MONTHYEARML13308A9021982-12-0606 December 1982 SER Re Environ Qualification of safety-related Equipment Project stage: Other ML13308A9011982-12-0606 December 1982 Forwards SER Re Environ Qualificatin of safety-related Electrical Equipment in Accordance w/NUREC-0588,per NRC 800523 Memorandum & Order CLI-80-21.W/o Stated Technical Evaluation Rept Project stage: Approval ML13317A4801983-01-18018 January 1983 Discusses Status of Environ Qualification of safety-related Electrical Equipment.Justification for Continued Operation for Auxiliary Feedwater Flow Transmitters & Radiation Monitors Provided,Per NUREG-0737 Project stage: Other ML13317A5071983-02-10010 February 1983 Notifies That Resources Necessary to Reply to Generic Ltrs 82-28 & 82-33,requesting Identification of Design for Reactor Coolant Inventory Sys & Schedule for Completion of Requirements for Emergency Response Capability,Unavailable Project stage: Other ML13333B8821983-04-18018 April 1983 Summary of 830413 Meeting W/Utils in Bethesda,Md Re Licensee Plans for Managing Plant Retrofit Items & Early Return to Power.List of Attendees & Handouts Encl Project stage: Meeting ML13317A5811983-04-21021 April 1983 Forwards Rept on Current Status of Emergency Response Capability Implementation,Per Suppl 1 to NUREG-0737 (Generic Ltr 82-33) Project stage: Other ML20023C1021983-05-0303 May 1983 Amend 91 to License DPR-49,revising Plan for Integrated Scheduling of Mods Project stage: Other ML20023C1061983-05-0303 May 1983 Notice of Issuance & Availability of Amend 91 to License DPR-49 Project stage: Other ML20023C1051983-05-0303 May 1983 Safety Evaluation Supporting Amend 91 to License DPR-49 Project stage: Approval ML13333B9021983-06-0101 June 1983 Plan for Managing Plant Retrofit Project stage: Other ML13333B9001983-06-0303 June 1983 Summary of 830601 Meeting W/Util Re Plan for Managing Retrofit Items.License Amend Schedule,W/Proposed safety- Based Integrated Schedule,Will Be Submitted on or About 831115.List of Attendees & Handouts Encl Project stage: Meeting ML13310A8011983-06-10010 June 1983 Submits Description & Basic Premise for Plan for Early Return to Power & Plan for Managing Plant Retrofit & Discusses Implementation of Each Plan Project stage: Other ML13310A8031983-06-13013 June 1983 Delineates Activities Associated W/Continuation of Work to Resolve Differences Resulting from Sep.Proposed Corrective Actions to Resolve Open Items Will Be Provided in Last Quarter of 1983 Project stage: Other ML13310A8041983-06-16016 June 1983 Forwards Replacement Page 2 for R Dietch Re Util Plans for Continuation of Work at Facility.Replacement Page Supplied to Clarify Possible Problems of Interpretation Due to Typographical Errors Project stage: Other ML13310A8051983-06-17017 June 1983 Forwards Plan for Managing Plant Retrofit to Assist in Reducing Capital Expenditures & to Improve Capacity Factor. NRR Concurrence Requested Project stage: Other ML13310A8751983-08-0101 August 1983 Comments on Util Approach to Continuation of Work at Facility.General Approach to Establish Integrated Schedule for Implementing Mods Acceptable.Plan for Early Return to Power,Per ,Not Received Project stage: Other ML13310A9371983-09-0101 September 1983 Application for Withholding Proprietary Westinghouse Analytical Ranking Process Project stage: Request ML13308A2891983-09-0202 September 1983 Notification of 830908 Meeting W/Util in San Diego,Ca to Discuss Unit 3 Readiness for Full Power Operation Project stage: Request ML13310A9341983-09-0202 September 1983 Submits Methodology to Be Used in Developing Integrated Living Schedule.Final Result Will Be long-term Schedule for Implementing Backfits Based on 18-month Operating Cycles. Proprietary Version Withheld (Ref 10CFR2.790) Project stage: Other ML13333B9511983-10-20020 October 1983 Summary of 831005 Meeting W/Util & Westinghouse Re Methodology Being Used to Prioritize Backfit Projects. Viewgraphs Encl Project stage: Meeting ML13310B0331983-10-24024 October 1983 Forwards Proprietary Viewgraphs Provided at 831005 Meeting W/Util & Westinghouse.Viewgraphs Withheld Per NRC Manual Chapter 9.5(4) Since Matl Intended for General Info & Will Not Be Used as Basis for NRC Actions Project stage: Meeting ML13310B0581983-11-0101 November 1983 Forwards Proprietary Affidavit of Jd Mcadoo,Identifying Info Sought to Be Withheld in 830901 Submittal.Affidavit Withheld (Ref 10CFR2.790) Project stage: Other ML13310B0731983-11-16016 November 1983 Advises That 830902 Proposed Methodology to Be Used to Develop Integrated Living Schedule for Implementation of Capital Mod Projects,Acceptable W/Two Exceptions Re Integrated Retrofit Schedule & Facility Restart Project stage: Other ML13310B0751983-11-21021 November 1983 Forwards Schedules for All Capital Backfit Projects Based on Westinghouse Analytical Ranking Process Methodology. Submittal Provided for Early Review & Comment.Upon Resolution,License Amend Will Be Submitted Project stage: Other ML13310B1081983-12-0606 December 1983 Forwards Summaries of All Regulatory Projects Included in Integrated Living Schedule & Edited Schedule of Backfits, in Response to NRC Request at 831122 Meeting Project stage: Meeting ML13333B9911983-12-15015 December 1983 Summary of 831122 Meeting W/Util & Westinghouse Re Results of Util Prioritization of Capital Backfit Projects & Integrated Living Schedule Project stage: Meeting ML13310B1591984-01-20020 January 1984 Advises That Revised Schedule for Capital Projects to Implement Proposed Integrated Living Schedule Unacceptable. Proposed Schedule Indicates Delays in Implementing Mods Prescribed in Commission Regulations Project stage: Other ML13310B2611984-02-27027 February 1984 Forwards Revised Integrated Living Schedule Based on Removing Any SEP & Fire Protection Safe Shutdown Backfits. Outage Schedules for Three Cycles of Operation Encl Project stage: Other ML13333C0191984-03-20020 March 1984 Summary of 840308 Meeting W/Utils in Bethesda,Md Re Licensee Revised Proposal for Integrated Living Schedule Submitted by .List of Attendees & Agenda Encl Project stage: Meeting ML13333C0201984-03-30030 March 1984 Summary of 840328 Meeting W/Util & Bechtel in Bethesda,Md Re Licensing Activities at Facility & Licensee Proposal for Integrated Living Schedule Project stage: Meeting ML13310B4131984-05-23023 May 1984 Forwards Application for Amend 119 to License DRP-13, Consisting of Proposed Change 134.Change Revises Section 3, Contents & Conditions to Include New Condition 3.J, Integrated Living Schedule of Backfits. Fee Encl Project stage: Request ML13310B4171984-05-23023 May 1984 Application for Amend 119 to License DPR-13,consisting of Proposed Change 134.Change Revises Section 3, Contents & Conditions, to Include New Condition 3.J, Integrated Living Schedule of Backfits Project stage: Request ML13324A5681985-03-11011 March 1985 Forwards SER Re Environ Qualification of Electric Equipment Important to Safety.Equipment Qualification Program in Compliance w/10CFR50.49.Final Environ Qualification of Electric Equipment Will Be Completed by 850331 Project stage: Approval ML13324A5711985-03-11011 March 1985 SER Supporting Environ Qualification of Electric Equipment Important to Safety,Per Requirements of 10CFR50.49 Project stage: Other ML20133P9341985-07-31031 July 1985 Informs That Completion of Integrated Safety Assessment Scheduled for Sept 1985 for Millstone Unit 1 & Sept 1986 for Haddam Neck.Projects Listed in Encl Should Be Conducted Independent of Integrated Safety Assessment Program Project stage: Other ML13324A7031985-08-29029 August 1985 Forwards Revised Integrated Living Schedule & Revised Proposed License Condition & Plan to Support Issuance of License Condition 3.J, Integrated Living Schedule of Backfits Project stage: Other ML13308A8981985-12-23023 December 1985 Directors Decision 85-20,concluding That Overall State of Equipment Qualification of Facilities Adequate to Assure Protection of Public Health & Safety.Notice of Issuance & Safety Evaluations Encl Project stage: Approval DD-85-20, Informs That Time Provided by NRC Regulations to Review Directors Decision DD-85-20 Expired.Commission Declined Review.Decision Became Final Agency Action on 860207.Served on 8602071986-02-10010 February 1986 Informs That Time Provided by NRC Regulations to Review Directors Decision DD-85-20 Expired.Commission Declined Review.Decision Became Final Agency Action on 860207.Served on 860207 Project stage: Other ML13324A8261986-03-26026 March 1986 Provides Written Notification of Changes to Integrated Living Schedule Section V.B & Justification for Deferral of Implementation to Cycle 10.Waste Gas Decay Tank Instrumentation Being Upgraded Project stage: Other ML13330B1231986-10-14014 October 1986 Forwards Third Edition of Integrated Living Schedule,Per 840523 Application for Amend to License DPR-13.Encl Includes Summary of Progress Since Last Submittal.Next Refueling/ Backfit Outage Scheduled for First Quarter 1988 Project stage: Request ML13330B1781987-03-23023 March 1987 Forwards Fourth Edition of Integrated Living Schedule,Per Project stage: Other ML13316A9701987-04-20020 April 1987 Safety Evaluation Supporting Amend 98 to License DPR-13 Project stage: Approval ML13316A9691987-04-20020 April 1987 Amend 98 to License DPR-13,implementing License Condition Which Establishes Integrated Implementation Schedule Program Plan.Plan Requires Util to Follow Plan & Terms for Establishing & Revising Schedules for Specific Plant Mods Project stage: Other ML13316A9661987-04-20020 April 1987 Forwards Amend 98 to License DPR-13 & Safety Evaluation. Amend Implements License Condition Establishing Integrated Implementation Schedule Program Plan.Evaluation of Plan & Plan Encl Project stage: Approval 1983-06-17
[Table View] |
Text
Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE KENNETH P. BASKIN ROSEMEAD, CALIFORNIA 91770 TELEPHONE VICE PRESIDENT 818-572-1401 February 27, 1984 Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Sir:
Subject:
Docket No. 50-206 Integrated Living Schedule San Onofre Nuclear Generating Station Unit 1 By letter dated November 21, 1983 and revised by letter dated December 6, 1983, we provided our Integrated Living Schedule (ILS) of backfits for San Onofre Unit 1. By letter dated January 20, 1984, you indicated that the ILS is not acceptable based on the following reasons: (1) the ILS is unreasonably long, (2) the assumption to use deterministic criteria for all projects whose scope has not been defined is not appropriate, and (3) the completion dates for Fire Protection Safe Shutdown, Appendix R to 10 CFR 50 and Environmental Qualification of Electrical Equipment beyond those specified by Regulation cannot be approved without exemptions. However, you reiterated that an integrated schedule for capital projects is desirable and that you are prepared to review any revision to our ILS that may be made in light of above comments.
Accordingly, our revised ILS is provided as Enclosure 1 to this letter. The revision is based on (1) removing any SEP, TMI and long-term seismic backfits whose scope is currently undefined, and (2) removing Fire Protection Safe Shutdown, Appendix R to 10 CFR 50 and Environmental Qualification of Electrical Equipment backfits whose implementation dates are currently prescribed by Regulation. With the removal of these backfits, the revised ILS spans three cycles of operation scheduled as shown in Enclosure 2 to this letter.
9402290180 840227 j
PDR ADOCK 05000206 P
RDR4
Mr. H.
February 27, 1984 As you are aware, the ILS, once approved, will contain provisions for adding or removing backfits.
Therefore, the removal of the backfits as discussed above at this time should not prevent you from approving the enclosed revised ILS. Specifically, it is expected that the following actions will be taken regarding the removed backfits:
- 1. The SEP, TMI and long-term seismic backfits will be added to the ILS once their scopes have been defined.
- 2. The Fire Protection Safe Shutdown, Appendix R to 10 CFR 50 backfit will be added to the ILS once a proposal to implement a dedicated shutdown system has been submitted to and approved by the NRC.
- 3. The Environmental Qualification of Electrical Equipment backfit will be added to the ILS once a request for exemption has been submitted to and approved by the NRC.
For your information, it is expected that the Post Accident Sampling System backfit cannot be completed prior to return to service as required by Confirmatory Order. Accordingly, this backfit will be added to the ILS once a request to revise the Confirmatory Order for TMI upgrade requirements has been submitted to and approved by the NRC.
In order to facilitate your timely review and approval of the enclosed revised ILS, we are prepared to meet with you at your earliest convenience. Please contact me if you have any questions or require further information.
Very truly yours, Enclosure
ENCLOSURE 1 SONGS 1 INTEGRATED LIVING SCHEDULE REGULATORY ITEMS BY REFUELING OUTAGE CYCLE 9 Title Efcomatic Actuator Replacement Electrical Drawing Verification Project Wide Range Gas Monitor Plate-Out:
Evaluation Regulated Instrument Buses Safety Grade Upgrade of AFWS Equipment Regulatory Guide 1.97:
Evaluation Control Room Design Review:
Evaluation Replacement of SV99 Actuation Circuit Automatic Trip of Reactor Coolant Pumps:
Evaluation CVCS Valves MOV-LCV-1100B, C, D Waste Gas Decay Tank Monitoring Instrumentation Condensate Storage Tank Flooding Potential:
Evaluation Safety Parameter Display System:
Evaluation Inadequate Core Cooling:
Evaluation Radiological Effluent Technical Specification Modifications Post Accident Sampling 02 and Cl Monitoring Improvements to Operational Radiation Monitoring System Resolve Long-Term Seismic Issues and Modification Schedule
SONGS 1 INTEGRATED LIVING SCHEDULE REGULATORY ITEMS BY REFUELING OUTAGE CYCLE 10 Title Third Train Auxiliary Feedwater Safety Injection System Modifications Replace GE Cable to RHR Pumps NIS Rockbestos Cable Replacement
SONGS 1 INTEGRATED LIVING SCHEDULE REGULATORY ITEMS BY REFUELING OUTAGE CYCLE 11 Title Health Physics Facility Upgrade, Including Facilities for Men and Women Reactor Coolant Pump Lift Rigs Steel Decking Under Turbine Deck North Extension Solidified Resin Storage Facility GEH:0886F
ENCLOSURE 2 OUTAGE SCHEDULE Begin Outage Return to Service January 1, 1985 9
April 1, 1986 July 1, 1986 10 January 1, 1988 April 1, 1988 11 October 1, 1989 January 1, 1990 GEH:0886F