Advises That Initial Review of 830901 Physical Security & Contingency Plan Disclosed Omissions Re 10CFR73.55 Requirements & Stds.Meeting W/Applicant Planned for 840118. Agenda Encl
ML20136C999
Person / Time
Site: 05000000, Vogtle
Issue date: 12/16/1983
From: Mccorkle G
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To: Thomas C
Office of Nuclear Reactor Regulation
Shared Package
ML082840446 List: ... further results
References
FOIA-84-663 NUDOCS 8601040175
Download: ML20136C999 (2)


Text

,

.) _ _

cf UNITED STATES NUCLEAR REGULATORY COMMisslON g

+g WASHINGTON D. C. 20555

,j

,,,,,/

DEC 161983 SGPR:SJB 50-424/425 MEMORANDUM FOR: Cecil 0. Thomas, Chief Standardization and Special Projects Branch Division of Licensing, NRR FROM:

George W. McCorkle, Chief Power Reactor SG Licensing Branch Division of Safeguards, NMSS

SUBJECT:

SCHEDULE FOR OL REVIEW - V0GTLE UNITS 1 AND 2 This is to advise that our initial review of the Vogtle Electric

.~

Generating Plant Unit 1 Physical Security and Contingency Plan dated September 1,1983 disclosed significant omissions relative to the require-ments of 10 CFR 73.55 and applicable standards.

- [be Region II Safeguards Inspector, Bill Tobin, agreed with our initial

~

assessment and contacted the applicant to determine if another submittal was forthcoming. The applicant was aware that his submittal needed work and suggested a meeting with the reviewers to discuss the security plan.

Melanie Miller, Vogtle Project Manager, arranged for a meeting at Vogtle on January 18, 1983.

t A proposed agenda for the meeting is enclosed.

MRC representatives at the -

meeting will be M. Miller, NRR, W. Tobin, RII, C. Gaskin, NMSS, and S. Brow ~n, NMSS.

Because a revised security plan must be submitted by Vogtle before we can complete our review, first round questions may not be ready by the April 15, 1984 schedule date.

~ l Geo W. McCorkle, Chief Pow Reactor SG Licensing Branch Division of Safeguards, NMSS

Enclosure:

As stated

(

B6 10 3 851127

"~'

p BELL 84-663 pm Q{

i.

{'

SECURITY AND CONTINGENCY PLAN REVIEW PROPOSED AGENDA V0GTLE ELECTRIC GENERATING PLANT Wednesday, January 18, 1984 8:30-9:00 am Introduction of personnel, presentation of proposed agenda and reasons for the meeting.

9:00-10:30 am Tour of site 10:30.12:00 pm -

Security Plan Review a.

Performance Objectives 2

b.

Securi'ty Organization

~

c.

Physical Barriers Q

12:00-1:00 pm Lunch 1:00-4:00 pm Securi'ty Plan Review continued a.

Access Requirements b.

Detection Aids

c.. Comunications-

=

d.

Security Audits e.

Response Capabilities f.

Special Situations 4:00-4:30 pm Contingency Plan Review 4:30-5:00 pm Sumary and Closing Comments No.te: Discussions involve safeguards information and therefore are not cpen to the pub.ltc.