MONTHYEARML17355A4601999-10-26026 October 1999 Forwards Revised Epips,Including Revs to 0-EPIP-1102, 0-EPIP-1212,0-EPIP-20110,0-EPIP-20111,0-EPIP-20132, 0-EPIP-20133 & 0-EPIP-20201,per 10CFR50.54(q) & 10CFR50, App E.Epip 0-EPIP-20107,has Been Deleted ML17355A4301999-10-0808 October 1999 Forwards Rev 16 of Updated Fsar.Info Accurately Reflects Plant Changes Made Since Previous Submittal.Rev Incorporates Changes Completed Between 971015 & 990408.Summary of Accuracy Review Changes & Instructions,Included ML17355A4461999-10-0404 October 1999 Notifies NRC of Change in Commitment to Perform Periodic Testing of Critical Welds & Parts on Special Lifting Devices IAW NUREG-0612.Use of Ae Technology Will Provide Same Level of Testing Quality as Did NDE Methods Noted in ANSI Std L-99-208, Forwards Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 971014-990408. Summary of PORV Actuations & Results of Plants SG Tube Insp,Which Occurred During That Time Included1999-10-0404 October 1999 Forwards Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 971014-990408. Summary of PORV Actuations & Results of Plants SG Tube Insp,Which Occurred During That Time Included ML17355A4291999-10-0404 October 1999 Forwards Response to NRC Telcon Questions Re License Amend Request Dtd 990727,proposing Amend on one-time Basis to Modify TS 3.8.1.1 & TS 3.4.3 & 3.5.2 to Extend Allowed Outage Time for EDG from 72 H to 7 Days ML20212M1601999-09-28028 September 1999 Refers to 990908 Engineering Meeting Conducted at NRC Region II to Discuss Engineering Issues at Lucie & Turkey Point Facilities.List of Attendees & Copy of Presentation Handout Encl ML17355A4251999-09-22022 September 1999 Forwards NRC Form 536 in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams, Issued 990820 ML17355A4111999-09-0909 September 1999 Informs That Thermo-Lag Upgrades for Fire Zones 47,54,113, 114,115,116,118,119,120 & 143 Completed on 990726,per GL 92-08 ML17355A4131999-09-0707 September 1999 Forwards Revised Relief Request 20 Re Requirement to Perform Exams as Required by IWL-2524 & IWL-2525,Table IWL-2500-1 for Exempt Tendon Insp,Per Recent Discussions with NRC ML17355A4141999-09-0202 September 1999 Documents That Util Has No Concerns or Challenges Related to site-specific Written Exam Administered at Plant on 990830 ML17355A4041999-08-23023 August 1999 Forwards Info to Support Assessment of Potential Risks Associated with Proposed Civil Aircraft Operations at Former Homestead Air Force Base to FP&L Turkey Point Nuclear Facility Units 3 & 4 ML17355A4071999-08-23023 August 1999 Informs That FPL Has Completed Review of Info Listed in Reactor Vessel Integrity Database,Version 2 & Found Listed Discrepancies,Re Closure of GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity. ML17355A4061999-08-23023 August 1999 Forwards Semiannual FFD Performance Rept for Period of Jan- June 1999,for Turkey Point Units 3 & 4.List of Events Reported & Summary of Mgt Actions Taken,Included ML17355A4001999-08-20020 August 1999 Informs That on 990722,util Determined Blind Specimen Submitted to Smithkline Beecham Clinical Labs on 990721,was Reported Back with Unsatisfactory Results.Attachment 1 Is Summary of Investigation of Unsatisfactory Performance ML17355A3941999-07-27027 July 1999 Submits Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for FY00 & FY01 ML17355A3871999-07-16016 July 1999 Provides Supplement to FP&L Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML17355A3851999-07-14014 July 1999 Informs That Pages Missing from 1998 Annual Radiological Environ Operating Rept, Contain Info Unrelated to ODCM- Specified Sampling & Were Not Included as Part of Rept ML17355A3711999-07-0606 July 1999 Forwards Revised EPIPs 0-EPIP-20201, Maintaining Emergency Preparedness - Radiological Emergency Plan Training & 0-EPIP-20126, Off-Site Dose Calculations. with Summary of Changes ML17355A3591999-06-30030 June 1999 Forwards Turkey Point,Unit 4 ISI Rept. Listed Repts Are Encl.No Eddy Current Exams Scheduled for Unit 4 Steam Generators ML17355A3661999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 ML17355A3571999-06-28028 June 1999 Informs That Util Voluntarily Reporting Facility Readiness as Outlined in Suppl 1 to GL 98-01.Encl Is Y2K Readiness Disclosure for Units 3 & 4,reporting Status of Facility Y2K Readiness ML17355A3521999-06-18018 June 1999 Forwards Response to NRC 990415 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves. ML17355A3491999-06-0404 June 1999 Forwards Summary of Corrective Actions Implemented by FPL Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions. ML17355A3441999-05-27027 May 1999 Modifies FPLs Consent to Confirmatory Order to Reflect Resolution of Four Issues Identified as Pending in L-99-031 ML17355A3451999-05-24024 May 1999 Requests Waiver of 520 Hours (13 Wks) Required Parallel Watchstanding in Control Room Prior to License Application Submittal for W Conley ML17355A2921999-04-22022 April 1999 Forwards Rev 35 to Turkey Point EP & Revised EPIP 0-EPIP-20101, Duties of EC, Per Requirements of 10CFR50, App E & 10CFR50.54(q).Summary of Changes,Encl.Implementation Date for Both Documents Was 990330 ML20205M0431999-04-13013 April 1999 Eighth Partial Response to FOIA Request for Records.App Q & R Records Encl & Being Made Available in PDR ML17355A2891999-04-0909 April 1999 Forwards Relief Request 20, Exempt Tendon Insp, Requesting Relief from ASME Section XI Code,1992 Edition,Paragraph IWL-2521.1(c) Which Requires That Each Exempted Tendon Be Examined IAW IWL-2524 & IWL-2525.Approval Needed by 991001 ML17355A2861999-04-0505 April 1999 Forwards COLR for Turkey Point Unit 4,Cycle 18,IAW TS 6.9.1.7 ML17336A0681999-04-0101 April 1999 Expresses Support for FP&L Request for Waiver of Applicable Review Fees Upon FP&L Submittal of an Application for License Renewal for Turkey Point Units 3 & 4 ML17355A2751999-03-25025 March 1999 Informs NRC & Staff of Fp&Ls Plans to Submit License Renewal Application for Turkey Point Units 3 & 4 by End of Dec 2000 ML17355A2641999-03-19019 March 1999 Requests Changes to FPL Official Service List for Turkey Point,Units 3 & 4.Add s Franzone & Remove G Hollinger from All Correspondence ML17355A2651999-03-19019 March 1999 Forwards Annual Radioactive Effluent Release Rept for Jan-Dec 1998 & Rev 7 to ODCM for Gaseous & Liquid Effluents from Turkey Point,Units 3 & 4. ML17355A2621999-03-16016 March 1999 Forwards Special Rept as Result of Turkey Point Unit 3 End-of-Cycle 16 ISI of SG Tubes.Rept Summarizes Results of SG Tube ISI ML17355A2631999-03-12012 March 1999 Forwards FPL Decommissioning Fund Status Repts for St Lucie, Units 1 & 2 & Turkey Point,Units 3 & 4.Rept for St Lucie, Unit 2 Provides Status of Decommissioning Funds for All Three Owners of That Unit ML20204C6991999-03-10010 March 1999 Requests Amend to Turkey Point PSP to Modify Requirement to Post Security Officers to Provide Continuous Observation of Entire PA Perimeter in Event of Security Computer Failure. Change to Security Force Staffing Level Also Requested ML17355A2451999-03-0909 March 1999 Submits Info on FPL Current Levels of Nuclear Property Insurance,Per 10CFR50.54(w)(3) ML17355A2501999-03-0808 March 1999 Informs That Licensee Reviewed NRC 990228 Ltr Issuing Exemption Requested Re Fire Rating of Raceway Fire Barriers in Open Turbine Bldg.Tabulated Summary of Util Comments & Marked Copy of NRC Ltr & SER Encl ML17355A2441999-03-0101 March 1999 Provides Update to Util Written Notices,Dtd 961120 & 970627 of Claim Involving Alleged Bodily Injury Arising Out of or in Connection with Use of Radioactive Matl at Units 3 & 4 ML17355A2431999-02-25025 February 1999 Informs That FPL Does Not Have Any Candidates from Turkey Point Scheduled to Participate in 990407,Generic Fundamentals Examination (GFE) ML17355A2301999-02-18018 February 1999 Forwards Semiannual Fitness for Duty Performance Data for Period of 980701-981231 for Turkey Point Units 3 & 4 ML17355A2361999-02-18018 February 1999 Forwards Tabulation of 1998 Occupational Exposure Data for Turkey Point,Units 3 & 4,per TS 6.9.1.2.a.Reactor Coolant Specific Activity Limits of 100/E-bar Mci Per Gram of Gross Radioactivity Were Not Exceeded During 1998 L-99-042, Forwards Rev 13 to Turkey Point Physical Security Plan,Per 10CFR50.54(p).Util Determined That Rev Does Not Decrease Safeguards Effectiveness of Plan.Encl Withheld,Per 10CFR2.790(a)(3)1999-02-18018 February 1999 Forwards Rev 13 to Turkey Point Physical Security Plan,Per 10CFR50.54(p).Util Determined That Rev Does Not Decrease Safeguards Effectiveness of Plan.Encl Withheld,Per 10CFR2.790(a)(3) ML17355A2341999-02-18018 February 1999 Provides Response to RAI Re GL 97-01, Degradation of Crdm/ CEDM Nozzle & Other Vessel Closure Head Penetrations. ML17355A2231999-02-0808 February 1999 Informs That Util Will Comply with Commitment with Respect to Units 3 & 4,in Response to Ja Zwolinski 990129 Ltr.Util Also Agrees to Incorporate Commitment Into Confirmatory Order Modifying License Effective Immediately Upon Issuance ML17355A2031999-01-29029 January 1999 Forwards Rev 3 to Turkey Point Nuclear Plant Recovery Plan. Rev Does Not Decrease Effectiveness of Plan ML17355A2171999-01-20020 January 1999 Forwards Listed ISI Repts for Turkey Point Unit 3,in Accordance with Provisions of ASME Code,Section XI ML17354B2241999-01-0606 January 1999 Forwards Annual 10CFR50.46 Rept Re Changes To,Or Errors Discovered in ECCS Evaluation Models,Or in Application of Such Models That Effect Peak Clad Temp Calculation ML17354B2081998-12-15015 December 1998 Informs That Fpl,In Cooperation with State of Fl & County Emergency Response Agencies,Will Conduct Exercise of Turkey Point Radiological Emergency Plan on 990210.Scenario Package Forwarded to Emergency Preparedness Section Chief,Region II ML17354B2091998-12-15015 December 1998 Forwards Price Anderson Guarantees Annual Financial Rept,Per 10CFR140.21.Exhibit 1 Submitted to Satisfy Annual Financial Reporting Requirement of 10CFR50.71(b) 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML17355A4601999-10-26026 October 1999 Forwards Revised Epips,Including Revs to 0-EPIP-1102, 0-EPIP-1212,0-EPIP-20110,0-EPIP-20111,0-EPIP-20132, 0-EPIP-20133 & 0-EPIP-20201,per 10CFR50.54(q) & 10CFR50, App E.Epip 0-EPIP-20107,has Been Deleted ML17355A4301999-10-0808 October 1999 Forwards Rev 16 of Updated Fsar.Info Accurately Reflects Plant Changes Made Since Previous Submittal.Rev Incorporates Changes Completed Between 971015 & 990408.Summary of Accuracy Review Changes & Instructions,Included ML17355A4461999-10-0404 October 1999 Notifies NRC of Change in Commitment to Perform Periodic Testing of Critical Welds & Parts on Special Lifting Devices IAW NUREG-0612.Use of Ae Technology Will Provide Same Level of Testing Quality as Did NDE Methods Noted in ANSI Std L-99-208, Forwards Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 971014-990408. Summary of PORV Actuations & Results of Plants SG Tube Insp,Which Occurred During That Time Included1999-10-0404 October 1999 Forwards Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 971014-990408. Summary of PORV Actuations & Results of Plants SG Tube Insp,Which Occurred During That Time Included ML17355A4291999-10-0404 October 1999 Forwards Response to NRC Telcon Questions Re License Amend Request Dtd 990727,proposing Amend on one-time Basis to Modify TS 3.8.1.1 & TS 3.4.3 & 3.5.2 to Extend Allowed Outage Time for EDG from 72 H to 7 Days ML17355A4251999-09-22022 September 1999 Forwards NRC Form 536 in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams, Issued 990820 ML17355A4111999-09-0909 September 1999 Informs That Thermo-Lag Upgrades for Fire Zones 47,54,113, 114,115,116,118,119,120 & 143 Completed on 990726,per GL 92-08 ML17355A4131999-09-0707 September 1999 Forwards Revised Relief Request 20 Re Requirement to Perform Exams as Required by IWL-2524 & IWL-2525,Table IWL-2500-1 for Exempt Tendon Insp,Per Recent Discussions with NRC ML17355A4141999-09-0202 September 1999 Documents That Util Has No Concerns or Challenges Related to site-specific Written Exam Administered at Plant on 990830 ML17355A4041999-08-23023 August 1999 Forwards Info to Support Assessment of Potential Risks Associated with Proposed Civil Aircraft Operations at Former Homestead Air Force Base to FP&L Turkey Point Nuclear Facility Units 3 & 4 ML17355A4071999-08-23023 August 1999 Informs That FPL Has Completed Review of Info Listed in Reactor Vessel Integrity Database,Version 2 & Found Listed Discrepancies,Re Closure of GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity. ML17355A4061999-08-23023 August 1999 Forwards Semiannual FFD Performance Rept for Period of Jan- June 1999,for Turkey Point Units 3 & 4.List of Events Reported & Summary of Mgt Actions Taken,Included ML17355A4001999-08-20020 August 1999 Informs That on 990722,util Determined Blind Specimen Submitted to Smithkline Beecham Clinical Labs on 990721,was Reported Back with Unsatisfactory Results.Attachment 1 Is Summary of Investigation of Unsatisfactory Performance ML17355A3941999-07-27027 July 1999 Submits Response to NRC AL 99-02, Operating Reactor Licensing Action Estimates, for FY00 & FY01 ML17355A3871999-07-16016 July 1999 Provides Supplement to FP&L Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML17355A3851999-07-14014 July 1999 Informs That Pages Missing from 1998 Annual Radiological Environ Operating Rept, Contain Info Unrelated to ODCM- Specified Sampling & Were Not Included as Part of Rept ML17355A3711999-07-0606 July 1999 Forwards Revised EPIPs 0-EPIP-20201, Maintaining Emergency Preparedness - Radiological Emergency Plan Training & 0-EPIP-20126, Off-Site Dose Calculations. with Summary of Changes ML17355A3591999-06-30030 June 1999 Forwards Turkey Point,Unit 4 ISI Rept. Listed Repts Are Encl.No Eddy Current Exams Scheduled for Unit 4 Steam Generators ML17355A3661999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 ML17355A3571999-06-28028 June 1999 Informs That Util Voluntarily Reporting Facility Readiness as Outlined in Suppl 1 to GL 98-01.Encl Is Y2K Readiness Disclosure for Units 3 & 4,reporting Status of Facility Y2K Readiness ML17355A3521999-06-18018 June 1999 Forwards Response to NRC 990415 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves. ML17355A3491999-06-0404 June 1999 Forwards Summary of Corrective Actions Implemented by FPL Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions. ML17355A3441999-05-27027 May 1999 Modifies FPLs Consent to Confirmatory Order to Reflect Resolution of Four Issues Identified as Pending in L-99-031 ML17355A3451999-05-24024 May 1999 Requests Waiver of 520 Hours (13 Wks) Required Parallel Watchstanding in Control Room Prior to License Application Submittal for W Conley ML17355A2921999-04-22022 April 1999 Forwards Rev 35 to Turkey Point EP & Revised EPIP 0-EPIP-20101, Duties of EC, Per Requirements of 10CFR50, App E & 10CFR50.54(q).Summary of Changes,Encl.Implementation Date for Both Documents Was 990330 ML17355A2891999-04-0909 April 1999 Forwards Relief Request 20, Exempt Tendon Insp, Requesting Relief from ASME Section XI Code,1992 Edition,Paragraph IWL-2521.1(c) Which Requires That Each Exempted Tendon Be Examined IAW IWL-2524 & IWL-2525.Approval Needed by 991001 ML17355A2861999-04-0505 April 1999 Forwards COLR for Turkey Point Unit 4,Cycle 18,IAW TS 6.9.1.7 ML17336A0681999-04-0101 April 1999 Expresses Support for FP&L Request for Waiver of Applicable Review Fees Upon FP&L Submittal of an Application for License Renewal for Turkey Point Units 3 & 4 ML17355A2751999-03-25025 March 1999 Informs NRC & Staff of Fp&Ls Plans to Submit License Renewal Application for Turkey Point Units 3 & 4 by End of Dec 2000 ML17355A2641999-03-19019 March 1999 Requests Changes to FPL Official Service List for Turkey Point,Units 3 & 4.Add s Franzone & Remove G Hollinger from All Correspondence ML17355A2651999-03-19019 March 1999 Forwards Annual Radioactive Effluent Release Rept for Jan-Dec 1998 & Rev 7 to ODCM for Gaseous & Liquid Effluents from Turkey Point,Units 3 & 4. ML17355A2621999-03-16016 March 1999 Forwards Special Rept as Result of Turkey Point Unit 3 End-of-Cycle 16 ISI of SG Tubes.Rept Summarizes Results of SG Tube ISI ML17355A2631999-03-12012 March 1999 Forwards FPL Decommissioning Fund Status Repts for St Lucie, Units 1 & 2 & Turkey Point,Units 3 & 4.Rept for St Lucie, Unit 2 Provides Status of Decommissioning Funds for All Three Owners of That Unit ML20204C6991999-03-10010 March 1999 Requests Amend to Turkey Point PSP to Modify Requirement to Post Security Officers to Provide Continuous Observation of Entire PA Perimeter in Event of Security Computer Failure. Change to Security Force Staffing Level Also Requested ML17355A2451999-03-0909 March 1999 Submits Info on FPL Current Levels of Nuclear Property Insurance,Per 10CFR50.54(w)(3) ML17355A2501999-03-0808 March 1999 Informs That Licensee Reviewed NRC 990228 Ltr Issuing Exemption Requested Re Fire Rating of Raceway Fire Barriers in Open Turbine Bldg.Tabulated Summary of Util Comments & Marked Copy of NRC Ltr & SER Encl ML17355A2441999-03-0101 March 1999 Provides Update to Util Written Notices,Dtd 961120 & 970627 of Claim Involving Alleged Bodily Injury Arising Out of or in Connection with Use of Radioactive Matl at Units 3 & 4 ML17355A2431999-02-25025 February 1999 Informs That FPL Does Not Have Any Candidates from Turkey Point Scheduled to Participate in 990407,Generic Fundamentals Examination (GFE) ML17355A2341999-02-18018 February 1999 Provides Response to RAI Re GL 97-01, Degradation of Crdm/ CEDM Nozzle & Other Vessel Closure Head Penetrations. L-99-042, Forwards Rev 13 to Turkey Point Physical Security Plan,Per 10CFR50.54(p).Util Determined That Rev Does Not Decrease Safeguards Effectiveness of Plan.Encl Withheld,Per 10CFR2.790(a)(3)1999-02-18018 February 1999 Forwards Rev 13 to Turkey Point Physical Security Plan,Per 10CFR50.54(p).Util Determined That Rev Does Not Decrease Safeguards Effectiveness of Plan.Encl Withheld,Per 10CFR2.790(a)(3) ML17355A2361999-02-18018 February 1999 Forwards Tabulation of 1998 Occupational Exposure Data for Turkey Point,Units 3 & 4,per TS 6.9.1.2.a.Reactor Coolant Specific Activity Limits of 100/E-bar Mci Per Gram of Gross Radioactivity Were Not Exceeded During 1998 ML17355A2301999-02-18018 February 1999 Forwards Semiannual Fitness for Duty Performance Data for Period of 980701-981231 for Turkey Point Units 3 & 4 ML17355A2231999-02-0808 February 1999 Informs That Util Will Comply with Commitment with Respect to Units 3 & 4,in Response to Ja Zwolinski 990129 Ltr.Util Also Agrees to Incorporate Commitment Into Confirmatory Order Modifying License Effective Immediately Upon Issuance ML17355A2031999-01-29029 January 1999 Forwards Rev 3 to Turkey Point Nuclear Plant Recovery Plan. Rev Does Not Decrease Effectiveness of Plan ML17355A2171999-01-20020 January 1999 Forwards Listed ISI Repts for Turkey Point Unit 3,in Accordance with Provisions of ASME Code,Section XI ML17354B2241999-01-0606 January 1999 Forwards Annual 10CFR50.46 Rept Re Changes To,Or Errors Discovered in ECCS Evaluation Models,Or in Application of Such Models That Effect Peak Clad Temp Calculation ML17354B2081998-12-15015 December 1998 Informs That Fpl,In Cooperation with State of Fl & County Emergency Response Agencies,Will Conduct Exercise of Turkey Point Radiological Emergency Plan on 990210.Scenario Package Forwarded to Emergency Preparedness Section Chief,Region II ML17354B2091998-12-15015 December 1998 Forwards Price Anderson Guarantees Annual Financial Rept,Per 10CFR140.21.Exhibit 1 Submitted to Satisfy Annual Financial Reporting Requirement of 10CFR50.71(b) ML17354B2061998-12-0909 December 1998 Informs That Request for Exemption Specified in Section II.B.3 Will Not Be Needed Re Fire Rating of Raceway Fire Barriers in Open Turbine Bldg ML17354B1981998-11-25025 November 1998 Forwards Scope & Objective for 1999 Plant Annual Emergency Preparedness Exercise.Objectives Developed in Conjunction with State & Local Govts.Exercise Scheduled for 990210 1999-09-09
[Table view] |
Text
ACCELERATED DISTRIBUTION DEMONSTPATION SYSTEM H
REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
CCESSION NBR:9105290195 DOC.DATE: 91/05/20 NOTARIZED: NO DOCKET FACIL:50-250 Turkey Point Plant, Unit 3, Florida Power and Light C 05000250 50-251 Turkey Point Plant, Unit 4, Florida Power and Light C 05000251 AUTH. NAME AUTHOR AFFILIATION GOLDBERG,J.H. Florida Power & Light Co.
RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)
SUBJECT:
Responds to NRC ltr re violations noted in Insp rept 50=250/91-11 & 50-251.Corrective actions:TP-644 revised to clarify reporting requirements & define temporary &
permanent configuration changes.
DISTRIBUTION CODE: IE01D COPIES RECEIVED:LTR ENCL SIZE:
TITLE: General (50'Dkt)-Insp Rept/Notice of Vio ation Re ponse NOTES'ECIPIENT 'RECIPIENT COPIES COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-2 PD 1 1 AULUCK,R 1 1 INTERNAL: AEOD 1 1 AEOD/DEIIB 1 1 AEOD/TPAB 1 1 DEDRO 1 1 NRR MORISSEAU,D 1 1 NRR SHANKMAN,S 1 1 NRR/DLPQ/LPEB10 1 1 NRR/DOEA/OEAB 1 1 NRR/DREP/PEPB9D 1 1 NRR/DRIS/DIR 1 1 NRR/DST/DIR SE2 1 .1 NRR/PMAS/ILRB12 1 1 NUDOCS-ABSTRACT 1 1 OE DIR 1 1 QE~ZEE
'ILE OGC/HDS3 RGN2 01 1
1 1
1 1
EXTERNAL EG&G/BRYCE i J H ~ ~ 1 1 NRC PDR 1 1 NSIC 1 1 NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOiil Pl-37 (EXT. 2%79) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED: LTTR 22 ENCL 22
0 P.O. Box14000, Juno Beach, FL 33408-0420 MAY. 2 0 1991 L-91-139 10 CFR 2.201 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Gentlemen:
Re: Turkey Point Units 3 and 4 Docket No. 50-250 and 50-251 Reply to Notice of Violation NRC Ins ection Re ort 91-11 Florida Power and Light Company has reviewed the subject inspection report and pursuant to 10 CFR 2.201, the required response is attached.
If there are any questions please contact us.
Very truly yours, J. H. Goldberg President Nuclear Division JHG/DPS/ds Attachment cc: Stewart D. Ebneter,.Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, Turkey Point Nuclear Plant Ip g()g2C/0 $ 9 i Y.l 052 gDi"iCi' i;'!i )00>~<0 p) )p PDR g
a', FPL Group company
e ATTACHMENT REPLY TO A NOTICE OF VIOLATION RE: Turkey Point Units 3 and,4 Docket Nos. 50-250 and 50-251 NRC Inspection Report 91-11 FINDING "Technical Specification (TS) 6.8.1 requires that written procedures be established, implemented, and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978, and Sections 5.1 and 5.3 of ANSI N18.7-1972. Section 5.1.2 of ANSI N18.7 1972 requires that procedures be followed.
1~ Procedure TP-644, Dual Unit Outage Configuration Control Notification, paragraph 3.1.3.2, requires a configuration control notice and a marked up figure, attachment F through J, notifying the Plant Supervisor Nuclear of changes in plant configuration which are expected in the next 24 to 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />.
Contrary to the above, on March 11, 1991, TP-644 attachments F through J, which are located in the control room, had not been marked up to reflect the removal of the 3B 4KV bus at 12:23 pm on March 8, 1991 and the removal of the 4B 4KV bus at 12:40 pm on March 7, 1991.
2 ~ Procedure ASP-23, General Installation Procedures for Electrical Raceways and Supports, paragraph 5.1.5 requires that the Project Field'Engineer be responsible for ensuring all supports required are listed on attachment A of ASP-23.
Procedure ASP-34, Preparation of Process Sheets and Installation Lists, paragraph 5.4 states that the Project, Field Engineer is responsible for ensuring full implementation of Plant Change/Modification requirements by the preparation, review, approval, and revision of all installation lists.
Contrary to the above, on March 5, 1991, installation list 0466/88-418, Revision 0, and,its associated attachment A had not been revised to reflect the requirement to reinstall temperature switch TS 6537A and its associated mounting support. TS 6537A and its mounting support had been previously removed on approximately February 28, 1991, to accommodate vital area barrier rework per Plant Change/Modification 88-418."
l~
0
NOV Response 91-11 Page 2 of 3
. 1. FPL concurs with the finding.
- 2. Example 1:
The reason for the event reported in Example 1 was inadequate procedural guidance in TP-644.
TP-644, Section 4.2.5 stipulates that the notification of Operations is necessary "... to alert the operations staff to changes in configuration ...". Since this event involved only the temporary removal of two power sources, this was thought to not constitute a configuration change.
-The change would therefore, not require a.report to Operations.
The following requirements are also in TP-644:
Section 3.1.3.2, requires, "... a marked up figure, .
attachment F through J, ... of changes in plant configuration which are expected Section 2.2.7, requires, "... a mark up of the drawings shown on attachment H and J ... when ever changes to the Spent Fuel Cooling Flowpaths are anticipated The definition of an applicable configuration change was not clearly written in TP-644 to include temporary power removals. Therefore, the root cause of this violation was inadequate procedural guidance.
Example 2:
The reason for the event reported in Example 2 was cognitive personnel error by contractor non-licensed personnel.
Contrary to the requirements of procedures ASP-23 and ASP-34, the Contractor Field Engineer failed to adequately.
update installation list 0466/88-418. This failure resulted in inadequate documentation of the temporary removal of a temperature sensor and its mounting bracket for a security barrier modification.
3 ~ Corrective steps which have been taken and the 'results achieved:
Example 1:
- a. TP-644 was revised on April 12, 1991, to clarify the reporting requirements and define temporary and permanent configuration changes.
0 NOV Response 91-11 Page 3 of 3
- b. Attachments F through J to TP-644, were marked up to reflect the removal of the 3B 4KV bus and the removal of the 4B 4KV bus on March 11, 1991.
Example 2:
a ~ All Contractor Field Engineers, Contractor Superintendents and FPL Construction Supervisors have been trained on the proper use of Installation Lists and Process Sheets. This training stressed the importance of work controls for any Plant Modification Work Package.
- b. The Contractor Field Engineering group performed plant walkdowns that showed that this event was an isolated case and that no other similar conditions existed.
c Installation list 0466/88-418, Revision 0, and its associated attachment A were revised to reflect
~
the requirement to reinstall temperature switch TS 6537A and its associated mounting support.
- d. These corrective actions were complete by March 26, 1991.
4 ~ Corrective steps which will be taken to avoid further violations include:
Example 1:
- a. No additional corrective actions are considered to be necessary.
Example 2:
- a. Plant Management requested that FPL Quality Assurance (QA) perform an audit of construction practices and configuration control. The audit has been completed. The audit established that construction configuration control practices are satisfactory. I
- 5. The date when full compliance will be achieved:
a~ Full compliance for Example 1 was achieved on March 11, 1991.
- b. Full compliance for Example 2 was achieved on March 26, 1991.
0