|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARL-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195H4651999-06-16016 June 1999 Forwards for Filing Answer of Firstenergy Corp in Opposition to Petition for Leave to Intervene of Local 29, Intl Brotherhood of Electrical Workers. Copies of Answer Have Been Served Upon Parties & Petitioner by e-mail ML20195J5221999-06-16016 June 1999 Forwards Answer of Duquesne Light Co to Petition to Intervene of Local 29,International Brotherhood of Electrical Workers in Listed Matter.With Certificate of Svc L-99-100, Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-1091999-06-15015 June 1999 Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-109 L-99-095, Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys1999-06-15015 June 1999 Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys L-99-099, Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr1999-06-14014 June 1999 Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr ML20195H3731999-06-0303 June 1999 Forwards Petition to Intervene of Local 29,Intl Brotherhood of Electrical Workers in Matter of Firstenergy Nuclear Operating Co,For Filing L-99-090, Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request1999-06-0202 June 1999 Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request L-99-086, Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 11999-05-28028 May 1999 Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 1 L-99-089, Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b)1999-05-28028 May 1999 Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b) L-99-084, Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon1999-05-27027 May 1999 Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon L-99-082, Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS1999-05-17017 May 1999 Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS L-99-071, Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS1999-05-12012 May 1999 Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS 1999-09-03
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059L4271990-09-0707 September 1990 Requests Approval for Use of Steam Generator Tube Plugs for Both Mechanical & Welded Applications ML20059G0821990-09-0404 September 1990 Forwards Application for Amend to License DPR-66,consisting of License Change Request 180,changing Section 3.3.3.2 to Reduce Required Number of Operable Incore Detector Thimbles for Remainder of Cycle 8 ML20059F7551990-08-29029 August 1990 Responds to Unresolved Item 50-334/90-16-01 Noted in Insp Rept 50-334/90-16.Corrective Actions:Initial Training for Maint Group Personnel Responsible for Maintaining Supplied Air Respirators Will Be Supplemented W/Biennial Retraining ML20059F1501990-08-29029 August 1990 Advises That Permanent Replacement Chosen for Plant Independent Safety Evaluation Group.Position Will Be Staffed Effective 900829 ML20028G8731990-08-29029 August 1990 Forwards fitness-for-duty Program Performance Data for Jan-June 1990,per 10CFR26.71 ML20059D3761990-08-24024 August 1990 Describes Cycle 3 Reload Design,Documents Util Review Per 10CFR50.59 & Provides Determination That No Tech Spec Changes or Unreviewed Safety Questions Involved.Reload Core Design Will Not Adversely Affect Safety of Plant ML20028G8881990-08-24024 August 1990 Withdraws Operator License SOP-10731 (55-60749) Issued to K Gilbert,Who Resigned 05000412/LER-1990-007, Responds to NRC Re Deviation 50-412/90-12-01 Noted in Insp Rept 50-412/90-12.Corrective Actions:Procedure OM 2.20-4.I Revised to Require Removal of Flanges Following Drain Operations & LER 90-007-00 Issued1990-08-23023 August 1990 Responds to NRC Re Deviation 50-412/90-12-01 Noted in Insp Rept 50-412/90-12.Corrective Actions:Procedure OM 2.20-4.I Revised to Require Removal of Flanges Following Drain Operations & LER 90-007-00 Issued ML20058P7651990-08-14014 August 1990 Provides Info on Acceptability of Rescheduling Response to Reg Guide 1.97 Ser,Item 4b, Neutron Flux Monitoring Instrumentation. Rescheduling of Util Response Will Be Determined on or Shortly After Meeting W/Nrc ML20059E0571990-08-10010 August 1990 Forwards Suppl 3 to Nonproprietary WCAP-12094 & Proprietary WCAP-12093, Evaluation of Pressurizer Surge Line Transients Exceeding 320 F for Beaver Valley Unit 2, for Review by 900901.Proprietary Rept Withheld (Ref 10CFR2.790(b)(4)) ML20059E7631990-08-0101 August 1990 Provides Results of Util Evaluation of Licensed Operator Requalification Exam Conducted During Wks of 900709 & 16. Crew That Failed to Meet Expected Performance Level Has Been Successfully Upgraded & re-evaluated to Be Satisfactory ML20059B8141990-08-0101 August 1990 Requests Exemption from 10CFR26 Re Fitness for Duty Program & 10CFR73 Re Physical Protection of Plants & Matls Concerning Unescorted Access Requirements for Nuclear Generating Stations ML20056A3471990-07-31031 July 1990 Responds to NRC Bulletin 90-001.Items 1 Through 5 of Requested Actions for Operating Reactors Completed ML20056A1841990-07-27027 July 1990 Forwards Revised Methodology for Achieving Alternate Ac for Plant,Per 900720 Telcon ML20055H2581990-07-25025 July 1990 Forwards Decommissioning Rept, Per 10CFR50.33(K) & 50.75(b) ML20055F7061990-07-0909 July 1990 Responds to NRC Re Dcrdr Requirements as Specified in Suppl 1 to NUREG-0737.DCRDR Corrective Actions Implemented & Mods Determined to Be Operational Prior to Startup Following Seventh Plant Refueling Outage ML20055D3871990-07-0202 July 1990 Provides Info Re long-term Solution to Action Item 3 of NRC Bulletin 88-008,per 890714 & s.Util Will Continue to Monitor Temp in Affected Lines & Evaluate Results ML20058K5031990-06-29029 June 1990 Discusses Use of Emergency Diesel Generators as Alternate Ac Source at multi-unit Sites,Per Licensee .Emergency Diesel Generator Load Mgt Methodology Evaluated to Meet Listed Criteria ML20044A3661990-06-21021 June 1990 Forwards Application for Amend to License NPF-73,consisting of Tech Spec Change Request 44,changing Stroke Time to 60 for Inside Containment Letdown Isolation Valves.Change Determined Safe & Involves No Unreviewed Safety Issue ML20043G6811990-06-14014 June 1990 Forwards Application for Amends to Licenses DPR-66 & NPF-73, Revising Tech Specs Re Electrical Power Sys - Shutdown & Ac & Dc Distribution - Shutdown ML20043H9341990-06-14014 June 1990 Forwards Issue 1 to Rev 4 to Inservice Testing Program for Pumps & Valves. Issue 1 Removes Relief Requests Requiring Prior NRC Approval & Adds Certain Program Changes Permitted by ASME XI & Generic Ltr 89-04 ML20043G5981990-06-12012 June 1990 Forwards Monthly Operating Repts for May 1990 for Beaver Valley Units 1 & 2 & Revised Rept for Apr 1990 for Beaver Valley Unit 1 ML20043G6851990-06-12012 June 1990 Forwards Application for Amend to License DPR-66,consisting of Proposed OL Change Request 176,revising Tech Specs to Replace Current Single Overpressure Protection Setpoint W/ Curve Based on Temp ML20043G7941990-06-12012 June 1990 Responds to NRC 900524 Request for Addl Info Re Proposed Operating License Change Request 156.Clarification of Magnitude of Confidence Level of Westinghouse Setpoint Methodology,As Specified in WCAP-11419,encl ML20043G8001990-06-11011 June 1990 Forwards Application for Amend to License NPF-73,consisting of Proposed Operating License Change Request 41.Amend Deletes Surveillance Requirement 4.4.9.3.1.d ML20043H0291990-06-11011 June 1990 Forwards Application for Amend to License NPF-73,consisting of Proposed OL Change Request 40,modifying Heatup & Cooldown Curves Applicable to 10 EFPYs Per WCAP-12406 Re Analysis of Capsule U from Radiation Surveillance Program ML20043F5251990-06-0707 June 1990 Requests Temporary Waiver of Compliance from Tech Spec Limiting Condition for Operation Re Operability of Containment Isolation Valves During Quarterly Slave Relay Testing.Evaluation to Support Request Encl ML20043F1361990-06-0404 June 1990 Advises That Chemistry Manual Chapter 5P1, Enhanced Primary to Secondary Leakrate Monitoring Program for Unit 1,per 880328 Request to Recommit to Item C.1 of NRC Bulletin 88-002 ML20043B5971990-05-18018 May 1990 Advises of Delay in Hiring Independent Safety Evaluation Group Replacement to Maintain Five Permanent Personnel Onsite,Per Tech Spec 6.2.3.2.Replacement Will Be Provided within 30 Days of Retirement of Engineer on 900531 ML20043B0511990-05-15015 May 1990 Responds to Telcon Request for Addl Info Re Elimination of Snubbers on Primary Component Supports.Probability of Case B/G Event Extremely Small & Does Not Represent Realisitic Scenario ML20043B1921990-05-11011 May 1990 Forwards Cycle 8 & Cycle 2 Core Operating Limits Rept,Per Tech Spec 6.9.1.14 ML20042G9761990-05-0808 May 1990 Responds to NRC 900226 Ltr Re Violations Noted in Insp Repts 50-334/89-80 & 50-412/89-80.Corrective Action:Maint Work Request Program Being Upgraded to Include Responsibilities of Nuclear Const Dept & Will Be Issued by 900601 ML20042G8541990-05-0303 May 1990 Forwards Technical Review,Audit Summary & Operability Assessments Re Potentially Invalid Leak Detection Tests Used as Alternative for Amse Section XI Hydrostatic Tests ML20042G9071990-05-0101 May 1990 Forwards Annual Financial Repts for Duquense Light Co,Ohio Edison Co,Pennsylvania Power Co,Centerior Energy Corp & Toledo Edison Co,Per 10CFR50-71(b) ML20042F1381990-04-30030 April 1990 Advises That Final SER for Implementation of USI A-46 Will Be Delayed Until Late 1990 ML20042F0991990-04-20020 April 1990 Forwards Response to Request for Addl Info Re Second 10 Yr ISI Program ML20012F5951990-04-10010 April 1990 Forwards Monthly Operating Repts for Mar 1990 & Revised Operating Data Rept & Unit Shutdown & Power Reductions Sheets for Jan 1990 ML20042E1471990-04-0404 April 1990 Forwards Application for Amends to Licenses DPR-66 & NPF-73, Consisting of License Change Request 174/36,updating Staff Titles to Reflect Nuclear Group Organization ML20012F6021990-03-30030 March 1990 Submits Supplemental Response to Station Blackout Rule for Plant,Per NUMARC 900104 Ltr.Summary of Changes to Condensate Inventory of Dhr,Effects of Loss of Ventilation, Control Room HVAC & Reactor Coolant Inventory Listed ML20012E3091990-03-23023 March 1990 Forwards Response to 900308 Request for Addl Info on Reg Guide 1.97 Re Variable for Steam Generator wide-range Level Instrumentation ML20012E3451990-03-23023 March 1990 Submits Addl Info for Exemption from General Design Criteria GDC-57,including Background Info Describing Sys Operation & Addl Bases for Exemption Request.Simplified Recirculation Spray Sys Drawings Encl ML20012D6491990-03-19019 March 1990 Requests Retroactive NRC Approval of Temporary Waiver of Compliance Re Tech Spec Limiting Condition for Operation 3.8.2.1 on Ac Vital Bus Operability.Sts Will Be Followed When Inverters Not Providing Power to Vital Bus ML20012E4091990-03-16016 March 1990 Forwards Inservice Insp 90-Day Rept,Beaver Valley Power Station Unit 1,Outage 7, for 880227-891221,per Section XI of ASME Boiler & Pressure Vessel Code 1983 Edition Through Summer 1983 Addenda,Section XI ML20012D6181990-03-15015 March 1990 Responds to NRC 900215 Ltr Re Violations Noted in Insp Repts 50-334/89-23 & 50-412/89-22.Corrective Actions:Safety Injection Signal Reset & Plant Returned to Presafety Injection Conditions & Crew Members Counseled ML20042D7401990-03-14014 March 1990 Forwards Corrected Annual Rept of Number of Personnel Receiving Greater than 100 Mrem & Associated Exposure by Work Function at Plant for CY89. ML20012D5801990-03-13013 March 1990 Forwards Correction to First 10-yr Inservice Insp Program, Rev 2 to Relief Request BV2-C6.10-1 Re Recirculation Spray Pump - Pump Casing Welds & Relief Request Index ML20012D6221990-03-13013 March 1990 Forwards Response to Generic Ltr 89-19, Resolution to USI A-47. Recommends All Westinghouse Plant Designs Provide Automatic Steam Generator Overfill Protection to Mitigate Main Feedwater Overfeed Events ML20012C1791990-03-0909 March 1990 Responds to NRC 900207 Ltr Re Deviations Noted in Insp Repts 50-334/89-25 & 50-412/89-23.Corrective Actions:Written Request Initiated to Identify Unit 2 post-accident Monitoring Recorders in Control Room & Recorders Labeled ML20012E0911990-03-0505 March 1990 Lists Max Primary Property Damage Insurance Coverages for Plant,Per 10CFR50.54(w)(2) ML20012B7051990-03-0202 March 1990 Responds to NRC 900131 Ltr Re Violations Noted in Insp Repts 50-334/90-05 & 50-412/90-04.Requests Withdrawal of Violation Re Stated Transport Problem & Reclassification as Noncompliance,Per 10CFR2,App C,Section G 1990-09-07
[Table view] |
Text
_ _-_ - _ _ - - ---
s 9:
}Vg 2NRC-4-097 (412) 787-$141 Telecopy 8 Nuclear Construction Division July 02, 1984 Robinson Plaza. Building 2 Suite 210 Pittsburgh, PA 15205 United States Nuclear Regulatory Commission Washington, DC 20555 ATTENTION: Mr. George W. Knighton, Chief Licensing Branch 3 Office of Nuclear Reactor Regulation
SUBJECT:
Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 Open Item / Response Gentlemen:
The Mechanical Engineering Branch Audit was held from April 3 to April 5, 1984, and has been formally documented by letter 2NRC-4-052 from E. J. Woolever to G . W. Knighton, dated May 7, 1984. Eleven open items have been identified in this documentation and ir. your minutes of the audit which were issued on June 4, 1984.
This letter forwards addit ional information on these itens.
Attachment I summarizes the present status of all 11 items. Attachments 2 through 6 provide responses or related informat ion on the following five questions (draft SER open i tem numbers are shown in parentheses): 210.12 (26), 210.31 (40), 210.32 (39), 210.34 (42) and 210.37. This information will be incorporated into FSAR Amendments 7 and 8. Please let us know if this information is accept ab le and if the staf f agrees with the closed or confirmatory status indicated for each item in Attachment 1.
During the audit , the NRC reviewers indicated a need to review the responses submitted for the following four questions : 210.27 (26), 210.28, 210.34 (42), and 210.39. Please inform us of the status of this review.
DUQUESNE LIGHT COMPANY SUBS 'RIBED AND,.S ORN TO BEFORE ME THIS .
of p Y OF c/g
/
, 1984. By ( - I
/ E
~Vice
{/J.Woolever 4/ President 7LVA'G. LESONDAK,410TARY PDtiRfy Public ROBINSON TOWNSHIP, ALLEGHENY COUNTY JJ$.I)OMMISS1QN EXPIRES OCTOBER 20,1986 Attachment cc: Mr. G. Walton, NRC Resident Inspector (w/a)
Mr. E. A. Licitra, Project Manager (w/a)
Ms. M. Ley, Project Manager, (w/a) 8407090019 840702 PDR ADOCK 05000412 Il E PDR
y -
- Unitsd Stctss Nuclear Riguletory Commission Mr. George W. Knighton, Chief Page 2 COMMONWEALTH OF PENNSYLVANIA )
) SS:
COUNTY OF ALLEGHENY )
On this J M day of f,, , //M , be fo re me ,
a Notary Public in and forbaid dmmonwealth and County, personally appeared E. J. Woolever, who being duly sworn, deposed and said that (1) he is Vice President of Duquesne Light, (2) he is duly authorized to execute and file the foregoing Submittal on behalf of said Company, and (3) the statements set fo rth in the Submittal are true and correct to the best of his knowledge.
4 1
fotaryPublic
+ ELVA C. LESONDAK, NOTARY PUBttC ROBINSON TOWNSHIP, ALLEGHENY COUNTY MY COMMISSION EXPlRES OCTOBER 20,198(i 9
ATTACHMENT 1 Status of MEB Open Items 210.10 (28)* This question is concerned with pipe-to-pipe impact. This subject has been addressed in the response submitted at the audit. In the audit, the question of the ef fects of jet impingement arose. This subject is addressed in Ques t ion 210.12. Question 210.10 (28) should be considered closed.
210.12 (26) A revised response is provided as Attachment 2. It now includes addit ional description of the jet impingement acceptance criteria.
Tables which show how the ef fects of jet impingement will be incor-porated with those from pipe whip are also included in Attachment 2.
This item should now be considered confirmatory.
210.27 (36) NRC indicated a need to review the response submitted at the audit .
210.28 NRC indicated a need to review the response submitted at the audit .
210.31 (40) A revised response is provided as Attachment 3. This item should now be considered confirmatory.
210.32 (39) A revised response is provided as Attachment 4. It now includes the results of the functional capability study. This item should now be considered closed.
210.34 (42) NRC Indicated a need to review the response submitted at the audit .
Tables 3.9B-14, 15, and l', referred to in the response to Question 210.34 have been revised and are provided in Attachment 5. Tables 3.9B-14 and 15 now include the jet impingement loads. The response to Question 210.34 was previously revised to clarify the buckling criteria employed by Westinghouse for linear type auxiliary equip-ment supports (Refer to 2NRC-4-052 dated May 7, 1984). A draft of the ASME Code Baseline Document is being submitted under separate cover. This item should now be considered confirmatory.
210.37 A revised res ponse is provided as Attachment 6. This item should now be considered closed.
210.39 NRC indicated a need to review the response submitted at the audit .
210.40 The Preservice Inspection Program is being submitted under separate cover. The valve listing is scheduled for six months later. This item remains open.
210.41 (43) The Ins ervice Inspection Program submittal is scheduled for June 1985. This item remalas open.
- Draft SER Open Item numbers are shown in parentheses t.
r- ,
ALLachment 2
- BVPS-2 FSAR I
! tRC Letter: February 9. 1984 i
L Question 210.12
! Tables concerning jet impingement effects could not be found.
l Provide these tables. i I
Response: ,.
The required information concerning jet impingement effects will be ;
j provided with the assessment of other jet impingement effects for all high energy systems where breaks are postulated, which is scheduled to be submitted by July 1985.
The submittal dates for the various buildings are the same as those
- provided in the response to Question 210.9, Amendment 7.
The tables for jet impingement effects will be integrated with those for pipe whip effects (refer to Question 210.9) and the table format will be provided at a later date.
Acceptance criteria for jet impingement targets are provided in the form of load combinations and design allowables in Section 3.8.3 for structures, and in Sections 3.68.1.3.2.3 and 3.9 for piping.
Other components identified as essential targets for jet impingement will be shielded from the fluid jets whenever possible. Where shielding of these components cannot be provided, acceptance criteria will be determined and provided in the appropriate sections addressing those components, i
l l
l Amendment 7 Q210.12-1 July 1984 NOTE: The following tables will be included in Amendment 8
5 e
e o
SvPS-2 t$et ectf 8 TO Fiel8185 3.06 824 T>stoume Feeunt 5.es-tac /
/
' )
Amst freens Ptee unge w sepsanemaet Llee~ Case sessen for eier- Rostralet Electralet -set latent ,s Snlege
-ls. e smte, ciese wi.et i. bee'." .%tes.else'88 strees teett'5' eses"8 pues. sties . tve.' S' h' ia=* ' rat ia M <
.e p
3ruS496-12-2 2 FutGel4>C C it se,eM $ . + Later Later Later
{ j s
a ,
4 P +
= Later Later Later , ,
5 g *
} g WuS4102-4-C C IP 17,412 $ 2ry'M4A LS ' Later / tater Later ,
. , $*S4Iun64C ~< LS I #J f 3re$-rene45 LS
,[
. '< - , my gg ,;
f - /-
r
+
- ,,.,' , P 2FuS45ulM t . LS Later .- , Later 'Leter '
l( .
NuS45umo) LS ,.
- . f - y FuS4eule55 LS
~ 8
[ f '
Nul45ute45 ,/ LS -
./ FuS41ule04A LS i; .T LS , [
/
{, ' Fubee3+C C 37 18,438 - ($ 3Fus4.uge9 L$ ,
/p Cater Later Later ,
, t - > 2FuS45ubseen LS ,
2FWS44Wieode LS <
l ,
2FuS45ueel LS 2Fus4tuell t$ ,-
f FuS44ute83 LS ,
t P 2FuS4ssIB42 LS Later Later Wer /
yut-tes-44; C TE 13,977 3 . - ' "- Later Later , , Latw P = = Later Later Later yes-e le-2>2 2 Nus eeS4 -C C TE 14,711 5 - - Later Later Later P . - Later Later Later
, Fubee64>C C IP 22,801 3 2Ful4Wluell L$ Later Later Later P 2Fus-fquis22 L5 Later Later Later 2Fu145ste25 LS 2FuS41ute24 LS i Fubes?-44: C IP 84.907 8 NuS45ute24 LS Later Later Later NWS4tute25 LS 2FuS45ute22 LS 1 P = = Later Later Later Fus-ces-A-C C TE I4,385 3 . . Later Later Later P - - Later Later Later aseeement e 1 el 2 Septeamer 3934 Wat 82248-63
e II t t t t t t t t 33 3 3 3 3 3 3 3 3
. I
=:
8 n t ) t b t k n l
-i 3i 3 3 s 3 3 33 3 J
.3 8]
t k n t t t t t 1 3 333 3 3 33 j: . . .I ~3 5 ..
s ia s
!.s -- -
i i 3
a :i 4 4 I] . . .!Il=,.
E a
j:
] .1 R
5-4 Ea l 's s 3 3 t i i i i 2 1 -
I c -
1 2
a-
{
e *l
~
I
r a s e i l
1 il 1
= 23 -
.g
. = = =
ja
.s g 11 i
[ f I :
==l
! k k 3 k:
if .
11 4
,. i
- -i
-8 1
- 44 I .I 22 yIcI - {~ga3i ((
1 -* .
- 2. - ! *I }I I
- 3ls ! It! :,3I g jy s3 4 i. a]E 2s3 i i !
$l t-..).
- 3
= ll1i'a51!
.. : a.l cas.
S a
I i
i i
g o$
e a l5.
1 a
oE f EO j k6d 1
e a
a f
i
- ._,,.._...e__..,.,..-_..
4
~.
?! y n i t s a i t t t i t t t t.
. 33 s 3 3 33 3 3 3 33 3 3 3 3 3 3 3 3!
I 1 u33 3# 3 3 33s 3 3 3 33 3 s 3 33 33
,1 3
2 3 ma t t t n i s i t 3 = *
- t i s 3 3 33 3 3 3 33 3 3 3 3 3 3 3 3 1:
- . . . . essere. . . . . terr. . .
amer. assere.
. it i
3 .3 a
- 2 22R l2ap 2*'2R-i il i ill I l1,51 i-s . . . . ..
.. . . . . I.I e
6 -
.c g f~ u > u > u > u > u > u >u > u >u >
~
na
- 6 a I j i . a a . s a . i r g i- i i i i i e 5 I-1 -
=
= s s = i s e s s 2
i
~
u o u o o u o o u 1
u u
l u
[ !!
v l,
11 Il 11 ls y
.a la li h . h .
I#
-il If 1 II
'gg -i.l
!!) -:!
I I j [g _
l.j * -2 1i i i i
. . na ; '. . . , :. _ . -~e--e -~
6 SUPS-2 FSMI sett$ TO FleWES 3.5-834 A88 S.#-15 SCoetl settse .
1 Areen Type:
C = C*rmaterestlet Greek L = Longitedleel Greek
- 3. Renees for Poeteletgees it Tereleol ted
- 4 BP = latermelete tream pelet setletyleg the regelreemet of e steles of too laterandlete treek golete EA = Tetel Additive Strees tem of Eg. 9 med IM esemede ellesable selee
- 3. Allementee inofer 94 secelen 3.S.2.3.2.Il
. Tetel Additive Stroes tem of Eg. 9 and l# e 8.4 ll.( e $gt
- 37, M pel 4 Stemdeses c = elesdens tres sentelement elde T = 88 m tree turtles belldlag olds
- t. 9 Restralet Typee 88 = Afgle Stauser PC = Plpe Creek Baseer
( Skleed Types FP = Flat Plate iP = Cerved Plate CL = CylledrIcel t
4 t
l t.
t 1
I GO I Ieptember 1994
a r
- o evPS-2 FSalt leTES TO FleWIE 3.es.844 Ase Fleimt 3.4e-943 AssE arente Plos Ilhfe M leleaguest Llee Code 8beseen for Sles- Restrelet theetrolet Jet Shfeld Sh8 eld UI esse I83 U3 Seelenettee Clees Deplanet$ge Twee Per
- let ten III Strees (nell III Destepetten Twee g Doetonatice [
24ssS432-5 4 me-lew ass 415+c C IP 24,289 C ass-amow as Later Lat.c tet, asleeleetly asES-PlutB38 as 3spoorted 365-MuiB32 M 365m33 IIS 3GS-Mins 34 lie as5S-FlulB3S AB T = - Later Later Leter I
3GS-48444 C tp 23,44 F C as58-Mute 39 M Later Later Later asLS-nute32 le ass-Miness as auss-elsW34 R$
anes-MumB3S se asES-MasM LS T as55-MuiB37 LS Later Later Later SES-GIS+C C TE - C 355-#9u1837 LS Later Later Later 7 - - Later Later Later
- 2458432-2 4 same-4hsteer 388-0064 4 C GP 29,250 C 348-Mule 40 le Later Later Later Salesleetly asESNI IIS Supported 3s58-Mul042 18 3ES-Mele43 15 3ES-Mue44 IIS astS-Musses me 7 - - Later Letw Later ESES 407-04 C IP 31,790 C 3s55-Mulee t at Later Later Later as5S-nm642 Rb 3s55-Huls43 11 8 as58-Mut04S RS as55-Mul045 88 3s55-MIRS44 LS T 2nsS-Mut447 LS Later Later Later 3GS eld 4 C C TE - C asSS-emas47 LS Later Later Leter T = - Later Later Later WG $ ef 2 September 1984 4 518-82249-42 4 .
e .C
- SWPS-2 FSal acTES TO FIGleit 3.5-14A de Fified 1.85-143 (Conti AM ereeks Plos uhle Jet Iamineesent Ilmosos for Ston= Ilestralet mostratet Jet Shield SaleI4 Llee Code dese W d IS8 Seelmtlee Clase SeelaaetIgo Twee III Pestalet tee III Strese testl OI Oosfeestlee Twee h costaaetlea wS w.u wiser MS el++c C iP 2. 322 C MS enasso as Lat.r Later Later Selenteeley M S M 458 51 8 W,4 MS-f4WIBS2 IIB MS-fulness Hs 3s55-flut994 fe ass $ MSS as T . . Later Later Later 3ESS 630-6 C C IP 27.432 C MS-8HRSSI as Later Later Leter 3s55-Peut 452 lie MS-#UIAS93 ft 365 6 54 IS ,
MS-#elsness Ile 365-fitfe96 LS T 3s55-#Iue57 LS Later Later Later Buss-ett-ed: C TE = C 3ESS-MIfitS7 LS Later Later Later T - - Later Later Let sr epitSe I
le greek Types S. 81mseslot Type:
C
- Altid Smeer t . Leag ted1.es g green LS = Lesleeted Strap 2 Rennen ter hoteletten 6 Shtete Types TE = Teraf ael End FP = tiet Plate
' IP
- Intermedlete treek pelet estistyleg fee receiresset et e mieleen et tus Intermodlete break lesetisme EP = Curved Piete EA = Tetet Adeltive Strese tem of Eg. 9 and lei emesses ellesette value CL = Cylledrical 3 assemensee istseer to Seceles 3.e.2.9.2.3 Totes AsdItBoe Strees (se of Eg. 9 and Iel e 0.8 (I.2 h
- I A) e 37.000 pel 4 Glendeems C
- Stendene tres esetelemmet olde T = 91eeden tres tortsee tultslag esse t8 2 et 2 September 1984 Amt-8774 8-42
Attachment 3 BVPS-2 FSAR NRC Letter: February 9, 1984 Question 210.31 (fection 3.9.3)
The staff finds that there is insufficient information describing the design of safety-related HVAC ductwork and supports. Provide the desigr, basis used for qualifying the HVAC ductwork ar.d support structural integrity.
Response
Design of Ducts Ductwork is not structurally designed, however, it generally follows S!!ACNA as a design basis. Testing on representative duct spans are being performed to verify the adequacy of the above.
Design of Duct Supports Seismic duct supports are designed to rigid range criteria which has been verified through on-site testing. A final test report is being developed and will be available with further details by September 1, 1984.
< Amendment 7 Q210.31 June 1984 i l
.~
Attachment 4 BVPS-2 FSAR URC Letter: February 9, 1984 Question 210.32 (Section 3.9.3)
Provide the basis for assuring that ASME Code Class 1, 2, and 3 piping systems are capable of performing their safety function under all plant conditions. Describe the methodology used to assure the functional capability of essential piping systems when service limits C or D are specified.
Response
ASME III Classes 1. 2 and 3 piping systems are designed for all plant conditions in accordance with the ASME III code requirements as shown in Tables 3.9B-5, 3.9B-8, 3.9B-9,-3.9B-11, and 3.9B-14.
Numerous operating fluid transient events have occurred in operating nuclear power plants (NUREG-0582 and MUREG/CR-2059). Many of these events caused code allowable stresses to be exceeded, and some were severe enough to significantly damage piping and pipe supports. None of these events resulted in a loss of functional capability where the integrity of the pressure boundary was maintained. Other experiences, such as the effects of the 1979 Imperial Valley earthquake on the El Centro Steam Plant (NUREG/CR-1665), which did not cause any loss of functional capability although design to withstand earthquake was minimal and the earthquake was of high +
intensity, indicate that functional capability is, again, not a practical concern.
The difference between operating experience and academic concern is in part explained by a study of seismic design margins for piping (NUREG/CR-2137) where lower bound margins of 1.4 or greater indicated significant reserve strength when designed to ASME III rules. In ,
l addition, stresses are dominated by stress intensification factors
-which address fatigue strength of local areas, but are not indicative of the general state of stress in the piping system. .Although ASME Level D stress limits theoretically permit gross yielding of - piping while only protecting the pressure boundary, practical experience indicates otherwise. Failures of the pressure boundary have occurred due to unanticipated loads (e.g. , waterhammer, vibration, etc) or corrosion / erosion, but gross yielding of an intact pressure boundary
- has not led to a loss of functional capability.
-The practice of reducing code allowable stresses to preclude theoretical gross yielding for very low probability loads may in fact reduce the overall safety and reliability ^o f the piping system.
Lower ellowable stresses are achieved by additional pipe supports,
~
and - usually snubbers (which reduce dynamic stresses without increasing thermal or deadweight stresses) resulting 'in a stiffer-system with higher . stresses during normal plant- operation,' but theoretically lower stresses for the low probability design events Amendment 7 Q210.32-1 Jt.y 1984 ;
l i
i L: --
a BUPS-2 FSAR applicable to Level D stress limits which are dynamic in nature.
Additional pipe supports, particularly snubbers, and increased piping stiffness are of ten cited (e.g. , NUREG/CR-2136 and S. H. Bush letter to N. J. Palladino of August 20, 1981) as sources of potential failures due to limiting access for maintenance and inservice inspection, difficulty in installation and proper adjustment, and higher stresses during normal plant operation.
The Staff requested additional justification for assuring that functional capability is maintained for piping systems subject to service conditions C and D. Although it is BVPS-2's position that the ASME III code requirements provide inherent conservatism such that functional capability is not a practical concern, an evaluation was performed to-further investigate this matter.
The question of functional capability addresses primary loads on piping systems for Level C and D service conditions. A review of the load combinations for the various service conditions is helpful in understanding the BVPS-2 specific situation. For all practical purposes, the difference between Level B and D is the OBE loading versus the SSE loading. The LOCA load in the faulted condition is
, not considered because DLC has requested an exemption from postulating breaks in the reactor coolant main loop piping. Service Level C includes pipe whip and jet impingement effects which are rarely required to be analyzed due to system redundancy and separation in the plant layout. Therefore, pipe design is governed
, either by Level B or D for primary loads.
( A review of the amplified response spectra (ARS) used for the OBE and SSE indicates additional conservatism in piping design for BVPS-2.
The OBE utilizes 1/2-percent damping while the SSE utilizes 1-percent
' damping, which is certainly conservative with respect to the current Regulatory Guide position. The difference in damping results in a situation in which the OBE tends to govern design (i.e., service Level B stress governs design).
The use of Icw damping and the fact that the Level B service condition typically governs pipe design for primary loads provides assurance that functional capability is not a practical concern for BVPS-2.
As additional justification for assuring that functional capability.
is not a practica1' concern, .a sample review .of certain critical systems w'as performed utilizing the functional capability criteria suggested by the NRC Staff'during the April 1984 meeting at SWEC.
Since the functional capability concern deals primarily with the SSE and accident conditions, those systems most critical to mitigate the consequences of an accident and to reach and maintain a safe shutdown condition were chosen for the review. The sample consisted 'of all pipe stress problems comprising the low head safety injection and high head safety injection systems inside the reactor containment I building.
( "
July 1984 Amendment 7 Q210.32-2
- 2; ;
. . BUPS-2 FSAR The details of the review are contained in Attachment Q210.32-A. The
- results substantiate 'the assumptions made above- regarding the
- practicality of the matter. In every case, the pipe stress problems
. passed the functional capability __ criteria by substantial margins.
Since the _ systems reviewed cover a variety of pipe sizes, these
- conclusicns can also be applied to the balance of Seismic Category I piping. Consequently, no further . action on this issue is deemed necessary.
f j
f 4
1 Amendment 7 Q210.32-3 July 1984
- BUPS-2 FSAR Attachment Q210.32-A Introduction For the BVPS-2 project, both the low head safety injection and high head safety injection systems are already designed and/or constructed. The original design basis was to the ASME Section III, 1971 Code, including the Addenda through Winter 1972. This investigation required reevaluation of existing calculated stresses by applying new stress indices and modified allowables.
Criteria The functional capability criteria deemed acceptable by the NRC Staff and utilized in this investigation consisted of the stress combinations, stress indices, and allowables contained in ASME Section III, 1983 Code for Class 1 and Classes 2/3 Piping. Since the concern is the development of a plastic hinge with a resulting reduction in flow area, the investigation only evaluated the primary stress terms that constitute Equation (9). The limits imposed on stress were the lesser of 1.8 5 or 2.25 S ,for Class 1 piping, and 1.8 Sy or 2.25 Sh for Class 2/3 IPiping.
For elbows, branch connections, and restraint locations on straight pipe, the calculated Level D (faulted condition) stresses were modified by the B indices of Equation (9) and compared to the
. i appropriate functional capability limit.
Results of the stress problems reviewed,- there were no piping components which failed the functional capability criteria. In fact, substantial margins exist. The high stressed component was only 66 percent of the function cability allowable, and the average was approximately 25 percent of the functional cabability allowable.
Amendment 7 Q210.32-A July 196.
_ _ _ _ . -s- _ _ ._
y e',N-~ ...w~
.n.
Attachment 5 BVPS-2 FSAR l
l NRC Letter: February 9, 1984 Question 210.34 (Section 3.9.3)
The staff review of FSAR Section 3.9B.3.4 and 3.9N.3.4 finds that there is insufficient information regardin'g the design of component supports. Per SRP Section 3.9.3, our review includes an assessment of design and structural integrity of the supports. The review addresses three types of supports: (1) plate and shell, (2) linear, and (3) component standard types.
For each of the above three types of supports, provide the following information (as applicable) for our review.
(a) Describe (for typical support details) which part of the support is designed and constructed as component supports and which part
.is designed and constructed as building steel' (NF vs. AISC jurisdictional' boundaries)
.(b) Provide the complete basis used for the design and construction of both the component support _ and the building steel up to the building structure. Include the applicable codes and standards used in the design, procurement, installation, examination, and inspection.
(c) Provide the loads, load combina'tions, and stress limits used for ,
-the component support up to the building structure. !
(d) Provide the~ deformation limits used for the component support.
(e) Describe the buckling criteria used for the design of component support.
Response
The' BVPS-2 is a non-ASME.III, NF plant.when addressing design and construction of component supports. A very small percentage' of components have' supports designed and constructed to ASME III, NF requirements, but this is due to.the . purchase order date'.for -the.
components. The. vast majority of component supports are not designed to ASME III, NF requirements and are not required to be.
The specific responses. to the questions are provided in three separate parts. 'Part 1 addresses Westinghouse' supplied component supports,:Part 2 addresses'SWEC designed / supplied component supports,-
and Part 3' addresses piping component supports.
Part -I - Westinghouse Supplied Component' supports Westinghouse has ' supplied supports only for those class 2 and 3 components also supplied by Westinghouse-to which the ' supports are attached. .This equipment is divided intoi wo t groups.-
Amendment 7 Q210.34-1 July 1984
. NOTE: ' Response is the~same as submitted inLLetter 2NRC-4-052 i dated
- May 7, L 1984. Tables 3.98-14; and 3.95-15 include jet impinRement" loads.. '
BVPS-2 FSAR The first group consists of auxiliary tanks and heat exchangers. The supports for these components are of two types; linear and, for the most part, plate and shell type supports. The supports for the tanks and heat exchangers meet either the requiremcnts of Subsection NF of the ASME Code or the requirements of the AISC Code depending on the procurement date of the component. Components procured prior to the inclusion of Subsection NF into the ASME Code were designed to the AISC Code requirements. A listing of the tanks and heat exchangers and the codes to which the respective supports were designed is available if needed.
The second group consists of Class 2 and 3 auxiliary pumps. The supports for these pumps are plate and shell and, for the most part, linear-type supports. The auxiliary pump supports are designed by the pump manufacturer to pressure boundary stress limits, with the exception of the boric acid transfer pumps, the supports for which are designed to the limits of the AISC Code.
The loads and loading combinations of the supports for the auxiliary equipment supplied by Westinghouse are the same as those of the supported component. These loads and combinations are given in FSAR Table 3.9N-4.
Deformation of the tanks and heat exchangers is accounted for through the use of the stress limits of AISC or ASME, NF. These limits ensure the supports remain elastic, thereby preventing permanent deformation. Additionally, the supports for active pumps must not deform such that specified critical clearances are maintained so that j
the pump remains operable. These clearances are specified in the
- pump specification.
Buckling is prevented by limiting compressive stresses for linear-type auxiliary equipment supports under loadings from all service conditions to the limits of AISC Section 1.5 or ASME Appendix XVII-2210. These limits, which are identical, are based on the Column Research Council (CRC) buckling curve for centrally loaded columns. A variable factor of safety, based on column length and section material properties, provides adequate margin to the critical buckling values of the CRC curve. A discussion of the buckling criteria for plate and shell type supports is as follows.
Buckling Criteria for Plate and Shell Type Supports Plate and shell type supports for Class 2 and 3 auxiliary equipment are evaluated for buckling and instability through selective use of the criteria of Appendix XVII, Subarticle XVII-2200 and Subsection 1 l
NC, Subparagraph NC-3133.6 of Section III of ASME Code.
Subparagraph NC-3133.6 gives methods for calculating the maximum allowable compressive stress in cylindrical shells subjected to axial and loading that produce longitudinal compression stresses in the shell.
A Amendment 7 Q210.34-2 July 1984
i---
BVPS-2 FSAR Subarticle- XVII-2200 gives requirements for structural steel members including allowable corpressive loads based on slenderness ratios and interaction equations for combined stresses.
Use of the above requirements, in addition to those of Subsection NF, in the design of plate and shell type supports for Westinghouse supplied auxiliary equipment, ensures the dimensional stability of the support throughout the range of applied loadings.
In accordance with the request of the MEB staff, a discussion on how allowable buckling stresses are calculated for linear-type supports are included in this response. In addition, FSAR Section 3.9N.3.4, Component Supports, has been revised to reflect the discussion on Class 2 and 3 auxiliary equipment support types and design criteria.
Component Supports (Section 3.9N.3.4)
Westinghouse has supplied supports only for those Class 2 and 3 components also supplied by. Westinghouse to which the supports are attached. The loads and loading combinations of the supports are the same as: those of the supported component. These loads and ombinations are given in FSAR Talbe 3.9N-4.
The Class 2 and 3 auxiliary equipment supplied'by Westinghouse is grouped into two general categories. One group consists of tanks and heat exchangers. The other group is auxiliary pumps. Design criteria for the supports'for these components are discussed below.
Tanks and Heat Exchangers (Section 3.9N.3.4.1) l The supports for auxiliary tanks and heat exchangers are of two l types: linear and, for the most part, plate and shell type supports.
The supports meet either the requirements of Subsection NF of the ASME Code or the requirements of the AISC Code, depending _ on the procurement date of the component. Components procured prior to the inclusion of Subsection NF into the ASME Code were designed to the
( AISC Code requirements.
I Auxiliary Pumps (Section 3.9N.3.4.2)
The supports for Class 2 and 3 auxiliary pumps are plate and shell and, for the most part, linear-type supports. The supports are i designet by the pump manufacturer to pressure boundary stress limits, l with t te exception of the boric acid transfer pumps, the supports for which are designed tc the limits of the AISC Code.
Part II - SWEC Supplied / Designed Component Supports (a) The SWEC supplied component supports are for the most part supplied with its component. Component supports supplied with the equipment are designed and constructed in accordance with AISC Code or ASME III, NF requirements. ASHE III components
- Amendment 7 Q210.34-3 July 1984 n
i
. 1 BVPS-2 FSAR constructed to ASME III, 1971 Edition through Summer 1973 Addenda or earlier have supports designed to AISC. After Summer 1973, supports are in accordance with NF requirements.
The loads, load combinations, and stress limits tut tne SWEC supplied component supports are identified in Table 3.9B-16, Anendment 7.
All equipment supports are designed to elastic limits.
Deformation limits are not used.
AISC jurisdiction is assigned to embedments or building steel to which the supports are attached. The anchorage design criteria is described in the response provided for Question 210.35.
(b) The SWEC designed equipment component supports are designed using AISC code allowables or the allowables of ASME III, NF as guidance, even though the requirements of ASME III, NF were not mandatory for these supports due to the procurement date of the components.
The loads, load combinations, and stress limits for the primary equipment supports are identified in Table 5.4-21 and the remaining equipment supports in Table 3.9B-16, Amendment 7.
All equipment supports are designed to elastic limits.
Deformation limits are not used.
The buckling criteria for the equipment supports are in accordance with the AISC code. .
AISC jurisdiction is assigned to the embedments or building steel to which the supports are attached. The anchorage design is described in the response provided for Question 210.35.
Part III - Piping Component Supports Except for integral welded attachmente defined in Section 3.9B.3.4.2, pipe supports are not designed or constructed to ASME III requirements because their design and procurement proceeded ASME III, NF. Therefore, plate and shell type designations are not applicable.
The response to items (a) through (e) of Question 210.34, as applicable to pipe supports, ares (1) All pipe supports are designed as described in Tables 3.9B-14 and 3.9B 15, Amendment 7. AISC jurisdiction is assigned to embedments or building steel to which the pipe supports are attached.
(2) Pipe supports meet the criteria of the AISC Code ANSI B31.1 Code and Tables 3.98-14 and 3.9B-15, Amendment 7. When pipe
(
Amendment 7 Q210.34-4 July 1984
BVPS-2 FSAR l
supports include integral attachments to pressure retaining l Jundaries, the integral welded attachments are designed, l fabricated, installed, and inspected in accordance with the criteria stated in Section 3.9B.3.4.2.1.
(3) Loads and load combinations used to design pipe supports are described in Tables 3.9B-14 and 3.9B-15, Amendment 7. The allowables are based on the AISC code. The loads, load combinations and the corresponding allowables for designing integral attachments to the pressure boundary are described in Section 3.9B.3.4.2.1.
(4) All pipe supports are designed to elastic limits.
Deformation limits are not used.
(5) Buckling criteria for pipe supports are in accordance with the AISC Code.
I Summary l
Component supports for BVPS-2 are not designed or constructed to ASME III, NF requirements for the majority of components. SWEC will specifically identify supports designed and constructed to NF l requirements in the ASME Code Baseline Document which is due to be issued in June 1984. This ASME Code Baseline Document will be referenced in and become part of the FSAR.
i l
l l
Amendment 7 Q210.34-5 July 1984
BUPS-2 FSAR TABLE 3.9B-14 LOAD COMBINATIONS FOR PIPE SUPPORTS EXCEPT QSS, RSS, AND SIS '3,* ,5,88 Plant Operating Load Allowable Tensile <2,7)
Condition Combinations Stress Normal / Upset D+T + R + R" + Stt,s> 0.6 S y ,
D+E +H+T.+R+A+ 0.6 S Y
w + S cs>
Emergency D+H +Y 0.8 5 y
Faulted D + E' + H + Y' O.S S Y
NOTES:
- 1. For definition of terms, see Table 3.9B-11.
- 2. Buckling criterion for pipe supports is in accordance with the AISC Code.
- 3. Generally, an enveloped design load is used, thus producing s
- conservative load combination. The above load combination and
( limits may be used when specific loading methods are needed.
- 4. Refer to Table- 3.9B-15 for allowable tensile stress values for QSS, RSS, and SIS systems.
- 5. QSS, RSS, and SIS systems correspond to:
QSS - Quench spray system RSS - Recirculation spray system SIS - Safety injection system
- 6. For pipe support designs on instrumentation tubing, thermal loads and seismic loads are evaluated separately if the instrument line is normally dead-ended (i.e., no flow).
- 7. The above allowables are the basic tensile stress-allowables.
All other requirements of the AISC Code related to member stresses are satisfied.
- 8. During containment pressure test. only system thermal conditions that occur during the. test need be considered.
- 9. Wind loads (W) are not considered acting concurrently with OBE' inertia effects (E) and OBE anchor movements (A).
Amendment 7. 1 of 1 July 1984
I l
- BVPS-2 FSAR TABLE 3.9B-15 LOAD COMBINATIONS FOR PIPE SUPPORTS FOR QSS, RSS, AND SIS '3,4,5)
Plant Operating Load Allowable Tensile <2,s>
Condition Combinations Stress Normal / Upset D + T + R + R" + S(1,7) 0.6 S y
D+E+H+T+R+A+ 0.8 S Y
W + Sts:
Emergency D+H+Y 0.8 S Y .
Faulted D + E' + H + Y' O.8 S T + R' + A' + X 0.8 S 7 Y
NOTES:
- 1. For defir.ition of terms, see Table 3.98-11.
- 2. Buckling criterion for pipe supports is in accordance with the AISC Code.
- 3. Generally,. an enveloped design load is used, thus producing a conservative load combination. The above load combination and limits may be used when specific loading methods are needed.
- 4. QSS, RSS, and SIS Systems correspond to:
QSS - Quench Spray System RSS - Recirculation Sprav System SIS - Safety Injection System
- 5. For pipe support designs on instrumentation tubing, thermal loads and seismic loads are evaluated separately if the instrument line is normally dead-ended (i.e., no flow).
- 6. The above allowables are the basic tensile stress allowables.
All other requirements of the AISC Code related to member stresses are satisfied.
- 7. During centainment pressure test, only system thermal conditions that occur during the test need be considered.
- 8. Wind loads (W) are not considered acting concurrently with OBE inertia effects (E) and OBE anchor movements (A).
Amendment 7 1 of 1 July 1984 k L.
, m '
BVPS-2 FSAR 1ABLE 3.98-16 LOADS, LOAD COMBINAT 10f4S, AND STRESS LIMilS Folt SAM DESIGNED AND SUPPLIED EQUIPHINI SUPPORIS Plant Design or Operating Loads and Loading Rress tipths fje f e re.nge_ _Sou rr;e Condetion Comhina Qons Igo rma l Deadweight of Component and St ruc tu ra l Members ASME 111 Subsection NT Supports lension and Bending (Fg) = 0.6Sy Suhart: HI-3100 Shea r ( fy) = HI-3230 lempe ra tu re 0.1 h 4
Pressure Bolts (f ither above or:) Article XVil-?OOO Mechanical ( Piping) Loads *** lension (ft) = Su/2 fable NF-3272.1-I Shear (Fy) - 0.6?Su/1 (Abovn used as a guide)
NormaI and OBE Same as norma i Same as notmai Upset Ese rgency Not appIicabie' Normal and SSE St r esc tu ra l Members ASHf Ill Subsection NF Faulted Appendie i Lessor of: .
1.2 ( /I g) or .1 (S /fg )*# Suhart: f-1370 (Above used as 4 guide)
Bo8ts
- 4. T Su/ F t<Sy l
!LOILS:
- As stated in Section 3.98.1-1.
- Used only when faulted stresses exceed normal / upset allowables (conservat ive),
is specified minimum material yield strength at temperature.
S is specified minimum material ultimate strength at temperature.
' For bolting materials 0.7 pS is less than (.
- Includes thermal expansion and anchor point' motion loads.
l 1 or 1 July 1981s Amendment 7 l
l l
W^-
- Attachment 6 QUESTION-210.37-l 'Due to a long history of problems dealing with inoperable and incorrectly installed snubbers, and due to the potential safety significance of failed snubbers in safety-related systems and components, it is requested that main-tenance records for snubbers be documented as follows:
Preservice Examination A preservice examination should be made on all snubbers listed in Tables 3.7-
.4a and .3.7-4b of Standard Technical Specification 3/4.7.9. This examination 3
i should be made af ter snubber installation, but not more than six months prior to initial system preoperational testing and should, as a minimum, verify the
- - following
y (1) There are no visible signs of damage or impaired operability as a result 4
of storage, handling, or installation.
l (2) The snubbe r location, orientation, position setting, and configuration (attachments, extensions, etc.) are according to design drawings and specifications.
I (3) Snubbers are not seized, frozen, or jammed.
(4). ' Adequate swing clearance is provided to allow snubber movement.
(5) If applicable, fluid is to the recommended level and is not leaking from
- the snubber system.
< (6) Structural connections such as pins, fasteners, and other connecting a hardware such as lock nuts , tabs, wire, and cotter _ pins are ins t alled
- correctly.
~
! If the period between the initial preservice examination -and initial system preoperational test exceeds six sonths due to unexpected situations, reexam-ination of Items 1, 4, and 5 shall be per formed. Snubbers which are in-stalled incorrectly or otherwise fail to meet the above requirements must be
~
repaired or replaced and reexamined in accordance with the above criterion. .
Preoperational Testing During preoperational testing, snubber thermal movements for systems whose
, operating temperature exceeds 250*F should be verified as follows:
t (a) During initial ' system heatup and cooldown, at specified temperature
~
I 1 intervals for any system which attains operating temperature, verify the snubber expected thermal'uovement.
l (b) For those systems which do not attain operating temperature, verify via observation and/or calculation that the' anubber will accommodat e the projected thermal movement.
j NOTE: This' response will be included in Amendment 8.-
i- .
1
QUESTION 210.37 Preoperational Testing (Cont'd.)
-(c) Verify the snubber swing clearance at specified heatup and cooldown intervals. Any discrepancies or inconsistencies shall be evaluated for cause and corrected prior to proceeding to the next specified inter-vals.
The above described operability program for snubbers should be included and documented by the Preservice Inspection and Preoperational Test Programs.
The preservice inspection must be a prerequisite for the preoperational test-ing of snubber thermal mot ion. This test program should be specified in Chapter 14 of the FSAR.
RESPONSE
4 A Preservice Inspection Integrated Program for BVPS-2 is being developed for submittal to the NRC in June 1984. This Program identifies the "ASME Section XI Preservice Inspection Plan for Snubbers", including the Preservice Examin-at ion and Preoperational Testing of all snubbers except those installed on non-safety related systems for which their failure or failure of the system they are installed would have no adve rs e effect on any safety-related system.
The Snubber Plan requires "Preservice Examination" of the snubbers no more than six months prior to initial system preoperational testing. As a mini-mum, the six (6) criteria, as desc ribed in the NRC question above, will be used. Manual stroking of the snubbers either in place or detached, will be performed to assure they are not seized, frozen, or jammed (Criterion No. 3) and will be limited to snubber sizes that can be manually handled.
The Snubber Plan will also perform "Preoperational Testing" to verify thermal movements of the snubbers for systems whose operating temperature exceeds 250*F. The criterion "a" through "c", as described in the above NRC ques-
~
t ion , will be used as a minimum basts for testing. The Preservice Examina-t ion will be a prerequisite for the preoperational testing for the rtaal motion. In the event that the period between initial preservice examination and preoperational testing exceeds 6 months, reexamination under Criterion 1, 4, and 5 of the preservice examination will be performed.
The Snubber Plan is expected to be complete by September 1984 and will be available at the site for review. Per NRC Generic Letter 84-13, dated May 3, 1984, the Technical Specification for snubbers will no longer contain Tables 3.7-4a and 3.7-4b . Therefore, we are taking exception to the NRC reference to these Tables. The Snubber Plan, however, will contain a listing of all the snubbers that will require Preservice Examination and Preoperational Testing. The FSAR will also be revised to include the Preservice Inspection and Testing in Chapter 14. This change will be incorporated in FSAR Amendement No. 8.
Although-it is not a ASME Section XI Code requirement , nor a BVPS-2. Licensing Commitment, the Snubber Plan includes preinstallation examination and test-ing, wherein snubbers received at the site prior to August 1983 will be retested to assure their operability.
t-