Lists Items of Fire Protection Program Requiring Addl Time for Response & Proposed Dates for Response
ML19225C771
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 07/27/1979
From: Early P
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To: Ippolito T
Office of Nuclear Reactor Regulation
References
JPN-79-44, NUDOCS 7908020422
Download: ML19225C771 (4)


Text

-- -- . - . .- -

e POWER AUTHORITY OF THE STATE OF NEW YORK 10 COLUMBUS CIRCLE NEW YORK. N. Y.10019 (212) 397 6200 un July 27, 1979 JPN-79-44 Director, 'Jffice of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Mr. Thomas A. Ippolito, Chief Operating Reactors Branch No. 3 Division of Operating Reactors

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Additional Responses to the Draft Safety Evaluation Report (SER) Relating to Fire Protection Program

Dear Sit:

'te have sent responses to the draft safety evaluation repcrt via several letters (JPN-79-12, March 7, 1979, JPN-79-25, May 7, 1979, and JPN-79-40, July 2, 1979). These letters contained two tables, Table 3.1, Implementation Dates for Licensee Proposed Modifications and Staff Requirements and Table 3.2, Completion Dates for Studies.

In discussion with your Mr. P. Polk and Mr. M. Virgillio in the last few weeks, we indicated that we intend to revise some of these dates and stated our reasons for doing the same.

By this letter, w_ _ listing below those items that require additional time from thoL_ stated previously:

Table 3.1 Item 3.1.1 Interior Hose Stations (PF-9)

Previously when we stated that this item was complete we had assumed that the staff requirements applied to existing hose stations. Our review indicates that some 29 new or relocated hose stations need to be modified to meet the staff requirement stated in Section 3.1.1 of the SER. These will be completed by October 1980.

442 265 ,

cre>4, Ij II / / j 79 8020 bW h

1 Item 3.1.7 Fire Doors (PF-35)

We had anticipated installing these fire doors by June 1979.

However, there was some delay in the delivery of the same. At present the doors are on site and will be installed by October 1979.

Item 3.3.2 Signaling Circuit Supervision (PF-19)

The study is expecr^'

' o be completed by August 1979 and any modifications ,ompleted by October 1980.

Item 3.3.'? .ctrical Cable Penetration Qualification (PF-27)

The testing of these penetrations are underway and any modifications if required will be completed by October 1980.

Item 3.3.15 Testing of Carbon Dioxide Fire Suppression Systems (PF-18)

At present this testing is expected to be done by January 1980 and if any modifications are required they will be completed by October 1980.

Item 3.3.16 Flame Retardant Coating As stated in our letter JPN-79-40, July 2, 1979, the entire fire test documentation for cabling installed in the FitzPatrick plant consists of several hundred pages and as agreed with your Mr. P. Polk, it will be forwarded to you by August 1979.

Item 3.2 Item 3.2.1, 3.2.3 and 3.2.5 All these studies are late by one to four months and are expected to he completed by August 1979. The submission dates to NRC are shown on Table 3.2.

For your convenience revised Tables 3.1 and 3.2 are attached.

Very trulv " urs,

/

,b ,b.

Paul J. Early Assistant Chi f Eng;neer-Projects 442 266

TABLE 3.1 (REVISED 7/26/79)

~

IMPLD1E!3TATIOff DATES FOR LICEf?SEE PROPOSED MODIFICATIO!1S AtJD STAFF REQUIRD1EliTS ITEM DATE 3.1.1 Interior llose Station (PF-9) (All Portions Except 29 tiew/ Relocated Stations are Complete) October 1980 3.1.2 Valve Supervision Implemented 3.1.3 Manual Fire Fighting Equipment (PF-28) Implemented 3.1.4 Self-Contained Breathing Apparatus December 1979 3.1.5 Administrative Controls January 1980 3.1.6 Emergency Lighting (PF-25) January 1980 3.1.7 Fire Doors (PF-35) October 1979 3.1.8 Ventilation System-Safety Related Pump Rooms * (PF-24) January 1980/ Spring 1980 3.1.9 Alternate Shutdown Capability-Relay Room

  • December 1979/Oct. 1980 3.1.10 Exterior Ilydrant ilose llouse (PF-12) October 1979 3.1.11 Post-Indicator Valve Operators (PP-14) Implemented 3.1.12 Post-Indicator Valve Labeling (PF-31) Implemented 3.1.13 Fire Brigade Leader Training (PF-30) Implemented 3.1.14 Control of Combustibles (PF-29) December 1979 3.3.1 Detector Testing December 1979/Oct. 1980 3.3.2 Signaling Circuit Supervision (PF-19) August 1979/ October 198 3.3.3 Fire Alarm Annunciation in the Control Room Implemented 3.3.4 Fire Pump Performance August 1979 3.3.5 Fire Pump Capacity August 1979 3.3.6 Water Suppression System Design Details August 1979 3.'.7 Total Flooding CO2 Suppression System Ventilation System Interlocks Spring 1980 3 3.3.d Fire Detection and Signalirg System (PF-19) October 1979/ October '8 3.3.9 Exposed Structural Steel (PF-22) August 1979/ October 198 N

3.3.10 Fire Brigade Composition (PF-17) Deleted / Completed 3.3.11 Crescent Area Fire Protection (PF-23) August 1979/ Spring 1980 N 3.3.12 Electrical Cable Penetration Qualification (PF-27 ) *

  • October 1979/ October '8 O 3.3.13 Ventilation Duct Penetration July 1980 N 3.3.14 Piping Penetration Seal Qualification December '79/ October '8 3.3.15 Testing of Carbon Dioxide Fire Suppression Systems (PF-18) October 1980 3.3.16 Flame Retardant Coating August 1979 3.3.17 Alternate Shutdown capability-Cable Spreading Room December '79/ October '8 110 t e 1<. The Authority will make every effort to complete all required modifications by October 31, 1980.
  • llo t e 2: The design details for these modifications will be subject to further staff review prior to implementation.
  • t Jo t e 3: Testing underway.

TABLE 3.2 (REVISED 7/26/79)

COMPLETION DATES VOR STUDIES DATES COMPLETION BY TO ITEM CONSULTANTS NRC 3.2.1 Fire llazard Analysis (PF-ll) August 1979 November 1979 3.2.2 Pipe Penetrations ( PF- 3 3 ) December 1979 February 1980 3.2.3 Fire Water Piping System (PF-36) August 1979 November 1979 3.2.4 Diesel Fire Pump Room Sprinkler llead Spacing (PF-32) Completed August 1979 3.2.5 Fire Door Supervision (PP-8) August 1979 November 1979 Note: The Authority will make every effort to complete all required modifications by October 31, 1980.

-h

-5 hJ rs' Os Co