Forwards Updated Const Status Repts as of 830327 for Inclusion in Const Status Rept (Yellow Book)
ML20115A584
Person / Time
Site: 05000000, Vogtle
Issue date: 05/17/1983
From: Foster D
GEORGIA POWER CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML082170543 List: ... further results
References
FOIA-84-367 GN-229, NUDOCS 8504150419
Download: ML20115A584 (5)


Text

Georgi; Power Company Post Off.ca Box 4545 Atlanta. Georgia 30302 TJephona 404 526-6526 southem Company services, Inc.

Georgia Power Post Office Box 2625 Birmingham, Alabama 35202 Southern CompanyServices Telephone 205 870-E011 D. O. Foster Vice President and General Manager Vogtle Project May 17, 1983 Chief, Management Information Branch Office of Management and Program Analysis V. S. Nuclear Regulatory Commission File: X78G48 Washington, D. C.

20555 Log:

GN-229

Reference:

50-424/50-425 Gentlemen:

Infonnation is provided herewith for your use in updating the NRC Construction Status Report (yellow book). Should you have any questions pertaining to this report, please contact my office at (404) 526-7707.

Very truly yoursj,

/

e i

,l' D. O. Foster CWH/D0F/jr Attachment xc: James P. O'Reilly, NRC Region II R. E. Conway D. E. Dutton R. H. Pinson L. T. Gucwa H. H. Gregory, III 8504150419 840606 PDR FOIA KILLEFE84-367 PDR

C0NSTRUCTI0N STATUS REP 0RT PAGE N0:

2-138 UNIT 1 NUCLEAR P0WER PLANTS STATUS AS OF: 03-27-83 PLANT C H A R A C T E R I S T I C S:

KEY P E R S O N N E L:

DOCKET N0:

05000424 CORPORATE CONTACT:

'D.

E. Dutton, Vice President CP NO. & DATE ISSUED: CPR-108/06-28-74 Generating Plant Projects CP EXPIRATION DATE:

04-30-81 CORPORATE ADDRESS:

Georgia Power Company APPLICANT:

GEORGIA POWER COMPANY 333 Piedmont, Atlanta, GA 30302 PLANT LOCATION:

BURKE COUNTY / GEORGIA CORPORATE PHONE N0:

(404) 522-6060 t II REGION:

II NRC LPM:

S. BURWELL AE:

SOUTHERN SERVICES /BECHTEL IE PRINCIPAL INSPECTOR:

NSSS:

WESTINGHOUSE

-CONSTRUCTION:

CONSTRUCTOR:

GPC

-TEST AND STARTUP:

REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

W. F. SANDERS DER (MWE):

1100 INSPECTION S T A T U S:

FUEL LOAD DATE CHANGES AS REP 0RTED BY U T I L I T Y:

TIME PERIOD REPORT BEG DATE END DATE REPORT NEW REASON FOR CHANGE NUMBER OF INSP.

OF INSP.

DATE SCHEDULE REPORTED BY UTILITY l

09-27-74 Not Known Construction Suspended For Financial Reasons 05-11-77 05-00-83 No Reason Given l

01-09-78 05-01-84 Overestimated Projected Need For Power 07-17-80 11-00-84 No Reason Given 11-18-81 09-01-86 Schedule Reassessment L0 CAL PUBLIC D0CUMENT R 0 0 M:

BURKE COUNTY LIBRARY 4Til STREET WAYNESBOR0, GEORGIA 30830

I i

6,$'

C0NSTRUCTION STATUS.

R E'P 0 R T PAGE N0:

2-139' UNIT 2 NUCLEAR P0WER PLANTS STATUS AS OF: 03-27.

C0NSTRUCTI0N S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

09-01-86 APPLICANT'S CONSTRUCTION COMPLETION APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-84 ESTIMATE AS DEFINED IN CP:

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-79 (EARLIEST) 04-01-80

! APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 03-01-87 (LATEST)

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

50.7%

DATE CONSTRUCTION STARTED:

08-01-76 CURRENT ESTIMATED CONSTRUCTION DURATION IN MONTHS:

126 COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION

% COMPLETE MOBILIZE AND PREPARE SITE:

08-01-76 09-15-77 100 PLACE STRUCTURAL CONCRETE:

08-01-78 02-15-64 83.5 %

INSTALL REACTOR PRESSURE VESSEL:

02-01-83 02-21-83 03-15-83 5

INSTALLED LARGE BORE PROCESS PIPE:

09-01-80 05-01-86 35 IPSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

09-01-80 05-01-86 14 INSTALL SMALL BORE PIPE:

07-01-81 05-01-86 17 INSTALL CABLE TRAY:

08-01-80 04-01-85 59.5 %

INSTALL EXPOSED METAL CONDUIT:

11-01-81 01-01-86 17.2 %

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

03-01-83 01-15-83 11-01-85 0

INSTALL ELECTRICAL TERMINATIONS:

05-01-83 01-01-86 0

CONDUCT REACTOR COLD HYDROSTATIC TEST:

03-01-86 04-01 0 CONDUCT HOT FUNCTIONAL TEST:

05-15-86 07-15-86 0

CONDUCT PRE 0P AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

07-24-84 08-01-86 0

_ _.. _ _ _.... _.. _.. _ _ _. _ _ _.. _. _. _..... _... _.. ~

C0NSTRUCTI0N STATUS REP 0RT

.PAGE NO:

2-140 UNIT 2

NUCLEAR P0WER PLANTS STATUS AS OF:

03-27-83*

PLANT C H A R A C T E R I S T I C S:

KEY P E R S 0 N N E L:

DOCKET N0:

05000425 CORPORATE CONTACT:

D. E. Dutton, Vice President CP NO. & DATE ISSUED:

CPR-109/06-28-74 Generating Plant Projects CP EXPIRATION DATE:

04-30-82 CORPORATE ADDRESS:

Georgia Power Company APPLICANT:

GEORGIA POWER COMPANY 333 Piedmont, Atlanta, GA 30302 PLANT LOCATION:

BURKE COUNTY / GEORGIA CORPORATE PHONE NO:

(404) 522-6060 t II REGION:

II NRC LPM:

S. BURWELL AE:

SOUTHERN SERVICES /BECHTEL IE PRINCIPAL INSPECTOR:

NSSS:

WESTINGHOUSE

-CONSTRUCTION:

CONSTRUCTOR:

GPC

-TEST AND STARTUP:

REACTOR TYPE:

PWR IE RESIDENT INSPECTOR:

W. F. SANDERS DER (MWE):

1100 INSPECTI0H S T A T U S:

FUEL L0AD DATE CHANGES AS REP 0RTED BY U T I L I T Y:

TIME PERIOD i

REPORT BEG DATE END DATE REPORT NEW REASON FOR CHANGE NUMBER OF INSP.

OF INSP.

DATE SCHEDULE REPORTED BY UTILITY 09-27-74 Not Known Construction Suspended For Financial Reasons 05-11-77 05-00-84 No Reason Given 11-02-77 05-00-85 Overestimated Projected Need For Power 07-17-80 05-00-87 No Reason Provided 1

11-18-81 03-01-88 Schedule Reassessment L0 CAL PUBLIC D0CUMENT R 0 0 M:

BURKE COUNTY LIBRARY 4TH STREET WAYNESBORD, GEORGIA 30830

C0NSTRUCTI0N STATUS REP 0RT PAGE N0:

2-141 UNIT 2

NUCLEAR P0WER PLANTS STATUS AS OF:

03-27-83 C0NSTRUCTI0N S T A T U S:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

03-01-88 APPLICANT'S CONSTRUCTION COMPLETION APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

05-00-87 ESTIMATE AS DEFINED IN CP:

APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

10-01-80 (EARLIEST) 04-01-81 i

! APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE:

09-01-88 (LATEST)

CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

15.6%

DATE CONSTRUCTION STARTED:

08-01-76 CURRENT ESTIMATED CONSTRUCTION DURATION.IN MONTHS:

147 COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION

% COMPLETE MOBILIZE AND PREPARE SITE:

08-01-76 09-15-77 100 PLACE STRUCTURAL CONCRETE:

08-01-78 08-15-84 55.5 %

INSTALL REACTOR PRESSURE VESSEL:

08-01-84 09-15-84 0

INSTALLED LARGE BORE PROCESS PIPE:

09-01-80 11-01-87 17 INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SNUBBERS:

09-01-80 11-01-87 3

INSTALL SMALL BORE PIPE:

02-01-83 02-06-83 04-01-88 4

INSTALL CABLE TRAY:

03-01-80 10-01-86 7.1 %

INSTALL EXPOSED METAL CONDUIT:

03-01-83 07-01-87 0.2 %

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

09-01-84 05-01-87 0

INSTALL ELECTRICAL TERMINATIONS:

11-01-84.

07-01-87 0

CONDUCT REACTOR COLD HYDR 0 STATIC TEST:

09-01-87 10-01-87 O

CONDUCT HOT FUNCTIONAL TEST:

12-15-87 02-15-88.

O CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

01-24-86 02-01-88 0

_ _..