Docket Nos: 50-424 liOV and 50-425 21 D
.~
.NEMORANDUM FOR:
E. Jordan, Director Emergency Preparedness and Engineering Response D. Muller, Assistant Director for Radiation Protection, DSI W. Houston, Assistant Director for Reactor Safe ~ty, DSI L. Rubenstein, Assistant Director for Core and Plant Systems, DSI W. Johnston, Assistant Director for Materials, Chemical and Environmental Engineering, DE J. Knight, Assistant Director for Components and Structures Engineering, DE F. Schroeder, Assistant Director for Generic Projects, DST J. Saltzman, Assistant Director for State and Licensee Relations, SP FROM:
Thomas M. Novak, Assistant Director for Licensing, DL
SUBJECT:
DRAFT SER INPUT FOR V0GTLE, UNITS 1 AND 2 The purpose of this memo is to communicate our understanding of when certain of your branches are to provide draft SER input on Vogtle, Units I and 2.
Since issuance of the DSER on November 6, 1984, ASB, EHEB and CSB have provided input to a supplement to the DSER.
The applicant has not yet submitted its final Emergency Plan but plans to do so on December 1, 1984.
Based on a committment made by Dave Matthews, EPB, at a May 15,.1984, meeting to provide a DSER to DL within 6 weeks of receipt of the applicant's plan, we anticipate EPB DSER input by January 18, 1985.
1 1
7
=...
__ The structural review audit is typically scheduled before the DSER;.however, for Vogtle it is not scheduled until the week of December 3,1984, at the request of the applicant. Based on discussions with George Lear, DL antigfpates receipt of DSER input incorporating the audit meeting discussions by January 18, 1985.
We need to inform the applicant as to the staff's schedule for issuing remaining DSER sections as indicated in the enclosure.
We plan to do so based on the dates in the enclosure unless we hear differently from you within one week of the date of this memo.
"Ori ;inal Tiyrod Ey:
i l
\\ Y bs[
%.) I s Thomas M. Novak, Assistant Director for Licensing Division of Licensing
Enclosure:
As stated
~
" " ~
cc:
H. Denton D. Eisenhut R. Bernero R. Vollmer T. Speis DISTRIBUTION:
~
Docket No. 50-424/425 PRC System LB #4 R/F MDuncan MMiller Attorney, OELD FMiraglia r;
/
/
D DCl'
- 4 Ad IbL DL:LS'A MMiUW, (/ah EA e sam TNov c
11/1o/84 11/p84 11 [ 84 k
,}
['
ENCLOSURE Missing Section Responsible Branch Estimated Issdance 3.2 MEB June 1985*
3.3 SGEB January 1985 3.4.2 SGEB January 1985 3.5.1 ASB, MTEB November 1984 3.5.3 SGEB January 1985 3.7 SGEB January 1985 3.8 SGEB January 1985 3.11 EQB June 1985*
5.2.1 MEB June 1985*
8 PSB June 1985*
9.5.2 - 9.5.8 PSB June 1985*
10.2 PSB Jun'e 1985*
10.2.3 MTEB November 1984 10.3.2 PSB June 1985*
-10.4.1 PSB-June 1985*
10.4.4 PSB June 1985*
13.3 EPB January 1985
?2-State Programs June 1985*
Appendix C GIB June 1985*
~
NOTE:
PSB Power Systems Branch EPLB Emergency Preparedness Branch MTEB Materials Engineering Branch MEB Mechanical Engineering Branch EQB Equipment QualificatJon Branch GIB Generic Issues Bran'ch
- This date corresponds to issuance of the SER l
4.
~
August 24, 1984 Docket Nos: 50-424 and 50-425 MEMORANDUM FOR: See Attached Distribution FROM:
Elinor G. Adensam, Chief Licensing Branch No. 4 Division of Licensing
SUBJECT:
DRAFT SER SCHEDULE FOR V0GTLE, UNITS 1 AND 2 The draft SER input for Vogtle, Units 1 and 2 is due to the project manager
~by October 1, 1984 as indicated in the Vogtle review schedule attached to D. Eisenhut's memo _ dated November 29, 1983 (enclosed).
Reviewers should be preparing their input at this point. The issuan'ce date of the draft SER is November 1,1964, so it is imperative that the October 1 date be met.
The iiiput to tha project manager must include a vehicle for CRESS to access-
~-
the SER material. For example, if it has been typed in CRESS include the cover sheet.
If disks or mag cards were used provide them to the PM indicating the system used and where the material is located on the disks or cards.
If an OCR font is used, the appropriate format should be used as dictated by CRESS.
If there are any questions, contact the project manager, Melanie Miller, at X24259.
Y! A
,)
.)
{jt.Elinor 6, 4 b
/
. Adensam, Chief Licensing Branch No. 4 Division of Licensing
Enclosure:
As stated O
d O
D
- 4 r/hmc EAdpnsam 8 '184 8Mf/84
-~
9
~
~.
MEMORANDUM FOR: (DISTRIBUTION)
R. Bosnak, MEB L. Reiter, GSB R. Ballard, EHEB V. Noonan, EQB W. Regan, SAB G. Lear, SGEB V. Benaroya, ChEB B. D. Liaw, MTEB B. Clayton, PSRB V. Moore, HFEB H. Booher, LQB J. Milhoan, QAB F. Rosa, ICSB W. Gamill, METB B. Sheron, RSB J. Hulman, AEB F. Congel, RAB
- 0. Parr, ASB W. Butler, CSB M. Srinivasan, PSB C. Berlinger, CPB K. Kniel, GIB C. Thomas, SSPB D. Mathews, EPLB 6
6
\\
D
e
/ h / h, //,,
k IN*
(k November 29, 1983 e.
Dockst Nos.: 50-424 e
and 50-425 MEMORANDUM FOR:
R. H. Vollmer Director, Division of Engineering R. J. Mattson, Director, Division of Systems Integration H. L. Thompson, Director, Division of Human Factors Safety T. P. Spels, Director, Division of Safety Technology E. L. Jordan. Director, Division of Emergency Preparedness and Engineering Response, IE J. M. Tylor, Director, Quality Assurance Safeguards and Inspection Programs, IE R. F. Burnett, Director, Division of Safeguards, NRSS FRON:
Darrell G. Eisenhut Director Division of Licensing
SUBJECT:
SCHEDULE FOR OL REVIEW OF V0GTLE 1/2 The purpose of this semo is to advise you of the safety and environmental review schedules for Yogtle 1/2.
The Vogtle FSAR acceptance review has been completed and the application was docketed on September 16, 1583.
Although the application has been docketed, we are requesting that the review not be initiated until February 1,1984 in order that NRC resources t:111 be utilized efficiently. Accordingly, the enclosed schedule reflects a date referred to as " Initiation of Review".
The schedule for the OL review of Yogtle is included in the enclosure. All the milestones which are included in the NRC monthly report to Congress (Bevill Sub-Cessittee) are identified with an asterisk. Please provide any cther intermediate milestones which may be required in certain disciplines
.such as emergency planning, security and instrumentation and control systems.
Crnstruction of Yogtle 1/2 is'about 60% and 175 complete, respectively, and fcel load is scheduled by the applicant for September 1986.
The safety review questions should be submitted to the project manager by Apri,1 15,1984. Each question should be accompanied by a reference to the applicab:le Standard Review Plan section.
AS.h)hN 0 l
""*""}"""*"""*""'*"*""*"
e nee"e e e e e e e e ee e.. e e. ""e ".." e e e "
" *" e e""" o u "e " eeeeee*****""""'
e ene"""e"e ee e. e e e e e e ""e" e e""e e eeeeee"ee""*""ee ee""e"**"""""
................................u......
^
2-
~
The project manager for Vogtle is Melanie A. Miller located in Rooom 118 (X24259). Please assure that each of your branches has received all portions of the FSAR or ER necessary for their review and scheduled their review so as to provide their inputs to the Project Manager in accordance with the enclosed schedule.
Darrell G. Eisenhut. Director Division of Licensir.g
Enclosure:
As stated cc w/ enclosure:
hRR A/D's NRR B/C's G. McCorkle, NM55 F. Pagano, IE DISTRIBUTION Docket No. 50-424, 50-425 LB 14 r/f EAdensam HMiller TNovak MDuncan DEisenhut/RPurple NRC PDR PRC System I
{C i
F ud optn/9 s
.o DL:L
..-.-.. D @... 4, A..D:
.........D 1.
l
~
omest a..
-..f.>..
EA,,,qe ga,9,,,,,,,,
,,,D W
....../.. - - / 8 3
..Q k-Q1/83 m
m
.9/,./83 09/f.../83 0
09
3 4+.a ENCLOSURE 1
"~
I-PROPOSED SCHEDULE FOR LICENSING ACTIVITIES FOR V0GTLE UNITS 1 AND 2
~
SER TargetaT SCHEDULED A T DATE l
(Months)
(P.onths) v Tender 0
0 06/30/83C Docket 2
2.5
,09/16/83C Initiation of Review 02/01/84 Q's to PM 2.5 7
04/15/84 O's to Applicant 0.5 0.5 05/01/84 Applicant Response Due 2.5 2.5 07/15/84
, y.
Draft SER Inputs to PM 2.5 2.5 10/01/84 SER Draft 4
1 1
.11 /01 /84
5 04/01/85
- 'SER Issued 2
2 06/01 /85
- ACRS Meeting 1
1
-07/01/85
- SSER Issued 2
2 09/01/85
- Start' Hearing 5
5 02/01/86
- ASLB Decision 6
6 08/01 /86 Com Effectivess 1
1 09/01/86
- Com. Dec. on F.P. Lic -
1 1
10/01 /86
(
i ER Tender 0
08/31/83C
~
Docket -
2 2
11/01/83 Initiation of Review 02/01/84 Site Visit Agenda to PM 0.75 0.75 02/21/84 Site Visit Agenda to Applicant 0.25 0.25 02/28/84 Site Visit 0.75 0.75 03/21/84 Q Input to PM 0.50 0.50 04/05/84 Q's Sent to Applicant 0.25 0.25 04/12/84 Applicant Response Due 1.50 1.50 05/26/84 i
Input to DES 2
2 07/26/84
- DES Issued 2
2 09/26/84 Input to FES 4
4 01/26/85
~* FES Issued 5
2 2
03/26/85
/
t
- Q
- -. y