Forwards LER 81-033/03L-0.Detailed Event Analysis Encl
ML18086A366
Person / Time
Site: Salem PSEG icon.png
Issue date: 04/28/1981
From: Uderitz R
Public Service Enterprise Group
To: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML18086A367 List:
References
NUDOCS 8105050627
Download: ML18086A366 (3)


Text

PS~G Public Service Electric and Gas Company 80 Park Plaza Newark, N.J. 07101 Phone 201/430-7000 April 28, 1981 Mr. Boyce H. Grier Director of USNRC Off ice of Inspection and Enforcement Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Grier:

LICENSE NO. DPR-70 DOCKET NO. 50-272 REPORTABLE OCCURRENCE 81-33/03L Pursuant to the requirements of Salem Generating Station Unit No. 1 Technical Specifications, Section 6.9.1, we are submitting Licensee Event Report for Reportable Occurrence 81-33/03L. This report is required within thirty (30) days of the occurrence.

Sincerely yours,

)

/[ t/ /-<<4??

R. A. Uderit.Z General Manager -

Nuclear Production CC: Director, Office of Inspection and Enforcement (30 copies)

Director, Office of Management Information and Program Control (3 copies)

Report Number:

Report Date: April 28, 1981 Occurrence Date: 4/02/81 Facility: Salem Generating Station, Units 1 and 2 Public Service Electric & Gas Company Hancocks Bridge, New Jersey 08038 IDENTIFICATION OF OCCURRENCE:

No. 2 Fire Pump Inoperable CONDITIONS PRIOR TO OCCURRENCE Unit 1 - Mode 5 - Rx Power 0% - Unit Load 0 MW Unit 2 - Mode 5 - Rx Power 0% - Unit Load 0 MW DESCRIPTION OF OCCURRENCE:

On April 2, 1981, the No. 2 Fire Pump was declared inoperable because of a leaking Fuel Oil Pressure Gage Supply Hose. Action Statement 3.7.10.la, entered at 1400 hours0.0162 days <br />0.389 hours <br />0.00231 weeks <br />5.327e-4 months <br />, requires that with one pump and/or one water supply inoperable, restore the inoperable equipment to operable status within seven days or, in lieu of any other report required by Specification 6.9.1, prepare and submit to the Commission

.pursuant to Specification 6.9.2 within the next 30 days outlining the plans and procedures to be used to provide for the loss of redundancy in this system.

This occurrence constituted operation in a degraded mode IAW Technical Specification 6.9.1.9.b.

DESIGNATION OF APPARENT CAUSE OF OCCURRENCE:

Equipment Failure - Investigation revealed a small hole in the Fuel Oil Pressure Gage Supply Hose.

ANALYSIS OF OCCURRENCE:

The four foot long Fuel Oil Pressure Gage Supply Hose connects the Fuel Oil Injector Manifold to a pressure gage which supplies local indication of the fuel oil pressure. Examination of the hose suggests that the leak was the long term effect of the hose chafing against the m~nifold as the pump was operated.

CORRECTIVE ACTION:

Pending the arrival of a replacement hose from the vendor, the pressure gage was isolated from the manifold by installing a cap on the manifold hose connection. The Action Statement was terminated at 2030 hours0.0235 days <br />0.564 hours <br />0.00336 weeks <br />7.72415e-4 months <br /> on April 2, 1981.

LER 81-33/03L 4/28/81 FAILURE DATA:

W. A. Kraft Corporation Fuel Oil Pressure Gage Supply Hose - Length 4'-10" Prepared By W. J. Steele SORC Meeting No. 81-31