Amend 98 to License DPR-13,implementing License Condition Which Establishes Integrated Implementation Schedule Program Plan.Plan Requires Util to Follow Plan & Terms for Establishing & Revising Schedules for Specific Plant Mods
ML13316A969
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 04/20/1987
From: Knighton G
Office of Nuclear Reactor Regulation
To:
Shared Package
ML13316A967 List:
References
DPR-13-A-098, TAC-54376 NUDOCS 8704290250
Download: ML13316A969 (4)


Text

0cl o

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 SOUTHERN CALIFORNIA EDISON COMPANY AND SAN DIEGO GAS AND ELECTRIC COMPANY DOCKET NO. 50-206 SAN ONOFRE NUCLEAR GENERATING STATION, UNIT NO. 1 AMENDMENT TO PROVISIONAL OPERATING LICENSE Amendment No).98 License No. DPR-13

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by Southern California Edison Company and San Diego Gas and Electric Company (the licensees) dated May 23, 1984, as modified on August 29, 1985 and supplemented on March 26, 1986, October 14, 1986 and March 23, 1987, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, Provisional Operating License No. DPR-13 is amended by adding a new paragraph 3.J. to read as follows:

8704290250 870420 PDR ADOCK 05000206 P

_PDR

-2 3.0 Integrated Implementation Schedule Southern California Edison Company shall implement a plan for scheduling all capital modifications based on the Integrated Implementation Schedule Program Plan (the "Plan") issued in License Amendment No. 98 on April 20, 1987.

(1) The Plan shall be followed by the licensee from and after the effective date of this amendment.

(2) Changes to completion dates for items identified in Schedules B and C do not require a license amendment. Dates specified in Schedule A

.shall be changed only in accordance with applicable NRC procedures.
3. This license amendment is effective as of the date of its issuance.

FOR THE NUCLEAR REGULATOR COMMISSION George. Knighton ;,rector Projec Directorat V Division of Reactor Projects-III/IV/V and Special Projects

Attachment:

Changes to License No. DPR-13 Date of Issuance: April 20, 1987

ATTACHMENT TO LICENSE AMENDMENT NO. 98 PROVISIONAL OPERATING LICENSE NO. DPR-13 DOCKET NO. 50-206 Revise License No. DPR-13 by removing the page identified below and inserting the enclosed page. The revised page is identified by the captioned amendment number and contains a marginal line indicating the area of change.

REMOVE INSERT 3b3-

-3b

[3.I. Deleted]

3.j Integrated Implementation Schedule Southern California Edison Company shall implement a plan for scheduling all capital modifications based on the Integrated Implementation Schedule Program Plan (the "Plan") issued in License Amendment No. 98 on April 20, 1987.

(1) The Plan shall be followed by the licensee from and after the effective date of this amendment.

(2) Changes to completion dates for items identified in Schedules B and C do not require a license amendment. Dates specified in Schedule A shall be changed only in accordance with applicable NRC procedures.

K. Post-Accident Sampling System (PASS), NUREG-0737, Item II.B.3 (1) By July 1, 1986 or startup from the Cycle IX refueling outage, whichever is earlier, SCE shall install a PASS and implement a Amd. No.

post-accident sampling program at San Onofre Unit 1.

85; 11-23-84 (2) Prior to the date in (1) above or until the PASS is operable, SCE shall maintain in effect those compensatory measures described in the SCE 14tter dated August 14, 1984.

Amendment No. 8.

98