Forwards Amend 98 to License DPR-13 & Safety Evaluation. Amend Implements License Condition Establishing Integrated Implementation Schedule Program Plan.Evaluation of Plan & Plan Encl
ML13316A966
Person / Time
Site: San Onofre 
Issue date: 04/20/1987
From: Dudley R
Office of Nuclear Reactor Regulation
To: Baskin K
Southern California Edison Co
Shared Package
ML13316A967 List:
References
TAC-54376 NUDOCS 8704290243
Download: ML13316A966 (6)


Text

2 0 APR 1987 Docket No. 50-206 Mr. Kenneth P. Baskin Vice President, Nuclear Engineering Safety and Licensing Department Southern California Edison Company 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

Dear.Mr. Baskin:

SUBJECT:

LICENSE AMENDMENT ESTABLISHING AN INTEGRATED IMPLEMENTATION SCHEDULE SAN ONOFRE NUCLEAR GENERATING STATION, UNIT NO. 1 (TAC NO. 54376)

The Commission has issued the enclosed Amendment No. 98 to Provisional Operating License No. DPR-13 for San Onofre Unit No. 1. This amendment is in response to your application dated May 23, 1984 as modified on August 29, 1985 and supplemented on March 26, 1986, October 14, 1986 and March 23, 1987.

The amendment implements.a license condition which establishes an Integrated Implementation Schedule Program Plan (the Plan).

The license condition requires that Southern California Edison Company follow the Plan.and the terms therein for establishing and revising schedules for specific plant modifications.

Our evaluation of the Plan is provided in Enclosure 2 and a copy of the Plan is enclosed as Attachment 1 of Enclosure 2. During our review of your submittals, certain minor modifications to the Plan were found to be necessary. These changes were discussed with your representative and found to be mutually agreeable. Based upon our review, we conclude that the revised Plan is acceptable.

A Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice.

Sincerely, WOW pt~dby Richard F. Dudley, Project Manager 6704290243 870420' Project Directorate V PDR ADOCK 05000206' Division of Reactor Projects-III/IV/V and P

PDR Special Projects

Enclosures:

1. Amendment No. 98 to License No. DPR -13
2. Safety Evaluation cc w/enclosures:

See next page

  • See previous concurrence LA/PAD#1:DPLA PM/PAD#1:DPLA OGC DR 5

PShuttleworth RDudley/tg G.

on 03/?9/87 03/03/87 04/14/87 04/7,-/87

Docket No. 50-206 Mr. Kenneth P. Baskin Vice President, Nuclear Engineering Safety and Licensing Department Southern California Edison Company 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

Dear Mr. Baskin:

SUBJECT:

LICENSE AMENDMENT ESTABLISHING AN INTEGRATED IMPLEMENTATION SCHEDULE Re:

San Onofre Nuclear Generating Station, Unit No. 1 The Commission has issued the enclosed Amendment No.

to Provisional Operating License No. DPR-13 for San Onofre Unit No. 1. This amendment is in response to your application dated May 23, 1984 as modified on August 29, 1985 and supplemented on March 26, 1986, October.14, 1986 and March 23, 1987.

The amendment implements a license condition which establishes an Integrated Implementation Schedule Program Plan (the Plan).

The license condition requires that Southern California Edison Company follow the Plan and the terms therein for establishing and revising schedules for specific plant modifications.

Our evaluation of the Plan is provided in Enclosure 2 and a copy of the Plan is enclosed as Attachment 1 of Enclosure 2. During our review of your submittals, certain minor-modifications to the Plan were found to be necessary. These changes were discussed with your representative and found to be mutually agreeable. Based upon our review, we conclude that the revised Plan is acceptable.

A Notice of Issuance will be included in the Commission's next regular biweekly Federal Register notice.

Sincerely, Richard F. Dudley, Project Manager PWR Project Directorate #1 Division of PWR Licensing-A

Enclosures:

1. Amendment No.

to License No. DPR-13

2. Safety Evaluation cc w/enclosures:

See next page

  • SEE PREVIOUS CONCURRENCE Office:

LA/PAD#1:DPLA PM/PAD#1:DPLA OGC PD/PAD#1 Surname:

PShuttleworth

  • RDudley/tg GLear Date:

03/ f/87 03/ 038B7

//87 03/ /87

Docket No. 50-206 Mr. Kenneth P. Baskin Vice President, Nuclear Engineering Safety and Licensing Department Southern California Edison Company 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770

Dear Mr. Baskin:

SUBJECT:

LICENSE AMENDMENT ESTABLISHING AN INTEGRATED IM EMENTATION SCHEDULE Re:

San Onofre Nuclear Generating Station, Unit No. 1 The Commission has issued the enclosed Amendment No.

to Provisional Operating License No. DPR-13 for San Onofre Unit No 1. This amendment is in response to your application dated May 23, 1 4 as modified on August 29, 1985 and supplemented on March 26, 198, October 14, 1986 and The amendment implements a license condition whi h establishes an Integrated Implementation Schedule Program Plan (the Plan). The license condition requires that Southern California Edison Comp y follow the Plan and the terms therein for establishing and revising s hedules for specific plant modifications.

Our evaluation of the Plan is provided in nclosure 2 and a copy of the Plan is enclosed as Attachment 1 of Enclosure During our review of your submittals, certain minor modifications o the Plan were found to be necessary. These changes were discusse with your representative and found to be mutually agreeable. Based upon our review, we conclude that the revised Plan is acceptable.

A Notice of Issuance will be inclu d in the Commission's next regular biweekly Federal Register notice.

Sincerely, George E. Lear, Director PWR Project Directorate #1 Division of PWR Licensing-A

Enclosures:

1. Amendment No.

0 License No. D -13

2. Safety Evaluation cc w/enclosures/

See next page Office:

LA/PAD#1:DPLA PM P OGC PD/PAD#1 Surname:

PShuttleworth RDudley/tg GLear Date:

02/ /87 01/3/87

/

/87

/

/87

Mr. Kenneth P. Baskin San Onofre Nuclear Generating Station Southern California Edison Company Unit No. 1 cc Charles R. Kocher, Assistant Joseph 0. Ward, Chief General Counsel Radiological Health Branch James Beoletto, Esquire State Department of Health Southern California Edison Company Services Post Office Box 800 714 P Street, Office Bldg. 8 Rosemead, California 91770 Sacramento, California 95814 David R. Pigott Mr. Hans Kaspar, Executive Director Orrick, Herrington & Sutcliffe Marine Review Committee, Inc.

600 Montgomery Street 531 Encinitas Boulevard, Suite 105 San Francisco, California 94111 Encinitas, California 92024 Mr. Stephen B. Allman Ann C. Vasques, Chief San Diego Gas & Electric Company Radiological Programs Division P. 0. Box 1831 Governor's Office of Emergency Svcs.

San Diego, California 92112 State of California 2800 Meadowview Road Sacramento, CA 95832 San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Resident Inspector/San Onofre NPS c/o U.S. NRC P. 0. Box 4329 San Clemente, California 92672 Mayor City of San Clemente San Clemente, California 92672 Chairman Board of Supervisors County of San Diego San Diego, California 92101 Regional Administrator, Region V U.S. Nuclear Regulatory Commission 1450 Maria Lane Walnut Creek, California 94596

Distribution Docket_ Flie5026 1 NRC PDR Local PDR PD5 Gray File RDudley JLee OGC-Bethesda LHarmon Edordan BGrimes JPartlow EButcher, TSCB TBarnhart (4)

Wdones FOB, DPLA ACRS (10)

OPA LFMB (TAC #54376)

KEccleston (TOSB)

HThompson (NMSS)

Zola 739 RIM 017T F.AJi 37 My1 jA;rn4 11