Notice of Granting Relief from ASME Code Inservice Insp Requirements
ML20024E088
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 07/29/1983
From: Rooney V
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20023A487 List:
References
TAC-07811, TAC-08019, TAC-7811, TAC-8019, NUDOCS 8308090166
Download: ML20024E088 (2)


Text

'

t 7590-01 UNITED STATES NUCLEAR REGULATORY COMMISSION DOCKETS NOS. 50-321 and 50-366 GEORGIA POWER COMPANY, Et Al.

NOTICE OF GRANTING RELIEF FROM ASME CODE REQUIREMENTS The U. S. Nuclear Regulatory Comission (thL Comission) has granted relief from certain requirenents of the ASME Code,Section XI,

" Rules for Inservice Inspection of Nuclear Power Plant Components", to the Georgia Power Company, Oglethorpe Power Corporation, Municipal Electric Authority of Georgia, and City of Dalton, Georgia ('the licensees),

which revised the inservice inspection program for the Edwin I. Hatch Nuclear Plant, Units Nos.1 and 2 (the facility) located in Appling County, Georgia.

The ASME Code requirements are incorporated by reference into the Commission's rules and regulations in 10 CFR 50.

The relief is effec-tive as of the date of issuance.

The requests for relief comply with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Com-mission's rules and regulations.

The Comission has marie appropriate

~

findings as required by the Act and the Comission's rules and regulations in 10 CFR Chapter I, which are set forth in the letter granting relief and accompanying Safety Evaluation.

The Comission has determined that the granting of this relief will not result in any significant environmental impact and that pur-suant to 10 CFR 151.5(d)(4) an environmental impact statement, or negative declaration and environmental impact appraisal need not be prepared in cnnnar-Haa w" this action

  • 8309090166 830729 PDR ADOCK 05000321 PDR 0

~ _. _. _

9 7590-01 For further details with respect to this action, see (1) the licensees' letters dated August 3,1978, January 24,1979, June 6,1979, January 27, 1981, and November 10, 1981 for Hatch Unit 1; letters dated September 21, 1978, May 1,1980, and November 18, 1981, for Hatch Unit 2; and letters dated March 2,1982, and June 11,, 1982, for both Units, (2) the Canmission's letter to Georgia Power Company dated

,, and (3) the Commission's related Safety Evaluation.

All of these itens are available for public inspection at the Commission's Public Document Room,1717 H Street, N.W.,

Washington, D. C. and at the Appling County Public Library, 301 City Hall Drive, Baxley, Georgia 31513.

A copy of items (2) and (3) may be 'obtained upon request addressed to the U. S. Nuclear Regulatory Commission, Wash-ington, D. C. 20555, Attention:

Director, Division of Licensing.

Dated at Bethesda, Maryland, this FOR THE NUCLEAR REGULATORY COMMISSION n-Vernon L. Rooney, Acting Branch Chief Operating Reactors Branch y2

' Division of Licensing 1