Letter Sequence Request |
---|
|
|
MONTHYEARML20079K8371982-12-21021 December 1982 Forwards Response to 820629 Safety Evaluation of Inservice Insp Program (ISI) for Pumps & Valves.Mods to ISI Program Being Implemented & Will Be Incorporated Into 20-month Update Due by 830531 Project stage: Other ML20090M7171984-05-17017 May 1984 Forwards Response to 840308 Request for Addl Info Re Requested Relief from Certain Requirements in ASME Code Section XI, Inservice Testing of Pumps & Valves. Appropriate Justification Provided Project stage: Request 1982-12-21
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARL-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages ML20196A6601999-06-16016 June 1999 Forwards Master Decommissioning Trust Agreements Revised After 1990 for Ohio Edison Co,Cleveland Electric Illuminating Co,Toledo Edison Co & Pennsylvania Power Co Re Bvnps,Units 1 & 2,DBNPS,Unit 1 & Perry Unit 1 ML20195H4651999-06-16016 June 1999 Forwards for Filing Answer of Firstenergy Corp in Opposition to Petition for Leave to Intervene of Local 29, Intl Brotherhood of Electrical Workers. Copies of Answer Have Been Served Upon Parties & Petitioner by e-mail ML20195J5221999-06-16016 June 1999 Forwards Answer of Duquesne Light Co to Petition to Intervene of Local 29,International Brotherhood of Electrical Workers in Listed Matter.With Certificate of Svc L-99-100, Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-1091999-06-15015 June 1999 Forwards Typed,Final TS Pages for LAR 109 Re Rcs.Summary Description of Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages Is Provided in Attachment B-109 L-99-095, Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys1999-06-15015 June 1999 Provides Addl Info to Support LARs 262 & 135,in Response to NRC 990527 Verbal Request.Info Describes Performance of Unit 1 Rod Position Indication Sys & Provides Some Background Info Re Normal Operation of Sys L-99-099, Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr1999-06-14014 June 1999 Requests Partial Withdrawal of LAR 120,which Requested Review of USQ Due to Increased Calculated Doses for Locked Rotor Event & Use of Unapproved Methodology for Evaluating Small Break LOCA Doses Involving W Natl Safety Advisory Ltr ML20195H3731999-06-0303 June 1999 Forwards Petition to Intervene of Local 29,Intl Brotherhood of Electrical Workers in Matter of Firstenergy Nuclear Operating Co,For Filing L-99-090, Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request1999-06-0202 June 1999 Forwards Summary Review Completed to Verify Adequacy of Design Basis Accident Thermal Overpressure Protection for BVPS Unit 2 Containment Penetrations,Per Request L-99-086, Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 11999-05-28028 May 1999 Forwards Bvps,Unit 2 SG Exam Rept for Aug 1998.Rept Provided to Document Results of SG Eddy Current Exams Performed in Aug 1998.Summary of Insps Provided in Encl 1 L-99-089, Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b)1999-05-28028 May 1999 Forwards Annual Financial Repts,Including Certified Financial Statements,Of Dqe,Firstenergy Corp,Ohio Edison Co,Pennsylvania Power Co,Cleveland Electric Illuminating Co & Toledo Edison Co,Iaw 10CFR50.71(b) L-99-084, Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon1999-05-27027 May 1999 Forwards Revised marked-up TS & UFSAR Pages to 990303 LARs 259 & 131 Which Revised Qualifications for Operations Mgt & Incorporated Generic Position Titles in Ts.Encl Pages Incorporate NRC Requested Changes,Per Recent Telcon L-99-082, Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS1999-05-17017 May 1999 Dockets Licensee Plan for Bvps,Unit 1,safety-related Small Bore Piping Evaluation Project Discussed in NRC 990311 Public Meeting at BVPS L-99-071, Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS1999-05-12012 May 1999 Notifies of License Withdrawal for J Scott,License SOP-11481,due to Resignation from Employment at BVPS 1999-09-03
[Table view] Category:UTILITY TO NRC
MONTHYEARML20059L4271990-09-0707 September 1990 Requests Approval for Use of Steam Generator Tube Plugs for Both Mechanical & Welded Applications ML20059G0821990-09-0404 September 1990 Forwards Application for Amend to License DPR-66,consisting of License Change Request 180,changing Section 3.3.3.2 to Reduce Required Number of Operable Incore Detector Thimbles for Remainder of Cycle 8 ML20059F7551990-08-29029 August 1990 Responds to Unresolved Item 50-334/90-16-01 Noted in Insp Rept 50-334/90-16.Corrective Actions:Initial Training for Maint Group Personnel Responsible for Maintaining Supplied Air Respirators Will Be Supplemented W/Biennial Retraining ML20059F1501990-08-29029 August 1990 Advises That Permanent Replacement Chosen for Plant Independent Safety Evaluation Group.Position Will Be Staffed Effective 900829 ML20028G8731990-08-29029 August 1990 Forwards fitness-for-duty Program Performance Data for Jan-June 1990,per 10CFR26.71 ML20059D3761990-08-24024 August 1990 Describes Cycle 3 Reload Design,Documents Util Review Per 10CFR50.59 & Provides Determination That No Tech Spec Changes or Unreviewed Safety Questions Involved.Reload Core Design Will Not Adversely Affect Safety of Plant ML20028G8881990-08-24024 August 1990 Withdraws Operator License SOP-10731 (55-60749) Issued to K Gilbert,Who Resigned 05000412/LER-1990-007, Responds to NRC Re Deviation 50-412/90-12-01 Noted in Insp Rept 50-412/90-12.Corrective Actions:Procedure OM 2.20-4.I Revised to Require Removal of Flanges Following Drain Operations & LER 90-007-00 Issued1990-08-23023 August 1990 Responds to NRC Re Deviation 50-412/90-12-01 Noted in Insp Rept 50-412/90-12.Corrective Actions:Procedure OM 2.20-4.I Revised to Require Removal of Flanges Following Drain Operations & LER 90-007-00 Issued ML20058P7651990-08-14014 August 1990 Provides Info on Acceptability of Rescheduling Response to Reg Guide 1.97 Ser,Item 4b, Neutron Flux Monitoring Instrumentation. Rescheduling of Util Response Will Be Determined on or Shortly After Meeting W/Nrc ML20059E0571990-08-10010 August 1990 Forwards Suppl 3 to Nonproprietary WCAP-12094 & Proprietary WCAP-12093, Evaluation of Pressurizer Surge Line Transients Exceeding 320 F for Beaver Valley Unit 2, for Review by 900901.Proprietary Rept Withheld (Ref 10CFR2.790(b)(4)) ML20059E7631990-08-0101 August 1990 Provides Results of Util Evaluation of Licensed Operator Requalification Exam Conducted During Wks of 900709 & 16. Crew That Failed to Meet Expected Performance Level Has Been Successfully Upgraded & re-evaluated to Be Satisfactory ML20059B8141990-08-0101 August 1990 Requests Exemption from 10CFR26 Re Fitness for Duty Program & 10CFR73 Re Physical Protection of Plants & Matls Concerning Unescorted Access Requirements for Nuclear Generating Stations ML20056A3471990-07-31031 July 1990 Responds to NRC Bulletin 90-001.Items 1 Through 5 of Requested Actions for Operating Reactors Completed ML20056A1841990-07-27027 July 1990 Forwards Revised Methodology for Achieving Alternate Ac for Plant,Per 900720 Telcon ML20055H2581990-07-25025 July 1990 Forwards Decommissioning Rept, Per 10CFR50.33(K) & 50.75(b) ML20055F7061990-07-0909 July 1990 Responds to NRC Re Dcrdr Requirements as Specified in Suppl 1 to NUREG-0737.DCRDR Corrective Actions Implemented & Mods Determined to Be Operational Prior to Startup Following Seventh Plant Refueling Outage ML20055D3871990-07-0202 July 1990 Provides Info Re long-term Solution to Action Item 3 of NRC Bulletin 88-008,per 890714 & s.Util Will Continue to Monitor Temp in Affected Lines & Evaluate Results ML20058K5031990-06-29029 June 1990 Discusses Use of Emergency Diesel Generators as Alternate Ac Source at multi-unit Sites,Per Licensee .Emergency Diesel Generator Load Mgt Methodology Evaluated to Meet Listed Criteria ML20044A3661990-06-21021 June 1990 Forwards Application for Amend to License NPF-73,consisting of Tech Spec Change Request 44,changing Stroke Time to 60 for Inside Containment Letdown Isolation Valves.Change Determined Safe & Involves No Unreviewed Safety Issue ML20043G6811990-06-14014 June 1990 Forwards Application for Amends to Licenses DPR-66 & NPF-73, Revising Tech Specs Re Electrical Power Sys - Shutdown & Ac & Dc Distribution - Shutdown ML20043H9341990-06-14014 June 1990 Forwards Issue 1 to Rev 4 to Inservice Testing Program for Pumps & Valves. Issue 1 Removes Relief Requests Requiring Prior NRC Approval & Adds Certain Program Changes Permitted by ASME XI & Generic Ltr 89-04 ML20043G5981990-06-12012 June 1990 Forwards Monthly Operating Repts for May 1990 for Beaver Valley Units 1 & 2 & Revised Rept for Apr 1990 for Beaver Valley Unit 1 ML20043G6851990-06-12012 June 1990 Forwards Application for Amend to License DPR-66,consisting of Proposed OL Change Request 176,revising Tech Specs to Replace Current Single Overpressure Protection Setpoint W/ Curve Based on Temp ML20043G7941990-06-12012 June 1990 Responds to NRC 900524 Request for Addl Info Re Proposed Operating License Change Request 156.Clarification of Magnitude of Confidence Level of Westinghouse Setpoint Methodology,As Specified in WCAP-11419,encl ML20043G8001990-06-11011 June 1990 Forwards Application for Amend to License NPF-73,consisting of Proposed Operating License Change Request 41.Amend Deletes Surveillance Requirement 4.4.9.3.1.d ML20043H0291990-06-11011 June 1990 Forwards Application for Amend to License NPF-73,consisting of Proposed OL Change Request 40,modifying Heatup & Cooldown Curves Applicable to 10 EFPYs Per WCAP-12406 Re Analysis of Capsule U from Radiation Surveillance Program ML20043F5251990-06-0707 June 1990 Requests Temporary Waiver of Compliance from Tech Spec Limiting Condition for Operation Re Operability of Containment Isolation Valves During Quarterly Slave Relay Testing.Evaluation to Support Request Encl ML20043F1361990-06-0404 June 1990 Advises That Chemistry Manual Chapter 5P1, Enhanced Primary to Secondary Leakrate Monitoring Program for Unit 1,per 880328 Request to Recommit to Item C.1 of NRC Bulletin 88-002 ML20043B5971990-05-18018 May 1990 Advises of Delay in Hiring Independent Safety Evaluation Group Replacement to Maintain Five Permanent Personnel Onsite,Per Tech Spec 6.2.3.2.Replacement Will Be Provided within 30 Days of Retirement of Engineer on 900531 ML20043B0511990-05-15015 May 1990 Responds to Telcon Request for Addl Info Re Elimination of Snubbers on Primary Component Supports.Probability of Case B/G Event Extremely Small & Does Not Represent Realisitic Scenario ML20043B1921990-05-11011 May 1990 Forwards Cycle 8 & Cycle 2 Core Operating Limits Rept,Per Tech Spec 6.9.1.14 ML20042G9761990-05-0808 May 1990 Responds to NRC 900226 Ltr Re Violations Noted in Insp Repts 50-334/89-80 & 50-412/89-80.Corrective Action:Maint Work Request Program Being Upgraded to Include Responsibilities of Nuclear Const Dept & Will Be Issued by 900601 ML20042G8541990-05-0303 May 1990 Forwards Technical Review,Audit Summary & Operability Assessments Re Potentially Invalid Leak Detection Tests Used as Alternative for Amse Section XI Hydrostatic Tests ML20042G9071990-05-0101 May 1990 Forwards Annual Financial Repts for Duquense Light Co,Ohio Edison Co,Pennsylvania Power Co,Centerior Energy Corp & Toledo Edison Co,Per 10CFR50-71(b) ML20042F1381990-04-30030 April 1990 Advises That Final SER for Implementation of USI A-46 Will Be Delayed Until Late 1990 ML20042F0991990-04-20020 April 1990 Forwards Response to Request for Addl Info Re Second 10 Yr ISI Program ML20012F5951990-04-10010 April 1990 Forwards Monthly Operating Repts for Mar 1990 & Revised Operating Data Rept & Unit Shutdown & Power Reductions Sheets for Jan 1990 ML20042E1471990-04-0404 April 1990 Forwards Application for Amends to Licenses DPR-66 & NPF-73, Consisting of License Change Request 174/36,updating Staff Titles to Reflect Nuclear Group Organization ML20012F6021990-03-30030 March 1990 Submits Supplemental Response to Station Blackout Rule for Plant,Per NUMARC 900104 Ltr.Summary of Changes to Condensate Inventory of Dhr,Effects of Loss of Ventilation, Control Room HVAC & Reactor Coolant Inventory Listed ML20012E3091990-03-23023 March 1990 Forwards Response to 900308 Request for Addl Info on Reg Guide 1.97 Re Variable for Steam Generator wide-range Level Instrumentation ML20012E3451990-03-23023 March 1990 Submits Addl Info for Exemption from General Design Criteria GDC-57,including Background Info Describing Sys Operation & Addl Bases for Exemption Request.Simplified Recirculation Spray Sys Drawings Encl ML20012D6491990-03-19019 March 1990 Requests Retroactive NRC Approval of Temporary Waiver of Compliance Re Tech Spec Limiting Condition for Operation 3.8.2.1 on Ac Vital Bus Operability.Sts Will Be Followed When Inverters Not Providing Power to Vital Bus ML20012E4091990-03-16016 March 1990 Forwards Inservice Insp 90-Day Rept,Beaver Valley Power Station Unit 1,Outage 7, for 880227-891221,per Section XI of ASME Boiler & Pressure Vessel Code 1983 Edition Through Summer 1983 Addenda,Section XI ML20012D6181990-03-15015 March 1990 Responds to NRC 900215 Ltr Re Violations Noted in Insp Repts 50-334/89-23 & 50-412/89-22.Corrective Actions:Safety Injection Signal Reset & Plant Returned to Presafety Injection Conditions & Crew Members Counseled ML20042D7401990-03-14014 March 1990 Forwards Corrected Annual Rept of Number of Personnel Receiving Greater than 100 Mrem & Associated Exposure by Work Function at Plant for CY89. ML20012D5801990-03-13013 March 1990 Forwards Correction to First 10-yr Inservice Insp Program, Rev 2 to Relief Request BV2-C6.10-1 Re Recirculation Spray Pump - Pump Casing Welds & Relief Request Index ML20012D6221990-03-13013 March 1990 Forwards Response to Generic Ltr 89-19, Resolution to USI A-47. Recommends All Westinghouse Plant Designs Provide Automatic Steam Generator Overfill Protection to Mitigate Main Feedwater Overfeed Events ML20012C1791990-03-0909 March 1990 Responds to NRC 900207 Ltr Re Deviations Noted in Insp Repts 50-334/89-25 & 50-412/89-23.Corrective Actions:Written Request Initiated to Identify Unit 2 post-accident Monitoring Recorders in Control Room & Recorders Labeled ML20012E0911990-03-0505 March 1990 Lists Max Primary Property Damage Insurance Coverages for Plant,Per 10CFR50.54(w)(2) ML20012B7051990-03-0202 March 1990 Responds to NRC 900131 Ltr Re Violations Noted in Insp Repts 50-334/90-05 & 50-412/90-04.Requests Withdrawal of Violation Re Stated Transport Problem & Reclassification as Noncompliance,Per 10CFR2,App C,Section G 1990-09-07
[Table view] |
Text
1 o
.,e Tg5 Telephone (412) 393-6000 Nuclear Division P.O. Box 4 Shippingport, PA 15077-0004 May 17, 1984
/ rector of Nuclear Reactor Regulation United States Nuclear Regulatory Cm missicn Attn: Mr. Steven A. Varga, Chief Operating Reactors Branch No. 1 Division of Licensing Washington, DC 20555
Reference:
Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 IST Punps and Valves Gentlemen:
On February 14 through 17, 1984, Mr. Donald Caphton of your Region I office conducted an inspection of the Beaver Valley Power Station to review our request for relief frcxn certain requirements in ASME Code Section XI, Inservice Testing of Punps and Valves. As a result of this review, a Request for Additional Infonnation, dated March 8, 1984, was addressed to the Beaver Valley Power Station and responses are set forth in Attachttent "A". Attachment "B" repre-sents our requests for relief frcm ASME XI with appropriate justifications.
Very yours, J. . Carey Vice President, Nuclear Attachnent ec: Mr. W. M. Troskoski, Resident Inspector U. S. Nuclear Regulatcry Comnission Beaver Valley Power Station 3hippingport, PA 15077 U. S. Nuclear Regulatory Ccmnission c/o Document Managment Branch Washington, DC 20555 Director, Safety Evaluation & Control Virginia Electric & Pow r Company P.O. Bo 26666 One Janes River Plaza Richmond, VA 23261 .
' I 8406290141 840517 PDR ADOCK 05000334 G PDR
ATTACHMENT A ITIN 1 Inside and outside Recirculation Spray Punps Inside Punps: RS-P-1A and RS-P-1B Outside Punps: RS-P-2A and RS-P-2B Provide a description of your nodification proposals and the bases to show how these nodifications will enable wet testing during refueling cutages in accordance with requirements of ASME Section XI, Subsection IWP, to determine the hydraulic and mechanical characteristics and any degradation of these punps. NorE: If any relief is requested frm Subsection IWP for specific test require-ments or quantities, provide a technical basis for each request and a basis to show that the punps will be adequately tested to demon-strate their required levels of performance and safety function.
Response
Inside Pecirculation Spray Punps: RS-P-1A and RS-P-1B Beginning with the 4th refueling outage scheduled to begin in October 1984, the Inside Recirculation Spray Punps will be run in the recirculation mode every refueling outage.- In order to perform this test, the normal flow path will be blocked to prevent containment frm being sprayed. In addition, a tetporary dike will be installed around the containment sunp to prevent unnecessary flooding of containment. Since this test arrangement disables the recirculation spray system, this test can only be performed during refueling outages.
'Ihe proposed testing will measure all of the applicable quantities listed in Table IWP-3100-1 except for the observation of proper lubricant level. Tais observation will not be made since these punps are self-lubricated by the fluid being punped.
Due to maintenance activities and nodifications performed on the Recirculation Spray system since pre-operational testing,. new reference valves for the punps will be established in accordance with the code during the first inservice test.
We believe that this proposed testing will allow us to evaluate the hydraulic and mechanical characteristics of these punps and permit detection of punp degradation thereby fulfilling the intent of the code.
Outside recirculation spray punps are addressed in Attachment B, Its 1.
ITEM 2 (See attachment B)
T Attachnent A
.Page 2 ITEM-3 Valves to be Tested at Cold Shutdown and Befueling Provide a corrected list ' and correlation of old and new valve numbers for the feed water valves that have been renumbered.
Response
%e corrected list of . valves to be tested at cold shutdown and refueling includes the following valves:
1 % 622 1 N 623 1 N 624 1 % 625 1EW-626 1 M 627
%ese valves were installed under DCP 130. In March 1980,-when the relief request was sent to the NRC, it was thought that their mark
~
nunbers would be 1%387 through lEW-392. However, when they.were 2
installed, the Stone and Webster assigned nunters were used -
1 % 622 through 1 % 627.
3 ITEM 4 Valves Beauiring Pressure Isolaticn Verification
%e condition of each of the following valves is inportant to maintain redundant isolation capability and system integrity.
._ RH-720A PR-720B E 700 RH-701 SI-850B SI-850D SI-850F SI-10* SI-ll*
SI-12* SI-15 SI-16 SI-17 SI-20 SI-21
, SI-22 SI-23* SI-24*
SI-25* SI-48 SI-49 SI-50 SI-51 SI-52 SI-53 SI-83 SI-84
- SI-100 SI-101 SI-102 CH-170 BC-556A PC-556B-I RC-556C f
- Isolation Valves Identified as Event V valves.
- Ebr each of the listed valves, state whether or not full cmpliance with lW-3420, Valve leak ' Rate Test, is achieved, and, if not describe:
- 1. your alternate testing nethod and frequency for each valve, clearly demonstrating an acceptable seat leakage condition of
, the valve,
- 2. the leakage rate detection capability of the alternate method,
, 3. the permissible leakage rate,
- 4. the procedure to be used to analyze and cm pare with previous
. measursents, and,
~ Attachment A Page 3
- 5. the corrective action, if different frm IW-3420(g), to be taken if the individual valve leakage rates exceed the permissible leakage rates.
Ibsponse
'Ihe following valves are tested in full cmpliance with IW-3420.
[SI-10], [SI-ll], [SI-12], [SI-23], [SI-24], [SI-25]
'Ihese valves are the Event V valves identified by the station operating supervisor. As such, they are leak tested by OST 1.11.16, "Ieakage Testing ES Pressure Isolation Valves", which is in full empliance with subsection IW-3420 of the Code.
I [SI-48], [SI-49], [SI-50], [SI-51], [SI-52] and [SI-53] are tested in accordance with the code in full empliance with IW-3420 by OST 1.11.4, "Accunnlator Check Valve Test".
[SI-83] and [SI-84] are tested with water to 40.3 psig and since they are check valves, IW-3420(c) (5) permits them to be tested at lower differential pressure. 'Iherefore, these valves are tested in full cmphance with IW-3420 by BVP 1.3 - 1.47.11, " Safety Injection and Charging System Valve Ieak Test".
[G-170] is leak tested with water to 40.3 psig. 'Ihis valve -is a check valve, however, so full empliance with IW-3420 is achieved by BVP 1.3 - 1.47.11, " Safety Injection and Charging System Valve Ieak Test".
[MOV-BC-556A] , [W-E-556B] and [MOV-RC-556C] are in the fill 2 header frm the charging system to the reactor coolant systs.
'Ihese valves will be leak tested; however, the test method has not been empleted. 'Ihe test method and acceptance criteria will be ca plete October 1, 1984.
4 The following valves were reviewed to determine whether er not they perform a pressure isolation function. Our review indicates that these valves do not perform a pressure isolation function and are L not Cateogy A valves. Since these valves are not Category A, the leak requirements of 1HA 3420 do not apply.
[lOV-SI-850B], [MOV-SI-850D] and [MOV-SI-850F] are 3/4 inch I
normally closed valves in a test line. Because of their position in the test line, . IW-1300 excludes them fr m the testing requirments of the code. 'Iherefore, these valves will not be leakage tested. However, if they leak-by, a change in the accunulator pressure and level would be observed and the operator 4
would receive and alarm to indicate a changing condition.
,. [SI-15] , [SI-16] , [SI-17) , [SI-20] , . [SI-21] and [SI-22]
'Ibese check valves are not the boundary between high and low pressure systems. According to station drawings h 41A and h 41B,
- the piping classification up and downstream of the valves is the same. It does not change until all the associated piping exits the containment. Furthermore, valve leak testing is performed on the associated redundant containment isolation' valves each refueling
- , y e ~ , n . - , ~ --
--r, -nm
Attachment-A Page 4 outage in accordance with 10CFR50, Appendix J, which is an acceptable alternative for the types of valves in question per IW-3420.
h refore, since [SI-15], [SI-16], [SI-17], [SI-20], [SI-21] and
[SI-22] do not act- as pressure isolation valves and the leak tests performed on the containment isolation valves provide confidence that pressure isolation capability is maintained, present Category C valve classification should be considered valid. As a result, these valves will not be leak tested to meet Category A requirements.
[SI-100], [SI-101] and [SI-102]
These check valves are not the boundary between high and low pressure systms. According to station drawings h 41A and RM-41B, the piping classification up and downstream of the valves is the same. Also, these valves are the second valves back frm the ICS.
The first valves in the system, [SI-23], [SI-24] and [SI-25], are leak tested in accordance with the code by OST 1.11.16, "Ieakage Testing RCS Pressure Isolation Valves".. Also included in the line are valves [SI-94] and (SI-95] which are leak tested every refueling in accordance with 10CFR50, Appendix J.
[SI-100], [SI-101] and [SI-102] are classified as Category C valves only and as such, they will not be leak tested to meet Category A requirements.
[MOV-RH-720A] , [10V-RH-720B] , [lOV-RH-700] and [MOV-RH-701]
'Ihese valves will not be leak tested since alternate methods for detecting leakage are available to verify valve integrity.
Currently continuous leakage pressure monitoring exists with Annunciator Al-125, "RHR Punp Discharge Pressure High" at a setpoint of 550 psig. Under normal plant operating conditions, this annunciator is not in the alarm state. 'Iherefore, any leakage past these valves would be monitored by the receipt of this alarm.
As added assurance to the continuous monitoring provided for by Annunicator Al-125, relief valve [RV-RH-721] with a setpoint of 600 psig would direct the discharge of any leakage to the Pressurizer Relief Tank (PRP) . If any leakage occurred, the amount would be indicated by a corresponding level increase in the PRT.
Further justification for these alternate metNds can be found in your previous approval of Relief Request 30 through 33 which classified these valves as ' Category B and the . staff guidance information_ previously provided which exenpts passive gate valves frm the testing requirements of Section XI. 'Iherefore, for these reasons cited, coupliance with IW-3420, Category A Valve Ieak Rate Testing, should not be rW for these valves.
ITDi 5 Event V Piping Configuration Beaver Valley, Unit No. 1 drawing % 38A, shows a piping interface where high pressure piping .is connecting with low pressure piping et 10-inch valves RH-720A and RH-720B. h low pressure piping
{.
c,- Attachment A' -
! ' Page;5 k
~ ~
', -(line 6"- RH-14-152) also leads outside of containment to the j1 refueling water. storage tank. 'Ihe ' high ' pressure piping side of i valves RH-720A and BH-720B are each in series with a check valve
~
~
SI-52 and SI-53,.respectively, and a cold leg of the reactor.-
p i - 'Ihe piping configuration described above matches the criteria L designated by the NRC as an Event V piping ccnfiguration, i.e., the F primary molant. system connects to a high pressure check valve, a i* motor operated valve - and . to low pressure piping that eventually leads ' outside of containment. . Refer' to . Event V piping
! - configurations described in Section 2.0 of the TER dated October '
i 24, 1980, an enclosure to the order, S.A. Varga to C. N. Dunn dated 1
t April 20, 1981.-
Provide any technical basis . you may have to justify excluding 7
- coverage of the Event V piping configuration- fr m Technical Specification Table 4.4-3, where the high pressure piping interface at valves RH-720A and' RH-720B connects with ~ low pressure piping
- that runs to the refueling water storage tank.
i j' Response 1 In order- to evaluate this configuration, additional reviews
[ describing the Event V piping ' configuration were performed.
i Included was the Reactor Safety Study '(RSS), - (WASH 1400), the
, original request that licensees evaluate for Event'V configurations dated February 23, 1980 and paragraph 2.0 ; of the Technical. ;
D Evaluation Report (TER) dated GeLuber . 24, 1980 which was attached j to our Order of April' 20,1981.
,I 'Ihe TER provided additional exanples . of configurations. with specific criteria to determine if an ~ Event- V arrangenent exists.
- 'Ihe TER did not provide any further description' of the = Event 'V F failure mechanics or provide sufficient detail to evaluate
!_ downstream piping and its potential for transferring radioactive i naterials outside'of containment. - NASH 1400 addresses the failure i of check valves that isolate low pressure _ piping frm the reactor.
coolant systan (RCS).
~
'Ihis event requires nultiple failures to-occur :in the form of the' failure of. both -in-series check valves.
'Ihe RSS also' assumes the low pressure ' piping to fail ate a point outside containment 2 resulting ?in a ' direct path for radioactive release to atmosphere, i thus bypassing - the radinaetivity removal L i systems. . Ihe February 23,:1980' letter- to all licensees further i
- . describes this event as possibly including :a locked open : n,
[ outside containment,:with the' high pressure-low pressure interface' j existing at the' downstream side of the M . In this configuration,'
the multiple failure _ of the check. valves leads to a direct' path.
~
outside contairment . to ^ low pressure piping . and the : leakage - path l cannot be isolated because the M is locked open.
- We -have reviewed the piping configuration dimmaad above in your item . 5 ' to determine if it' meets the . Event . _V
- configuration. Based
.cn the background information contained in the source dar,= ants, .
WhSH 1400 and the February 23,:1980 letter,'we have concluded that.
1 this is not' an Event V _ piping configuration'. While the1 series arrangementD of- SI-52 with p-RH-720A and SI-53 with p-RH-720B m-A w e- e - - , gr-.".w w. -- 3- f- riu = , w as g ==+1 3-=9-'g- *- ,e>'+ y -t.m- .py ye ?--*eg y9 .-
t~'*P T T'N' '""""
Attachment A Page 6 are similar to the configuration given in the TER, they are not the ,
same since each MOV is in the closed position with power renoved frm its motor operator during power cperation. Also, the M and the low pressure piping is inside containment and are protected frm overpressurization by a relief valve set to lift at 600 psig and the RHR punp seals. 'Ihis low pressure piping also has a closed manual isolation valve installed in the piping systan prior to the piping leaving containment. This overpressure protection results in potential releases frm the low pressure piping being contained within containment. 'Ihe cmbination of the closed MOV and the pressure relief path remaining inside containment prevents this configuration frm meeting the Event V definition.
To provide additional assurances on the integrity of the conponents, the following is presented for your consideration.
Both SI-52 and SI-53 are tested each refueling to determine leak tightness in accordance with the criteria given in ASME Subsection IW-3420. (See response to Item 4) Any leakage past the KN's would result in a gradual pressure increase of the low pressure piping which would be detected by the installed pressure switch which annunciates at 550 psig in the control rom. Due to the piping arrangment, the SI accumulators maintain approximately 600 psi between the SI check valves and the RHR KNs. This in effect represents in-situ pressure testing of the MOVs to 600 psig.
Finally, the containment isolation valve, RH-14, is tested in accordance with 10CFR50, Appendix J to determine if there is any valve leakage.
Therefore, we do not consider the subject piping arrangment as meeting the Event V configuration and adequate testing and the normal system characteristics represent sufficient means for determining the leak tightness of the subject valves. On this basis, it is not necessary to include these cmponents in Technical Specification Table 4.4-3.
ITEM 6 Additional Event V Piping Configurations Our review of your subnittal on Event V piping configuration has identified that your evaluation and response, as described in a C.
Dunn letter to D. Eisenhut dated March 17, 1980, was based upon Event V criteria provided in a D. Eisenhut letter to all IMR licensees dated February .42 , 1W0. However, the Event V identi-fication criteria was subsequently updated and sent to you by an NBC " Order for Modification of License Concerning Primary Coolant System Pressure Isolation Valves" dated April 20, 1981. Specif-ically, the updated Event V criteria was provided in paragraph 2.0 of the Technical Evaluation Report (TER), dated October 24, 1980, an attachnent to the order Describe the valve configurations at Beaver Valley Unit 1 based upon the criteria in paragraph 2.0 of the TER, and indicate whether additional Event V isolation valve configurations exist within. the class I boundary of the high pressure piping connecting primary :
coolant system piping to low pressure system piping. You may l exclude frcm your response those piping configurations described in u
)
' Attachment'A !
Page 7-your March 17, 1980 letter-and the TER, that are currently incor-
- porated'in Technical Specification Table 4.4-3.
i' response
< 'Ihe prints of all-tha systems connected to the BCS were examined to determine if any. additional Event V valve configurations exist at BVPS. No other areas of concern were found.
4 h
4 t
f a
i e
- . . , - e,.. -
1 , , .- - - - . , . ,,.-
i A'ITACHMENT B ITIM 1 Inside and Outside Recirculation Spray Punps Inside Punps: RS-P-1A and RS-P-1B Outside Punps: RS-P-2A and RS-P-2B Provide a description of your modification proposals and the bases to show how these mtdifications will enable wet testing during refueling cutages in accordance with requirements of ASME Section XI, Subsection IWP, to determine the hydraulic and mechanical characteristics and any degradation of these punps. NOTE: If any relief is requested frcm Subsection IWP for specific test require-ments or quantities, provide a technical basis for each request and a basis to show that the punps will be adequately tested to demon-strate their required levels of performance and safety function.
Response
Outside Recirculation Spray Pumps: RS-P-2A and RS-P-2B Code Requirement:
An inservice test shall be conducted on all safety-related punps, naninally once each month during normal plant operation. Each inservice test shall include the measurement, observation, and recording of all quantities in Table IWP-3100-1, except bearing tenperature, which shall be nsasured during at least one inservice test each year.
Basis for Belief Regt.est:
Relief is requested fran the testing requirements of Section XI for the outside recirculation spray punps.
These punps are dry tested monthly for a maxinum of 60 seconds to verify operability by observing the punps have started when given a start signal. During this test, it is not possible to obtain the data required by subsection IWP. During refueling outages these punps are wet tested in the recirculation mode so that speed, inlet pressure, differential pressure, flowrote, vibration anplitude and bearing temperature can be measured. However,'due to the size of the recirculation line, the punps nust be shut dcnn to prevent punp overheating and punp damage before stable bearing tarperatures can be achieved. 'Ihe current testing is the only type possible under present plant design.
Additional methods have been evaluated to permic continued operation of these punps while testing during refueling outages.
We have concluded that in order to prevent punp overheating before stable bearing tepperatures can be achieved woulf. require increasing the size of the recirculation line. - At p cesent, ' the method of testing these ptmps (OST 1.13.7) , "Becirculation Pung Auto Start and Flow Test" provides sufficient information for the E _ _ , _ . _ .
. Rttachment B Page 2 determination that the purtps are capable of performing as designed by ccriparison with the pumps pre-determined characteristics. 'Ihis assures that no punp degradation has occurred. Since this determination can be made, the safety benefit gained through this modification would not justify the cost to implement this backfit.
It is therefore concluded that. the present methods of testing these punps are adequate for determining the hydraulic and mechanical characteristics and any degredation of these punps.
ITEM 2 Exercising of Check Valves Using Alternate Methods Check valves: ISI-48 ISI-5' 1SI-49 1SI-53 ,
1SI-50 1 p 197 1SI-51 1 % 198 Explain how your testing meets the Section XI, Subsect. ion IW 3410, Valve Exercising Test, cold chutdown requirements for each of the above listed valves. If a flow test is the method of test, provide information to show that the full design ficw is attained.
Response (ISI-48,1SI-49, ISI-50,1SI-51,1SI-52 and 1SI-53)
'Ihese valves are classified as category AC and are governed by subsections IW-3410 and IW-3520.
Code Requirenent 1W-3410 states in part:
" Valves shall be exercised to the position required to fulfill their function unless such operation is not practical during plant operation... Normally closed valves that cannot be operated during normal plant operation shall be specifically identified by the Gmer and shall be full-stroke exercised d.tring each cold shutdown.
Code Requirenent IW 3520 b states in part:
" Check valves shall be exercised to the rosition required to fulfill their function unless such operation is not practical during plant operation . . . Normally closed check valves that cannot be operated during normal plant operation shall be specif-ically identified by the Owner and shall be full-stroke exercised during each cold shut-down."
Subsection (2) of the above paragraph states:
" Valves normally closed during plant operation, whose function is to open on reversal of pressure differential, shall be tested by proving that the disk moves prmptly away frca the seat when the closing pressure differential is reoved and flow through the valve is initiated, or a mechanical opening force is applied to the disk."
^
y _7 -c , .. ; ' . . ;. 1
- , s -
' .'- 4Attim L._d. B iPage 3' Basis ~for Relief Request:
Relief 'is requested _ from full-stroke exercising of these valves
.( ISI-48 through 1SI-53) for the following reasons: '1hese check valves are:in the discharge path of the SI Accunnlators to the cold -i legs. '1 heir function is to open and allow flow from the l acctmulator when the closing differential pressure is removed. OST !
y 1.11.15, " Safety-Injection Acctmulator Check Valve Test" tests the i
function of these valves by creating a differential pressure and allowing flow. Successful empletion of this test verifies the
{J operability of these valves for performing their safety function.
l' In the Safety Evaluation Report performed by the NHC's contractor ,
I attached to the NRCs June : 29, 1982 letter it. was concluded that i I with the present piping configurations, only partial stroke
- . exercising of these check valves is possible. However, we were to perform investigations of other methods for full-stroke exercising i of _these valves (e.g., manual exercising during refueling outages) .
Based .on our review, we have concluded that- the design of these
[ check valves will not- permit a manual ' full-stroke exercise test.
E Also, we have investigated disassenbly of these valves to verify -
full stroke capability. 'Ibese valvesEare installed in a high radiation area and represent considerable man-rm exposure for this type of examination, and . is therefore considered unameptable.
~
4 Also, in order to disassemble them valves would: require' draining
- ' of the BCS loops.. In the past, . maintenance activities have
- necesciitated draining the loops to the mid-loop level which has
( resulted in occasional air binding of the' RHR ptmps. Our.present i criteria for maintaining adequate BCS loop levels for meeting NPSH
- for the RHR I.unps will'not permit draining of the loops to a level' ,
i adequate to disassenble these valves for inspection plu.rr#s.
r In order to provide the ability to full-stroke exercise these j valves, either - manually or by providing new piping arrar.pents t i would require significant plant :nodifications. '1he present test i methods are considered: acceptable for determining operability of
- thase valves.' As such, a plant backfit of this type is not -
- considered an acceptable optim with respect to the safety benefit
1 inprovenent versus the cost of the nodification.
Response (1%197 and 1%198)-
1
=
'1hese valves are . classified as category- C and are goverend by J
Subcaction IW-3520' rather than 'IW 3410.
t Code Requirement IW 3520_ b states in part:,
2
" Check valves shall be ' exercised to. the: position required to
- fulfill their function unless such operation-- is -not practical
- during plant' operation . . -..' Normally- closed check valves that cannot be operated _during normal' plant- operation shall- be specif-i -ically identified' by the Owner and shall be full-stroke exercised ' .
- l. during each cold shut h ."
l , subsection (2) of the above paragraph states:
- ?
,mr . -. < - - .e em -m- e6+ ,4.w-- g, . . . . . . , -. --me- r.< .,e., w--o,-, ww.-e--ent-w--*= - - - - - - ,
i, .f..5ttachmentB 4
" Valves normally closed during plant operatim, whose function is to open on reversal of pressure differential, snall be tested by proving that the ' disk moves pronptly away frm the seat when the closing pressure differential is removed and flow through the valve
-is initiated, or a mechanical opening force is applied to the
' disk."
' Basis for Relief Request:
Relief is requested frm full-stroke exercising 'of these valves (1BN-197 and 1RN-198) for the following reasons: 'Ihese check valves are partial stroke exercised by a flow test monthly per OSTs 1.30.2, 3 and 6, " Reactor Plant River Water Punp Tests",
regardless of plant status. 'Ihe OSTs measure the flow just before it enters the recirculation spray heat exchangers. 'Ihe only path away fr m the~ heat exchangers is through the check valves which are in parallel non-isolable lines, therefore, the flow seen by both valves together is full design flow. With the present system design, the individual flow rate thru each valve cannot be verified. However, the above test does verify that at least one of the check valves open. In . order to verify the operation of both valves, we are evaluating a method of obtaining accoustic measurements during refueling outages.
With the above test modification, both valves will be verified to open at least partially. Experience with other valves of similar.
construction in river water lines has shown that partial stroking of these valves is sufficient to detect degradation. '!herefore, relief is requested fr m full stroke exercising these valves every refueling for the above mentioned rmanns.
Additionally, perforran of a flow test to determine if each valve-disc is stroked sufficiently to demonstrate the ability to pass the design flow rate was cx)nsidered. Due to the design'of the syste ,
it'is not possible to isolate flow through me check valve in order-
~
to verify full -design flow passing through the ' other valve. - In order to acccuplish this test, a ,nodification to the existing systs would have to be. performed. It was concluded that modifications to this syst s could not be justified. ,This is based on the successful ocupletion of the above referenced tests to=
demonstrate the ability of- the recirculation spray system to pass design river water. flow and our pwpuied evaluation for obtaining -
-accoustic measurements of flow through each ofEthese valves'duris; refueling outages. ' mis. action is adequate to acsure the systes ,
capability to pass : full- design- flow s and ~ therefore, any i
nodifications will not significantly increase assurance of this
- system to fulfill 'its safety function and therefore are not i considered viable with respect =to the .backfit criteria ~in i
l evaluation of the benefit gained versus the cost for the modification.
i 1 I !
- i l
l ,
f i 'i I
I' i^ . .
, . . - - . , , _ , - . - . - - , - - , , - - , , - - - - . - .