Forwards Updated Const Status Rept as of 830331.Const Approx 88% Complete
ML20115A648
Person / Time
Site: 05000000, Callaway
Issue date: 04/30/1983
From: Schnell D
UNION ELECTRIC CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML082170543 List: ... further results
References
FOIA-84-367 ULNRC-621, NUDOCS 8504150461
Download: ML20115A648 (3)


Text

\\

,1 UNION ELECTRIC COM PANY 1908 GRATIOT STREET ST. Louis, Missouri

    • "*4*,*,*"'"

April 30,1983

,,., ",$"o',"h,,..

ULNRC-621 Chief, Management Information Branch Office of Management and Program Analysis U.S. Nuclear Regulatory Commission Washington, DC 20555 Dear Sirs CONSTRUCTION STATUS REPORT CALLAWAY UNIT 1 Enclosed is the Construction Status Report revised for a status date of March 31, 1983.

Construction of Unit 1 is approximately 88 percent complete.

This letter constitutes our report to be filed be April 30, 1983.

Very truly yours, Donald F. Schnell FLK/lkr Enclosure cc Messrs. H. M. Wescott E. K. Dille J. Neisler 4~367 p

I

~

CONSTRUCTION STATUS REPORT Paga No. 2-018

.j CALLAMAY l NUCLEAR PONER PLANTS Status As of:

3-31-83 i

CONSTRUCTION STATUS:

Applicant's Current Estimated Fuel Applicants Construction Completion Estimate l

Loading Date:

04-02-84 As Defined in CP:

(Earliest) 06-30-81 Applicant's Previous Estimated Fuel (Latest) 12-31-83 Loading Date:

06-01-83 Applicant's Estimated Fuel Loading l

Date At CP Issuance:

06-01-81 l

Applicant's Current Estimated l

Cosumercial Operation Date:

Late 1984/Early 1985 Current Estimated Percent Construction Complete:

88%

Comments Regarding Current Construction Status:

(

Estimated Actual Estimated Actual Estimated Start Start Completion Completion 4 Complete i

Mobilize and Prepare Site:

09-03-75 05-01-76 100%

Place Structural Concrete:

04-01-76 10-11-82 1004 t

l Install Reactor Pressure Vessel:

03-15-79 05-02-83 994 Install Large Bore Process Pipe:

01-12-78 09-01-83 99%

Install Large Bore Pipe Hangers, Restraints and Snubbers:

01-10-78 11-30-83 92%

Install Small Bore Pipe:

01-19-78 09-01-83 984 Install Cable Tray:

07-09-78 10-01-83 994 Install Exposed Metal Conduit:

07-01-78 11-01-83 91%

Install Power, Control, Instrumentation and Security Cable:

08-08-79 12-01-83 91%

l

o

[

_2_

i l

Estimated Actual Estimated Actual Estimated Start Start Completion Completion t Complete i

l Install Electrical Terminations:

04-04-80 03-01-84 714 1

Conduct Reactor Cold Hydrostatic Test:

04-29-83 05-02-83 04 Conduct Hot Functional Test:

09-12-83 10-25-83 04 Conduct Preop and Acceptance Tests Necessary For Fuel Load:

10-30-81 02-02-84 38%

l l

l l

l i

l 1

_. _..