ML19350E872

From kanterella
Jump to navigation Jump to search
Commits to Provide Detailed Test Procedure & Safety Analysis Re NRC Position on I.G.1 at Least 90 Days Prior to Fuel Loading
ML19350E872
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/22/1981
From: Colbert W
DETROIT EDISON CO.
To: Kintner L
Office of Nuclear Reactor Regulation
References
EF2---53-825, NUDOCS 8106230607
Download: ML19350E872 (1)


Text

,

t:

.o.

bffiQ 44 - 2000 Secced Avenue

^ i t4ai3>

/ {;.O '  %* '*%

t :: e, h.Nb ;O Detro %cnican 48225 N 237.aoco - . [e c'f-.- ,1 g- ,

.,q_

i_ . .

m1.

\E ' , u.4 5.N..J...?i'#,

- ~ , .

7 June 22, 19.81 6, .

EF2 - 53,8259 O 5'

-o, -ek /

'W:f '

Mr..L. L. Kintner Division of Project Management Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Conuaission

- Washington, D. C. 20555

Dear Mr. Kintner:

Reference:

Enrico Fermi Atomic Power Plant, Unit 2 NRC Docket No. 50-341

Subject:

Position on I.G.1'Special Test PTRB-1: The Staff concludes that the test proposed in the applicant's June'3, 1981 letter complies with item I.G.1 requirements. The applicant should commit to provide a. detailed test procedure and a safety analysis for our review at least 90 days prior to fuel' loading.

. Response: -Detroit Edison commits to provide a detailed test procedure and a safety analysis'to the NRC at least

. 90 days prior to fuel loading. '

Sincerely, WYh!

W. F. Colbert Technical Director Enrico Fermi 2 WFC/AEW:j1 cc: Mr. B. Little