Forwards Updated Const Status Repts as of 830331
ML20115A616
Person / Time
Site: 05000000, Palo Verde
Issue date: 04/26/1983
From: Fasnacht D
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML082170543 List: ... further results
References
FOIA-84-367 ANPP-SCM-10200, NUDOCS 8504150446
Download: ML20115A616 (4)


Text

ARIZONA NUCLEAR POWER PROJECT Post Office Bon 21666 Phoenix, Arizona 85036 ANPP-SCM-10200 April 26,1983 Chief Management Information Branch Office of Management and Program Analysis U. S. Nuclear Regulatory Commission Washington, D. C.

20555 Subj ect:

USNRC Construction Status Report Update File:

Subj ect Attached for your use and information is the Construction Status Report Update worksheets for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 updated through March 31, 1983.

Should you need any addit.ional information, please do not hesitate to call.

D. B. Fesnacht Nuclear Construction Manager DBF/KCK/csw Attachments cc:

E. E. Van Brunt, Jr.

G. C. Andognini 46 840606 PDR g -367 E

fl 1

C0N5TRUCTIOM STATUS REP 0RT PAGE NO2 NUCLEAR POWER PLANTS STATUS A5 0F: 3/31/83 PALO VERDE I C0N5TRUCTION

$TATU5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

09-01-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-01-83 DEFINED IN CP: (EARLIEST) 06-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE: 11-00-81 (LATEST) 11-01-82 APPLICANT'S CURRENT ESTIMATED CONNERCIAL OPERATIDH DATE: 03-15-84 CURRENT ESTIMATED PERCENT CPMSTRUCTION COMPLETE: 99%

C0fTIENTS REDARDING CURRENT COMSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START 11ARI_

COMPLETION COMPLETION % C0t1PLETF MOBILIZE #ND PREPARE SITE:

05-00-76 10-00-76 100%

PLACE STRUCTURAL CONCRETE:

08-00-76 01-00-81 100%

INSTALL REACTOR PRES $URE VESSEL:

11-00-78 12-00-78 100%

INSTALL LARGE BORE PROCESS PIPE:

03-00-77 03-00-83 100%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

09-00-78.

06-00-83 99%

INSTALL SMALL BORE PIPE:

06-00-78 06-00-83 99%

INSTALL CABLE TRAY:

10-00-77 11-00-81 100%

INSTALL EXPOSED METAL CONDUIT:

03-00-78 06-00-83 99%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-79 07-00-83 99%

INSTALL ELECTRICAL TERMINATIONS:

08-00-79 08-00-83 93%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

07-00-82 07-00-82 100%

CONDUCT HOT FUNCTIONAL TEST:

04-15-83 05-15-83 0%

CONDUCT PREOP AND ACCEPTAMCE TESTS MECESSARY FOR FUEL LOAD:

10-00-81 09-01-83 30%

i I

l 1

l

C0N5TRUCTION 5TATUS REP 0RT PAGE NO:

NUCLEAR POWER PLANTS STA WS AS OF PALO VERDE 2 C0N5TRUCTION STATUS APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

08-01-84 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-01-84 DEFIMED IN CP (EARLIEST) 02-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-83 (LATEST) 11-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-84 CURRENT ESTIMATED PERCENT COMSTRUCTION COMPLETE:

97%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ELTIMATED START START COMPLETION COMPLETION % COr1PLETF MOBILIZE AND PREPARE SITE:

06-00-76 06-00-77 100%

PLACE STRUCTURAL CONCRETE:

08-00-77 12-00-81 100%

IN! TALL REACTOR PRESSURE VESSEL:

06-00-80 07-00-80 100%

INSTALL LARGE BORE PROCESS PIPE:

09-00-78 06-00-83 98%

INSTALL LARGE BORE PIPE HANGERS, RESTRAIMTS AND SMUBBERS:

10-00-78 09-00-83 95%

IMSTALL SMALL BORE PIPE:

04-00-79 10-00-83 94%

INSTALL CABLE TRAY:

06-00-78 03-00-82 100%

INSTALL EXPOSED METAL CONDUIT:

01-00-78 10-00-83 97%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-81 11-00-83 87%

INSTALL ELECTRICAL TERMINATIONS:

05-00-81 12-00-83 79%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

09-29-83 10-07083 0%

CONDUCT HOT FUNCTIONAL TEST:

02-01-84 03-01-84 0%

CONDUCT PRE 0F AMD ACCEPTANCE TESTS MECESSARY FOR FUEL LOAD:

06-00-83 08-00-84 0%

4 1

C0N5TRUCTION 5TATUS REP 0RT PAGE MO:

PALO VERDE 3 MUCLEAR P0WER PLANTS STATUS AS OF: 3/31/83 I

C0M$TRUCTIOM STATUSe l

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS i

APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-85 DEFINED IN CP: (EARLIEST) 11-01-84 i

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-85 (LATEST) 11-01-86 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-00-86 l

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

62%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

4 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION CONPLETION % COMPLETT MOBILIZE AND PREPARE SITE:

06-00-76 04-00-79 100%

PLACE STRUCTURAL CONCRETE:

03-00-79 01-00-84 97%

INSTALL REACTOR PRESSURE VESSEL:

04-00-82 05-00-82 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-79 02-00-85 84%

INSTALL LARGE BORE PIPE MANGERS, RESTRAINTS AND SMUBBERS:

10-00-80 06-00-85 47%

INSTALL SMALL BORE PIPE:

06-00-80 07-00-85 39%

INSTALL CABLE TRAY:

04-00-80 03-00-84 90%

INSTALL EXPOSED METAL CONDUIT:

01-00-80 07-00-85 43%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

03-00-83 08-00-85 2%

INSTALL ELECTRICAL TERMINATIONS:

03-00-83 09-00-85 1%

CONDUCT REACTOR COLD HYDROSTATIC TEST:

02-00-85 02-00-85 0%

CONDUCT HOT FUNCTIONAL TEST:

6-00-86 08-00-85 0%

CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD 09-00-84 11-00-85 0%