Forwards Proposed Task Lists for Discussion on 910211 at NRC Headquarters
ML20028H823
Person / Time
Site: 05000054
Issue date: 01/21/1991
From: Mcgovern J
CINTICHEM, INC.
To: Micheals T
Office of Nuclear Reactor Regulation
References
NUDOCS 9101300187
Download: ML20028H823 (3)


Text

<

CINTICHEM, INC.

P.O GOX B1G TUXEDO. NEW YORK 10907 [014) 351-2131 [O" January 21, 1991 Mr. Theodore S. Michaels U. S. Nuclear Regulatory Commission PDNP Mail Stop 11-B-20 Washington, DC 20555

Dear Mr. Michaels:

Please find attached, two proposed task lists we would like to discuss with you on February 11, 1991 at NRC headquarters. One list outlines pre-approval tasks which we feel could be done under our existing license. The second sheet defines post approval taska that we feel could be performed with spent fuel on site without compromising either safety or security.

As you know, it is possible that spent fuel will be on our site through June 1991 due to the ongoing moratorium on fuel shipments. In the Decommissioning Plan we have submitted, we estimated that the decommissioning project will take 27 months to complete. Only if we begin the listed tasks in the first quarter of 1991 will we have a good chance of completing the project before the end of December 1992.

Please contact me if you have any questions about the agenda.

Very truly yours, fo tw

f. J . McGovern President / Plant Manager JJMcG/bjc Attachments JJM/17.91B /

9101300187 910121 j PDR ADOCK 05000054 l p PDR ij

CINTICilEM DECOMMISSIONING PROJECT Pre-D&D Work List (Pre-Plan Approval)

1. Remove lead shield blocks and graphite blocks f rom thermal Column.
2. Remove equipment from hot cells #1-5; wipe down surfaces and hydrolase hot cells and conveyor station. Construct containments for scabbling.
3. Remove walls between operating area and radiochem lab, l radiochem lab and charging area, and enlarge door between I radiochem lab and radwaste shipping area.  !

1

4. Dismantle uranium labs (hot lab building), uranium welding lab, QC lab and radiochem lab (reactor building) (originally part of Phase I) and decontaminate surfaces.
5. Remove everything in reactor pool except reactor core and spent fuel (originally part of Phase I).
6. Saw cut floor above underground exhaust ducts and above reactor coolant piping (to facilitate Phase II removal of buried pipes).
7. Remove South and West wall storage tubes (vaults).
8. Remove asbestos from buildings.
9. Dismantle not needed equipment in T1/cvaporator room.

i l

l JJM/17.91B

CINTICilEM DECOMMISSIO! LING PROJECT Work That can Be Performed With Spent Fuel On-Site (Post-Plan Approval)

1. Remove reactor core structures

- move core / bridge to pool position move spent fuel to reactor position

- install gate proceed with normal plan for reactor structure removal

2. Remove SK tanks and associated piping.
3. Scabble and remove embedded fixtures and ducting in hot cells. Remove underground duct system from hot lab building.
4. Scabble T1/ evaporator rooms (interior).
5. Isolate reactor pool from pump room, perform D&D work on pump room, and storage tank. Install separate means of maintaining or draining water in reactor pool.
6. Decontaminate storage wells and plugs (must maintain cask movement path).
7. Remove ilUT and soil overburden.

JJM/17.91B