Forwards Listed Sealed Drawings for Salem Generating Station Oil Water Separator Project Treatment Works Approval,(Twa) Twa Application 93-7504-4,per Recipient 930412 Ltr.W/O Encls
ML18100A367
Person / Time
Site: Salem  PSEG icon.png
Issue date: 04/30/1993
From: Thomson F
Public Service Enterprise Group
To: Pyarilal R
NEW JERSEY, STATE OF
References
NLR-E93131, NUDOCS 9305120126
Download: ML18100A367 (2)


Text

Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038 Nuclear Department HAND DELIVERED APR 3 0 1993 NLR-E93131 NJ Department of Environmental Protection and Energy Wastewater Facilities Regulation Program Bureau of Standard Permitting CN 029 Trenton, NJ 08625-0029 Attention: Mr. Ramamurthy Pyarilal, P.E.

Supervising Environmental Engineer

Dear Mr. Pyarilal:

SALEM GENERATING STATION NJPDES PERMIT NO. NJ0005622 OIL WATER SEPARATOR PROJECT TWA APPLICATION NO. 93-7504-4 In accordance with your April 12, 1993 letter, Public Service Electric and Gas (PSE&G) Company is providing the following signed and sealed drawings for the above-referenced Treatment Works Approval (TWA) project:

1. Piping and Instrumentation Diagram
2. Hydraulic Profile
3. Process Flow Diagram
4. South Yard Drain Inlet Drawing

.5. General Site Plan In addition, PSE&G is providing a copy of Resolution Number 50-93 adopted by Lower Alloways Creek Township on April 6, 1993 endorsing the oil water separator project. This endorsement is being submitted in accordance with NJAC 7:14A-2.l(k)2 and Section A of Form WQM-003.

The April 12 letter also requires a copy of the signed and dated letter requesting endorsement of this project from the affected sewerage authority in accordance with NJAC 7:14A-2.l(k). As discussed by Mr. Jay Acharya of your staff and Mr. Patrick McCabe o~ PSE&G on April 14, the site of this project does not fall within the service area of any sewerage authority. As a result, \

no endorsement is warranted.. f (\\=l\ \ O The power. is in your hands. 0 '7 0 0 51 VUV

-* --9305126126 930430---~\ "**""~EV. 11/91 PDR ADOC~ 05000272 i p . PDR

.f Mr. R. Pyarilal 2 NLR-E93131 APR 3 0 1993 Due to the schedule required for completion of this project and the requirement to conduct an Effluent Characterization Study on the discharge from the new system, PSE&G is requesting that the Department expedite the technical review of this project to allow timely installation and operation of this system.

If you have any questions, or require additional information, please feel free to contact Pat McCabe at (609) 339-1245.

Sincerely,

~Y~/

F. X. Thomson, ;/.

Manager -

Licensing and Regulation Enclosures (6) c (All without enclosures)

Mr. Edward Post, Chief NJ Department of Environmental Protection and Energy Southern Bureau of Water and Hazardous Waste Enforcement 20 East Clementon Road Gibbsboro, NJ 08026 US Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555