STAFFING IN TE ENGINEERING AREA IS GENERALLY ADEQUATE, BUT THERE
AE WEAK? ESSES IN EXERIENCE AND TRAINING
TE LICENSEE'S ABILITY TO ERFORM ROOT CAUSE ANALYSIS AND IMPLEENT
,
TIE LY AND APPROPRIATE CORRECTIVE ACTIONS WAS A NOTED WEAKNESS
CORPORATE FANAGEENT OVERSIGHT OF PLANT ACTIVITIES DOES NOT ALWAYS
ENSURE ADEQUATE INVOLVEEtU OF TE QUALITY AND ENGINEERING
ORGANIZATIONS IN PLANT OERATIONS
REC 0ftENDED LICENSEE ACTION
INCREASED CORPORATE MANAGEENT INWLVEENT IN SITE ACTIVITIES IS
'
RECCttENDED,
,
ADDITIONAL CORPORATE MANAGEENT INVOLVEENT IS NEEDED TO ENSURE THAT
i
PROKR ENGINEERING AND QUALITY ASSURANCE INWLVEENT IS MAINTAIED IN
ALL ACTIVITIES.
- -
- .-
, ...
, , ,
.
LICENSING ACTIVITIES
CATEGORY 2
THE LICENSEE'S EVIEWS WERE GEERALLY TIELY, THOROUGH, AND
TECHNICALLY SOUND
,
TE QUALITY AND LEWL OF DETAll 0F TE LICENSEE'S SAFETY EVALUATION
'
SlfEARIES SUMITTED PURSUANT TO 10 CFR 50,59(B)(2) ARE NOT ALWAYS
FULLY ADE00 ATE TO PERMIT TE STAFF TO CONCLUDE TEIR ACCEPTABILITY
l
OCCASIONALLY, TE LICENSEE'S RESPONSES HAVE NOT BEEN ADEQUATE TO
ERMIT TE STAFF TO RESOLVE TECHNICAL ISSUES WITH0lfT TE NEED FOR
ADDITIONAL INTERACTION WITH TE LICENSEE
REC 0 WENDED LICENSEE ACTION
TE LICENSEE SHOULD IMPROVE TE QUALITY OF TE SAFETY EVALVATION
SlfEARIES SUBMITTED PURSUANT TO 10 CFR 50.59,
'
!
TE LICENSEE SHOULD IMPROVE TE CONTENT OF LICENSING SUBMITTALS TO
PRECLUDE TE NEED FOR STAFF REQUESTS FOR ADDITIONAL INF0fEATION THAT
4
COULD HAVE BEEN FORESEEN BY TE LICENSEE,
1
l
l
1
. _ - - - - - - - - - - - -
'
' '
, . .
.
.
TRAINING AND QUALIFICATION EFFECTIVENESS
CATEGORYJ
TE INITIAL TRAINING OF LICENSED OERATORS AND TE TRAINING 0F TE
NONLICENSED STAFF IS EFFECTIVELY CONTROLLED AND TE LICENSEE'S
PERFORMANCE IN LICENSING EXAMINATIONS HAS EEN GOOD
TRAINING RECORDS WERE GEERALLY COMPLETE AND WELL MAINTAINED
TE AREA 0F EQUALIFICATION TRAINING FOR LICENSED OPERATORS HAS
SUFFERED FROM AN APPARENT LACK 0F PANAGE E NT OVERSIGHT AND
INATTENTION TO DETAIL ON TE PART OF TE TRAINING STAFF
REC 0ftENDED LICENSEE ACTION
I
TE LICENSEE SHOULD FURTER EMPHASIZE TE NEED FOR OVERSIGHT OF
OPERATOR EQUALIFICATION TRAINING AND TE NEED FOR TE TRAINING STAFF
TO E MORE ATTENTIVE TO DETAILS IN TE RF0WANCE OF TEIR ACTIVITIES,
1
i
s
e
i
- - - . .__
_ _ __ . _ _ _ _ _ , _ _ _ _ . . _ _ . _ _ _
.- . --. . -. - -- , .
k
. .
l
-
ATTACHMENT 2
ATTENDEES
,
,
Name Affiliation
.
t
'
R. Martin NRC - RIV ~
'
L. Callan NRC - RIV t
J. Milhoan- NRC - RIV
D. Chamberlain .NRC - RIV
v. Calvo NRC - NRR i
'
P. O'Connor NRC - NRR
B. Bartlett NRC - RIV l
M. Skow NRC - RIV
'
G. Boyer WCN00
F. Rhodes WCNOC i
B. Withers WCNOC !
J. Bailey WCNOC !
i W. Wood . WCf'0C
J. Houghton WCNOC
'
B. Hagan WCNOC
'
B. McKinney :WCNOC
H. Chernoff WCNOC- l
C. Parry WCNOC
l 0. Maynard WCNOC
a T. Morrill WCNOC
1
^
K. Moles WCN00
R. Holloway WCNOC l
C. Estes WCNOC
T. Deddens, Jr. WCNOC
>
R. Hackman WCNOC
D. Fehr WCNOC
4 A. Freitag WCNOC
P. Potter WCNOC
i C. Sprout WCNOC
<
G. Rathbun WCNOC .
4
M. Grimsley WCNOC l
R. Smith
'
J. Pippin WCNOC :
J. Johnson WCNOC !
i
M. Williams WCNOC
1 H. Dyer Dan Glickman's Office
,
M. Johnson KG&E i
- J. Kramer KCPL !
1
i B. Gashom KEPCO
'
T. Ryan KEPC0 i
J. Hays Wichita Eagle Beacon l
l S. Kempin Kansas City Star I
i S. Swartz Topeka Capitol - Journal !
l P. Wenske Kansas City Times I
i
l
4
!
4
)