ML20084S360
ML20084S360 | |
Person / Time | |
---|---|
Site: | Vogtle |
Issue date: | 05/31/1995 |
From: | GEORGIA POWER CO. |
To: | |
Shared Package | |
ML20084S330 | List: |
References | |
NUDOCS 9506120076 | |
Download: ML20084S360 (50) | |
Text
.
O REACTOR CONTAINMENT BUILDING INTEGRATED LEAK RATE TEST UNIT 2 - SECOND PERIODIC l
O Vogtle Electric Generating Plant Georgia Power Company Georgia Power 0 the southem erectric system 1
eE8'*$88?R88888223 P pg
. . . . . . - - _ - . . . . . - . . . - - . _ - . - .. __ - - ..=. .
b i
1 O i i
GEORGIA POWER COMPANY !
VOGTLE ELECTRIC GENERATING PLANT t
UNIT 2 i
I t
i SECOND PERIODIC REACTOR !
i CONTAINMENT BUILDING !
INTEGRATED LEAK RATE TEST l MAY 1995 ,
FINAL REPORT l 4
l 5
i l
t i
Prepared by j Southern Company Services,Inc. l l
f i
l s
O ;
i
_ _ _ _ . - . . . - . ~ . . . _ - . _ . . _ . _ _ _ . . . _ . _ . . . . _ _ . _ - _ _
i TABLE OF CONTENTS 1.0 Introduction Page 1 1 2.0 Summary Page 2 l 3.0 Methodology Page 3 f I
3.1 Leakage Rate Calculations Page 3 i
3.2 Test Measurements Page 3 i 4.0 Test Procedure Page 5 [
4.1 Initial Conditions Page 5 4.2 Pressurization Page 5 !
4.3 Stabilization . Page 6 I 4.4 Type A Test Page 6 !
4.5 Verification Page 7 i 4.6 Depressurization Page 7 5.0 Results and Analysis Page 8 5.1 Total Time Results Page 8 j 5.2 Verification Results Page 10 l 6.0 References Page 12 i Tables and Figures 5 Appendix 1 ILRT Computer Program Description Appendix 11 Type B and C Local Leakage Rate Test Results Appendix III Instrument Calibration Summary Appendix IV GeneralInformation O
F l
t i
LIST OF TABLES !
r Table Iille ;
1 Dry-Bulb and Dew Point Temperature Sensor Locations !
2 Temperature Stabilization Report 3 Data Summary Report j 4 Total Time Leakage Rate Report i t
5 Total Time Leakage Rate Report - Verification ;
6 Mass Point Leakage Rate Report f LIST OF FIGURES Figure Iille 1 Temperature During Stabilization j i
2 Air Mass - Type A Test
{
3 Mean Temperature - Type A Test l 4 Total Pressure - Type A Test ,
5 Vapor Pressure - Type A Test 6 Total Time Leakage Rate - Type A Test ,
i 7 Air Mass - Verification 8 Total Time Leakage Rate - Verification ,
O i l
l 1
l i
1.0 INTRODUCTION
L The Second Periodic Integrated Leakage Rate Test (ILRT) at Georgia Power Company's Vogtle Electric Generating Plant (VEGP) Unit 2 was performed on March 4-5,1995. The ILRT was performed as required by 10CFR50 Appendix J (reference 1) and the VEGP Unit 1 and Unit 2 Final Safety Analysis Report (FSAR)(reference 4) to demonstrate that leakage through the containment boundary at design basis accident pressure does not exceed the VEGP Technical Specification (reference 2) limit. The test was performed in accordance with Procedure VEGP 28329-2 Revision 9 (reference 3). The following documentation is retained at the site along with the Official Test Copy of the procedure:
o systems status (lineup) o eventlog o instrumentation validation (calibrations, Instrument Selection Guide (ISG), etc.)
o temperature stabilization data o integrated leakage rate data r o verification leakage rate data o quality assurance o local leak rate test data A summary of general plant information as related to the Integrated Leak Rate Test is provided in appendix IV.
O O
1
~
2.0
SUMMARY
l 0, The Second Periodic Integrated Leakage Rate Test for the VEGP Unit 2 containment was ;
successfully completed at 7:30 a.m. on March 5,1995. The duration of the test was 8 l hours. The results of the test follow: (Additional leakage to account for penetrations in service or isolated during the test and not in post accident alignment is included in the leakage rates. The 95-percent upper confidence level (UCL) plus any penalty addition is referred to as the final leakage rate.) l Leakage Rate !
(weight % per day)
TotalTime Analysis Determined Value Acceptance Limit 95% Upper Confidence Limit 0.0938 0.1500 O
Extrapolated Leakage Rate < 0.0500 0.1500 Mean of Measured Leakage Rates 0.0574 0.2000 t
Leakage penalties are added to the above 95-percent UCL total time leakage rate to account for penetrations in nonstandard alignment and for water inventory change. Total penalties amounted to a leakage of 0.0001 weight percent / day. This results in a final a:,-
left leakage rate of 0.0939 weight percent / day, which is less than the acceptance limit of 0.1500 weight percent / day.
To determine the as-found leakage rate, minimum pathway improvements made during the local leakage rate testing program previous to the Type A test are added to the sum of the 0.0938 weight percent / day UCL and the 0.0001 weight percent / day penalties. Since the minimum pathway improvements amounted to zero, the final as-found leakage rate is 0.0939 weight percent / day which is less than the acceptance limit of 0.2000 weight .
percent / day.
O 2
l 1
3.0 METHODOLOGY 3.1 Leakage Rate Calculations Test methods and procedures are specified in ANSI N45.4-1972 (reference 6) and in Bechtel Topical Report BN-TOP-1 (reference 7). ANSI N45.4 and BN-TOP-1 are cited in the VEGP FSAR. ANSI N45.4 is cited in 10CFR50 Appendix J. BN-TOP-1 is an alternative method acceptable to the USNRC.
Reference 7 describes the total time test which is used for Type A tests of a duration less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Since the Type A test described in this report was less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, the total time calculations as described in reference 7 were used to determine leakage rate.
Reference 1 allows leakage rate calculations to be performed using the mass point method defined in ANSI /ANS 56.8 (reference 5). The Type A test must have a duration of at least 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to use this methodology per reference 1. Mass point results are provided in this report for information only.
Data from the instrumented containment is reduced by direct application of the ideal gas law, PV = w RT, to calculate air mass at each data point. The change in air mass provides information to develop the leakage rate.
The total time data analysis technique is based on the premise that the leakage rate varies with time. A measured leakage rate is calculated as the initial air mass minus current air
("f mass divided by current time minus initial time. A straight line is then fitted to the measured rate versus time data. The calculated leakage rate is defined as the ordinate of this line at the end of the test.
The total time test has three acceptance criteria. First, the end-of-test leakage rate 95-percent UCL must be less than the acceptance leakage ra:e (0.75 La). Second, the calculated leakage rate extrapolated to a 24-hour test duration must be less than the acceptance leakage rate (0.75 La). Third, the mean of the measured leakage rates over the final 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> of the test must be less than the maximum allowable leakage rate (La).
3.2 Test Measurements Thirty dry-bulb and six dew point temperature sensors located inside containment at approximately equally spaced elevations were used to collect information for leakage rate calculations. Sensor locations and volume fractions (table 1) were established by considering temperature distributions in past tests, previous temperature surveys, and the containment free volume.
Since both dry-bulb and dew point temperatures tend to exhibit a vertical stratification at the completion of pressurization and throughout the test, sensors were set at approximately aque!!y spaced elevations. The volume associated with each sensor was taken as a pb horizontal slice through the containment with the sensor at its approximate vertical 3
p) i vertical centroid. Sensor support points were created by ropes hung from spray rings, the polar crane, and structural steel. The bearing of each sensor was advanced to the next support point from that of the sensor above it, creating a downward spiral. Above the refueling floor, the radius was set such that one-half of the horizontal area was inside the spiral surface and the other half outside. Below the refueling floor, sensors were positioned about midway between the secondary shield wall and the containment liner.
One dry-bulb sensor was suspended in the refueling cavity. Sensors above the refueling floor were suspended from spray rings, the polar crane, and structural steel. Those below the refueling floor were suspended from grating, piping and structural steel.
Dry-bulb temperatures were measured using 100-Ohm platinum resistance temperature detectors (RTDs). Dew point temperatures were measured using optical chilled mirror dew point hygrometers. These dew point devices use a direct-measuring sensor automatically held at the dew point temperature by an optical system. This technique is a primary measurement of the water vapor content of the air. The mirror temperature represents the true dew point temperature and is measured by an imbedded precision platinum resistance thermometer.
Absolute pressure was measured using a vibrating cylinder element sensor connected through tubing to a modified electrical penetration. The change in pressure during an ILRT is quite small relative to absolute pressure. The pressure device used has an accuracy of +/- 0.015 percent RDG, +/- 0.002 percent F.S. and a repeatability of +/- 0.001 percent F.S.
A data logger was used to collect data at 15-miaute intervals. Information from the RTDs, dew point sensors, and pressure indicators was transferred from the data logger to the ILRT computer for analysis. The data system generated a printed tape and floppy disk record of each data set transmitted to the computer.
The computer used for the ILRT was an IBM compatible. A compiled Basic program as described in appendix I was run on the computer.
The imposed leakage rate for the verification test was measured using a float type flowmeter.
All instrumentation was calibrated within 6 months of the ILRT. Instrumentation characteristics and calibration information are summarized in appendix III. Calibration documents are included with the site procedure.
4
4.0 TEST PROCEDURE (q) 4.1 Initial Conditions A general inspection of the accessible interior and exterior surfaces of the containment building was performed prior to the ILRT. No repairs or adjustments were made to the containment after initiation of the inspection so that the building could be tested as close as practical to the "as is" condition. The inspection uncovered no evidence of structural deterioration which would affect the containment structural integrity or leak-tightness.
Since the Type A test was performed at the beginning of the outage, the Type B and C local leakage rate testing (LLRT) was only partially completed prior to the inspection. All Type B and C as-found tests were completed before the ILRT.
Plant systems were aligned for the ILRT as specified in the plant procedure. Isolation valves, except those in systems required to maintain the plant in a safe condition and those systems used to conduct the ILRT, were set in post-LOCA positions specified in the FSAR. Any penetrations deviating from the FSAR positions are listed and justified in the
! ILRT procedure.
For those systems or penetrations that were in service or isolated during the test, a penalty addition must be made to the Type A test results. The penalty addition is the sum of the minimum pathway leakages for those penetrations determined to be in a position other than normal post-LOCA position. Penetrations included in this penalty calculation were
\, ILRT Pressurization (#68), ILRT Pressurization (#87), ILRT Sensing (#31), and Containment Sump Discharge (#78).
Piping was vented and drained to expose valve seats per post-LOCA scenarios. All sources of gas at pressures above containment test pressure were isolated or vented to prevent leakage into the containment during the ILRT.
An in-situ test on the sensors was performed to demonstrate the proper functioning of the sensors and the data collection system. RTD in-situ tests were done using an ice bath (32 degrees F) and verifying that temperature at the data system. Dew point in-situ tests were done using a calibrated dew point instrument (spare dew cell) or a calibrated sling psychrometer to measure dew point temperature at each sensor and comparing the results with dew point temperature at the data system. The in-situ checks that all RTDs were operating within +/- 1 degree of the standard and all dew cells were operating within +/- 5 degrees of the standard.
The site procedure documents the completion of the prerequisites for the test, including all exceptions to specified conditions.
4.2 Pressurization The containment was pressurized using oil free compressors discharging through an after j cooler / moisture separator and refrigerated air dryer. A total compressor capacity of 5
l I
fm ~
approximately 18,000 SCFM was used. Compressor discharge to containment was routed through temporary piping to' containment penetrations 68 and 87. Start of pressurization occurred at 8:35 a.m. on March 4,1995. Pressurization was terminated when containment pressure reached 37.8 psig at 5:00 p.m. on March 4,1995. This allowed a 0.8-psi margin for pressure drop to ensure the gage pressure would be at or above the 37-psig minimum pressure required for the test.
Containment lights were turned off and temporary power to containment was isolated for f the test. In addition, permanent plant instmmentation that was not qualified to 37 psig I was removed from containment.
l 4.3 Stabilization Upon reaching ILRT test pressure, the containment was allowed to stabilize. An initial drop in pressure was observed and then stabilized at approximately 37.4 psig. The i
stabilization period was not started until 6:45 p.m. on March 4 in order to verify the i containment pressure was going to stabilize above 37 psig. Data was recorded at 15-minute intervals. The last stabilization data point was taken at 11:30 p.m. on March 4, 1995. All stabilization criteria were met for this point (table 2). Actual change rates and maximum allowable change rates are listed below:
Stabilization Rate O
Rate Actual Maximum Allowable Rate of change of average temperature averaged over -0.238 degrees F / hour 1.0 degrees F / hour the last 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Rate of change of tempera-ture changes averaged over 0.052 degrees F / hour / hour 0.5 degrees F / hour / hour the last 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> Containment temperature stabilization data is shown graphically in figure 1.
4.4 Type A Test The Type A test was started at 11:30 p.m. on March 4. Containment conditions were O recorded at 15-minute intervals. The test was successfully concluded at 7:30 a.m. on 6
March 5. Results of the test are recorded in section 5.1 of this report. The Type A test was conducted in accordance with the provisions of BN-TOP-1 (reference 7).
During the acquisition of Type A test data, a momentary loss of signal was experienced for dew cell #1 at the 12:45 a.m. data point. The data acquisition paper tape recorded a negative value indicating a loss of signal. A visual reading of the LED display for this sensor immediately after 12:45 indicated a correct reading of 45.12 degrees. The data points before and after this data point both recorded correct values. No further incorrect values were recorded. Based on the negative value (the 12:45 a.m. data point for dew cell
- 1) being attributed to a momentary loss of signal, the visually observed value was manually inserted for the data point in question.
To further demonstrate the validity of this approach, another method of disposition of this data would be to reject the data point. (The data point with the negative temperature value meets data rejection criteria). By removing the data set, the net effect on the final leakage rate would be 0.0005 weight percent / day; i.e., no effect.
Thus, it is concluded that insertion of the visually recorded value is reasonab!c. The details of the action are recorded in the test log.
4.5 Verification Following completion of the Type A test, a 13.04 SCFM (0.1966 weight percent / day)
( verification leak was imposed, which is between the limits of 0.75 La and 1.25 La specified in reference 7. Containment atmospheric conditions were allowed to stabilize for I hour. The verification test was then started at 8:45 a.m. on March 5 and successfully completed at 12:45 p.m. on March 5. Results of the test are recorded in section 5.2.
Table 3 provides a summary of data collected during the stabilization, the Type A test, and the verification as discussed in sections 4.3,4.4, and 4.5.
4.6 Depressurization Containment depressurization was started at 1:00 p.m. on March 5 at an average rate of no more than 10-psi per hour. Depressurization was completed at 6:50 p.m. on March 5.
Containment and other plant systems modified for the ILRT were restored following depressurization to support the outage schedule.
O 7
l 5.0 RESULTS AND ANALYSIS 5.1 Total Time Results :
The end of test leakage rate was well within the acceptance criteria stated in references 2 and 3. This includes the 95-percent UCL plus any penalty additions. Penalty additions are the sum of the minimum pathway leakages determined for those penetrations which were not in a normal post-LOCA position. A summary of these penetrations and their contribution to the penalty addition is presented below:
Penalty Additions Penetration Description As-left leakage (SCCM 31 ILRT Sensing 0.0 68 ILRT Pressurization 6.0 78 Containment Sump Discharge 180.6 87 ILRT Pressurization 6.0 Total Leakage (SCCM) 192.6 Total Leakage 0.0001 (wt %/ day)
Other test result adjustments consider water inventory corrections. The overall water inventory correction review yielded a slight reduction in leakage rate and thus, being ;
conservative, no adjustment was made. Details of the documentation are included in the l plant procedure.
The VEGP Technical Specifications specify a maximum allowable leakage rate of 0.2000 weight percent / day. To allow a margin for deterioration of the leakage boundary the as- l lefl leakage rate must be less than 75-percent of the maximum allowable rate (0.1500 weight percent / day). UCL leakage rate, penalty addition, final as left leakage rate and acceptance limit are listed below:
O 8
l j
l
'() . As-left Leakage Rate 95% UCL Leakage Rate 0.0938 wt %/ day -
Penalty Addition 0.0001 wt %/ day Final As-left Leakage Rate 0.0939 wt %/ day Acceptance Limit (0.75 La) 0.1500 wt %/ day i
f The as-found leakage rate is calculated by adding the 95-percent UCL, the penalties for non-standard alignment, the adjustments for water level inventory, and the penetration minimum pathway improvements made during the local leakage rate testing program previous to the Type A test. As stared above, no correction was included for the water inventory adjustment since it yielded a slight reduction in the leakage rate. The minimum pathway improvement was zero. Thus the as-found leakage rate is as follows:
O !
l As-found Leakage Rate 95% UCL Leakage Rate 0.0938 wt %/ day Penalty Addition 0.0001 wt %/ day Final As-found Leakage Rate 0.0939 wt %/ day Acceptance Limit (La) 0.2000 wt %/ day To demonstrate meeting the Type A test acceptance criteria of BN-TOP-1(reference 7), ,
O the table below shows how all three acceptance criteria of the total time methodology are met. The extrapolated leakage rate is determined by extrapolating the calculated leakage
]
9 l
_-______-___-_____-____-__ __________________-____-____________A
rates out to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. These points show a falling rate trend. The mean of the measured q ' leakage rates is the mean of the fina4 21 leakage rate points.
f g
I Leakage Rate (weight % per day)
Total Time Analysis Determined Value Acceptance Limit 1
I 95% Upper Confidence Limit 0.0938 0.1500 Extrapolated Leakage Rate < 0.0500 0.1500 Mean of Measured Leakage Rates 0.0574 0.2000 Figures 2 through 6 present a graphic demonstration of the data collected during the Type A test. The air mass plot (figure 2) shows lines whose slopes represent leakage rates. A least squares fit line is plotted through the actual test data which must lie above a line representing the acceptance limit. As seen in the graph, the actual leakage rate was easily less than the allowable rate. The temperature plot (figm 3 3) shows the weighted average dry-bulb temperature of the containment air mass. The atal temperature change was 0.9305 degrees F over the 8-hour test period. The pressui plot (figure 4) shows the containment total pressure and a total change of 0.0952 psi. The vapor pressure plot l (figure 5) shows a change in vapor pressure of 0.0032 psi. Figure 6 shows a plot of total time leakage rate data from table 4. The leakage rate UCL must be below a line representing the acceptance limit. As seen from the graph the UCL is well below the allowable limit.
5.2 Verification Results The verification test introduced an additional leak of 13.04 SCFM (0.1966 weight percent
/ day). Verification test results are listed in table 5 and graphed in figures 7 and 8. The results of the verification test are acceptable if the leakage rate calculated after imposition 10 r4 -
-p of the additional leak falls within the limits of(Lam + Ln) +/- 0.25 La, where Lam is the
( previously calculated leakage rate (0.0497), Lo is the imposed leakage (0.1966), and La is the maximum allowable leakage rate (0.2000). The final results and acceptance limits are listed below:
Verification Results t
Upper Limit Rate 0.2963 wt %/ day Total Time Calculated Rate 0.2735 wt %/ day Lower Limit Rate 0.1963 wt %/ day r~
k O .
11
6.0 REFERENCES
\]
- l. Code of Federal Regulations, Title 10, Part 50, Appendix J, Reactor Containment Leakage Testing for Water Cooled Power Reacters.
- 2. Vogtle Electric Generating Plant, Units 1 and 2, Technical Specifications.
- 3. Vogtle Electric Generating Plant, Procedure No. VEGP 28329-2 Revision 9, Containment Integrated Leak Rate Test.
- 4. Vogtle Electric Generating Plant, Units 1 and 2, Final Safety Analysis Report Update.
- 5. ANSI /ANS 56.8-1987, Containment System Leakage Testing Requirements.
- 6. ANSI N45.4-1972, Leakage Rate Testing of Containment Structures fc.c Nuclear Reactors.
- 7. Bechtel Topical Report BN-TOP-1, Testing Criteria for Integrated Leakage Rate Testing of Primary Containment Structures for Nuclear power Plants, Revision 1,1972.
O O
12
A M A-,- .a - - - - -, a- Am ga- -A Js- A a a mad.,4J ,-L. s aa1 s__, u _,y ,
3 __
a TABLES AND FIGURES .
i l
I 1
l 1
l i
4 1
1
i TABLE 1 DRY-BULB AND DEW POINT TEMPERATURE SENSOR LOCATIONS DRY-BULB SENSORS Sensor Elevation Azimuth Distance From Volume Number (feet) (decrees) Ctr of Ctmt (ft) Fractions 1 387 135 24 0.018 2 377 225 24 0.026 3 368 315 24 0.032 4 359 45 24 0.037 5 351 135 24 0.038 6 343 225 24 0.039 7 336 315 24 0.037 8 329 345 49 0.037 '
9 322 165 49 0.038 10 315 325 49 0.038 11 308 20 49 0.038 12 301 145 49 0.038 13 294 200 49 0.038 14 287 325 49 0.038 15 280 20 24 0.038 16 273 145 24 0.038 266 200 O 17 18 19 259 252 325 20 49 49 49 0.037 0.036 0.03>
20 245 145 49 0.033 21 238 200 49 0.033 22 231 325 49 0.033 23 224 20 49 0.036 24 202 270 12 0.017 25 216 180 58 0.022 26 208 285 56 0.029 27 200 0 59 0.029 28 192 90 63 0.029 29 184 195 60 0.029 30 176 310 62 0.035 1.000 DEW POINT SENSORS 1 386 225 24 0.151 2 329 345 49 0.189 3 294 145 49 0.190 4 259 325 49 0.178 5 227 20 49 0.119 6 196 195 59 0.173 1.000 O
t
Table 2 TEMPERATURE STABILIZATION REPORT I Start Time = 1845 304
- = stabilization criterion satisfied
- ANSI - --- BN-TOP-1 ---
data elapsed temperature dT1 dT4 dT1-dT4 dT or d(dT) I est time, hr T, deg F avg dT avg dT avg avg l (1 hr) (4 hr) (2 hr) (2 hr) I l
1 0.00 79.485 l 2 0.25 79.312 I 3 0.50 79.140 I 4 0.75 79.005 5 1.00 78.877 -0.607 )
6 1.25 78.765 -0.548 7 1.50 78.658 -0.482 j 8 1.75 78.561 -0.443 9 2.00 78.464 -0.414 -0.510* 0.150*
10 2.25 78.400 -0.365 -0.456* 0.216*
11 2.50 78.324 -0.334 -0.408* 0.119*
12 2.75 78.230 -0.331 -0.387* 0.067*
13 3.00 78.159 -0.305 -0.359* 0.083*
14 3.25 78.095 -0.305 -0.335* 0.085*
15 3.50 78.039 -0.286 -0.310* 0.081*
16 3.75 77.968 -0.263 -0.297* 0.053*
17 4.00 77.920 -0.239 -0.391 0.152* -0.272* 0.033*
18 4.25 77.857 -0.238 -0.364 0.126* -0.272* O.025*
4.50 77.800 -0.238 -0.335 0.097* -0.262* 0.075*
O 4.75 77.755 -0.213 -0.312 0.100* -0.238* 0.052*
l I
I 1
lo
l l
l Tablo 3 (STABILIZATION) l DATA
SUMMARY
REPORT
[~'T
\ d' data time date temperature pressure vapor dry air i
set deg F psia pressure mass psia lbm 1 1845 304 79.4846 52.2854 0.1403 717895.59 2 1900 304 79.3122 52.2671 0.1402 717873.75 3 1915 304 79.1402 52.2509 0.1400 717882.82 4 1930 304 79.0050 52.2365 0.1399 717865.98 5 1945 304 78.8774 52.2234 0.1403 717850.35 6 2000 304 78.7645 52.2117 0.1400 717842.88 7 2015 304 78.6581 52.2008 0.1400 717835.00 8 2030 304 78.5615 52.1906 0.1401 717822.25 9 2045 304 78.4638 52.1811 0.1399 717823.14 10 2100 304 78.3999 52.1721 0.1402 717780.57 11 2115 304 78.3243 52.1636 0.1403 717763.41 12 2130 304 78.2302 52.1556 0.1404 717776.25 13 2145 304 78.1587 52.1481 0.1403 717769.99 14 2200 304 78.0949 52.1409 0.1405 717753.06 15 2215 304 78.0387 52.1345 0.1404 717741.03 16 2230 304 77.9675 52.1283 0.1406 717748.30 17 2245 304 77.9199 52.1224 0.1405 717731.35 18 2300 304 77.8569 52.1166 0.1408 717731.28 19 2315 304 77.8005 52.1113 0.1408 717733.14 20 2330 304 77.7550 52.1064 0.1411 717722.04 O
O
Table 3 (Type A Test)
- DATA
SUMMARY
REPORT data time date temperature pressure vapor dry air set deg F psia pressure mass psia lbm 1 2330 304 77.7550 52.1064 0.1411 717722.04 2 2345 304 77.7053 52.1014 0.1410 717720.92 3 0 305 77.6674 52.0967 0.1413 717702.04 4 15 305 77.6123 52.0921 0.1412 717714.41 5 30 305 77.5683 52.0876 0.1420 717699.12 6 45 305 77.5314 52.0833 0.1415 717696.78 7 100 305 77.5104 52.0794 0.1417 717667.36 8 115 305 77.4614 52.0753 0.1417 717676.12 9 130 305 77.4259 52.0716 0.1415 717675.33 10 145 305 77.3922 52.0682 0.1419 717667.70 11 200 305 77.3627 52.0647 0.1419 717658.96 12 215 305 77.3179 52.0615 0.1421 717672.04 13 230 305 77.2916 52.0583 0.1422 717661.19 14 245 305 77.2596 52.0552 0.1424 717658.08 15 300 305 77.2279 52.0521 0.1426 717655.60 16 315 305 77.1989 52.0491 0.1427 717650.59 17 330 305 77.1721 52.0465 0.1426 717653.21 18 345 305 77.1489 52.0436 0.1428 717640.79 19 400 305 77.1141 52.0410 0.1430 717649.05 20 415 305 77.1034 52.0385 0.1431 717626.84 21 430 305 77.0600 52.0360 0.1432 717648.90 22 445 305 77.0540 52.0335 0.1432 717622.83 23 500 305 77.0348 52.0311 0.1432 717615.28 24 515 305 77.0056 52.0289 0.1435 717619.24 25 530 305 76.9878 52.0267 0.1436 717611.78 26 545 305 76.9615 52.0247 0.1435 717619.84 27 600 305 76.9322 52.0226 0.1437 717627.79 l 28 615 305 76.9251 52.0205 0.1438 717606.98 1 29 630 305 76.8930 52.0186 0.1439 717621.92 l 30 645 305 76.8893 52.0166 0.1441 717596.94 31 700 305 76.8587 52.0149 0.1440 717614.92 32 715 305 76.8463 52.0130 0.1443 717601.34 33 730 305 76.8245 52.0112 0.1443 717606.18 O
l
Table 3 (Verification)
DATA
SUMMARY
REPORT Odata time date temperature pressure vapor dry air i set deg F psia pressure mass psia lbm 5 845 305 76.7349 51.9960 0.1448 717507.49 6 900 305 76.7339 51.9930 0.1448 717468.18 7 915 305 76.7114 51.9901 0.1449 717456.13 -
8 930 305 76.7046 51.9872 0.1452 717421.35 9 945 305 76.6831 51.9844 0.1451 717412.74 10 1000 305 76.6642 51.9815 0.1452 717396.85 11 1015 305 76.6549 51.9785 0.1452 717367.72 12 1030 305 76.6475 51.9759 0.1454 717338.48 13 1045 305 76.6347 51.9731 0.1456 717314.85 14 1100 305 76.6202 51.9704 0.1458 717293.81 15 1115 305 76.5961 51.9676 0.1457 717288.74 l 16 1130 305 76.5837 51.9648 0.1458 717264.57 '
17 1145 305 76.5794 51.9623 0.1458 717235.19 18 1200 305
)
76.5680 51.9597 0.1459 717213.19 19 1215 305 76.5623 51.9570 0.1462 717179.61 20 1230 305 76.5474 51.9546 0.1463 717165.86 21 1245 305 76.5289 51.9518 0.1462 717151.90 O
i
()
. _ _ - _ . _ - - - _ - - *----r
Table 4 7, TOTAL TIME LEAKAGE RATE REPORT
/ data time date elapsed dry air measured leakage uc1 set time mass rate rate rate (hrs) (lbm) (%/ day) (%/ day) (%/ day) 1 2330 304 0.00 717722.04 0.0000 0.0000 0.0000 2 2345 304 0.25 717720.92 0.0150 0.0150 0.0150 3 0 305 0.50 717702.04 0.1338 0.1338 0.1338 4 15 305 0.75 717714.41 0.0340 0.0704 0.9348 5 30 305 1.00 717699.12 0.0767 0.0776 0.3946 6 45 305 1.25 717696.78 0.0676 0.0750 0.2765 7 100 305 1.53 717667.36 0.1219 0.1019 0.2612 8 115 305 1.75 717676.12 0.0877 0.1011 0.2339 9 130 305 2.00 717675.33 0.0781 0.0963 0.2136 10 145 305 2.25 717667.70 0.0808 0.0939 0.1990 11 200 305 2.50 717658.96 0.0844 0.0933 0.1888 12 215 305 2.75 717672.04 0.0608 0.0853 0.1764 13 230 305 3.00 717661.19 0.0678 0.0814 0.1668 14 245 305 3.25 717658.08 0.0658 0.0779 0.1584 15 300 305 3.50 717655.60 0.0635 0.0745 0.1509 16 315 305 3.75 717650.59 0.0637 0.0719 0.1445 17 330 305 4.00 717653.21 0.0575 0.0685 0.1380 18 345 305 4.25 717640.79 0.0639 0.0671 0.1336 19 400 305 4.50 717649.05 0.0542 0.0640 0.1280 20 415 305 4.75 717626.84 0.0670 0.0639 0.1255 21 430 305 5.00 717648.90 0.0489 0.0605 0.1203 j 22 445 305 5.25 717622.83 0.0632 0.0602 0.1180 23 500 305 5.50 717615.28 0.0649 0.0602 0.1163 24 515 305 5.75 717619.24 0.0598 0.0595 0.1138 25 530 305 6.00 717611.78 0.0615 0.0591 0.1119 26 545 305 6.25 717619.84 0.0547 0.0577 0.1091 27 600 305 6.50 717627.79 0.0485 0.0556 0.1059 28 615 305 6.75 717606.98 0.0570 0.0550 0.1041 29 630 305 7.00 717621.92 0.0478 0.0533 0.1012 30 645 305 7.25 717596.94 0.0577 0.0530 0.1000 31 700 305 7.50 717614.92 0.0478 0.0516 0.0975 32 715 305 7.75 717601.34 0.0521 0.0508 0.0958 33 730 305 8.00 717606.18 0.0484 0.0497 0.0938 Allowable leakage rate, La = 0.2000 %/ day 75% La = 0.1500 %/ day Total time leakage rate = 0.0497 %/ day Total time UCL = 0.0938 %/ day l
1 i
O
d t
Table 5 ,
TOTAL TIME LEAKAGE RATE REPORT
- VERIFICATION data time date elapsed dry air measured leakage ;
set time mass rate rate.
(hrs) (lbm) (%/ day) (%/ day) .
5 845 305 0.00 717507.49 0.0000 0.0000 6 900 305 0.25 717468.18 0.5260 0.5260 7 915 305 0.50 717456.13 0.3436 0.3436 !
8 930 305 0.75 717421.35 0.3842 0.3471 9 945 305 1.00 717412.74 0.3170 0.3047 ,
10 1000 305 1.25 717396.85 0.2961 0.2761 11 1035 305 1.50 717367.72 0.3117 0.2716 12 1030 305 1.75 717338.48 0.3230 0.2758 13 1045 305 2.00 717314.85 0.3222 0.2793 14 1100 305 2.25 717293.81 0.3177 0.2807 15 1115 305 2.50 717288.74 0.2927 0.2737 16 1130 305 2.75 717264.57 0.2955 0.2700 17 1145 305 3.00 717235.19 0.3036 0.2702 18 1200 305 3.25 717213.19 0.3029 0.2705 :
19 1215 305 3.50 717179.61 0.3134 0.2737 20 1230 305 3.75 717165.86 0.3047 0.2744 ,
21 1245 305 4.00 717151.90 0.2974 0.2735
~
Upper limit on leakage rate = 0.2963 %/ day Total time leakage rate O
= 0.2735 %/ day Lower limit on leakage rate = 0.1963 %/ day P
6
Table 6
- MASS POINT LEAKAGE RATE REPORT
\ data time date elapsed dry air leakage ucl set time mass rate rate (hrs) (lbm) (%/ day) (%/ day) 1 2330 304 0.00 717722.04 0.0000 0.0000 2 2345 304 0.25 717720.92 0.0150 0.0150 3 0 305 0.50 717702.04 0.1338 0.7206 4 15 305 0.75 717714.41 0.0559 0.2160 5 30 305 1.00 717699.12 0.0700 0.1465 6 45 305 1.25 717696.78 0.0685 0.1139 7 100 305 1.50 717667.36 0.1028 0.1529 8 115 305 1.75 717676.12 0.0988 0.1351 9 130 305 2.00 717675.33 0.0910 0.1197 10 145 305 2.25 717667.70 0.0877 0.1104 11 200 305 2.50 717658.96 0.0872 0.1055 12 215 305 2.75 717672.04 0.0768 0.0954 13 230 305 3.00 717661.19 0.0728 0.0889 '
14 245 305 3.25 717658.08 0.0694 0.0835 15 300 305 3.50 717655.60 0.0662 0.0788 16 315 305 3.75 717650.59 0.0642 0.0753 l 17 330 305 4.00 717653.21 0.0608 0.0711 18 345 305 4.25 717640.79 0.0603 0.0695 ,
19 400 305 4.50 717649.05 0.0572 0.0659 20 415 305 4.75 717626.84 0.0584 0.0663 21 430 305 5.00 717648.90 0
f
, 0.0547 0.0628 22 445 305 5.25 717622.83 0.0554 0.0627 '
23 500 305 5.50 717615.28 0.0564 0.0632 24 515 305 5.75 717619.24 0.0561 0.0623 25 530 305 6.00 717611.78 0.0563 0.0620 26 545 305 6.25 717619.84 0.0550 0.0604 >
27 600 305 6.50 717627.79 0.0527 0.0582 '
28 615 305 6.75 717606.98 0.0526 0.0576 29 630 305 7.00 717621.92 0.0507 0.0558 30 645 305 7.25 717596.94 0.0510 0.0557 31 700 305 7.50 717614.92 0.0495 0.0542 32 715 305 7.75 717601.34 0.0490 0.0534 33 730 305 8.00 717606.18 0.0480 0.0522 Allowable leakage rate, La = 0.2000 %/ day ,
75% La = 0.1500 %/ day '
Mass point leakage rate = 0.0480 %/ day Mass point UCL = 0.0522 %/ day <
O
O O O -
VOGTLE UNIT 21995 ILRT Temperature During Stabilization 80 C
g 79 a
R E
78 F-77 . .
6:45 pm 3/4/95 11:30 pm 3/4/95 TIME (Hours)
FIGURE 1
O O O VOGTLE UNIT 21995 ILRT Air Mass - Type A Test 717800 717700 " - 4, -.....,
- s. ....
s, ....
s, -
E ~. --
.o 717600 '. ... -
v s. s (f) '. s U) -s
( 's. s 2 -s. '
g 717500 -
s.
4 - s, s
'. s s '
Air Mass Plot '.
717400 '
Least Squares Fit Line Through Data '. s
0.75 La Acceptance Limit '
-s, s
717300 , . . . . .
11:30 7:30 pm am 3/4/95 3/5/95 TIME (Hours)
FIGURE 2
O O O VOGTLE UNIT 21995 ILRT Mean Temperature - Type A Test 78
^
LL g 77.5 8
E i
E 77 f-76.5 . ,
11:30 pm 3/4/95 7:30 am 3/5/95 TIME (Hours)
FIGURE 3
O O O VOGTLE UNIT 21995 ILRT Total Pressure -Type A Test 52.15 g 52.1 To O
w W
D- 52.05 11:30 pm 3/4/95 7:30 am 3/5/95 FIGURE 4
O O O VOGTLE UNIT 21995 ILRT Vapor Pressure - Type A test 0.145 0.144 S
- iin v
0.143 D
LIJ Z
0.142 O
CL s
0.141 0.14 . . .
11:30 pm 3/4/95 7:30 am 3/5/95 TIME (Ho'Jrs)
FIGURE 5
O O O VOGTLE UNIT 21995 ILRT Total Time Leakage Rate Type A Test 1
o 0.9 f.
0.8 .*.'
- Sm Ik
!; ---- 0.75 La Acceptance Limit = 0.1500 V 0 .7
- g
{ Total Time Leakage Rate
- ; - - - - - Total Time UCL LU 0.6 l -
l-- : ;
[ 0.5 : ;
t.0 - ;
2
- p 0.4
- _.s .
<C : '
W 0.3 -
o l--
0.2 :
.-.a...-.--.-.-. ....a, - - , .
^^'*-- -----............. ,,,,,,,,,,,,,,,_ _,
0 , , , , , ,
11:30 pm 3/4/95 7:30 am 3/5/95 TIME (Hours)
FIGURE 6
c
- s. (v)
VOGTLE UNIT 21995 ILRT Air Mass - Verification 717600 Air Mass Plot
- - - - Lower Limit 717500 s ------Least Squares Fit Line Through Data
~.s,- - - - - Upper Limit
- s. .,,
~. .,
E 717400 , " '
.o '.. .'
y) -
~.s,'
u) . .. '
<( ' s ,, ~.s 2 < .... ~.,
O' 717300
- %- ~..
< s. .
~.
.s
~.
.q, 717200 .
's. ..
N 717100 , , , , , , , , ,
8:45 am 3/5/95 12:45 pm 3/5/95 TIME (Hours)
FIGURE 7 l
l
w' o O G VOGTLE UNIT 21995 ILRT Total Time - Verification 0.5 -
l i
1
-- -- Lower Limit = 0.1963
- - - - Upper Limit = 0.2963 g 0.4 Total Time Rate m
u v _
LU F-0.3 _._._._._. .__._._ .___.__._._.___ ______.___._._.__._._________._._.
LU 2
~
f-I F<-
O F- 0.2 ....................................................................................................
0.1 . . . . . . . . .
8:45 am 3/5/95 12:45 pm 3/5/95 TIME (Hours)
FIGURE 8
APPENDIX I O ILRT COMPUTER PROGRAM DESCRIPTION The ILRT computer program used in this test was a program purchased by Southem Company Services (SCS) from BCP Technical Services. The program is a modified version of the BCP standard ILRT program prepared for specific use at VEGP. Complete verification of the VEGP version has been performed and documented. The program source code was included in the purchase of the software should there be the need to review the routines used to calculate the various ILRT parameters. The BCP ILRT program is written in Microsoft QuickBASIC, Version 4.5, for IBM Personal Computers and Compatibles.
Upon starting the program the user is prompted for the fbliowing predata:
Number of temperature sensors Number of dewpoint sensors Number of pressure sensors Containment free air volume Allowable leakage rate, La Sensor volume fractions Once the test is started the following data is received from'the data acquisition system during the test:
Time and date Containment atmosphere drybulb temperatures Containment atmosphere pressure Containment atmosphere dewpoint temperatures Program options provide calculation of the following reports:
DATA
SUMMARY
REPORT. Displays data set number, time, date, temperature, pressure, vapor pressure and dry air mass for all data sets.
DATA SET REPORT. Displays data set number, time, date, sensor data (raw data and calibrated values), weighted average temperature, pressure and vapor pressure, and volume and dry air mass.
MASS POINT LEAKAGE RATE REPORT. (ANSI /ANS 56.8 - 1987). Displays data set number, time, date, elapsed time, dry air mass, mass point leakage rate and UCL for all data sets.
TOTAL TIME LEAKAGE RATE REPORT. (BN-TOP-1, rev.1). Displays data set number, time, date, elapsed time, dry air mass, total time measured leakage rate, leakage rate (calculated) and UCL for all data sets.
TREND REPORT. Displays data set number, time, date, elapsed time, total time measured leakage rate, leakage rate (calculated) and UCL, and mass point leakage rate and UCL for all data sets, DATA REJECTION REPORT. (ANSI /ANS 56.8 - 1987). Displays data set number, time, air O mass, linear least square fit (air mass), residual from least square fit, standard error of residual and standardized residual for all data sets.
I l
i
,73 TEMPERATURE STABILIZATION REPORT. (ANSI /ANS 56.8 - 1987 and BNTOP-1, rev.1).
Q Displays start time and date, data set number, elapsed time, temperature, I hour and 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> average rates of temperature change and difference (ANSI criteria), and 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> average rate of temperature change and 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> average change in rate of temperature change, i.e., second derivative, (DNTOP-1 criteria) for all data sets.
The following plots are available:
AIR MASS. Plots the air mass, regression line and 75% La line.
LEAK RATES. Plots the mass point and total time leakage rate, UCLs and 75% La line.
TEMPERATURE. Plots the weighted average temperature, temperature for one sensor, or temperature for all sensors.
PRESSURE. Plots the weighted average pressure, pressure for one sensor, or pressure for all sensors.
DEWPOINT / VAPOR PRESSURE. Plots the weighted average vapor pressure, dewpoint temperature for one sensor, or dewpoint temperature for all sensors.
In addition the program allows for manual data entry, data correction, data set insenion, and deletion of a data set.
O O
O
e APPENDIX II TYPE B AND C LOCAL LEAKAGE RATE TEST RESULTS Results for Type B and C local leakage rate tests performed between the completion of the 1992 ILRT and the start of the 1995 ILRT are presented herein.
O 1
j 1
b
A p e. J,_ .44 - - ___u_ 4_._ :4 } uc 4 - ,r__&
4 . . ._ .i - ___ -
TYPE B AND C RESULTS O
T 8ie erce <e e-TITLE SHEET J
Type B and C Results for Refueling Outage Tests 1 Type B and C Results-Quarterly Purge Valve Surveillances 6 Type B and C Results--Personnel and Escape Airlock Surveillances 8 .
Type B and C Results--Tests Performed Between Refueling Outages 9 Type B and C Results--Notes 10 i
O ,
t 6
O !
I
U o q V
q v
TYPE B AND C RESULTS REFUELING OUTAGE TESTS Sheet I of 10 2R3 LEAKAGE - SCCM 2R4 LEAKAGE - SCCM AS FOUND AS LEFT AS FOUND AS LEFT PEN DESCRIPTION EQUIPMENT DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE COMMENTS 5 ISI Penetration Blind Flange 09/09/93 8.2 10/09/93 14.2 02/26/95 22 03/24/95 23.7 11A Chemical 2-14 I l-U4-676 09/11/93 -
10/04/93 821 02/28/95 6.1 02/28/95 6.1 Note 1, Note 2 Addition 211V-5280 09/11/93 42.6 10/04/93 46.3 02/28/95 148.5 02/28/95 148.5 12A Chemical 2-1411-U4-677 09/11/93 105 10/03/93 45.3 02/28/95 101.3 02/28/95 101.3 Note 2 Addition 211V-5281 09/11/93 258 10/03/93 257 02/28/95 122.7 02/28/95 122.7 13A Containment 211V-12975 09/12/93 141.8 09/12/93 141.8 02/27/95 96.2 02/27/95 96.2 Radiation Monitor 211V-12976 09/12/93 180.8 09/12/93 180.8 02/27/95 112.2 02/27/95 112.2 13B Containment 211V-12978 09/12/93 6.0 09/12/93 6.0 02/27/95 6.0 02/27/95 6.0 Radiation Monitor 211V-12977 09/12/93 8.9 09/12/93 8.9 02/27/95 6.0 02/27/95 6.0 15 Demin Water 2-1213-U6-051 09/12/93 12.3 09/14/93 392 03/01/95 8.0 03/01/95 8.0 to Cavity 2-1213-U6-050 09/12/93 18 09/14/93 22.1 03/01/95 52.1 03/01/95 52.1 22 Demin Water 2-1418-U4-038 09/10/93 88.7 09/10/93 88.7 03/01/95 18.5 03/01/95 18.5 2-14 I 8-U4-005 09/I0/93 86.4 09/I0/93 86.4 03/0I/95 6.0 03/0I/95 6.0 23 Breathing Air 2-2401-U4-184 09/11/93 33.6 09/11/93 33.6 01/31/95* 41.5 01/31/95* 41.5 2-2401-U4-211 09/1I/93 222 09/I1/93 222 01/3I/95* 29.3 01/3I/95* 29.3 24 Ilot Leg Sample 211V-3548 09/13/93 59.3 10/07/93 8.6 03/01/95 78.5 03/12/95 84.3 f211V-3502] 09/15/95 14,320 10/07/93 13.8 03/01/95 11,310 03/12/95 90.7 (211V-8220]
28 ACCW Supply 211V-1978 09/26/93 5.4 09/26/93 5.4 03/02/95 6.7 03/08/95 10.1 211V-1979 09/26/93 4.2 09/26/93 4.2 03/02/95 12.2 03/08/95 18.3
- Performed just prior to refueling outage Brackets denote these valves are tested in parallel
O O O TYPE B AND C RESULTS REFUELING OUTAGE TESTS Sheet 20f 10 2R3 LEAKAGE - SCCh1 2R4 LEAKAGE - SCChi AS FOUND AS LEFT AS FOUND AS LEFT PEN DESCRIPTION EQUIPh1ENT DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE CON 1h1ENTS 29 ACCW Return [211V-1974 1 09/26/93 8.1 09/26/93 8.1 03/02/95 25.7 03/02/95 25.7 L2-1217 U4-113 J 2iiV-1975 09/26/93 4.2 09/26/93 4.2 03/02/95 165.3 03/02/95 165.3 34 Containment 2-1206-U6-016 09/11/93 393 09/13/93 418 02/28/95 288 02/28/95 288 Spray 211V-9001B 09/11/93 32.8 09/13/93 53.7 02/28/95 400 02/28/95 400 35 Containment 2-1206-U6-015 09/12/93 451 09/14/93 1870 02/28/95 33.7 03/14/95 181.0 Spray 211V-9001 A 09/12/93 738 09/14/93 6.0 02/28/95 6.0 03/14/95 26.8 36 RIIR Encap 2-1205-V4-002 09/10/93 80.3 09/16/93 17.3 02/16/95* 195 03/24/95 164.3 Vessel 37 RilR Encap 2-1205-V4-001 08/31/93* 650 09/02/93* 93.5 02/20/95* 242 03/25/95 701.0 Vessel 38 CS Encap Vessel 2-1206-V4-001 09/10/93 77.4 09/16/93 89.3 02/21/95* 177 03/21/95 162.0 39 CS Encap Vessel 2-1206-V4-002 09/07/93* 356 09/11/93 54.0 02/17/95* 36.2 03/2I/95 16.7 40 Fire Protection 2-2301-U4-036 09/12/93 2400 09/12/93 2400 02/28/95 1180 02/28/95 1180 211V-27901 09/12/93 1430 09/12/93 1430 02/28/95 552 02/28/95 552 41 Accumulator Fill 2ilV-8871 09/13/93 6.0 09/13/93 6.0 02/28/95 6.0 02/28/95 6.0
& Test [2ilV-8964] 09/13/93 16.7 09/13/93 16.7 02/28/95 66.5 02/28/95 66.5 L211V-8988]
42 Accumulator N2 2-2402-U4-017 09/12/93 108 09/12/93 108 02/27/95 133.4 02/27/95 133.4 Supply 211V-8880 09/12/93 5.8 09/12/93 5.8 02/27/95 785 02/27/95 785
- Performed just prior to refueling outage Brackets denote these valves are tested in parallel
O O O TYPE B AND C RESULTS REFUELING OUTAGE TESTS Sheet 3 of 10 2R3 LEAKAGE - SCCM 2R4 LEAKAGE - SCCM AS FOUND AS LEFT AS FOUND AS LEFT PEN DESCRIPTION EQUIPMENT DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE COMMENTS
- 48 Letdown 2ilV-8160 09/17/93 7.2 09/17/93 7.2 03/02/95 11.8 03/02/95 11.8 211V-8152 09/17/93 6.0 09/17/93 6.0 03/02N5 7.2 03/02/95 7.2 49 Seal Water [211V-8112 1 09/19/93 42.1 09/19/93 42.1 03/02M5 85.6 03/17/95 79.3 Leak-off L2-1208-U4-021 J 211V-8100 09/19/93 8.0 09/19/93 8.0 03/02/95 49.4 03/17/95 44.9 50 Charging 2-1208-U6-038 09/22/93 1390 09/28/93 1289 03/02 S 5 544 03/02/95 544 211V-8105 09/22/93 64 09/28/93 17.2 03/02M5 11.2 03/02/95 11.2 55 ISI Penetration Blind Flange 09/09/93 19.1 10/09/93 10.5 02/26/95 11.2 02/26/95 11.2 62 PRT Vent 211V-8047 09/12/93 6.0 09/12M3 6.0 03/02M5 6.0 03/02/95 6.0 2ilV-8033 09/12M3 6.1 09/12/93 6.1 03/02/95 6.0 03/02/95 5.0 63 PRT Make-up 2-1201-U6-112 09/17/93 6.0 09/17/93 6.0 03/02/95 247 03/12 S 5 6.0 211V-8028 09/17/93 6.2 09/17/93 6.2 03/02/95 114.2 03/12/95 17.3 64A ILRT Test Blind Flange 09/10/93 7.5 09/10/93 7.5 02/26/95 7.5 02/26/95 7.5 64B ILRT Test Blind Flange 09/09/93 6.0 09/09/93 6.0 02/26/95 12 02/26/95 12 67A PZR Steam Space 2ilV-3513 09/16/93 6.0 09/16M3 6.0 03/02/95 6.0 03/02/95 6.0 Sample 2f tV-3514 09/16/93 6.0 09/16/93 6.0 03/02/95 6.0 03/02/95 6.0 67B PZR Liquid Space 211V-3507 09/16/93 6.0 09/16/93 6.0 03/02/95 6.0 03/02 S 5 6.0 Sample 211V-3508 09/16/93 6.0 09/16/93 6.0 03/02/95 6.0 03/02/95 6.0 68 ILRT Test Blind Flange 09/10/93 6.0 09/10/93 6.0 02/26/95 6.0 02/26S5 6.0 Brackets denote these valves are tested in parallel I
__m_. __ _
b b TYPE B AND C RESULTS REFUELING OUTAGE TESTS Sheet 4 of 10 2R3 LEAKAGE - SCCM 2R4 LEAKAGE - SCCM ASFOUND AS LEFT AS FOUND AS LEFT PEN DESCRIPTION EQUIPMENT DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE COMMENTS 69A Chemical 2-1411-U4-678 09/11/93 847 10/03/93 6.0 02/28/95 8.2 02/28/95 8.2 Note 2 Addition 2ilV-5278 09/11/93 37 10/03/93 6.0 02/28/95 730 02/28/95 730 69B Chemical 2-1411-U4-679 09/11/93 55.7 10/03/93 6.0 02/28/95 6.0 02/28/95 6.0 Note 2 Addition 2ilV-5279 09/11/93 19.2 10/03/93 83 02/28/95 63.5 02/28/95 63.5 70A Containment 112 211V-2790A 09/12/93 4.2 09/12/93 4.2 02/26/95 6.0 02/26/95 6.0 Monitor 2ilV-2790B 09/12/93 4.2 09/12/93 4.2 02/26/95 6.0 02/26/95 6.0 2ilV-2791A 09/12/93 5.0 09/12/93 5.0 02/26/95 7.9 02/26/95 7.9 70B Containment 112 2-1513-U4-001 09/12/93 43.3 09/12M3 433 , 02/26/95 12.0 02/26/95 12.0 Monitor 211V-2793A 09/12/93 4.6 09/12/93 4.6 02/16/M 6.0 02/26/95 6.0 71A Containment 112 211V-2792A 09/12/93 6.0 09/12/93 6.0 02/27/95 6.0 02/27/95 6.0 Monitor 2ilV-2792B 09/12/93 7.5 09/12/93 7.5 02/27/95 63 02/27/95 63 2ilV-2791B 09/12/93 25.1 09/12/93 25.1 02/27/95 12.9 02/27/95 12.9 71B Containment 112 2-1513-U4-002 09/12/93 107.5 09/12/93 107.5 02/27/95 98.2 02/27/95 98.2 Monitor 2ilV-2793B 09/12/93 76.5 09/12/93 76.5 02/27/95 19.5 02/27/95 19.5 72A Accumulator 2ilV-10950 09/12/93 152 09/12/93 152 02/27/95 75.2 02/27/95 75.2 Sample 2-1204-U4-159 09/12/93 6.0 09/12/93 6.0 02/27/95 6.0 02/27/95 6.0 72B Accumulator 211V-10952 09/11/93 149 09/11/93 149 02/27/95 62.2 02/27/95 62.2 Sample 2-1204-U4-161 09/11/93 6.0 09/11/93 6.0 02/27/95 22.8 02/27/95 22.8 73A Accumulator 211V-10951 09/12/93 10.2 09/12/93 10.2 02/27/95 117.5 02/27/95 117.5 Sample 2-1204-U4-160 09/12/93 103 09/12/93 10.3 02/27/95 51.7 02/27/95 51.7
! 73B Accumulator 211V-10953 09/12/93 351 09/12/93 351 02/27/95 571 02/27/95 571 l
Sample 2-1204-U4-162 09/12/93 6.0 09/12/93 6.0 02/27/95 6.0 02/27/95 6.0 77 RCDT Discharge 211V-7699 09/09/93 37.0 10/11/93 16.0 02/23/95 183 02/28/95 183 2flV-7136 09/09/93 5.2 10/11/93 22.2 02/28/95 30.4 02/28/95 30.4 i
O O O TYPE B AND C RESULTS REFUELING OUTAGE TESTS Sheet 5 of 10 2R3 LEAKAGE - SCCM 2R4 LEAKAGE - SCCM AS FOUND AS LEFT AS FOUND AS LEFF PEN DESCRIPTION EQUIPMENT DATE LEAlU.CE DATE LEAKAGE DATE LEAKAGE DATE LEAKAGE COMMENTS 78 Containment 2ilV-0780 09/1033 10.1 09/10'93 10.1 03/02/95 3240 03/06/95 375 Sump Discharge 2ilV-0781 09/1033 83.4 09/10/93 88.4 03/02/95 180.6 03/06M5 136.2 79 RCDT Vent 211V-7126 09/11/93 6.0 09/13/93 6.0 02/26/95 6.0 02/26/95 6.0
& 112 Supply 211V-7150 09/11/93 6.0 09/13/93 6.0 02/26/95 14.8 02/26/95 14.8 80 Service Air 2-2401-U4-034 09/10/93 1032 09/10/93 1032 01/3I/95* 597 01/31/95* 597 211V-9385 09/10/93 284 09/1083 284 01/31/95* 395 01/31/"5* 395 81 Instrument Air 2-2420-U4-049 09/24/93 1912 09/27/93 301 03/03/95 4540 03/17M5 657 2iiV-9378 09/24/93 17.5 09/27/93 12.2 03/03/95 356 03/17/95 21.7 l 86A Pass Accident 211V-8211 09/13/93 6.0 09/13/93 6.0 03/17/95 6.0 03/17/95 6.0 l Sample 211V-8212 09/13/93 17.2 09/13/93 17.2 03/17/95 20.8 03/17/95 20.8 l
86C Post Accident 211V-8209 09/12/93 17.9 09/12/93 17.9 02/28/95 6.0 02/28/95 6.0 Sample 211V-8208 09/12/93 18.0 09/12/93 18.0 02/28/95 6.0 02/28/95 6.0 87 ILRT Test Blind Flange 09/09/93 6.0 09/09/93 6.0 02/26/95 6.0 03/09/95 6.0 89 Fuel Xfer Canal Blind Flange 09/09/93 9.3 10/11/93 6.0 02/26/95 6.0 03/26/95 11.3 90 ISI Penetration Blind Flange 09/09/93 14.8 10/09/93 17.2 02/26/95 13.4 03/24/95 13.4 100 Containment Post 2ilV-2626A 09/12/93 53.2 09/13/93 89 03/01/95 107.7 03/01/95 107.7 LOCA Purge 211V-2626B 09/12/93 81.8 09/13/93 83 03/01/95 79.8 03/01/95 79.8 f211V-2627A ] 09/12/93 77.2 09/13/93 82 03/01/95 73.1 03/01/95 73.1
[211V-2627B j
- Equipment flatch -
09/09/93 8.8 10/15/93 9.2 02/26/95 9.9 03/27/95 10.2
- Performedjust prior to refueling outage Brackets denote these valves are tested in parallel
O O O TYPE B AND C RESULTS QUARTERLY PURGE VALVE SURVEILLANCE !
Sheet 6 of 10 PEN DESCRIPTION EQUIPMENT DATE LEAKAGE-SCCM COMMENTS DATE LEAKAGE-SCCM COMMENTS ,
83 Containment 211V-2626A 07/07/92 218.0 01/26/94 138.4 Purge Supply 211V-2626B 07/07/92 34.6 01/26/94 9.5 2ilV-2627A & B 07/07/92 36.5 0I/26/94 56.7 I
83 Containment 211V-2626A 09/30/92 275 04/19/94 122 Purge Supply 211V-2626B 09/30/92 33.4 04/19/94 26 2iiV-2627A & B 09/30/92 187 04/19/94 80.3 83 Containment 2flV-2626A 12/17/92 6.0 07/07/94 20.0 Purge Supply 21IV-2626B 12/17/92 46.1 07/07/94 12.2 21tV-2627A & B 12/I7/92 168.7 07/07/94 16.6 83 Containment 2ilV-2626A 03/17/93 132.0 10/19/94 6.4 Purge Supply 2ilV-2626B 03/17/93 27.0 10/19/94 5.5 21tV-2627A & B 03/17/93 55.0 10/19/94 36.2 83 Containment 211V-2626A 06/02/93 410 01/04/95 60.4 Purge Supply 211V-2626B 06/02/93 623 01/04/95 . 14.2 211V-2627A & B 06/02/93 582 01/04/95 174 83 Containment 21tV-2626A 09/09/93 272 02/20/95 14.2 Purge Supply 211V-2626B 09/09/93 659 02/20/95 132 2ilV-2627A & B 09/09/93 547 02/20/95 122 83 Containment 2ilV-2626A 10/12/93 152 03/26/95 23.9 Purge Supply 2ilV-2626B 10/12/93 12 03/26/95 36.8 211V-2627A & B 10/12/93 32 03/25/95 70.7 F
i i
~ _ . . , - _.y - _ , , - .. r.m .-1 -..
O O O TYPE B AND C RESULTS QUARTERLY PURGE VALVE SURVEILLANCE Sheet 7 of 10 PEN DESCRIPTION EQUIPMENT DATE LEAKAGE-SCCM COMMENTS DATE LEAKAGE-SCCM COMMENTS 84 Containment 211V-2626A 07/08S2 111.2 . OI/27/94 10.0 J Purge Exhaust 211V-2626B 07/08/92 60.7 01/27/94 13.6 f
l 21IV-2627A & B 07/08/92 274.0 01/27/94 283 84 Containment 211V-2626A 09/30/92 290 04/20/94 46.7 Purge Exhaust 211V-2626B 09/30/92 38 04/20/94 23.3 211V-2627A & B 09/30/92 457 04/20/94 77.6 84 Containment 211V-2626A 12/17/92 460 07/06/94 104 Purge Exhaust 21IV-2626B 12/17/92 130 07/06/94 93.0 21IV-2627A & B 12/17/92 635 07/06/94 54.0 j 84 Containment 21IV-2626A 03/18/93 112.0 10/20/94 123 l Purge Exhaust 211V-2626B 03/18/93 6.0 10/20 S 4 79.5 211V-2627A & B 03/18/93 157.0 10/20/94 69.4 84 Containment 211V-2626A 06/03/93 114 01/05/95 36.6 i Purge Exhaust 211V-2626B 06/03/93 54 01/05/95 53.8 211V-2627A & B 06/03/93 89 01/05/95 708 84 Containment 211V-2626A 09/09/93 189 02/20/95 36.8 Purge Exhaust 211V-2626B 09/09/93 27 02/20/95 23.3 1 211V-2627A & B 09/09/93 460 02/20/95 369 ,
84 Containment 211V-2626A 10/12/93 67.2 03/27/95 84 3 j Purge Exhaust 211V-2626B 10/12/93 38.5 03/27/95 293 2ilV-2627A & B 10/12/93 65.8 03/27/95 55.2 I
t f
1
O O O TYPE B AND C RESULTS PERSONNEL AND ESCAPE AIRLOCK SURVEILLANCES Sheet 8 of 10 PERSONNEL AlRLOCK ESCAPE AIRLOCK DATE LEAKAGE-SCCM DATE LEAKAGE-SCCM 10/02/92 3306 08/19/92 3~,64 03/20/93 467 01/29/93 '1715 09/09/93 3306 07/16/93 321 10/12/93 905 09/09/93 1003 03/29/94 1273 10/10/93 601 09/II/94 907.7 04/05/94 618 !
02/24/95 517 09/23/94 10.6 03/27/95 614 02/23/95 903 03/23/95 263 i
e b
-. - . - . _ . _ . _ _ _ _ . _ .______._______.___.._.__._.____._____._________.m______.___m.__ . _ _ _ _ _ . _ _ _ _ _ ._._.__m._ . _ _ _ _ _ _ _ _ ___ _ _ _ _ _ _ _ . . _ _ _ . - - _ _ _ _ _ _ - ~ _ _ _ - _~_.,--m -
_ _m -,
~
O O O TYPE B AND C RESULTS TESTS PERFORMED BETWEEN REFUELING OUTAGES Sheet 9 of 10 AS FOUND AS LEFT PEN DESCRIPTION EQUIPMENT DATE LEAKAGE
- DATE LEAKAGE
- COMMENTS i
15 Demin Water 2-1213-U6-051 08/01/92 --
08'01/92 25.5 Note 3 to Cavity 2-1213-U6-050 08/01/92 ' 50.6 08/01/92 50.6 17 Electrical Pen 17 2-1818-II3-Pl7 05/12/93 0.0 05/12/93 0.0 Note 4 36 RilR Encap 2-1205-V4-002 04/09/93 151.2 04/09/93 151.2 Note 5 Vessel 37 RilR Encap 2-1205-V4-001 04/08/93 143.9 04/08/93 143.9 Note 5 Vessel 38 CS Encap Vessel 2-1206-V4-001 04/10/93 68.8 04/10/93 68.8 Note 5 39 CS Encap Vessel 2-1206-V4-002 04/08/93 340 04/08/93 340 Note 5 36 RilR Encap 2-1205-V4-002 03/21/94 683 03/21/94 683 Note 6 Vessel 37 RllR Encap 2-1205-V4-001 04/04/94 1108 04/04/94 1108 Note 6 Vessel 38 CS Encap Vessel 2-1206-V4-001 03/21/94 77.2 03/21/94 77.2 Note 6 39 CS Encap Vessel 2-1206-V4-002 04/04/94 272 04/04/94 272 Note 6 36 RilR Encap 2-1205-V4-002 01/19/95 1090 01/26/95 178 Note 7 Vessel 37 RilR Encap 2-1205-V4-001 12/11/94 37.0 12/15/94 46.2 Note 7 Vessel 38 CS Encap Vessel 2-1206-V4-001 01/13/95 8.3 01/18/95 160 Note 7 39 CS Encap Vessel 2-1206-V4-002 12/09/94 737 01/13/95 lI1.7 Note 7
- All leakage values are in SCCM.
. .- .... . - - - - . . . . . . . - ._ . - - ~ . _ - - --
a b (
r
()
(
v TYPE B AND C RESULTS NOTES Sheet 10 of 10 NOTEI Penetration 11 A: Check valve 2-1411-U4-031 would not seat initially. While the technician was verifying the leakage was past the check valve, the check valve seated. Reference Deficiency Card 2-93-096. Note that the "As Found" leakage on the outboard valve was within limits (42.6 sccm). In addition, the outboard valve is administratively held closed while in Modes 1-4 (the fuses to the solenoid that operates this fail-closed AOV are removed prior to Mode 4 entry.
NOTE 2 Penetrations 11 A,12A,69A, and 69B: "As Found" LLRT's for 2R3 were performed on check valves 2-1411-U4-029,-031,-043, and -044. These valves were replaced with manual globe valves under Design Change Package 92-V2N0135 during 2R3. He "As Len" leakage values for 2R3 and subsequent 2R4 leakage values are for the new globe valves. The check valves were replaced due to their history of LLRT failures.
NOTE 3 Penetration 15: De bonnet bolts were tightened on 2-1213-U6-051 prior to performing an "As Found" LLRT. The valve was reported as having water spraying at the valve body and the bonnet bolts were tightened immediately prior to performing the LLRT. The LLRT was being performed
- to determine the operability of the two containment isolation valves. De LLRT was acceptable on both 2-1213-U6-050 and 2-1213-U6-051.
l Reference Deficiency Card 2-92-259.
l NOTE 4 Electrical Penetration 17: Nitrogt pressure for electrical penetration 2-1818-il3-Pl7 was found at 12 psig. Reference MWO 29203468.
NOTE 5 Penetrations 36,37,38, and 39: Two encapsulation vessels were found to have loose nuts. Reference Deficiency Card (DC) 2-93-027. Those two vessels were retoiqued, while the other two had their torques verified.
l NOTE 6 Penetrations 36,37,38, and 39: Leak Rate Tests performed to check for relaxation of gasket clamping force. Tests were a corrective action based on DC 2-93-027 described in Note 5 above.
NOTE 7 Penetrations 36,37,38, and 39: "As Found" and "As Len" LLRT's performed due to performance of Design Change Package 93-V2N0080 for the installation ofinspection ports on the encapsulation vessel heads to allow visually observation of valve stroke without requiring removal of vessel head. Only one vessel lid was removed at a time, and each modified vessel was LLRT'd prior to the removal of the next vessel lid.
l l
l
_ =_
(O u)
APPENDIX III INSTRUMENT CALIBRATION
SUMMARY
Parameter / Instrument Data Pressure / Range: 0 - 100 psia Volumetrics Model PPM-1000 Accuracy: '/-0.015% RDG Precision Pressure Gauge +/-0.005% F.S.
Repeatability: 0.001 PSIA Sensitivity: 0.0001 PSIA Cal. Date: 12-8-94 Drybulb Temperature / Range: 60 - 120 degrees F 100 OHM Platinum Resistance Accuracy: +/-0.5 degrees F Temperature Detectors Sensitivity: 0.02 degrees F Repeatability: 0.07 degrees F Cal. Date: 12-30-94 Dewpoint Temperature / Range: -40 to +140 degrees F EG&G Dewtrak Humidity Accuracy: +/-1 degrees F
(~' Transmitter Cal. Date: 12-14-94
\
Flow / Range: 1.34 to 13.4 scfm Brooks Rotameter Accuracy: +/-2.0% F.S.
Model GT/1000 Cal. Date: 1-13-95 l
l O
1
~
1 I
l APPENDIX IV I GENERAL INFORMATION General Data Owner - Georgia Power Company ,
Plant Name - Vogtle Electric Generating Plant (VEGP)
Unit - 2 Outage Cycle - 4th refueling Containment Description - steel lined prestressed concrete Containment net free volume - 2,750,000 cf Date test was completed - March 5,1995 Test Data Test Method - absolute Test Duration - 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Data Analysis Technique - total time Test Pressure - 37.0 psig (+1.0 psig, -0 psig)
Maximum Allowable Leakage Rate (La) 0.20 %/ day Acceptance Limit (0.75La)- 0.15 %/ day Calculated Leakage Rate - 0.0497 %/ day '
Leakage rate at 95% upper confidence limit (UCL) - 0.0938 %/ day Final leakage rate - as-found (UCL + penalties) - 0.0939 %/ day Final leakage rate - as-left (UCL + penalties) - 0.0939 %/ day Verification Test Calibrated Leak Superimposed - 0.1966 wt.%/ day Upper limit rate - 0.2963 wt.%/ day Lower limit rate - 0.1963 wt.%/ day Total time calculated rate - 0.2735 wt.%/ day Duration of Test Segments i
Pressurization 8.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> ,
Stabilization 6.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> Type A Test 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Verification 1.25 + 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> Depressurization 6.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Total 34.25 hours2.893519e-4 days <br />0.00694 hours <br />4.133598e-5 weeks <br />9.5125e-6 months <br /> O