ML20042G710

From kanterella
Jump to navigation Jump to search
Third Suppl to Summary Rept of Startup Test Program. W/900511 Ltr
ML20042G710
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 05/11/1990
From: Hairston W
GEORGIA POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
ELV-01635, ELV-1635, NUDOCS 9005150324
Download: ML20042G710 (3)


Text

-

i ' Georgte Power Company l~

.d 333 Piedmont Avenue -

f' Atlanta. Georgia 30308 -

.,:: ' Teephono 404 526 3195

. Maiting /ddress' . .

40 inverness Center Parkway .

- Post ORce Dox 1295 Domingham, Nabama 06201 Telephone 205 608 5501 -

-May:11, 1990 n, mo,,,,n marc mm,n W. G. Hairston, til Serwor Vco Presdent Nuclear Operat ons ELV-01635  ;

0380  ;

Docket No. 50-425 U. S. Nuclear Regulatory Commission ATTN: - Document Control: Desk Washington, D. C. 20555 Gentlemen:

V0GTLE ELECTRIC GENERATING PLANT THIRD-SUPPLEMENT TO

SUMMARY

REPORT OF STARTUP TEST PROGRAM In accordance with Technical Specification 6.8.1.1, attached is the-third supplement to the initial startup-report which-was submitted by letter ELV-00789 ~!

dated August 21, 1989.  !

i If you have any questions, please contact this office. '! 4 Sincerely, j fod

'W. G.-Hairsto ,'III i WGH,III/NJS/gm Attachment xc: Georaia Power Comoany Mr.-C. K. McCoy Mr. G. Bockhold, Jr.

Mr. P. D. Rushton Mr. R. M. Odom "

NORMS U. S. Nuclear Reaulatory Commission Mr. S. D. Ebneter, Regional- Administrator i Mr. T. A.- Reed, Licensing Project Manager, NRR Mr. R. F.- Aiello, Senior Resident Inspector, Vogtle

[0051503249005,1y p,DR ADOCK 05000425 PDC .

/6r i

j i

V0GTLE ELECTRIC GENERATING' PLANT - UNIT 2 .

THIRD SUPPLEMENT TO

SUMMARY

REPORT OF STARTUP TEST PROGRAM i

This third supplement to the initial startup report addresses the remaining startup test that was incomplete at the time of submittal of the initial startup  :

report,

- The test is identified according to the section numbering scheme used in the initial report.. The test procedure number is provided in parenthesis.

7.6.10 Thermal Expansion Test (2-600-11)

The only remaining' testing to be completed consists of cold post-test readings  :

which require the plant-to be in a cold shutdown condition. The readings will l be performed during the Unit 2 refueling outage under Procedure 2-600-11.

1 l

1 l

j i

l l

l t

l L

f . ., .

l l

ADMINISTRATIVE CONTROLS

, h 6.8 REPORTING REQUIREMENTS I ROUTINE REPORTS 6.B.1 In addition to the applicable reporting requirements of Title 10, Code of Federal Regulations, the following reports shall be submitted to the Regional

( Administrator of the Regional Office of the NRC unless otherwise noted.

STARTUP REPORT 6.8.1.1 A-summary report of plant startup and power escalation testing shall be submitted following: (1) receipt of an Operating License, (2) amendment to I the license involving a planned increase in power level, (3) installation of fuel that has a different design or has been manufactured by a different fuel supplier, and (4) modifications that may have significantly altered the nuclear, thermal, or hydraulic performance of either unit.

The initial Startup Report shall address each of the startup tests iden-tified in the Final Safety Analysis Report and shall include a description of .

the measured values of the operating conditions or characteristics obtained during the test program and a comparison of ~ these values with design predictions and specifications. Any corrective actions Any that were required to obtain satis-additional specific details  !

factory operation shall also be described.  !

required in license conditions based on other commitments shall be included in this report. Subsequent Startup Reports shall address startup tests that are necessary to demonstrate the acceptability of changes and/or modifications.

g Startup Reports shall be submitted within: (1) 90 days following comple-tion of the Startup Test Program, (2) 90 days following resumption or commence-ment of commercial power operation, or (3) 9 months following initial criticality, whichever is earliest. If the Startup Report does not cover all.three events (i.e., initial criticality, completion of Startup Test Program, and resumption e commencement of commercial operation), supplementary. reports shall be submitted 'at least every 3 months until all three . events have been completed.

ANNUAL REPORTS **

6.8.1.2 Annual Reports cover ms the activities of the plant as described below q

/ for the previous calendar year shall be submitted prior to March 1 of each year. The initial report shall be submitted prior to March 1 of the year

. following initial criticality.

Reports required on an annual basis shall include:

a. A tabulation on an annual basis of the number of plant, utility, 4 and other personnel (including contractors) receiving exposures

( greater than 100 mrem /yr and their associated man-rem exposure according to work and job functions * (e.g., reactor operations and

  • This tabulation supplements the requirements of $20.407 of 10 CFR Part 20.
    • A single submittal may be made for Units 1 and 2. The submittal should

{ combine those sections that are common to both units at the plant.

)

V0GTLE UNITS - 1 & 2 6-17

. l