ML20134M841

From kanterella
Jump to navigation Jump to search
Forwards Insp Rept 50-461/96-10 on 960905-1004.Violations Noted from Assessment of Recirculation Pump Seal Package Failure Event on 960905 Being Considered for Escalated Enforcement Action.Enforcement Conference Will Be Scheduled
ML20134M841
Person / Time
Site: Clinton Constellation icon.png
Issue date: 11/19/1996
From: Beach A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Jackie Cook
ILLINOIS POWER CO.
Shared Package
ML20134M845 List:
References
NUDOCS 9611260057
Download: ML20134M841 (6)


See also: IR 05000461/1996010

Text

{{#Wiki_filter:_ __

 ,,                                                                                                      1

-

                                                                                          pr o /
                                              Noveuber 19, 1996
     John G. Cook
      Senior Vice President
      Illinois Power Company
      500 South 27th Street
      Decatur,IL 62525
      Dear Mr. Cook:
      On October 4,1996, the NRC completed two inspections at your Clinton facility: a
      Special inspection into the circumstances surrounding the September 5,1996,
      recirculation pump seal package failure and an independently chartered Operational Safety         11
     Team inspection (OSTI) which was initiated as a result of operator performance in the'              I
      recirculation pump seal package failure event. The enclosures to this letter present the
      results of those inspections.
      As will be discussed below, on September 5,1996, the operations department put in
      motion a sequence of events which revealed sigoificant deficiencies throughout the
      organization at the Clinton facility. These deficiencies included procedural adequacy and
      adherence problems, lack of rigor in conducting plant operations, and weak engineering
      support to operations. And, most significantly, the deficiencies included serious lapses in
      safety focus by both plant management and staff. It appears that plant management and
      staff made decisions which placed plant production ahead of plant operational safety. .This
      matter is the subject of an ongoing Office of Investigations review.
      Our review of the activities associated with the September 5, event, and additional                i
      confirmatory findings from the OSTI, identified a number of actions and practices which            1
      are inconsistent with procedural and pr'ogrammatic controls for assuring safe operation of         l
      a nuclear power plant. These actions and practices were also evident in the April reactor          l
      scram when station management decided to maintain the unit in a hot standby condition,             4
     .thereby minimizing down time. This decision resulted in degraded safety relief valves. In          l
      both events, actions necessary to place the unit in the safest, most stable condition were
      not taken. Further, the decision to maintain the unit in hot standby following the June
      r_eactor ccram resulted in a lost opportunity to address the degrading "B" recirculation
      pump seal package.
    ~ Specifically during the September 5, event, operators were attempting to place the unit in
      single loop operation to allow continued unit operation by isolating a reactor coolant leak in
      the "B" reactor recirculation pump shaft seal package. While attempting to isolate the
       loop, seal pressure, temperature, and leak rate were not decreasing quickly enough to
       ensure continued unit operation. To increase the pump shaft seal's cool down rate and
       reduce leakage, shift supervision directed actions which were inconsistent with both
       Clinton procedures and vendor recommendations for isolating the seal package. After this
       procedural noncompliance, sealleakage increased to greater than 5.0 gallons-per-minute,
      the technical specificaticn (TS) allowable leakage rate. The shift crew entered the
       emergency plan, declared a Notice of Unusual Event, and made appropriate notifications. f
                                       #
    9611260057 961119
    PDR       ADOCK 05000461           s
    G                      PDR
                                                                                                        ;
             - -     -                .-    -        .                . - .-         .     -           .

I s . l -

 0
         J. Cook                                         -2-
         The plant was now in a TS limiting condition for operation (LCO) which required reducing
         the leakage within four hours or shutting the plant down. Based on the four-hour
         limitation, additional procedural steps were not followed in another attempt to reduce the
         leakage to less than the TS limit to allow for continued unit operation. These activities
         exacerbated the seal condition resulting in a seal failure and leakage exceeding the
         installed instrumentation's ability to accurately monitor the leakage. The crew, although
         recognizing the seal failure, did not recognize the instrumentation's limitations. It was not
         until a relief Shift Technical Advisor arrived that leakage rates were properly calculated.
         Even though shift management was aware that these actions would furthe: degrade the
         seals and was aware that a previous seal failure had resulted in leakage in excess of the
         criteria for declaring an Alert under the emergency plan, an Alert was not dxlared
         following all of the obvious indications that a seal failure had occurred.
         After the seal package failed, shift supervision continued to delay commencing the reactor
         shutdown, maximizing the operating time and fully expecting the leakage to drop below
         the TS limit so that single loop operation could be maintained. Finally, four hours after the

l '

         seal package failed (two hours after the LCO expired), with a leakage rate still greater than
         twice the TS limit, a briefing was held for the planned orderly shutdown of the unit. Plant
         shutdown continued to be inappropriately protracted with plant operation continuing to
         within 46 minutes of the 12-hour shutdown requirement being exceeded.
         Throughout the event, operators' actions were complicated by preexisting equipment
         deficiencies. The originally installed leakage rate instrumentation has been a continuing
         problem at Clinton. A modification installed to provide similar information had its
         indication capped at 8 gallons-per-minute, well below the actual leakage achieved during
         the September 5 event. While providing leakage rates, the modification did not support
         continued leakage rate information or emergency classification assessments when most
         needed. Safety relief valves, cycled 85 times in the April event discussed earlier, were
         leaking and contributed to operators diverting their attention from the plant shutdown to
         enter an Emergency Operating Procedure to reduce suppression poollevel.
         Even after the unit was placed in a shutdown condition, the operations department still
         appeared to be driven by schedule pressures rather than conservative operating practices.
         For example, while placing the feedwater system in a cleanup mode, the operations
         department determined there was a need to expedite the cleanup rate and again operated
         equipment / components outside of procedural controls. This procedural non-compliance
         resulted in the spinning of the feedwater pump without oil to the bearings which could
         have caused serious damage to the pump.

l Following the event, our observations indicated that the Clinton staff believed that the i actions taken during the event were appropriate. The failures to follow procedures,

         inadequate procedures, operator performance issues, and inadequate management
         involvement were not promptly identified nor understood. it was not until the NRC had

2

         extensively intervened, through a number of calls with senior plant management over a
          period of several days that action was taken to initiate a thorough and comprehensive
         assessment. This commitment was formalized in our Confirmatory Action Letter dated

l l

  _ -                                                                                                                _ . . .
            s - .-                                                                                                           l
        .
      D

I J. Cook -3- L

                  September 11,1996. The initial assessment, while drawing appropriate overall
                  conclusions, did not provide a solid basis for some of the conclusions. For example, while
                  the initial assessment concluded that procedures were not followed, the detailed report
                  indicated that procedural steps were followed, or a procedure deficiency existed, when in
                  fact the problem was that procedural steps were not followed. Following subsequent
                  discussions with the NRC, the Clinton staff's revised assessment corrected these issues.
                  In summary, our assessment of the recirculation pump seal package failure event identified
                  three significant concerns. First, the operations department lacked an appropriate safety
                  focus as exhibited by: (1) the failure to follow procedures in an extraordinary attempt to
                  keep the unit in an operating condition, and (2) the protracted unit shutdown. Secondly,                   l
                  the failure to correct known material condition deficiencies that complicated operators'                   i
                  actions and responses indicated a lack of management sensitivity and priority to the
                  removal of barriers affecting operator performance. Finally, the engineering department's                  ,
                  support to operations was weak as exhibited by' poor corrective actions for the original
                  leakage instrumentation problems and the deficient compensatory modification.
                  While the examples differed, the same issues were independently confirmed during the

l' OSTl. A number of problems with procedure adequacy and adherence were identified.

                ' Two cases of preconditioning for a diesel generator surveillance and an inadequate local
                  leak rate test procedure were identified. The preconditioning is of concern because this
                  could mask materiel condition issues affecting the operability of the diesel generators.
                  Problems with procedure adherence were further exemplified by operators failing to follow
                  the procedure for isolating spent fuel pool cooling and thereby allowing a 1000 gallon per
                - day leak. In addition, when an operator was asked why they (operators) were having
                  difficulty with a specific procedure, he responded that they were trying to do this the right
                  way because the NRC was watching. This statement demonstrates a poor attitude toward
                  and understanding the importance of procedure adherence.
                  The OSTI identified, through control room observations, a lack of management oversight
                  and a full appreciation for the responsibilities held by licensed operators. At one point the
                  "at the controls" operator left the designated control area without obtaining a relief. Short
                  term relief turnovers were weak, and variations in crew communications and formality
                  were observed. That these activities would occur during a major NRC team inspection,
                  with inspectors in the. control room, indicates to us that these problems may be more
                  widespread.
                  Engineering support to operations was weak and the engineers exhibited a weak safety
          .       focus. Engineering and operations on occasion conducted tests on facility systems with

i the reactor at power to identify potential impacts on safety systems. For example, cyc%d l condensate was isolated from the residual heat removal system to determine the potential l impact. This test resulted in the residual heat removal system being declared inoperable. 1- These special tests did not receive the required safety evaluations (10 CFR 50.59) or site

                  reviews for acceptability. Further, engineers indicated it was acceptable to perform
                  actions by combining steps from disparate procedures without further review. Conducting

l unreviewed, unauthorized tests demonstrate'.s a lack of a safety focus by engineers and [ licensed operators. L ! \

                                            ,            , _ . _                  .     _             . . . _ - . ~.
      . _ -           -           --          ..      . .     .           .--                   ..    -

i

            '
              .
    .
  %
                J. Cook                                         -4-

i

                The OSTI also noted that often engineers seemed focused on finding a way to justify
                system operability rather than performing an in-depth evaluation and analysis
                demonstrating system operability and compliance with the FSAR. The operability
                evaluation program was poor with the process for operability evaluations not fully
                described. The Clinton staff did not know how many or what operational evaluations were
                in-place. Further, the staff had no mechanism of tracking evaluations. This is of
                significant concern to us because degraded plant equipment needs to be promptly
                evaluated to ensure appropriate safety margins are maintained.
                Most of these significant issues described in this report including several apparent

l violations with multiple examples, were identified by the NRC, including: 12 examples of l failing to follow procedures,8 examples of inadequate / inappropriate procedures,4 l examples of failure to perform safety evaluations (10 CFR 50.59), two examples of

                inadequate corrective actions, an example of an operator leaving the " control" area
                without relief, and an example of operations management not performing appropriate
                administrative activities. The failure of the Clinton staff to recognize the significance of  ,
                the issues identified and to promptly and appropriately respond to the them shows a lack      l
                of appreciation for the importance of adherence to NRC requirements.                          l

l Based on the results from the inspections and as noted above, several apparent violations l of NRC requirements were identified and are being considered for escalated enforcement l action in accordance with the " General Statement of Policy and Procedure for NRC

                Enforcement Actions" (Enforcement Policy), NUREG-1600.
                No Notice of violation is presently being issued for these inspection findings, in addition,
                the number and characterization of apparent violations described in the enclosed inspection
                reports may change as a result of further NRC review.
                A pre-decisional enforcement conference to discuss these apparent violations will be
                scheduled. The decision to hold a pre-decisional enforcement conference does not mean
that the NRC has determined that a violation has occurred or that enforcement action will

I be taken. The conference will be held to obtain information to enable the NRC to make an !

                enforcement decision, including a common understanding of the facts and circumstances
                surrounding the violations, their root causes, your opportunities to identify the apparent
                violations sooner, your corrective actions, and the significance of the issues.

l l In addition, this is an opportunity for you to point out any errors in our inspection reports l and for you to provide any information concerning your perspectives on 1) the severity of l the violations: 2) the application of the factors that the NRC considers when it determines l the amount of a civil penalty that may be assessed in accordance with Section VI.B.2 of I the Enforcement Policy; and 3) any other application of the Enforcement Policy to this

                case, including the exercise of discretion in accordance with Section Vll.
;
                You will be advised by separate correspondence of the results of our deliberations on this

-

                 manner. No response regarding these apparent violations is required at this time.

I

                                                     _     .                            . _ .            _            _    _ __
     , .
   -

l ! ,

         J. Cook                                                -5-
Docket No. 50-461

l l cc w/ encl: Mr. Wilfred Connell, Vice President l l P. Yocum, Plant Manager l

                            Clinton Power Station

j R. Phares, Manager-Nuclear Assessment !

                          P. J. Telthorst, Director - Licensing

l

                          Nathan Schloss, Economist
                            Office of the Attorney General

l K. K. Berry, Licensing Services Manager l General Electric Company

                          Chairman, DeWitt County Board
                          State Liaison Officer
                          Chairman, Illinois Commerce Commission
                                       .
                          Office of Enforcement (3)
                          J. Goldberg, OGC
                          G. Marcus, NRR

i i l

                                                                                                                                  l
         Distribution:
                                                                                                                                  !

! Docket File w/ encl DRP w/enci

         OC/LFDCB w/ encl                                               y      ;PUBLIC IE-01 w/enci

l SRI Clinton, Dresden, Rill PRR w/ encl

           LaSalle, Quad Cities                                                  CAA1 w/enci (E-mail)

l Project Manager, NRR w/ encl A. B. Beach, w/enci l B. L. Burgess, w/enci W. L. Axelson, w/ encl

         B. McCabe, OEDO
                                                                                              -
         Document: R: INSPRPTS\ CLIN \CLl96010; 96011
         g ,r .. . . . , . ,sni.         . $ wi.. . . in. n.. c    c.,, ,, ism . .ss..nf      i e - c.,,  ism .ss..nf   i =-
            0FFICE       RIII ,         8      RIII     6     RIII 3 ,/                REII              RIII
            NAME        Mrkt/LeTd Granth Bu M /01
                                                                    i
                                                                                       [[Mll
                                                                                       w
                                                                                                         Axelson/ Beach
DATE 11//f[96 11/)h/96 11/5/96 11/\,/;/96 11/ /96
                                                    0FFICIAL RICORD COPY
             No k e a l2d hv d, f.u9 0] reciea0 ecoet lollrr ce

.

                        hoc $ vo o(jecbarf 4 Ws denty (Srat cN),                                      ,
                                                                 I ,q )h6

,

                            --
                                                           -         ..     . _ _            -       -.         _-
      '
        .                                                                                                          l
   .-
 '

l ! l l J. Cook -5-  ; i 1

                                                                                                                   I
          In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter
          and its enclosures will be placed in the NRC Public Document Room (PDR).
                                                  Sincerely,
                                                 /s/A. Bill Beach                                                  l
                                                  A. Bill Beach                                                    I
                                                  Regional Administrator
                                                                                                                   l
          Docket No. 50-461                                                                                        l
          cc w/ encl:     Mr. Wilfred Connell, Vice President
                          P. Yocum, Plant Manager
                           Clinton Power Station                                                                   l
                          R. Phares, Manager-Nuclear Assessment
                          P. J. Telthorst, Director - Licensing
                          Nathan Schloss, Economist
                           Office of the Attorney General
                          K. K. Berry, Licensing Services Manager
                            General Electric Company
                          Chairman, DeWitt County Board
                          State Liaison Officer
                          Chairman, Illinois Commerce Commission
                          Office of Enforcement (3)
                          J. Goldberg, OGC
                          G. Marcus, NRR
           Distribution.
           Docket File w/ encl                                           DRP w/enci
           OC/LFDCB w/enci                                               PUBLIC IE-01 w/enci
           SRI Clinton, Dresden,                                         Rill PRR w/enci
            LaSalle, Quad Cities                                         CAA1 w/enci (E-mail)
           Project Manager, NRR w/enct                                   A. B. Beach, w/ encl
           B. L. Burgess, w/ encl                                        W. L. Axelson, w/ encl
           B. McCabe, OEDO
           See orevious concurrence
           Document: R: INSPRPTS\ CLIN \CLl96010; 96011
                                    -i . iwi..  4. en. n.. c - c.,, -itu .it.cnf.ui c - c.,r  itm .st. nf.=i n-
           g gi.. . . , .e ini.
             0FFICE      RIII               RIII           RIII                   RIII       RIfif

l NAME Wright / Leach Grant Burgess /0I Caldwell Axkl3n/ Beach j DATE 11/ /96 11/ /96 11/ /96 11/ /96 11/M/96

                                                0FFICIAL RECORD COPY                                               l
                                                                                                                   l

}}