cf UNITED STATES NUCLEAR REGULATORY COMMisslON g
+g WASHINGTON D. C. 20555
,j
,,,,,/
DEC 161983 SGPR:SJB 50-424/425 MEMORANDUM FOR: Cecil 0. Thomas, Chief Standardization and Special Projects Branch Division of Licensing, NRR FROM:
George W. McCorkle, Chief Power Reactor SG Licensing Branch Division of Safeguards, NMSS
SUBJECT:
SCHEDULE FOR OL REVIEW - V0GTLE UNITS 1 AND 2 This is to advise that our initial review of the Vogtle Electric
.~
Generating Plant Unit 1 Physical Security and Contingency Plan dated September 1,1983 disclosed significant omissions relative to the require-ments of 10 CFR 73.55 and applicable standards.
- [be Region II Safeguards Inspector, Bill Tobin, agreed with our initial
~
assessment and contacted the applicant to determine if another submittal was forthcoming. The applicant was aware that his submittal needed work and suggested a meeting with the reviewers to discuss the security plan.
Melanie Miller, Vogtle Project Manager, arranged for a meeting at Vogtle on January 18, 1983.
t A proposed agenda for the meeting is enclosed.
MRC representatives at the -
meeting will be M. Miller, NRR, W. Tobin, RII, C. Gaskin, NMSS, and S. Brow ~n, NMSS.
Because a revised security plan must be submitted by Vogtle before we can complete our review, first round questions may not be ready by the April 15, 1984 schedule date.
~ l Geo W. McCorkle, Chief Pow Reactor SG Licensing Branch Division of Safeguards, NMSS
Enclosure:
As stated
(
B6 10 3 851127
"~'
p BELL 84-663 pm Q{
i.
{'
SECURITY AND CONTINGENCY PLAN REVIEW PROPOSED AGENDA V0GTLE ELECTRIC GENERATING PLANT Wednesday, January 18, 1984 8:30-9:00 am Introduction of personnel, presentation of proposed agenda and reasons for the meeting.
9:00-10:30 am Tour of site 10:30.12:00 pm -
Security Plan Review a.
Performance Objectives 2
b.
Securi'ty Organization
~
c.
Physical Barriers Q
12:00-1:00 pm Lunch 1:00-4:00 pm Securi'ty Plan Review continued a.
Access Requirements b.
Detection Aids
- c.. Comunications-
=
d.
Security Audits e.
Response Capabilities f.
Special Situations 4:00-4:30 pm Contingency Plan Review 4:30-5:00 pm Sumary and Closing Comments No.te: Discussions involve safeguards information and therefore are not cpen to the pub.ltc.