Comments on Util Approach to Continuation of Work at Facility.General Approach to Establish Integrated Schedule for Implementing Mods Acceptable.Plan for Early Return to Power,Per ,Not Received
ML13310A875
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 08/01/1983
From: Eisenhut D
Office of Nuclear Reactor Regulation
To: Dietch R
Southern California Edison Co
References
TAC-54376 LSO5-83-08-002, LSO5-83-8-2, NUDOCS 8308030424
Download: ML13310A875 (3)


Text

DISTRIBUTION Docket August 1, 1983 NRC PDR Local PDR NSIC Docket No. 50-206 ORB Reading LS05-83-08-002 DCrutchfield HSmith WPaulson OELD Mr. R. Dietch, Vice President ELJordan Nuclear Engineering and Operations JMTaylor Southern California Edison Company ACRS (10) 2244 Walnut Grove Avenue o

Post Office Box 800 Rosemead, California 91770

Dear Mr. Dietch:

SUBJECT:

INTEGRATED SCHEDULING FOR IMPLEMENTATION OF PLANT MODIFICATIONS San Onofre Nuclear Generating Station, Unit No. I During the past several months, in meetings with NRC management, you'\\ave presented the Southern California Edison (SCE) approach to continuation of work on San Onofre Unit No. I, Your letter dated June 10, 1983 indicated that SCE would be developing a Plan for Early Return to Power and-a Plan for Managing Plant Retrofit. Your letter dated June 17, 1983 provided additional information regarding your proposed Plan for Managing Plant Retrofit and it requested NRC concurrence on the scope and constraints of.

your program. Your Plan for Early Return to Power has not yet been received by the NRC.

The enclosure to your June 17, 1983 letter shows that the initial schedule for long-teri plant modifications would extend through the Cycle XII outage (April 1 throughdJun.e 30,-1990).

The assumptions on which this initial schedule was developed include (1) an 18 month operating cycle and a 3 month outage during which plant backfits would be performed, and (2) station betterment items that would represent about 10% of the total backfit effort, Your June 17, 1983 letter also states that the methodology for the integrated backfit schedule is being developed and that it will be submitted for NRC review. As we understand it, this methodology will include a process for prioritizing projects based on safety significance.

Based on the metings with SCE representatives and your June 10 and 17, 1983 letteks, we find that your general approach to estab1Lsh an integrated schedule for implementing plant modifications is acceptable. Before final approval can be given, the methodology for establishing p"orities as-well as the bases for your proposed schedule must be submitted for NRC review and approval. Your Plan for Early Return to Power thould also be provided si 0

<8308030424 830801 I

PDR ADOCK 05000206 P

PDR V

OFFICE)

I..

SURNAME..

DATE.

NRC FORM 318 (10-80) NRCM 0240 OFFICIAL RECORD COPY USGPO: 1981-335-960

Mr. R. Dietch

- 2.

August 1, 1983 for our review and approval. This latter plan may interface.with your proposed long-term plan and will be considered during our review of your integrated schedule, Similarily, the Systematic Evaluation Program Integrated Assessment may also establ(.sh certain backfit items.

Finally, your June 17,,1983 letter indicated that there is a potential immediate need to develop exemptions and/or renegotiate schedules on certain regulatory related projects. In this regard, we will consider such requests and make a determination based on whether good cause is shown, compensatory measures that may be instituted, and the safety significance of the issue for which relief is sought.

Sincerely, O.riginal signedbY Darrell G.EFisenhut Darrell G* Eisenhut, Director Division of Licensing cc: See next page OFFICE A.

SURNAMEj~usnc

~i~chir1Fia~Yu DATE 8**

  • ....0
  • 4*
  • FI*A

-. C R D..

8 -............80 NRC FORM 318 (10-80) NRCM 0240 OFFI'CIAL R ECO RD COPY USGPO: 1981-335 -960

Mr. August 1, 1983 cc Charles R. Kocher, Assistant General Counsel James Beoletto, Esquire Southern California Edison Company Post Office Box 800 Rosemead, California 91770 David R. Pigott Orrick, Herrington & Sutcliffe 600 Montgomery Street San Francisco, California 94111 Harry B. Stoehr San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Resident Inspector/San Onofre NPS c/o U. S. NRC P. 0. Box 4329 San-Clemente, California 92672 Mayor City of San Clemente San Clemente, California 92672 Chairman Board of Supervisors County of San Diego San Diego, California 92101 California Department of Health ATTN: Joseph 0. Ward, Chief Radiation Control Unit Radiological Health Section 714 P Street, Room 498 Sacramento, California 95814 U. S. Environmental Protection Agency Region IX Office ATTN:

Regional Radiation Representative 215 Freemont Street San Francisco, California 94111 John B. Martin, Regional Administrator Nuclear Regulatory Commission, Region V 1450 Maria Lane Z

Walnut Creek, California 94596