April 18, 1983 DISTRIBUTION Docket ELJordan ORB Reading JMTaylor NRC PDR ACRS (10)
Docket No. 50-206 Local PDR SEPB LS05-83-04039 NSIC SVarga DCrutchfield DVassallo WPaulson RClark' HSmith JStolz LICENSEE:
SOUTHERN CALIFORNIA EDISON COMPANY OELD FMiraglia WRussell FACILITY: San Onofre Nuclear Generating Station, Unit No. 1 DEisenhut
SUBJECT:
SUMMARY
OF APRIL 13, 1983 MEETING RPurple On April 13, 1983, members of the NRC staff met with representatives of Southern California Edison Company (SCE) and San Diego Gas and Electric Company. The purpose of the meeting was to discuss SCE's plans for (1) managing plant retrofit items, and (2) early return to power. Enclosure 1 is a list of attendees. Enclosure 2 are the handouts provided by SCE.
SCE discuss!ed the projected retrofit costs for San Onofre Unit No. 1.
The licensee is seeking senior NRC management endorsement for their integrated implementation plan that is designed to spread-out retrofit items over several reload outages. The proposed plan would extend through the Cycle XII outage (April through June 1990). The implementa tion plan is based on operating the plant on an 18 month fuel cycle and then implementing retrofit items during a three-month outage.
The NRC staff indicated that it supports an integrated implementation approach and that the licensee should submit a formal proposal.
SCE representatives also discussed their plan for early return to power.
The general provisions of the plan are:
- 1. Structures and systems whose failure could cause an accident will be available following a 0.67g earthquake.
- 2. Structures and systems requfred to get to a safe cold shutdown will be available following a 0.67g earthquake.
D"
%1V
- 3. Structures and systems not rqquired to get to a safe cold shutdown will be deferred.
8 9304220387 830418 PDR ADOCK 05000206 P
PDR OFFICE 4...
SURNAME.
DATE NRC FORM 318 (10-80) NRCM 0240 OFFICIAL RECORD COPY USGPO: 1981-335-960
-2 April 18, 1983 The NRC staff raised the question whether some Of the backfits other than seismic upgrades would provide a greater increment of safety.
The staff and the licensee plan to investigate this question.
Original signed by/
Walter A. Paulson, Project Manager Operating Reactors Branch #5 Division of Licensing
Enclosures:
As stated cc w/enclosures:
See next page DL.*
5
- 0RB#5 OFFICE a~..
I SURNAME SURNAME.
NRC FORM 318 (10-80) NRCM 0240 OFFICIAL RECORD COPY USGPO: 1981-335-960
cc Charles R. Kocher, Assistant Mr. R. Dietch General Counsel Vice President James Beoletto, Esquire Nuclear Engineering and operations Southern California Edison Company Southern California Edison Company Post Office Box 800 2244 Walnut Grove Avenue Rosemead, California 91770 Post Office Box 800 Rosemead, California 91770 David R. Pigott Orrick, Herrington & Sutcliffe 600.Montgomery Street San Francisco, California 94111 Harry B. Stoehr San Diego Gas & Electric Company MrP.
- 0. Box 1831 San Diego, California 92112 Resident Inspector/San Onofre NPS d/o U. S. NRC PsP.
- 0. Box 4329 San Clemente, California 92672 Mayor City of San Clemente San Clemente, California 92672 Chairman Board of Supervisors County of San Diego San Diego, California 92101 eCalifornia Department of Health ATTN:
Chief, Environmental Radiation Control Unit
- Radiological Health Section 714 P Street, Room 498 Sacramento, California 95814 U. S. Environmental Protection Agency Region IX Office ATTN:
Regional Radiation Representative BoaFreemont Street San Francisco, California 94111 Robert H. Engelken, Regional Administrator Nuclear Regulatory Commission, Region V 1450 Maria Lane Walnut Creek, California 94596
ENCLOSURE 0
9 APRIL 13, 1983 MEETING NRC STAFF AND SOUTHERN CALIFORNIA EDISON CO. &
SAN DIEGO GAS & ELECTRIC CO.
ATTENDANCE LIST Name Affiliation W. A. Paulson NRC R. Dietch SCE J. G. Haynes SCE W. T. Russell (AM only)
NRC F. J. Miraglia (AM only)
NRC K. P. Baskin SCE D. K. Nelson SCE R. W. Krieger SCE D. Crutchfield NRC Lou Bernath SDG&E D. G. Eisenhut (PM only)
NRC R. Purple (PM only)
NRC
ENCLOS.JPF 2 0
PLAN FOR MANAGING PLANT RETROFIT SAN ONOFRE UNIT 1
SUMMARY
G NEED FOR INTEGRATED PLAN O
INTEGRATED SCHEDULE INITIAL SCHEDULE SAFETY SIGNIFICANCE
NEED TO ESTABLISH INTEGRATED PROGRAM FOR MODIFICATIONS O
MANAGE RESOURCES EFFICIENTLY CAPITAL EXPENDITURES CAPACITY FACTOR MANPOWER O
UNDERSTAND TOTALITY OF WORK REGULATORY COMMITMENTS STATION BETTERMENT O
PLAN TO ACHIEVE STABILITY AND PREDICTABILITY OF PROCESS
TORNADO & HIGH ENERGY LINE BREAKS 900 FIRE PROTECTION, SINGLE FAILURE CRITERIA 800.
FIRE PROTECTION, NEW o
FEEDWTR PUMPS, E3V VALVE ACTUATOR 700 Ix SEISMIC UPGRADE, DRAWING VERIFICATION, ELECT. EQPT.
600w QUALIFICATION w
cc TMI, FIRE PROTECTION 500 SPHERE ENCLOSURE, TMI, 400 STEAM GENERATOR SLEEVING 300 Z Forecast BASE PLANT 200 Committed 100 SONGS 1 0
RETROFIT COSTS O
o (INCLUDING MEMOS)
SONGS1 ANNUAL CAPACITY FACTORS rq
"~~~~...
H H H H V A............
4G q1 17
~7
'175 ur hI
~
90 1
.W
.I.........
YEAR~~
PRVPRAIQ
UNDERSTAND TOTALITY OF WORK 0
EXISTING REGULATORY COMMITMENTS SEISMIC UPGRADE ENVIRONMENTAL QUALIFICATION FIRE PROTECTION APPENDIX R SYSTEMATIC EVALUATION PROGRAM BACKPIT DEDICATED SAFETY INJECTION AND FEEDWATER SYSTEMS INSTRUMENTATION SYSTEM FOR DETECTION OF INADEQUATE CORE COOLING CONTROL ROOM DESIGN REVIEW SAFETY PARAMETER DISPLAY SYSTEM REGULATORY GUIDE 1.97 INSTRUMENTATION AUXILIARY FEEDWATER SYSTEM SAFETY GRADE UPGRADE AND THIRD TRAIN CONTROL ROOM HABITABILITY, HVAC UPGRADE POST ACCIDENT SAMPLING SYSTEM OXYGEN AND CHLORIDE MONITORING PARTICULATE EFFLUENT MONITORING SYSTEM PLATE-OUT CONCERN HEAVY LOADS LIFT RIGS AND TURBINE DECK SPALLING PROTECTION SYSTEM VOLTAGE DEGRADATION 4 KV UNDERVOLTAGE RELAYS RADIOLOGICAL EFFLUENT MONITORING SYSTEMS PURGING AND VENTING SYSTEM VALVE REPLACEMENT AND DEBRIS SCREEN PRESSURIZER PORV BLOCK VALVES ECCS SINGLE FAILURE UPGRADE DIESEL GENERATOR FANS SIS ANNUNCIATOR WINDOWS ISOLATION VALVES FOR STEAM GENERATOR SAMPLE AND BLOWDOWN LINES CONTAINMENT ISOLATION RELAYS SIS PUMP SUCTION NOZZLES G & W (EFCOMATIC)
ACTUATORS REGULATED INSTRUMENT BUSES NITROGEN SUPPLY FOR PORV'S AND FCV'S 1115 D, E AND F UPGRADE TO SAFETY GRADE CV 525 AND 527 VALVE SEATS SEPARATE POWER SUPPLY TO LETDOWN ISOLATION VALVES INLAND METEOROLOGICAL TOWER SOLIDIFIED RESIN STORAGE BUILDING AND TRANSPORTATION EQUIPMENT WASTE GAS DECAY TANK SYSTEM CORRODED SAFETY RELATED AND NON-SAFETY RELATED PIPING COMPONENT COOLING WATER HEAT EXCHANGER SERVICEABILITY SV-99 REPLACE ACTUATION TO RELIABLE CHANNEL TURBINE LAB DRAINS CONDENSATE STORAGE TANK FLOODING POTENTIAL HEALTH PHYSICS BUILDING REACTOR COOLANT PUMP TRIP
0 STATION BETTERMENT MODIFICATION TO THE 125-VDC SYSTEM UPGRADE SAFETY RELATED AND NON-SAFETY RELATED POWER SUPPLY SALTWATER COOLING VALVES POV 1-10 ELECTRICAL POWER BUSES CHEMICAL AND VOLUME CONTROL SYSTEM VALVES MOV-LCV-1100 B, C & D STEAM PIPE EROSION CONTROL ROOM IMPROVEMENT BATTERY NO. 1 CATHODIC PROTECTION LEADS UPGRADE BALANCE CF SAFETY RELATED SNUBBERS REPLACE SIS RECIRCULATION LINE BORON ANALYZER PROCESS PH METER SLUDGE REMOVAL TRAP INLET PRESSURE GAUGES ON RHR PUMPS CONTAINMENT SUMP LEVEL CONTROLLER PERMANENT DOMESTIC WATER LINE TO UNIT 1 DEMINERALIZED WATER CROSS TIE TELECOMMUNICATIONS NORTH GUARD TOWER VIDEO STATION SERVICE TRANSFORMER SYSTEM DESCRIPTION BREATHING AIR FOR SPHERE INSTALL PERMANENT WALKWAY HALON AWS COMMUNICATIONS ROOM 12 KV CONSTRUCTION POWER SYSTEM SEQUENCER LOGIC BOARDS LOCAL ASHCROFT GAUGES CONTROL ROOM INSTRUMENT RACKS 1-5 FLUX MAPPING SYSTEM NUISANCE ALARMS BATTERY CHARGER HYDRAZINE LOW FLOW AND CONTAINMENT SUPPLY SYNCHRO CHECK RELAY PROTECTION STEAM GENERATOR MANWAY TENSIONER POWER SUPPLY FOR DECONTAMINATION SYSTEMS ELECTRO POLISHER INSTALL RACEWAY IN SPENT FUEL AREA RADIATION DETECTORS OUTER CIRCLE TEMPERATURE AVERAZE CIRCUITS SECONDARY CHEMISTRY MONITORING GLAND SEAL EXHAUST SEISMIC MONITORING INSTRUMENTATION OPERATIONAL RADIATION MONITORING SYSTEM
PLAN TO ACHIEVE STABILITY AND PREDICTABILITY OF PROCESS O
INTEGRATE NRC REQUIREMENTS, PLANT BETTERMENT, AND OUTAGE MANAGEMENT 0
PROCEDURE TO UPDATE LIVING SCHEDULE
INTEGRATED SCHEDULE ACTION 0 INITIAL SCHEDULE IDENTIFIED PROJECTS (TOTALITY OF WORK)
SCHEDULE MANAGEMENT (18 M-ONTH CYCLE -
3 MONTH OUTAGE)
PLANT BETTERMENT REGULATORY COMMITMENTS INTEGRATION INITIAL SCHEDULE O SAFETY SIGNIFICANCE SCHEDULE EMPHASIZE SAFETY SIGNIFICANCE BEING PREPARED
INITIAL SCHEDULE LONG TERM PLANT MODIFICATION UPGRADE SCHEDULE OUTAGE SCHEDULE CYCLE IX 01/01/85 -
03/31/85 CYCLE X 10/01/86 -
12/31/86 CYCLE XI 07/01/88 -
09/30/88 CYCLE XII 04/01/90 -
06/30/90 9A
INITIAL SCHEDULE CYCLE IX REFUELING OUTAGE MODIFICATIONS O
COMPLETE SEISMIC UPGRADE O
PARTIAL ENVIRONMENTAL QUALIFICATION 0
PARTIAL SYSTEMATIC EVALUATION PROGRAM O
SYSTEM VOLTAGE DEGRADATION 4 KV UNDERVOLTAGE RELAYS O
PRESSURIZER PORV BLOCK VALVES O
DIESEL GENERATOR FANS O
PARTICULATE EFFLUENT MONITORING SYSTEM PLATE-OUT CONCERN O
ISOLATION VALVES FOR STEAM GENERATOR SAMPLE AND BLOWDOWN LINES O
AUXILIARY FEEDWATER SYSTEM SAFETY GRADE UPGRADE O
CONTAINMENT ISOLATION RELAYS O
SIS ANNUNCIATOR WINDOWS 98
INITIAL SCHEDULE CYCLE X REFUELING OUTAGE MODIFICATIONS O
PARTIAL FIRE PROTECTION APPENDIX R O
PARTIAL SYSTEMATIC EVALUATION PROGRAM O
COMPLETE ENVIRONMENTAL QJALIFICATION O
POST ACCIDENT SAMPLING SYSTEM OXYGEN AND CHLORIDE MONITORING 0
CONTROL ROOM HABITABILITY HVAC UPGRADE O
ECCS SINGLE FAILURE UPGRADE O
DEDICATED SIS AND FEEDWATER SYSTEMS 0
SIS PUMP SUCTION NOZZLES 9C
INITIAL SCHEDULE CYCLE XI REFUELING OUTAGE MODIFICATIONS O
COMPLETE FIRE PROTECTION APPENDIX R O
PARTIAL SYSTEMATIC EVALUATION PROGRAM O
PARTIAL INSTRUMENTATION SYSTEM FOR DETECTION OF INADEQUATE CORE COOLING 0
PARTIAL REQUIREMENTS FOR EMERGENCY RESPONSE CAPABILITY O
NITROGEN SUPPLY FOR PORV'S AND FCV'S 1115 D, E & F UPGRADE TO SAFETY GRADE O
G & W (EFCOMATIC) ACTUATORS O
UPGRADE BALANCE OF SAFETY RELATED SNUBBERS O
REGULATED INSTRUMENT BUSES 9D
INITIAL SCHEDULE CYCLE XII REFUELING OUTAGE MODIFICATIONS O
PARTIAL SYSTEMATIC EVALUATION PROGRAM O
PARTIAL REQUIREMENTS FOR EMERGENCY RESPONSE CAPABILITY O
PARTIAL INSTRUMENTATION SYSTEM FOR DETECTION OF INADEQUATE CORE COOLING O
RADIOLOGICAL EFFLUENT MONITORING SYSTEMS O
HEAVY LOADS LIFT RIGS AND TURBINE DECK SPALLING PROTECTION O
REPLACE SIS RECIRCULATION LINE 0
CV 525 AND 527 VALVE SEATS 9E
INITIAL SCHEDULE MODIFICATIONS IF NOT COMPLETED BY CYCLE XII REFUELINC OUTAGE WOULD B SCHEDULED AFTER THAT O
COMPLETE SYSTEM"ATIC EVALUATION PROGRAM O
COMPLETE INSTRUMENTATION SYSTEM FOR DETECTION OF INADEQUATE CORE COOLING O
COMPLETE REQUIREMENTS FOR EMERGENCY RESPONSE CAPABILITY O
INLAND METEOROLOGICAL TOWER 0
MODIFICATION TO THE 125-VDC SYSTEM 0
CORRODED SAFETY RELEATED AND NON-SAFETY RELATED PIPING O
BATTERY NO.
1 0
SALTWATER COOLING VALVES POV 1-10 0
BORON ANALYZER O
PROCESS PH METER O
SLUDGE REMOVAL TRAP 0
INLET PRESSURE GAUGES ON RHR PUMPS O
CONTAINMENT SUMP LEVEL CONTROLLER O
STEAM PIPE EROSION O
PERMANENT DOMESTIC WATER LINE TO UNIT 1 0
DEMINERALIZED WATER CROSS TIE O
TELECOMMUNICATIONS O
NORTH GUARD TOWER VIDEO O
STATION SERVICE TRANSFORMER 0
SYSTEM DESCRIPTION O
BREATHING AIR FOR SPHERE O
ELECTRICAL POWER BUSES O
INSTALL PERMANENT WALKWAY O
CONTROL ROOM IM ROVEMENT 0
HALON AWS COMMUNICATION ROOM O
12 KV CONSTRUCTION POWER SYSTEM O
SEPARATE POWER SUPPLY TO LETDOWN ISOLATION VALVES O
UPGRADE SAFETY RELATED AND NON-SAFETY RELATED POWER SUPPLY O
SEQUENCER LOGIC BOARDS O
LOCAL ASHCROFT GAUGES O
SOLIDIFIED RESINS STORAGE BUILDING AND TRANSPORTATION EQUIPMENT O
WASTE GAS DECAY TANK SYSTEM 0
COMPONENT COOLING WATER HEAT EXCHANGER SERVICEABILITY O
SV-99 REPLACE ACTUATION TO RELIABLE CHANNEL 0
TURBINE LAB DRAINS O
CONDENSATE STORAGE TANK FLOODING POTENTIAL O
HEALTH PHYSICS BUILDING O
CHEMICAL AND VOLUME CONTROL SYSTEM VALVES MOV-LCV 11008, C AND D O
CONTROL ROOM INSTRUMENT RACKS 1-5 O
FLUX MAPPING SYSTEM 0
NUISANCE ALARMS BATTERY CHARGER, HYDRAZINE LOW FLOW AND CONTAINMENT SUPPLY O
SYNCHRO CHECK RELAY PROTECTION O
STEAM GENERATOR MANWAY TENSIONER O
POWER SUPPLY FOR DECONTAMINATION SYSTEM -
ELECTRO POLISHER 0
INSTALL RACEWAY IN SPENT FUEL AREA O
RADIATION DETECTION OUTER CIRCLE O
TEMPERATURE AVERAGE CIRCUITS O
SECONDARY CHEMISTRY MONITORING 0
GLAND SEAL EXHAUST 0
SEISMIC MONITORING INSTRUMENTATION 9F
SAFETY BASED INTEGRATED SCHEDULE INPUTS O SAFETY SIGNIFICANCE O CONSTRAINTS ON IMPLEMENTATION 0 10% PLANT BETTERMENT O JUSTIFICATION FOR DEFERRAL O INTEGRATION 10
INTEGRATED SCHEDULE SAFETY SIGNIFICANCE PARAMETERS O SYSTEM IMPROVEMENT IMPACT ON RELIABILITY IMPACT ON FAILURE MODES O SYSTEM IMPORTANCE CRITICAL FUNCTIONS DOMINANT SEQUENCES METHODOLOGY O RELIABILITY ANALYSIS DATA FROM PRIOR PRA'S O DETERMINISTIC ANALYSIS 0 INSIGHTS FROM RELATED PRA'S
INTEGRATED SCHEDULE CONSTRAINTS ON IMPLEMENTATION O
SCHEDULAR CONSTRAINTS O
OUTAGE DURATION O
MANPOWER CAPABILITY O
CAPITAL EXPENDITURES O
OTHERS 12
INTEGRATED SCHEDULE JUSTIFICATION FOR DEFERRAL O
SAFETY PLATEAU ACHIEVED O
ALTERNATIVES AVAILABLE O
COMPENSATING MEASURES O
OVERALL SAFETY SIGNIFICANCE 13
INTEGRATED SCHEDULE UPDATING 0 INTEGRATION OF NEW REGULATORY REQUIREMENTS O FIRM SCHEDULE CHANGE IN OUTAGE DOES NOT AFFECT SCHEDULE O OPTIMIZATION PROCESS IMPROVED SAFETY PRIORITIZATION 0 NRC APPROVAL
PLAN FOR IMPLEMENTATION O NRC SENIOR MANAGEMENT ENDORSEMENT O PRESENTATION OF INTEGRATED SCHEDULE METHODOLOGY 3 TO 6 WEEKS O SUBMITTAL OF SAFETY BASED INTEGRATED SCHEDULE 10 TO 20 WEEKS O PLANT STARTUP BASED ON INTEGRATED BACKFIT PLAN 15
INTEGRATED SCHEDULE CONCLUSION O NECESSARY FOR STABILITY AND PREDICTABILITY O EMPHASIZES SAFETY SIGNIFICANCE O REQUIRES NRC ENDORSEMENT 16
PLAN FOR EARLY RETURN TO POWER SAN ONOFRE UNIT 1 o
General Provisions o
Specific Aspects o
Program for NRC Approval March 1983
SEISMIC REEVALUATION PROGRAM TOTAL SCOPE The scope of items reevaluated and upgraded to 0.67g Housner includes:
- 1.
All safety-related structures
- 2. NSSS components
- 3.
Reactor coolant pressure boundary
- 4.
Safe shutdown systems
- 5.
Accident mitigation systems For the above systems and equipment the program includes:
- 1.
Piping
- 2.
Equipment and valves
- 3.
Instruments
- 4.
Backup nitrogen for air operated valves
- 5.
Electrical raceways
- 6.
Resolution of in situ backfill soil conditions
- 7.
Control room ceiling and HVAC
PLAN FOR EARLY RETURN TO POWER SAN ONOFRE UNIT 1 General Provisions I.
Structures and systems whose failure could cause an accident will be available following a U.67g earthquake.
II. Structures and systems required to get to a safe cold shutdown will be available following a 0.67g earthquake.
III.
Structures and systems not required to get to a safe cold shutdown will be deferred.
I. Structures and systems whose failure could cause an accident will be available following a 0.67g earthquake.
Structures o Containment o -Reactor Building o Turbine Pedestal o Turbine Building - North, West and East Extensions*
Systems o Reactor coolant loop o NSSS conponents o All piping connected to reactor coolant loop up to first isolation valve o Main steam and steam blowdown piping o Main feedwater piping
- Requires resolution of pipe reaction loads.
Will demonstrate the.overall structural capacity -of the structure and individual capacities of structural nembers.
II. Structures and systems required to get to a safe cold shutdown will be available following a 0.67g earthquake.
Structures o Control Administration Building o Reactor Auxiliary Building o Intake Structure o Fuel Storage Building o Seawall o Ventilation Equipment Building**
Systems o Charging, including a source of borated water backup piping from spent fuel pool, including assurance of integrity of spent fuel pit cooling piping to resolve in situ backfill soil conditions o Component cooling
- Requires resolution of in situ backfill soil conditions
o Saltwater cooling two temporary 6" lines pump manufacturer indicates bearing flush water not required o Auxiliary feedwater new auxiliary feedwater tank new suction piping modification to auxiliary feedwater pump foundations to resolve loose soils bearing cooling water to turbine driven pump o Residual heat removal o Control room ceiling o Vent stack o Above systems include pressure boundary piping, equipment, valves and instruments
-3 o Back.up nitrogen for atmospheric dump valves (CV 76, 77, 78, 79) charging and auxiliary pressurizer spray valves (CV 304, 305) saltwater cooling pump discharge valves (POV 5, 6) turbine driven auxiliary feedwater pump steam supply valve (CV 113) auxiliary feedwater pump flow control valves (PCV 2300, 2301, 3300, 3301) gland seal steam supply-isolation valve (CV 96) safety injection recirculation -
reactor coolant pump seal valves (FCV 1115 D, E, F) residual heat removal heat exchanger and flow control valves (TCV 601A, 601B, HCV 602)
. Structures and systems not required to get to a safe cold shutdown will be deferred.
Structures o South turbine building extension Basis:
Failure will not impact ability to attain safe cold shutdown Systems o Safety injection o Recirculation o Containment spray o Containment isolation valves and penetrations o
Hydrazine addition a
o Main feedwater pumps and lube oil cooler fans o Control room HVAC
-2 o Backup nitrogen will not be Provided for feedwater pump mini-flow valves (CV 36, 37)
PORVs and PORV block valves (CV 530, 531, 545, 546) safety injection pump recirculation valves (CV 875A, 875B) o Resolution of in situ backfill soil conditions refueling water pump saltwater cooling lines pipe supports in Area 14 if piping can satisfy stress criteria o
Above systems include piping, equipment, valves and instruments; except where it is required as part of safe shutdown systems Basis:
Reactor coolant pressure boundary, main steam piping and main feedwater piping will be available, therefore an earthquake will not cause an accident. Probability of concurrent earthquake and accident is low.
o Electrical Raceways - completion of modifications Basis:
Electrical raceways have not experienced failure in testing programs. Selected modifications will be implemented to ensure applicability of tests.
PLAN FOR EARLY RETURN TO POWER SAN ONOFRE UNIT 1 Program for NRC Approval o
Maintain dialogue on specific aspects o
Meetings to discuss details as required o
Submittal of plan for early return to power o
NRC approval of plan for early return to power o
SCE will initiate plan for early return to power only after concurrence is obtained on Plan for Managing Plant Retrofit (i.e., long term integrated plant modification upgrade schedule)