Forwards Updated Const Status Rept as of 830630.Info for Inclusion in Yellow Book.Const 72.53% Completed
ML20127C970
Person / Time
Site: 05000000, Nine Mile Point
Issue date: 08/15/1983
From: Rhode G
NIAGARA MOHAWK POWER CORP.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML082170543 List: ... further results
References
FOIA-84-367 7192, NUDOCS 8504120435
Download: ML20127C970 (3)


Text

s NIAGARA MOHAWK POwtR CORPORATION HlAGARA MOHAWK 300 Emit SOULEVAmo wtST sym4 Cutt.se y s3#0f M

PR pdf August 15, 1983 (7192)

Chief, Management Inf omation Branch Office of Management & Program Analysis U.S. Nuclear Regulatory Commission Washington, DC 20555 Gentlemen:

Subject:

NRC YELLOW BOOK SCHEDULE AS OF JUNE 30, 1983 NINE MILE POINT NUCLEAR STATION - UNIT 2 Transmitted herewith is our current submittal indicating the status of the Nine Mile 2 project for all activities as they appear in the new format for the M C Yellow Book.

The congletion percentages are derived from project reports that are current as of June 30, 1983.

Total plant construction is 72.53 percent complete through June 30, 1983.

Very t uly yours, A

K.

Senior Vice President SFM/AR:Ja Attachment xc D. Shelton (SWEC) (w/ attachment)

C. V. Mangan (w/ attachment)

)

340606 g41 KILLE

-367 PD"

_)

l MIME MILE POINT COMSTRUCTION STATUS REPORT PAGE 1 of 2 i

NUCLEAR STATIDM - UMIT 2 NUCLEAR POWER PLANTS STATUS AS OFe 6/30/83 -

PLANT CFARACTERISTICS:

KEY PERS0!#fEL:

DOCKET X):

05000410 CORPORATE CONTACT:

S. F. MANNO, VICE PRESIDENT -

CP NO. & DATE ISSUED:

CPPR-112 / 6/24/74 NUCLEAR CONSTRUCTION CP EIPIRATION DATE:

7/31/73 REVISED TO 12/31/78 CORPORATE ADDRESS:

300 ERIE BOULEVARD WEST i

APFLICANT:

NIAGARA MWAWK POWER CSPEATIOM SYRACUSE, NEW YORK 13202 1

PbtXT LOCATIOM:

8 MI NE OF OSMEGO, NY IE REGIOM:

1 CORPORATE PFONE NO:

(315) 474-1511 EC:

STONE & WEBSTER PRC LPM:

M. Haughey l

i MSSS:

GEMERA ELECTRIC IE PRINCIPAL INSPECTOR:

l CONSTR'ITCR:

STONE & WEBSTER

-CONSTRUCTION:

R. Grann REACTCR TYFE:

2WR

-TEST AND STARTUP:

CER (MiE):

1080 IE RESIDENT INSPECTOR:

INSFECTICM STATUS:

FUEL LOAD DATE CHANGES AS REPCRTED BY UTILITY:

TIIE PERICO l

REPORT NEW REASON FOR CHANGE l

DATE SCHEIULE REPCRTED BY UTILITY REPCRT BEG DATE END DATE E M ER OF IMP.

OF INSP.

3/14 /78 3/31/83

1. DESIGN CHANGES TO MITIGATE CONTAll#ENT DYNAMIC LOADS.
2. DESIGN CHANGES TO IMPLEMENT SEPARATION REQUIREXENTS CF REG. GUIDE 1.75.

12/14/78 3/31/84

1. WORK STOPPAGES AND SHUTDOWN OF J08.
2. DELAYS IN PROCUREMENT OF EQUIPMENT.
3. REESTIMATE OF SCHEDULE POWER RE0MTS.
4. HEARING DELAYS l

7/28/80 2/24/86

1. POWER GENERATION CONTROL COMPLEX (PGCC)

LOCAL PUELIC 00C17ENT RCDt:

2. GEOLOGICAL IMPACTS
3. MARK II CONTAINMENT STATE UNITERSITY COLLEGE AT OSWEGO
4. BIOLOGICAL SHIELD WALL PEFIELD LI2RARY
5. THREE MILE ISLAND IMPACTS l

OSMEGO, MEM YCEK 13125

6. NEW YORK STATE PUBLIC SERVICE COMMISSION

BINE NILE POINT CONSTRUCTION STATUS REPORT PAGE 2.of 2 BKLDR STATION - UNIT 2 NUCLEAR POWUt PLANTS STATUS AS OF: 6/30/83 FUEL LOAD DATES OARENT ESTIMTE FIEL LOAD DATE:

3/00/86 ESTIMTED CONSTRUCTION PERCENT CtMPLETE:

72.53%

REVIINS ESTIMTE FUEL LDAD DATE: 4/00/86 ESTIMTE FtEL L0e8 BATE AT CMSTRUCTIM PEMIT ISSUSCE:

5/1/78 GMENT ESTIlutTED CINSERCIA C0fufMTS ON CURRENT CONSTRUCTION STATUS:

OPetATION DATE:

10/1/86 CMSTRUCTION CtNFLETION ESTIMTE l

AS DEFIRED IN CtMSTRUCTION PERMIT:

NILESTEE DATES

  • ESTIftLTED ACTUAL ESTIMTED ACTUAL ESTIMATED l

START START CENm.ETE CONPLETE PERCENT CONPLETE

1. MOBILIZE & PREPR E SITE:

8/25/75 8/25/75 8/1/N 8/1/76 1005 2.

PLACE STRICitR A CONCRETE:

5/9/77 5/9/77 8/19/85 97%

3.

MSTALL REACTER RESSWE ESSEL:

8/13/79 8/13/79 8/8/80 8/8/80 1(BX 4

4 RSTEL LARGE NRE PROCESS PIPE:

6/7/M 6/7/M 12/3/M 745 5.

ESTALL L.8. PIPE MAMERS, RSTR's & SNUSSERS:

9/5/77 9/5/77 12/3/84 53%

6.

INSTALL SULL MRE PIPE:

4/1/82 5/1/82 3/11/85 27%

l 7.

NSTALL OLSLE TRAY:

11/6/78 11/6/78 7/9/84 68%

8.

INSTALL EIPOSED PETAL GMRffT:

9/12/ 77 9/12/77 8/12/85 71%

9.

WSTALL RR., CONWt., NSTRU. & SEC. CA8tE:

1/4/82 3/I/82 10/7/85 21%

D.

RSTEL ELECTRICE TEmmRTIONS:

4/1/82 1/12/83 12/2/85 35

11. CIMOET REACTR CKD WSMSTATIC TEST:

4/29/85 5/20/85

12. GIROUCT 2T FUETIORE. TEST:

3/24/86 9/15/86

13. CoueuCT PREOP & ACCEPT TESTS NECESS. F/ FUEL LOAD:

11/14/83 2/24/86

  • Early Start Date

-.