Recommends Listed New Milestones Be Followed for Mechanical Engineering Branch Review Schedule Re Draft SER Input & Draft SER Meeting & Audit to Be Held Wk of 841203.Listed FSAR Review Milestones Should Be Deleted from Schedule
ML20136E653
Person / Time
Site: 05000000, Vogtle
Issue date: 12/14/1983
From: Bosnak R
Office of Nuclear Reactor Regulation
To: Adensam E
Office of Nuclear Reactor Regulation
Shared Package
ML082840446 List: ... further results
References
FOIA-84-663 NUDOCS 8312190347
Download: ML20136E653 (2)


Text

nrou o

UNITED STATES g

NUCLEAR REGULATORY COMMISSION n

CASHINGTON, D. C. 20555 c:

% ****/

DEC141983

~

MEMORANDUM FOR:

E. Adensam, Chief Licensing Branch #4 Division of Licensing FROM:

R. J. Bosnak, Chief Mechanical Engineering Branch Division of Engineering

SUBJECT:

V0GTLE 1/2 OL REVIEW SCHEDULE

Reference:

Memo from D. Eisenhut to R. Vollmer, et al, dated November 29, 1983 The' Mechanical Engineering Branch review schedule for Vogtle 1/2 is not

~'

totally consis to the referen, tent with the review schedule appearing in the Enclosure ced memorandum.

For the past four years, the MEB has by-passed the milestone associated with the first round of questions (Q inputs to PM) and have proceeded directly to a draft Safety Evaluation i

Report which is submitted to the LPM approximately six to eight months prior to the due date for the "SER Input to PM" milestone. The draft SER documents all of our questions, unresolved issues, and staff positions which we have identified during our FSAR review.

Approximately two to three months after the applicant reviews our draft SER we conduct an extendad meeting with the applicant with the objective of resolving the majority of these issues. Approximately four months after this meeting, we submit our final SER input to the LPM.

We recommend that the following new milestones be followed for the MEB review schedule applicable to Vogtle 1/2:

1.

Draft SER input to LPM from MEB, 9/7/84 2.

Draft SER meeting and audit held at AE office with applicant week of 12/3/84 The following FSAR review milestones associated with the first round of questions to the applicant should be deleted from our review schedule:

a f [f qo /

U} *)(

) }

1 j

E. Adensam )

1 Q inputs to PM 4/15/84 Q sent to applicant 5/1/84 Applicant response due 7/15/84 Draft SER input to PM 10/1/84 0

j'

<s R. J. Bosnak, Chief Mechanical Engineering Branch Division of Engineering cc: