NRC 2012-0044, Technical Requirements Manual Change Summary

From kanterella
(Redirected from ML12164A752)
Jump to navigation Jump to search
Technical Requirements Manual Change Summary
ML12164A752
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/12/2012
From: Jim Costedio
Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2012-0044
Download: ML12164A752 (3)


Text

/

BEACH June 12,2012 NRC 2012-0044 10 CFR 50.71 (e)

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Technical Requirements Manual Chanqe Summarv In accordance with 10 CFR 50.71 (e), NextEra Energy Point Beach, LLC (NextEra), is submitting changes made to the Point Beach Nuclear Plant Technical Requirements Manual (TRM).

The enclosure contains the TRM change summary for the period January 1, 201 1, through December 31, 201 1. NextEra previously submitted the TRM change summary for January 1,2010, through December 31,201 0, on June 9,201 1 (MLI 11610157).

This letter contains no new commitments and no revisions to existing commitments.

If you have questions or require additional information, please contact William Hennessy at 9201755-7656.

Very truly yours, NextEra Energy Point Beach, LLC James Costedio Licensing Manager Enclosure cc: Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

ENCLOSURE NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 TECHNICAL REQUIREMENT MANUAL CHANGE

SUMMARY

FOR 2011 Date of Affected Affected Channe Section Panests) Summary 1011911I TRM 2.1 All Revision 13 of the Unit 1 Core Operating Limits Report U1 (COLR) (MLI 13080091). Unit 1 Cycle 34 COLR.

1110211I TRM 2.1 All Revision 14 of the Unit 1 COLR (MLI 13080091). Unit 1 U1 Cycle 34 COLR.

03123111 TRM 2.1 All Revision 13 of the Unit 2 COLR (MLI 10830008). Unit 2 U2 Cycle 32 COLR.

05/18/11 TRM 2.1 All Revision 14 of the Unit 2 COLR (MLI 11390426). Unit 2 U2 Cycle 32 COLR.

08/02/11 TRM 2.1 All Revision 15 of the Unit 2 COLR (MLI 12170414). Unit 2 U2 Cycle 32 COLR.

05/18/11 TRM 2.2 All Revision 7 of the Pressure and Temperature Limits Report (MLI 11390426).

1111511 1 TRM 3.3.2 All Changed the applicability of the leading edge flow meter for extended power uprate (EPU).

1111511 1 TRM 3.5.1 3.5.1 -4, 5, Changed the minimum combined volume requirements and 7 on Table 3.5.1-1. Changed the refueling water storage tank boron concentration to 2800 ppm borated water.

Added a reference; NRC Safety Evaluation for License Amendments 2411245, dated May 3,201 1.

I112311I TRM 3.5.1 3.5.1 -4 Added a 3.00 to < 3.50 Boric Acid Solution Concentration Line to Table 3.5.1 -1.

1111511I TRM 3.7.6 3.7.6-4, 8 Increased the electrical power level at which the crossover steam dump system is activated. Added two references; Siemens letter TL SPG-FPLE PB 0120, dated June 8, 2009, and NRC Safety Evaluation for License Amendments 2411245, dated May 3,201 1.

0111811I TRM 3.7.7 3.7.7-3, 4, Clarified information regarding flushing activities.

11,12 Page 1 of 2

ENCLOSURE NEXTERA ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 TECHNICAL REQUIREMENT MANUAL CHANGE

SUMMARY

FOR 201 1 Date of Affected Affected Chanqe Section Paqesk) Summary 06/01/11 TRM 3.7.7 3.7.7-7, 9 Updated to reflect changes in the auxiliary feedwater system.

06/01/11 TRM 3.7.9 All New TRM chapter for control room emergency fitration system.

06118111 TRM 3.7.9 3.7.9-3, 4 Clarified information for a filter train inoperable due to an inoperable CRE boundary, and for two isolation dampers in the kitchen exhaust duct inoperable.

06/30/11 TRM 3.9.4 All Reactor vessel head lift administrative controls were removed from the TRM. These controls were removed based on a new analysis demonstrating that a postulated reactor vessel head (RVH) drop would not result in a loss of reactor coolant system (RCS) inventory. This chapter is cancelled.

06/01/11 TRM 4.3 All Added WCAP-14986-A, Revision 2, Westinghouse Owners Group Post Accident Sampling System Requirements, July 2000, as a reference. Removed the reference to NUREG 0737 item ll.B.3, "Post Accident Sampling Capability."

06/04/11 TRM 4.1 0 All Added ASME AG-1 ,2009 as a reference. Changes made to reflect the changes in the control room emergency filtration system.

II I I TRM 4.1 2 4.1 2-1, 5, Revised sulfur specification in accordance with the 201 1 6 Wisconsin Air Pollution Control Construction Permit.

06/04/11 TRM 4.1 8 All New TRM chapter for the control room envelope habitability program.

Page 2 of 2