ML20206J746
| ML20206J746 | |
| Person / Time | |
|---|---|
| Site: | Clinton |
| Issue date: | 05/05/1999 |
| From: | Dapas M NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Mcelwain J ILLINOIS POWER CO. |
| Shared Package | |
| ML20206J751 | List: |
| References | |
| 50-461-99-04, 50-461-99-4, NUDOCS 9905120320 | |
| Download: ML20206J746 (4) | |
See also: IR 05000461/1999004
Text
, _ . . . ..
. .
-
- -
_
_
-
_ _ _ _ _ - _ - - _ - _ - _ - _
y:
1
ci
'
Msy'5, 1999
L
f
'Mr. John P. McElwain .
Chief Nuclear Officer
Clinton Power Station
Illinois Power Company
Mail Code V-275 -
P. O. Box 678
Clinton,IL 61727
-;
SUBJECT:
NRC INSPECTION REPORT 50-461/99004(DRS)
Dear Mr. McElwain:
On April 7,1999, the NRC completed an operational readiness team inspection at the Clinton -
Power Station. The enclosed report presents the results of that inspection.
The team evaluated the effectiveness of the Clinton Power Station (CPS) operators to safely.
_
operate the facility. The two weeks of onsite inspection focused on your operational activities
. and included two separate periods of continuous 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of control room and plant
- observations by NRC inspectors.
'
t During the first week of the onsite inspection, the inspectors noted some deficiencies in control
,
. room supervisor command and control, operator response to alarms, and work group supervisor
l review of work packages and questioning of work group personnel.' However, the inspectors
informed your management staff of these deficiencies and by the second week of the onsite
inspection, performance in these areas had improved. In particular, operators appropriately
used and adhered to procedures, conducted informative shift tumovers and briefings, promptly
recognized degraded plant conditions, correctly implemented technical specifications, effectively
communicated,' and understood the plant status. As a result, the NRC concluded that your .
- operators were capable of safely operating the plant. . However, the recent improvement in these
and other operational performance areas is attributable to intense management focus and
<
short-term corrective actions; therefore,' continued long-term management focus is necessary to
.;
l ensure operational performance improvement is sustained.
,
- In addition, the inspectors reviewed the activities associated with NRC Manual Chapter 0350
2 Case Specific Checklist Restart item IV.1, " Establish Program to Reduce and Maintain Control
.
Room Deficiencies." To evaluate this item, the inspectors reviewed existing operator
workarounds, operator challenges, and main control room (MCR) deficiencies. The inspectors
.
concluded that workarounds, challenges, and MCR deficiencies which would not be resolved
_ prior to unit startup would not significantly complicate plant operations and that adequate
. processes existed to manage and address these items.~ Based on this, the inspectors
determined that your staff had adequately addressed this item and it was subsequently closed
- by the NRC Oversight Panel.'
, , . -
f
?
'
e
FDR
,
4
-
t
!
A
J. McElwain
-2-
j
. Based on the results of this inspection, the NRC has determined that four violations of NRC
requirements occurred. The first violation, which was identified by NRC inspectors, pertained to
a control room supervisor who for several minutes did not provide proper oversight of control rod
movements during a surveillance test. The second violation, which was identified by NRC
inspectors, involved a failure to perform an audit of accessible temporary modifications during
the last month of the first calendar quarter of 1999. The third violation, which was identified by
'
NRC inspectors, pertained to an inadequate control rod scram time surveillance test procedure
that did not direct the withdrawal of subsequent rods in accordance with the existing plant
configuration. The fourth violation, which was identified by NRC inspectors, related to an
inadequate diesel generator surveillance test procedure that did not ensure acceptable
frequency requirements could be met.
These Severity Level IV violations are being treated as Non-Cited Violations (NCVs) consistent
with Appendix C of the Enforcement Policy. These NCVs are described in the subject
inspection report. If you contest the violations or severity level of these NCVs, you should
provide a response within 30 days of the date of this inspection report, with the basis for your
j
denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,
DC 20555-0001, with copies to the Regional Administrator, Region 111, and the Director, Office of
Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001.
In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter, the
enclosure, and your response, if you choose to respond, will be placed in the NRC Public
Document Room.
Sincerely,
.
Original /s/ M. L. Dapas
Marc L. Dapas, Deputy Director
Division of Reactor Projects
<
Docket No. 50-461
License No. NPF-62
Enclosure: Inspection Report 50-461/99004(DRS)
L
See Attached Distribution
!
DOCUMENT NAME: G:\\ CLIN \\CLl99004.DRS
- See previous concurrence
To receive a copy of this document, indicate in the box: "C" a Copy w/o attach /end *E' = Copy w/ attach / encl "N" a No copy
OFFICE
- Rlil:DRS
- Rill:DRS
- Rllt:DRP
Rill DRP
[f
NAME
Bielby:sd
Hills
Kozak
Dapas //f;@
DATE
05/ /99
05/ /99
05/ /99
05/5/99
l
_ OFFICIAL RECORD COPY
t
i
o
i
4
. J. McElwain
-2-
Based on the results of this inspection, the NRC has determined that four violations of NRC
j
requirements occurred. The first violation, which was identified by NRC inspectors, pertained to
'
a control room supervisor who for several minutes did not provide proper oversight of control rod
movements during a surveillance test.~ The second violation, which was identified by NRC
inspectors, involved a failure to perform an audit of accessible temporary modifications during
the last month of the first_ calendar quarter of 1999. The third violation, which was identified by
NRC inspectors, pertained to an inadequate control rod scram time surveillance test procedure
!
- that did not direct the withdrawal of subsequent rods in accordance with the existing plant
configuration. The fourth violation, which was identified by NRC inspectors, related to an
inadequate diesel generator surveillance test procedure that did not ensure acceptable
)
]
. frequency requirements could be met.
These Severity Level IV violations are being treated as Non-Cited Violations (NCVs) consistent.
with Appendix C of the Enforcement Policy. These NCVs are described in the subject
inspection report. If you contest the violations or severity level of these NCVs, you should
provide a response within 30 days of the date of this inspection report, with the basis for your
denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,
DC 20555-0001, with copies to the Regional Administrator, Region lil, and the Director, Office of
Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001,
'In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter, the ~
enclosure, and your response, if you choose to respond, will be placed in the NRC Public -
Document Room.
Sincerely,
Marc L. Dapas, Deputy Director
Division of Reactor Projects .
Enclosure:' Inspection Report 50-461/99004(DRS)
- Docket No. 50-461
License No. NPF-62
.
See Attached Distnbution
DOCUMENT NAME: G:\\ CLIN \\CLl99004.DRS
To recehe a ao py of this I: : r : t ledicate in the box: "C" = Copy w/o attach /enci *E' = Copy // attach /enci "N" = No copy
OFFICE
Rill:DRS
N
Rlll:DRS
_
E
Rlli:DRP , _
fJ
Rill DRP
NAME'
Bielby:sd PW & Hills DM
Kozak W
Dapas
'
DATE
05/3 /99
05/3 199
05/~4/99 -
05/ /99
. OFFICIAL RECORD COPY
-
,
l
.
"
,
4
J. McElwain
-3-
- cc w/ encl:
. G. Hunger, Station Manager
R. Phares, Manager, Nuclear Safety
"-
and Performance improvement
- J. Sipek, Director- Licensing
.
M. Aguilar, Assistant Attomey General
- G. Stramback, Regulatory Licensing
Services Project Manager
General Electric Company
Chairman, DeWitt County Board
- State Liaison Officer
'
Chairman, Illinois Commerce Commission
Distribution:-
RPC (E-Mail) -
- Project Mgr., NRR w/enci
J. Caldwell, Rill w/enci
'
' B. Clayton, Rlli w/enci
'
. SRI Clinton w/enci
- DRP w/enci
DRS w/enci ;
l
Rill PRR w/enci-
PUBLICMw/enci[h.
Docket File w/ encl .:
' GREENS
LEO (E-Mail)'
'j
DOCDESK (E-Mall)
3)
mm
l
<