05000293/LER-2015-001, Regarding Loss of 345KV Power Resulting in Automatic Reactor Scram During Winter Storm Juno
| ML15097A259 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 04/01/2015 |
| From: | Noyes D Entergy Nuclear Operations |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LER 15-001-00 | |
| Download: ML15097A259 (9) | |
| Event date: | |
|---|---|
| Report date: | |
| Reporting criterion: | 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(ix)(A) 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(iv)(B), System Actuation |
| 2932015001R00 - NRC Website | |
text
" Entegy-Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 April 1, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555
SUBJECT:
Licensee Event RZeport 2015-001-00, Loss of 345KV Power Resulting in Automatic Reactor Scram During Winter Storm Juno Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket No.: 50-293 License No.: DPR-35 LETTER NUMBER:
2.15.024
Dear Sir or Madam:
The enclosed Licensee Event Report (LER) 2015-001-00, Loss of 345KV Power Resulting in Automatic Reactor Scram During Winter Storm Juno, is submitted in accordance with 10 CFR 50.73.
As specified by NUREG-1 022, the delay in submittal of the LER was discussed with the NRC Region I office on March 30, 2015.
This letter contains no commitments.
Please do not hesitate to contact Mr. Everett P. Perkins, Jr. (508) 830-8323, if there are any questions regarding this submittal.
Sincerely, David E. Noyes Director, Regulatory and Performance Improvement : Licensee Event Report 2015-001-00, Loss of 345KV Power Resulting in Automatic Reactor Scram During Winter Storm Juno (6 pages)
PNPS Letter 2.15.024 Page 2 of 2 cc:
Mr. Daniel H. Dorman Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-2713 Ms. Nadiyah S. Morgan, Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-8-F2 11555 Rockville Pike Rockville, MD. 20852 USNRC Senior Resident Inspector Pilgrim Nuclear Power Station Letter Number 2.15.024 Licensee Event Report 2015-001 -00 Loss of 345KV Power Resulting in Automatic Reactor Scram During Winter Storm Juno (6 Pages)
NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0104 EXPIRES: 0113112017 (01-2014)
Estimated burden per response to comply with this mandatory collection request: 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br />.
Reported lessons learned are incorporated into the licensing process and fed back to industry.
i.*
Send comments regarding burden estimate to the FOIA, Privacy and Information Collections LICENSEE E(LER)
Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by EVENT REPORT internet e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
- 3. PAGE Pilgrim Nuclear Power Station 05000293 1 OF 6
- 4. TITLE Loss of 345KV Power Resulting in Automatic Reactor Scram During Winter Storm Juno
- 5. EVENT DATE
- 6. LER NUMBER
- 7. REPORT DATE
- 8. OTHER FACILITIES INVOLVED MONTH DAY YEAR YEAR SEQUENTIAL REV DAY YEAR CITYNAME DOCKET NUMBER NUMBER NO.
N/A N/A 01 27 2015 1
20 1
ACIT NAME DOCKET NUMBER 2015-001 00 03 30 2
N/A
- 9. OPERATING MODE
- 11. THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR §: (Check all that apply)
H 20.2201(b) 20.2203(a)(3)(i) 50.73(a)(2)(i)(C) 50.73(a)(2)(vii)
N H 20.2201(d) 20.2203(a)(3)(ii) 50.73(a)(2)(ii)(A) 50.73(a)(2)(viii)(A)
H 20.2203(a)(1)
E 20.2203(a)(4) 50.73(a)(2)(ii)(B)
D 50.731a)(2)(viii)(g) 20.2203(a)(2)(i) 50.36(c)(1)(i)(A)
K 50.73(a)(2)(iii)
[] 50.73(a)(2)(ix)(A)
- 10. POWER LEVEL K 20.2203(a)(2)(ii)
K] 50.36(c)(1)(ii)(A)
[ 50.73(a)(2)(iv)(A)
K] 50.73(a)(2)(x)
K] 20.2203(a)(2)(iii)
K 50.36(c)(2)
K] 50.73(a)(2)(v)(A)
E] 73.71(a)(4) 52 E] 20.2203(a)(2)(iv)
K] 50.46(a)(3)(ii) 50.73(a)(2)(v)(B)
K] 73.71(a)(5)
K] 20.2203(a)(2)(v)
K] 50.73(a)(2)(i)(A)
K 50.73(a)(2)(v)(C)
K] OTHER Specify in Abstract betow or in 20.2203(a)(2)(vi) 50.73(a)(2)(i)(B) 50.73(a)(2)(v)(D) 12. LICENSEE CONTACT FOR THIS LER LICENSEE CONTACT TELEPHONE NUMBER (Include Area Code)
Mr. Everett P. Perkins, Jr. - Regulatory Assurance Manager 508-830-8323MANU-REPORTABLE MANU-REPORTABLE
CAUSE
SYSTEM COMPONENT FACTURER TO EPIX
CAUSE
SYSTEM COMPONENT FACTURER TO EPIX B
FK BU M-YRT B
SB RV T020 Y
LD CMP A544 Y
- 14. SUPPLEMENTAL REPORT EXPECTED
- 15. EXPECTED MONTH DAY YEAR SUBMISSION D YES (If yes, complete 15. EXPECTED SUBMISSION DATE)
NO DATE ABSTRACT (Limit to 1400 spaces, i.e., approximately 15 single-spaced typewritten lines)
On Tuesday January 27, 2015, at 0402 hours0.00465 days <br />0.112 hours <br />6.646825e-4 weeks <br />1.52961e-4 months <br />, while in the process of lowering reactor power, with the reactor in the RUN mode at 52 percent core thermal power, Pilgrim Nuclear Power Station (PNPS) experienced a loss of 345KV power resulting in a load reject and an automatic reactor scram. The loss of 345KV power was due to faults from flashovers in the PNPS switchyard. All control rods fully inserted.
The Emergency Diesel Generators had been previously started and were powering safety-related buses A5 and A6. The plant stabilized in Hot Shutdown. At the time of the event a significant winter storm (Juno) was buffeting Southern New England.
The root cause of the event is that the design of the PNPS switchyard does not prevent flashover when impacted by certain weather conditions experienced during severe winter storms. A modification of the switchyard is planned to address the susceptibility of the PNPS switchyard to flashovers during severe winter storms.
This event posed no threat to public health and safety.
NRC FORM 366 (01-2014)U.S. NUCLEAR REGULATORY COMMISSION (01-2014)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE SEQUENTIAL REV NUMBER NO.
Pilgrim Nuclear Power Station 05000293 2
20F6 2015 001 00 BACKGROUND Pilgrim Station Nuclear Power Station (PNPS) is connected to the transmission lines through a 345KV ring bus located within the station's switchyard. The 345KV ring bus connects the output of the main transformer (GSU), the startup transformer (SUT), Line 355, and Line 342. There are four gas circuit breakers connecting PNPS's 345KV ring bus sections: ACB-1 02, ACB-1 03, ACB-104 and ACB-1 05.
The Line 355 bus connects PNPS to NSTAR (Eversource) Carver Station and is connected to ACB-102 and ACB-1 05. The Line 342 bus connects PNPS to the Canal Power Plant's Switchyard in Sandwich, MA and to Auburn Street Station Switchyard in Whitman, MA. The Canal Switchyard is owned and operated by NSTAR and Auburn Street Station Switchyard is owned and operated by National Grid. ACB-103 and ACB-104 connect the Line 342 bus to the SUT and GSU bus. The 345KV system is the PNPS preferred off-site power source via the SUT.
The 345KV ring bus design locates the power transmission lines such that a failure of any one line will not result in the loss of the other line. Specifically, with both transmission lines in service, a failure of either 345KV line will not result in a main generator trip, a SUT trip, or a failure of the other 345KV line. Either of the two 345KV lines is capable of carrying full station output and supplying station loads via the SUT.
The 345KV protective relay system is designed and coordinated to isolate system faults and minimize the impact to the overall transmission system. The protective systems are comprised of a primary and secondary protection scheme and are divided into four zones of protection.
The main transformer bus (isolated by ACB-104 and ACB-105)
- The SUT bus (isolated by ACB-102 and ACB-103)
- Line 355 bus (isolated by ACB-102 and ACB-105 and Carver Station)
- Line 342 bus (isolated by ACB-103 and ACB-104 and Auburn Street Station and Canal Station)
When ACB-104 and ACB-105 open, the main transformer is isolated from the 345KV transmission system thus resulting in a generator load reject event.
In addition to the preferred 345KV off-site power lines, PNPS has a secondary off-site power source, a 23KV line from NSTAR's Manomet Substation that provides power to a shutdown transformer (SDT).
During normal station start-ups and shutdowns, the station's 4160V demands are supplied by the SUT. Once the station main generator is synchronized to the 345KV transmission system, the station unit auxiliary transformer (UAT) supplies all station 4160V demands, with the SUT maintained in standby, ready to provide 4160V power if necessary.
In anticipation of a major snow storm impacting the site on January 26, 2015, Operations entered Procedure 2.1.37 (Coastal Storm Preparations). Procedure 2.1.42 (Operation During Severe Weather) and EN-FAP-EP-010 (Severe Weather Response). During the storm on January 26-28, 2015, meteorological instruments at PNPS recorded sustained wind speeds between 37 and 61 mph with the wind direction predominantly from the ocean toward the switchyard.
1U.S. NUCLEAR REGULATORY COMMISSIO (01-2014)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE YEAR SEQUENTIAL REV NUMBER NO.
Pilgrim Nuclear Power Station 05000293 3 OF 6 2015 001 00
EVENT DESCRIPTION
On 1/25/15 with PNPS operating at 100 percent power, the National Weather Service (NWS) issued a blizzard warning for winter storm Juno. Wind speed of 40 mph sustained with 50 mph gusts and snow fall of more than two inches/hour were predicted. PNPS entered procedures 2.1.42, Operation During Severe Weather and 2.1.37, Coastal Storm Preparations and Actions, and started making preparations for storm arrival.
Preparations were completed on 1/26/15. At 0132 hours0.00153 days <br />0.0367 hours <br />2.18254e-4 weeks <br />5.0226e-5 months <br /> on 1/27/15, the 345 KV Line 355 bus faulted (for the first of five times) whereupon Operations personnel commenced a reactor shutdown at 0134. The Emergency Diesel Generators (EDGs) were started and loaded with the safety related buses. Reactor Protection System (RPS) bus "A" was placed on the backup power supply. At 0235 hours0.00272 days <br />0.0653 hours <br />3.885582e-4 weeks <br />8.94175e-5 months <br />, the Line 355 bus faulted for the final time at which time the Line 355 breakers at both Carver and PNPS were left tripped open. This configuration left PNPS with one transmission line connected to the grid.
At 0402 hours0.00465 days <br />0.112 hours <br />6.646825e-4 weeks <br />1.52961e-4 months <br /> with the reactor at 52 percent power, Line 342 faulted resulting in a trip of ACBs 103 and 104.
This isolated PNPS from the grid causing a generator load reject and automatic reactor scram. All control rods were verified fully inserted. The non-safety related back-up diesel driven air compressor, K-1 17 failed to start on instrument air system low pressure. K-1 17 failure to start was due to a battery low voltage condition.
Primary Containment Isolation System (PCIS) Group II - Sampling Systems, Group VI - Reactor Water Cleanup (RWCU) System and Reactor Building Isolation System (RBIS) isolations occurred as expected.
Reactor water level was maintained by the Reactor Core Isolation Cooling (RCIC) system and reactor pressure was maintained by the High Pressure Coolant Injection (HPCI) System. Once normal reactor level and pressure were restored, operators commenced a depressurization to the cold condition. At 0641 a Non-Emergency Notification to the NRC of the RPS and safety system actuations was made. (EN 50769)
During the reactor vessel depressurization, the High Pressure Coolant Injection (HPCI) System was removed from service prior to reaching the low pressure automatic isolation setpoint (Approx. 80 psig). Shortly after system shutdown, the HPCI Gland Seal Condenser Blower Overload Alarm was received. The HPCI System was declared inoperable. At 1656 hours0.0192 days <br />0.46 hours <br />0.00274 weeks <br />6.30108e-4 months <br />, a Non-Emergency Notification to the NRC of the HPCI System inoperability was made. (EN 50771) Subsequent analysis determined that the cause of the overload condition was due to the inability to remove water from the condenser with the HPCI pump discharge piping isolated, since the air operated valves that would normally open to remove water were unavailable due to the loss of instrument air when K-1 17 failed to start. The analysis also determined that HPCI would have been available to perform pressure control or restore reactor water level if required. Upon opening of a valve in the HPCI discharge piping flow path, the HPCI Gland Seal Condenser Hotwell Pump would restore the condenser level to normal.
The depressurization continued using Main Steam Safety Relief Valves (SRVs) for pressure decrease and Core Spray Loop "B" to maintain reactor vessel water inventory. When SRV RV-203-3C was manually opened, the SRV did not appear to open or failed to open fully. Part 21 Event Report 50900 documents this condition. Post-event removal and disassembly of the valve revealed damaged parts in the main stage assembly. Further investigation by the valve manufacturer is required to determine the cause.
Core Spray Loop "A" discharge header low pressure alarm was received due to the unavailability of the non-safety related keep-fill system due to the loss of power to the non-safety related buses. Operators recognized the potential for voiding within the piping. To preclude the potential for damage of the piping due to water hammer pressure pulses, the Core Spray Loop "A" was not used during this event.U.S. NUCLEAR REGULATORY COMMISSION (01-2014)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE YEAR SEQUENTIAL REV NUMBER NO.
Pilgrim Nuclear Power Station 05000293 4 OF 6 2015 001 00 At 1626 hours0.0188 days <br />0.452 hours <br />0.00269 weeks <br />6.18693e-4 months <br />, Residual Heat Removal (RHR) Loop "B" was placed in service in the shutdown cooling mode.
At 1658 hours0.0192 days <br />0.461 hours <br />0.00274 weeks <br />6.30869e-4 months <br />, the reactor moderator temperature was less than 212 degrees F.
Prior to restoration of offsite power to the switchyard, the switchyard bus insulators and bushings were cleaned of snow and salt contamination to prevent further flashovers.
On January 29, 2015 at 1643 hours0.019 days <br />0.456 hours <br />0.00272 weeks <br />6.251615e-4 months <br />, the loss of 345KV power condition was cleared when offsite power was restored to the switchyard and the startup transformer.
CAUSE OF THE EVENT
The design of the PNPS switchyard does not prevent flashover when impacted by certain weather conditions experienced during severe winter storms.
CONTRIBUTING CAUSES
Previous corrective actions to preclude recurrence taken in response to LER 2008-006-00, Automatic Scram Resulting From Switchyard Breaker Fault During Winter Storm, LER 2008-007-00, Momentary Loss of all 345kv Off-Site Power to the Startup Transformer from Switchyard Breaker Fault, and LER 2013-001-00, Loss of Offsite Power and Reactor Scram, did not prevent recurrence. Previous cause analyses of loss of 345KV transmission lines failed to fully analyze all available weather related data to understand precisely what weather related attributes (and characteristics) were necessary to guide operators in making decisions to maneuver the plant to shutdown prior to or during snow storms with the potential for creating flashovers. As a result, Procedure 2.1.42 failed to guide operators to the correct actions necessary to preclude the automatic scram during winter storm Juno.
Previous cause analyses did not effectively use repeat events to evaluate design aspects to effectively communicate the risk of the current design.
CORRECTIVE ACTIONS
The switchyard insulators and bushings were cleaned prior to return of the switchyard to service.
The following corrective actions are planned to correct / preclude recurrence:
Implement a switchyard design change to minimize switchyard flashovers during snow storms Revise procedure PNPS 2.1.42 to provide additional guidance including the requirement to place the reactor in cold shutdown prior to the anticipated arrival of certain severe winter storms Additional corrective actions are captured in the corrective action program in Condition Report CR-PNP-2015-00558.U.S. NUCLEAR REGULATORY COMMISSIOIN (01-2014)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE SEQUENTIAL REV NUMBER NO.
Pilgrim Nuclear Power Station 05000293 50F6 2015 001 00..
SAFETY CONSEQUENCES
The Loss of Coolant Accident (LOCA) design basis accident (DBA) analyzed in the Updated Final Safety Analysis Report (UFSAR) assumes coincident loss of both 345 KV and 23 KV (preferred and secondary) sources (LOOP). The design imposes a 10 second delay in re-energizing the 4160V Emergency Buses required to mitigate the DBA to allow the EDG to start and reach voltage. This delay also allows the operating motors to coast down to a stop to prevent being repowered out of phase. In cases where coincident loss of an EDG presents a bounding condition, the affected safety bus is not assumed to be picked up by the shutdown transformer (SDT). The bounding condition in which all off-site power and onsite AC (EDGs) sources would be lost is a Station Blackout (SBO) transient event (10 CFR 50.63). PNPS is designed to recover from the SBO event by having a separate SBO diesel generator capable of providing power to the required safety buses to shutdown the plant and maintain it in a safe condition. Thus, the loss of 345KV power experienced by PNPS is within the analyzed conditions.
During the event, the EDGs, RHR, Core Spray Loop "B", HPCI, and RCIC were available. These systems provided capability to supply makeup water to the vessel and ensured adequate core cooling was maintained.
During and following the storm, operators were able to maintain safe shutdown conditions (reactivity control, reactor water inventory, decay heat removal, etc.). While loss of power to non-safety related spent fuel pool cooling was a key consideration, time-to-boil never became an overriding concern with respect to reenergizing buses and there was no recently irradiated spent fuel in the pool. The most recent recently irradiated fuel was almost 21 months old, and the time to boil was approximately seven days upon loss of fuel pool cooling. The spent fuel pool temperature remained less than 105 degrees F.
The Emergency Diesel Generators were started and loaded with the safety related buses prior to the loss of 345KV power. The amount of fuel onsite initially was sufficient to operate the EDGs for 7 days (under LOCA conditions) and the SBO DG was always available.
Throughout these events there was no adverse impact on the public health or safety.
REPORTABILITY
This report is submitted in accordance with:
- 10CFR50.73(a)(2)(iv)(A)- System Actuation,
- 10CFR50.73(a)(2)(v)(B) and 10CFR50.73(a)(2)(v)(D) - Event or Condition that Could Have Prevented Fulfillment of a Safety Function.
The Reactor Protection System, Containment Isolation System, High Pressure Coolant Injection System, and Low Pressure Core Spray System are included in 10CFR50.73(a)(2)(iv)(B). The Reactor Protection System and Containment Isolation System automatically actuated. The High Pressure Coolant Injection System and Low Pressure Core Spray System were manually actuated.
Since High Pressure Coolant Injection System is a single train system to fulfill a safety function, the inoperability was reported in accordance 1 OCFR50.73(a)(2)(v)(B) and 1 OCFR50.73(a)(2)(v)(D).U.S. NUCLEAR REGULATORY COMMISSION (01-2014)
LICENSEE EVENT REPORT (LER)
CONTINUATION SHEET
- 1. FACILITY NAME
- 2. DOCKET
- 6. LER NUMBER
- 3. PAGE YEAR SEQUENTIAL REV NUMBER NO.
Pilgrim Nuclear Power Station 05000293 j 6OF6 2015 001 00 PREVIOUS EVENTS The most recent loss of 345KV power events at PNPS reported as LERs are as follows:
LER 2008-006-00, Automatic Scram Resulting from Switchyard Breaker Fault During Winter Storm, dated February 12, 2009.
LER 2008-007-00, Momentary Loss of all 345KV Off-Site Power to the Startup Transformer from Switchyard Breaker Fault, dated February 12, 2009.
LER 2013-001-00, Loss of Offsite Power and Reactor Scram due to Winter Storm Nemo, dated April 4, 2013.
ENERGY INDUSTRY IDEBTIFICATION SYSTEM (EIIS) CODES COMPONENTS CODES Switchyard Bus BU Relief Valve RV Compressor CMP SYSTEMS Switchyard System FK Main Steam System SB High Pressure Coolant Injection System BJ\\
Low Pressure Core Spray System BM Instrument Air System LD ESF Actuations (RPS,PCIS, RBIS)
JE REFERENCES Condition Report CR-PNP-2015-0558, Loss of Offsite Power and Reactor Scram Condition Report CR-PNP-2015-0559 - K1 17 air compressor failed to start following unit scram.
Condition Report CR-PNP-2015-0561 - SRV-3C appears to have not opened fully during manual operation.
Condition Report CR-PNP-2015-0563, HPCI Overload alarm received during HPCI operation - Observed water emitting from P-223, Gland Seal Condenser Blower