ARIZONA NUCLEAR POWER PROJECT Post Office Bon 21666 Phoenix, Arizona 85036 ANPP-SCM-10200 April 26,1983 Chief Management Information Branch Office of Management and Program Analysis U. S. Nuclear Regulatory Commission Washington, D. C.
20555 Subj ect:
USNRC Construction Status Report Update File:
Subj ect Attached for your use and information is the Construction Status Report Update worksheets for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 updated through March 31, 1983.
Should you need any addit.ional information, please do not hesitate to call.
D. B. Fesnacht Nuclear Construction Manager DBF/KCK/csw Attachments cc:
E. E. Van Brunt, Jr.
G. C. Andognini 46 840606 PDR g -367 E
fl 1
C0N5TRUCTIOM STATUS REP 0RT PAGE NO2 NUCLEAR POWER PLANTS STATUS A5 0F: 3/31/83 PALO VERDE I C0N5TRUCTION
$TATU5:
APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
09-01-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
08-01-83 DEFINED IN CP: (EARLIEST) 06-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE: 11-00-81 (LATEST) 11-01-82 APPLICANT'S CURRENT ESTIMATED CONNERCIAL OPERATIDH DATE: 03-15-84 CURRENT ESTIMATED PERCENT CPMSTRUCTION COMPLETE: 99%
C0fTIENTS REDARDING CURRENT COMSTRUCTION STATUS:
ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START 11ARI_
COMPLETION COMPLETION % C0t1PLETF MOBILIZE #ND PREPARE SITE:
05-00-76 10-00-76 100%
PLACE STRUCTURAL CONCRETE:
08-00-76 01-00-81 100%
INSTALL REACTOR PRES $URE VESSEL:
11-00-78 12-00-78 100%
INSTALL LARGE BORE PROCESS PIPE:
03-00-77 03-00-83 100%
INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:
09-00-78.
06-00-83 99%
INSTALL SMALL BORE PIPE:
06-00-78 06-00-83 99%
INSTALL CABLE TRAY:
10-00-77 11-00-81 100%
INSTALL EXPOSED METAL CONDUIT:
03-00-78 06-00-83 99%
INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:
02-00-79 07-00-83 99%
INSTALL ELECTRICAL TERMINATIONS:
08-00-79 08-00-83 93%
CONDUCT REACTOR COLD HYDROSTATIC TEST:
07-00-82 07-00-82 100%
CONDUCT HOT FUNCTIONAL TEST:
04-15-83 05-15-83 0%
CONDUCT PREOP AND ACCEPTAMCE TESTS MECESSARY FOR FUEL LOAD:
10-00-81 09-01-83 30%
i I
l 1
l
C0N5TRUCTION 5TATUS REP 0RT PAGE NO:
NUCLEAR POWER PLANTS STA WS AS OF PALO VERDE 2 C0N5TRUCTION STATUS APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
08-01-84 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
08-01-84 DEFIMED IN CP (EARLIEST) 02-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:
11-00-83 (LATEST) 11-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-84 CURRENT ESTIMATED PERCENT COMSTRUCTION COMPLETE:
97%
COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:
ESTIMATED ACTUAL ESTIMATED ACTUAL ELTIMATED START START COMPLETION COMPLETION % COr1PLETF MOBILIZE AND PREPARE SITE:
06-00-76 06-00-77 100%
PLACE STRUCTURAL CONCRETE:
08-00-77 12-00-81 100%
IN! TALL REACTOR PRESSURE VESSEL:
06-00-80 07-00-80 100%
INSTALL LARGE BORE PROCESS PIPE:
09-00-78 06-00-83 98%
INSTALL LARGE BORE PIPE HANGERS, RESTRAIMTS AND SMUBBERS:
10-00-78 09-00-83 95%
IMSTALL SMALL BORE PIPE:
04-00-79 10-00-83 94%
INSTALL CABLE TRAY:
06-00-78 03-00-82 100%
INSTALL EXPOSED METAL CONDUIT:
01-00-78 10-00-83 97%
INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:
02-00-81 11-00-83 87%
INSTALL ELECTRICAL TERMINATIONS:
05-00-81 12-00-83 79%
CONDUCT REACTOR COLD HYDROSTATIC TEST:
09-29-83 10-07083 0%
CONDUCT HOT FUNCTIONAL TEST:
02-01-84 03-01-84 0%
CONDUCT PRE 0F AMD ACCEPTANCE TESTS MECESSARY FOR FUEL LOAD:
06-00-83 08-00-84 0%
4 1
C0N5TRUCTION 5TATUS REP 0RT PAGE MO:
PALO VERDE 3 MUCLEAR P0WER PLANTS STATUS AS OF: 3/31/83 I
C0M$TRUCTIOM STATUSe l
APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
11-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS i
APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
11-00-85 DEFINED IN CP: (EARLIEST) 11-01-84 i
APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:
11-00-85 (LATEST) 11-01-86 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 05-00-86 l
CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:
62%
COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:
4 ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION CONPLETION % COMPLETT MOBILIZE AND PREPARE SITE:
06-00-76 04-00-79 100%
PLACE STRUCTURAL CONCRETE:
03-00-79 01-00-84 97%
INSTALL REACTOR PRESSURE VESSEL:
04-00-82 05-00-82 100%
INSTALL LARGE BORE PROCESS PIPE:
04-00-79 02-00-85 84%
INSTALL LARGE BORE PIPE MANGERS, RESTRAINTS AND SMUBBERS:
10-00-80 06-00-85 47%
INSTALL SMALL BORE PIPE:
06-00-80 07-00-85 39%
INSTALL CABLE TRAY:
04-00-80 03-00-84 90%
INSTALL EXPOSED METAL CONDUIT:
01-00-80 07-00-85 43%
INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:
03-00-83 08-00-85 2%
INSTALL ELECTRICAL TERMINATIONS:
03-00-83 09-00-85 1%
CONDUCT REACTOR COLD HYDROSTATIC TEST:
02-00-85 02-00-85 0%
CONDUCT HOT FUNCTIONAL TEST:
6-00-86 08-00-85 0%
CONDUCT PREOP AND ACCEPTANCE TESTS HECESSARY FOR FUEL LOAD 09-00-84 11-00-85 0%
O