Forwards Updated Const Status Repts as of 830331 for Inclusion in NUREG-0030
ML20115A634
Person / Time
Site: 05000000, Harris
Issue date: 05/04/1983
From: Zimmerman S
CAROLINA POWER & LIGHT CO.
To: Hartfield R
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML082170543 List: ... further results
References
FOIA-84-367, RTR-NUREG-0030, RTR-NUREG-30 LAP-83-150, NUDOCS 8504150455
Download: ML20115A634 (5)


Text

B LAP-83-150 Carolina Power & Light Company MAY 041983 Mr. R. A. Hartfield, Chief Management Information Branch Office of Management and Program Analysis United States Nuclear Regulatory Commission Washington, DC 20555 SHEARON HARRIS NUCLEAR POWER PLANT UNIT NOS. 1 AND 2 D0%ET NOS. 50-400 AND 50-401 CONSTRUCTION STATUS REPORT

Dear Mr. Hartfield:

Carolina Power 6 Light Company hereby submits, as requested for NUREG-0030 (Construction Status Report), the updated Shearon Harris Nuclear Power Plant construction information for the first quarter of 1983, to reflect the construction status data as of March 31, 1983.

Yours very truly, 8

'=

~

S. R.

mmerman Manager Licensing & Permits PS/pgp (6776 PUB)

Attachment ec:

Mr. N. Prasad Kadambi (NRC)

Mr. G. F. Maxwell (NRC-SHNPP)

Mr. J. P. O'Reilly (NRC-RII) g41 5 840606 KILLEFEB4-367 pyg 411 Fayetteville Street

  • P. O. Box 1551
  • Raleigh, N. C. 27602

, o a

C0NSTRUCTION STATUS REPORT PAGE NO : 1 H ARRI S 1 NUCLEAR POWER PLANTS STATUS AS OF: 03/31 Al3 PLANT C4ARACTERISTICS:

KEY PERSONNEL:

D00(ET NO:

05000400 COFFORATE CONTACT:

M. A. MQ)UFFI E, SEN. V. PRESIDENT CP NO. & DATE ISSUED:

CPR-158 / 01-27-78 CORPORATE ADDRESS:

ENGINEERING & CONSTRUCTION CP EXPERATION DATE:

06-01-84 411 FMETTEVILLE STREET N'PL ICANT :

CAROLINA POWER & LIOIT RALEIGH, NORTH CAROLINA 27602 PLANT LOCATION:

NEW H ILL, NC IE REGION:

II COFPORATE PHONE NO:

(919)'836-6663 AE :

EEASCO NRC LFM:

PRASAD KADAMBI NSSS:

WESTINGiOUSE lE PRINCIPAL INTECTOR:

CONSTRUCTOR :

DANIEL INTERNATIONAL 4:0NSTRUCTl0N :

REACTOR TYPE PWR

-TEST AND STARTUP:

DER NWE):

900 lE RESIDENT INSFECTOR :

G. F. M A* ELL IN$PECTION S T A T U S:

FUEL LOAD DATE CH A N G E S AS REPORTED RY UTILITY:

TIME PERIOD REPORT NEW REASON FOR CH ANGE REPORT BEG DATE END DATE DATE S0iEDULE REPORTED BY UTILITY NtM KR OF1NP.

OF i NP.

05-07-75 06-01-83 REVISED CURRENT ENEFGY AND LOAD FORECAST.

09-08-80 06-00-84 LOWER RATE Gt0WTH IN CUSTOMER DEMAND Pi AN PROJECTED.

I2-16-81 12-00-84 LOWER RATE GROWTH IN CUSTOMER DEMAND TH AN IRO JECTE D.

09-30-D2 05-00-85 12-31-82 06-00-85 l

LOCAL PUBLIC DOCUMENT ROOM:

W AKE COUNTY PUS _lc L IERARY 104 F AYETTEVILLE STREET i

R ALEIG1, NORTH C AROLINA 27601 (6776 PUB)

CONSTRUCT 1ON STATUS REPORT PAGE NO. : 2 H ARRIS 1 NUCLEAR POWER PLANTS STATUS AS OF: 03/31/83 C0NSTRUCTl0N STATUS:

APPLICANT'S C' RRENT ESTM ATED FUEL LOADING DATE:

06-00-85 APPLICANT'S CONSTRUCTION COMPLET10N ESTMATE AS J

APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

12-00-84 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTMATED FUEL LOADING DATE AT CP ISSUANCE:

09-00-80 (LATEST)

APPLICANT'S CLRRENT ESTIMATED CoWERCI AL OPERATION DATE: 03-01-86 CLRRENT ESTM ATED PERCENT CONSTRUCT 10N COWLETE: 78%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

EST MATED ACTIML EST MATED ACTUAL ESTMATED START START COWLETION COWLETION 5 COWLETE MOBILIZE AND FREPARE SITE:

01-14-74 01-14-74 01-28-78 01-28-78 100%

PLACE STRUCTLRAL CONCRETE:

01-28-78 01-28-78 02-01-84 945

  • lNSTALL REACTOR PRESSURE VESSEL:

12-01-79 04-15-80

'04-01-80 08-29-80 1005 INSTALL LARGE BORE PROCESS PIPE:

04-01-79 04-01-79 08-01-84 77%

INSTALL LARGE BDRE PlPE H ANGERS, RESTRAINTS AND SNUB 8ERS:

04-01-79 04-01-79 11-01-83 595 lNSTALL SMALL BORE PIPE:

04-01-79 04-01-79 08-01-84 705 INSTALL CABLE TRAY 04-01-79 04-01-79 04-01-84 87%

INSTALL EXPOSED METAL CONDUIT:

04-01-79 04-01-79 04-01-84 675 INSTALL POWER, CONTROL, INSTRtMENTATION AND SECURITY CABLE:

03-01-81 02-26-81 06-01-84 425 INSTALL ELECTRICAL TERMINATIONS: (POWER AND CONTROL ONLY) 01-01-82 06-15-81 12-01-84 22%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

05-01-84 06-01-84 05 CONDtCT HOT FUNCTIONAL TEST:

08-01-84 10-01-84 0%

CONDUCT PREOP AND ACCEPTANCE TEST NECESSARY FOR FUEL LOAD:

06-01-83 12-01-84 05

  • RPV set; exclude Internals and head package.

c (6776 PUB)

c.________.

e-.

C0NSTRUCTION STATUS-REPORT PAGE NO.: 3 H ARRI S 2

~ NUCLEAR' POWER PLANTS STATUS AS OF: 03/31 Al3 PLANT CHARACTERISTICS:

KEY PERSONNEL:

D00(ET NO:

05000401 COFORATE CONTACT:

M. A. M(DUFFIE, SEN. V. PRESIDENT CP NO. & DATE ISSUED:

CPR-159 / 01-27-78 CORPORATE ADDRESS:

ENGINEERING & (DNSTRIETION CP EXPlRATION D ATE:

06-01-86 411 F AYETTEVILLE STREET FPL ICANT :

CAROLINA POWER & LIG1T RALEIGH, NORTH CAROLINA 27602 PLANT LOCATION:

NEW H ILL, NC IE REGION:

1I C0FORATE PHONE NO:

(919) 836-6663 AE :

EBASCO NRC LIN:

FRASAD KADAMBI NSSS:

WESTINGiOUSE IE PRINCIPAL INSPECTOR:

CONSTRUCTOR :

DANIEL INTERNATIONAL

- -CONSTR UCTION :

REACTOR TYPE PWR

-TEST AND STARTUP:

. DER MWE):

900 IE RESIDENT INSPECTOR :

G. F. M AMdELL INSPECTION S T A T U S:

FUEL LOAD DATE CHANGES AS REPORTED BY UT1LITY:

TIME PERIOD REPORT NEW REASON FOR 04 ANGE i

REPORT EEG DATE END DATE DATE SO4EDULE -

REPORTED BY UTILITY NLMEER OF 1 NP.

OF 1NSP.

05-07-75 06-01-85 REVISED CURRENT ENERGY AND LOM) FORECAST.

01-00-80 06-01-86 REVISED CtRRENT ENERGY AND LOAD FORECAST.

09-08-80 06-01-87 SLOWER RATE GROWTH IN CUSTOMER DEMAND 1H AN IROKCTED.

12-16-81 06-01-88 EXPANDED CONSERVATION AND LOM) MAN #3ENENT FROGRAM.

09-30-8 2 UWER REVIEW 12-31-82 06-00-89 i

LOCAL PUBL1C DOCUMENT ROOM:

+

W AKE COUNTY PUILIC LIERARY 104 F AYETTEVILLE STREET

{

R ALEIG1, NOR1H C AROLINA 27601 (6776 PUB)

CONSTRUCTION STATUS REPORT PAGE NO. : 4 H ARRIS 2 NUCLEAR POWER PLANTS STATUS AS OF: 03/31/83 C0NSTRUCTION STATUS:

APPLICANT'S CURRENT ESTMATED FUEL LOADING DATE:

06-00-89 APPLICANT'S CONSTRUCTION COWLETION ESTMATE AS M'PLICANT'S PREVIOUS ESTINATED FUEL LOM) LNG DATE:

06-01-88 DEFINED IN CP: (EARLIEST)

APPLICANT'S ESTMATED FUEL LOADING DATE AT CP ISSUANCE:

06-01-85 (LATEST)

M'PLICANT'S CLRRENT ESTINATED COMERCI AL OPERATION DATE: 03-00-90 CLRRENT EST M ATED PERCENT CONSTRUCTION C(M'LETE: 45 CONNENTS REGARDING CURRENT CONSTRUCTION STATUS:

EST M ATED ACTUAL EST M ATED ACTUAL EST M ATED START START COWLETlON COWLETION 5 COWLETE N081LIZE AND PREPARE SITE:

01-14-74 01-14-74 01-28-78 01-28-78 1005 PLACE STRUCTLRAL CONCRETE:

02-01-79 02-01-79 04-01-86 315 INSTALL REACTOR RESSURE WESSEL:

09-01-85 01-01-86 05 INSTALL LARGE BORE PROCESS PlPE:

06-01-79 06-01-79 02-01-87 13%

It. STALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUB 8ERS:

07-01-82 07-01-82 02-ni-88 05 INSTALL SMALL BORE PIN:

06-0?-79 06-01-79 02-01-88 45 INSTALL CABLE TRAY 04-01-85 10-01-87 05 INSTALL EXPOSED METAL CONDUIT:

04-01-85 10-01-87 35 INSTALL POWER, CONTROL, INSTRlMENTATION AND SECLRITY CAS.E:

06-01-85 03-01-88 0%

INSTALL ELECTRICAL TEMINATIONS:

08-01-85 04-01-88 05 CONDUCT REACTOR COLD HYOROSTATIC TEST:

11-01-87 12-01-87 05 CONDtCT HOT FUNCTIONAL TEST:

02-01-88 04-01-88 05 CONDUCT REOP AND ACCEPTANCE TEST NECESSARY FOR FUEL LOAD:

12-01-86 06-01-88 0%

r (677tiPUB)

.