Letter Sequence Other |
|---|
|
Results
Other: ML13310A801, ML13310A803, ML13310A804, ML13310A805, ML13310A875, ML13310A934, ML13310B058, ML13310B073, ML13310B075, ML13310B159, ML13310B261, ML13316A969, ML13317A507, ML13317A581, ML13324A703, ML13324A826, ML13330B178, ML13333B902, ML20023C102, ML20023C106
|
MONTHYEARML13317A5071983-02-10010 February 1983 Notifies That Resources Necessary to Reply to Generic Ltrs 82-28 & 82-33,requesting Identification of Design for Reactor Coolant Inventory Sys & Schedule for Completion of Requirements for Emergency Response Capability,Unavailable Project stage: Other ML13333B8821983-04-18018 April 1983 Summary of 830413 Meeting W/Utils in Bethesda,Md Re Licensee Plans for Managing Plant Retrofit Items & Early Return to Power.List of Attendees & Handouts Encl Project stage: Meeting ML13317A5811983-04-21021 April 1983 Forwards Rept on Current Status of Emergency Response Capability Implementation,Per Suppl 1 to NUREG-0737 (Generic Ltr 82-33) Project stage: Other ML20023C1051983-05-0303 May 1983 Safety Evaluation Supporting Amend 91 to License DPR-49 Project stage: Approval ML20023C1061983-05-0303 May 1983 Notice of Issuance & Availability of Amend 91 to License DPR-49 Project stage: Other ML20023C1021983-05-0303 May 1983 Amend 91 to License DPR-49,revising Plan for Integrated Scheduling of Mods Project stage: Other ML13333B9021983-06-0101 June 1983 Plan for Managing Plant Retrofit Project stage: Other ML13333B9001983-06-0303 June 1983 Summary of 830601 Meeting W/Util Re Plan for Managing Retrofit Items.License Amend Schedule,W/Proposed safety- Based Integrated Schedule,Will Be Submitted on or About 831115.List of Attendees & Handouts Encl Project stage: Meeting ML13310A8011983-06-10010 June 1983 Submits Description & Basic Premise for Plan for Early Return to Power & Plan for Managing Plant Retrofit & Discusses Implementation of Each Plan Project stage: Other ML13310A8031983-06-13013 June 1983 Delineates Activities Associated W/Continuation of Work to Resolve Differences Resulting from Sep.Proposed Corrective Actions to Resolve Open Items Will Be Provided in Last Quarter of 1983 Project stage: Other ML13310A8041983-06-16016 June 1983 Forwards Replacement Page 2 for R Dietch Re Util Plans for Continuation of Work at Facility.Replacement Page Supplied to Clarify Possible Problems of Interpretation Due to Typographical Errors Project stage: Other ML13310A8051983-06-17017 June 1983 Forwards Plan for Managing Plant Retrofit to Assist in Reducing Capital Expenditures & to Improve Capacity Factor. NRR Concurrence Requested Project stage: Other ML13310A8751983-08-0101 August 1983 Comments on Util Approach to Continuation of Work at Facility.General Approach to Establish Integrated Schedule for Implementing Mods Acceptable.Plan for Early Return to Power,Per ,Not Received Project stage: Other ML13310A9371983-09-0101 September 1983 Application for Withholding Proprietary Westinghouse Analytical Ranking Process Project stage: Request ML13308A2891983-09-0202 September 1983 Notification of 830908 Meeting W/Util in San Diego,Ca to Discuss Unit 3 Readiness for Full Power Operation Project stage: Request ML13310A9341983-09-0202 September 1983 Submits Methodology to Be Used in Developing Integrated Living Schedule.Final Result Will Be long-term Schedule for Implementing Backfits Based on 18-month Operating Cycles. Proprietary Version Withheld (Ref 10CFR2.790) Project stage: Other ML13333B9511983-10-20020 October 1983 Summary of 831005 Meeting W/Util & Westinghouse Re Methodology Being Used to Prioritize Backfit Projects. Viewgraphs Encl Project stage: Meeting ML13310B0331983-10-24024 October 1983 Forwards Proprietary Viewgraphs Provided at 831005 Meeting W/Util & Westinghouse.Viewgraphs Withheld Per NRC Manual Chapter 9.5(4) Since Matl Intended for General Info & Will Not Be Used as Basis for NRC Actions Project stage: Meeting ML13310B0581983-11-0101 November 1983 Forwards Proprietary Affidavit of Jd Mcadoo,Identifying Info Sought to Be Withheld in 830901 Submittal.Affidavit Withheld (Ref 10CFR2.790) Project stage: Other ML13310B0731983-11-16016 November 1983 Advises That 830902 Proposed Methodology to Be Used to Develop Integrated Living Schedule for Implementation of Capital Mod Projects,Acceptable W/Two Exceptions Re Integrated Retrofit Schedule & Facility Restart Project stage: Other ML13310B0751983-11-21021 November 1983 Forwards Schedules for All Capital Backfit Projects Based on Westinghouse Analytical Ranking Process Methodology. Submittal Provided for Early Review & Comment.Upon Resolution,License Amend Will Be Submitted Project stage: Other ML13310B1081983-12-0606 December 1983 Forwards Summaries of All Regulatory Projects Included in Integrated Living Schedule & Edited Schedule of Backfits, in Response to NRC Request at 831122 Meeting Project stage: Meeting ML13333B9911983-12-15015 December 1983 Summary of 831122 Meeting W/Util & Westinghouse Re Results of Util Prioritization of Capital Backfit Projects & Integrated Living Schedule Project stage: Meeting ML13310B1591984-01-20020 January 1984 Advises That Revised Schedule for Capital Projects to Implement Proposed Integrated Living Schedule Unacceptable. Proposed Schedule Indicates Delays in Implementing Mods Prescribed in Commission Regulations Project stage: Other ML13310B2611984-02-27027 February 1984 Forwards Revised Integrated Living Schedule Based on Removing Any SEP & Fire Protection Safe Shutdown Backfits. Outage Schedules for Three Cycles of Operation Encl Project stage: Other ML13333C0191984-03-20020 March 1984 Summary of 840308 Meeting W/Utils in Bethesda,Md Re Licensee Revised Proposal for Integrated Living Schedule Submitted by .List of Attendees & Agenda Encl Project stage: Meeting ML13333C0201984-03-30030 March 1984 Summary of 840328 Meeting W/Util & Bechtel in Bethesda,Md Re Licensing Activities at Facility & Licensee Proposal for Integrated Living Schedule Project stage: Meeting ML13310B4171984-05-23023 May 1984 Application for Amend 119 to License DPR-13,consisting of Proposed Change 134.Change Revises Section 3, Contents & Conditions, to Include New Condition 3.J, Integrated Living Schedule of Backfits Project stage: Request ML13310B4131984-05-23023 May 1984 Forwards Application for Amend 119 to License DRP-13, Consisting of Proposed Change 134.Change Revises Section 3, Contents & Conditions to Include New Condition 3.J, Integrated Living Schedule of Backfits. Fee Encl Project stage: Request ML13324A7031985-08-29029 August 1985 Forwards Revised Integrated Living Schedule & Revised Proposed License Condition & Plan to Support Issuance of License Condition 3.J, Integrated Living Schedule of Backfits Project stage: Other ML13324A8261986-03-26026 March 1986 Provides Written Notification of Changes to Integrated Living Schedule Section V.B & Justification for Deferral of Implementation to Cycle 10.Waste Gas Decay Tank Instrumentation Being Upgraded Project stage: Other ML13330B1231986-10-14014 October 1986 Forwards Third Edition of Integrated Living Schedule,Per 840523 Application for Amend to License DPR-13.Encl Includes Summary of Progress Since Last Submittal.Next Refueling/ Backfit Outage Scheduled for First Quarter 1988 Project stage: Request ML13330B1781987-03-23023 March 1987 Forwards Fourth Edition of Integrated Living Schedule,Per Project stage: Other ML13316A9661987-04-20020 April 1987 Forwards Amend 98 to License DPR-13 & Safety Evaluation. Amend Implements License Condition Establishing Integrated Implementation Schedule Program Plan.Evaluation of Plan & Plan Encl Project stage: Approval ML13316A9701987-04-20020 April 1987 Safety Evaluation Supporting Amend 98 to License DPR-13 Project stage: Approval ML13316A9691987-04-20020 April 1987 Amend 98 to License DPR-13,implementing License Condition Which Establishes Integrated Implementation Schedule Program Plan.Plan Requires Util to Follow Plan & Terms for Establishing & Revising Schedules for Specific Plant Mods Project stage: Other 1983-06-16
[Table View] |
Text
Southern California Edison Company P. O. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 M. 0. MEDFORD TELEPHONE MANAGER OF NUCLEAR ENGINEERING (818) 302-1749 AND LICENSING March 23, 1987 U. S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, D.C.
20555 Gentlemen:
Subject:
Docket No. 50-206 Fourth Edition of the Integrated Living Schedule (ILS)
San Onofre Nuclear Generating Station Unit 1
References:
A. Letter, M. 0. Medford, SCE, to G. E. Lear, NRC, dated October 14, 1986 B. Letter, M. 0. Medford, SCE, to 3. A. Zwolinski, NRC, dated August 29, 1985 The third edition of the ILS was submitted by Reference A. The proposed ILS Program Plan submitted with Reference B specifies that SCE will provide semi-annual updates of the schedules to the NRC. Accordingly, enclosed is the fourth edition of the ILS.
If there are any questions on the enclosure or if you require additional information, please let me know.
Very truly yours, Enclosure cc:
R. F. Dudley, NRR Project Manager, San Onofre Unit 1 J. B. Martin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3 8703310281 870323 PDR ADOCK 05000206 P
PDR' L
Enclosure INTEGRATED LIVING SCHEDULE SAN ONOFRE NUCLEAR GENERATING'STATION, UNIT 1 Fourth Edition March, 1987 Introduction Proposed License Condition 3.J, "Integrated Living Schedule of Backfits,"
requires SCE to follow the ILS Program.Plan ("Plan").
The Plan specifies that periodic schedule updates be submitted to the NRC along with specific information regarding progress in implementing NRC requirements, changes since the previous report, reasons for schedule changes and the expected percentage allocation of resources on regulatory vs. betterment projects. This document is the fourth edition of the ILS which provides that information.
Progress in Implementing NRC Requirements Since SCE's last submittal in October, 1986, SONGS 1 has not had a backfit outage. Work continues on projects scheduled for implementation during the next refueling/backfit outage scheduled for early 1988.
Of the two evaluations scheduled for completion on the Cycle X schedule, we submitted the SPDS design criteria this month. The next milestone for the Supplement 1 to NUREG-0737 projects is the submittal of the Control Room Design Review,Report. The schedule for submittal has been extended from May 1, 1987 to August 14, 1987 due to the unanticipated workload associated with evaluating the SONGS 1 control room and a secondary review of the effort to ensure compliance with NRC review requests.
This has been discussed and agreed with the NRC staff.
Changes Since Last Edition There has been only one new project added to the ILS since our last submittal. This project is the FSA update required by 10 CFR 50.71(e). In accordance with the regulation, this project is due two years after our notification by the Director of NRR of the completion of the Systematic Evaluation Program.
Expected Allocation of Resources for Upcoming Outage The refueling/backfit outage for Cycle X of plant operation is expected to have resources allocated approximately 70% to regulatory projects,and 30% to betterment projects. This allocation reflects a balancing of resource allocation following the last refueling/backfit outage which was approximately 90% regulatory work.
Updated Schedules Schedules A, B and C are attached.
GEH:8209F
ATTACHMENT ILS SCHEDULE A (RULE, REGULATION OR ORDER)
CYCLE X ANTICIPATED TRANSIENTS WITHOUT SCRAM DIVERSE TURBINE TRIP CYCLE XI NONE EVALUATION FSA UPDATE DECEMBER 30, 1988
ILS SCHEDULE B (NRC COMMITMENTS AND OTHER REQUIREMENTS)
CYCLE X AUTOMATION OF THIRD AUXILIARY FEEDWATER PUMP REGULATED INSTRUMENT BUSES INDICATING LIGHTS ON-SITE Toxic GAS SOURCES MODIFICATIONS IN-SERVICE TESTING DIFFERENTIAL PRESSURE INDICATORS MAGNACRAFT RELAY REPLACEMENTS AUTOMATIC VENT SYSTEM FOR BORIC ACID SYSTEM REACTOR CAVITY SAFETY CAGE (OSHA)
CONTROL ROOM HVAC DUCT HEATERS VITAL BUS 4 UNINTERRUPTIBLE POWER SUPPLY CYCLE XI UPGRADE OF CORE EXIT THERMOCOUPLES FOR DETECTION OF INADEQUATE CORE COOLING CONTROL ROOM AND TECHNICAL SUPPORT CENTER HVAC UPGRADES CVCS VALVES MOV-LCV-1100 B, C, D CONTROLS MODIFICATIONS WASTE GAS DECAY TANK MONITORING INSTRUMENTATION STEEL DECKING UNDER TURBINE BUILDING NORTH EXTENSION UNDERVOLTAGE RELAYS FOR PROTECTION FROM DEGRADED GRID VOLTAGE AUTOMATIC TERMINATION OF SAFETY INJECTION PUMPS ON Low RWST LEVEL REMOVAL OF AUTOMATIC REACTOR COOLANT PUMP TRIP ON SAFETY INJECTION ADDITION OF SYNCROCHECK RELAYS TO EMERGENCY DIESEL GENERATORS EVALUATION CONTROL ROOM DESIGN REVIEW AUGUST 14, 1987
ILS SCHEDULE C (BETTERMENT PROJECTS)
CYCLE X NUCLEAR INSTRUMENTATION SYSTEM REPLACEMENT TURBINE VIBRATION DETECTION INSTRUMENTATION MASONILIAN ISOLATION VALVE UPGRADES RADIATION MONITOR SV-99 UPGRADE CYCLE XI CONTROL ROOM INSTRUMENT RACKS REPLACEMENT GEH:8210F