Letter Sequence Other |
|---|
TAC:MC3743, Revise Containment Requirements During Handling Irradiated Fuel and Core Alterations (Approved, Closed) TAC:MC3744, (Approved, Closed) TAC:MC3812, Revise Containment Requirements During Handling Irradiated Fuel and Core Alterations (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: ML042370100, ML050380283, ML050590036, ML050900421, ML051150191, ML051160036, ML051320148, ML051430036, ML051570381, ML051660602, ML052290397, ML060530185, ML060670304, ML060680586, ML060680590, ML060680596, ML060680599, ML060720253, ML060720272, ML060720273, ML060720281, ML060720293, ML060720295, ML060720298, ML060720303, ML060720354, ML060830009, ML060880464, ML060880469, ML061040217, ML061210117, ML061770163, ML061840027, ML061910705, ML062050056, ML062090482, ML062090555, ML062120411, ML062130163, ML062130343, ML062200277, ML062210102, ML062220647, ML062270240, ML062400472, ML062510022, ML062510371, ML062510374, ML062510382, ML062510385... further results
|
MONTHYEARML0607202531975-05-23023 May 1975 May 23, 1975 - Final Summary Report Unit 2 Startup Project stage: Other ML0606805861975-05-23023 May 1975 May 23, 1975 - Final Summary Report Startup, Enclosure 4 Project stage: Other ML0607202721977-05-0909 May 1977 May 9, 1977 - Final Summary Report Unit 3 Startup Project stage: Other ML0606805901977-05-0909 May 1977 May 9, 1977 - Final Summary Report Startup, Enclosure 5 Project stage: Other ML0607202731992-11-30030 November 1992 A Guide for Environmental and Best Management Practices for Tennessee Valley Authority Transmission Construction and Maintenance Activities Project stage: Other ML0607202982001-03-13013 March 2001 Environmental Assessment Bear Creek Reservoirs Land Management Plan Project stage: Other ML0607202952001-03-31031 March 2001 Bear Creek Reservoirs Land Management Plan, Resource Stewardship Bear Creek Watershed Project stage: Other ML0606805992001-03-31031 March 2001 Bear Creek Reservoirs Land Management Plan Project stage: Other ML0423701002004-08-23023 August 2004 Ltr, Framatome Proprietary Review Project stage: Other ML0429202832004-11-18018 November 2004 Ltr, Results of Acceptance Review for Extended Power Uprate Project stage: Acceptance Review ML0431004762004-11-18018 November 2004 Ltr, Results of Acceptance Review for EPU Project stage: Acceptance Review ML0433701792004-12-29029 December 2004 RAI Re Extended Power Uprate Project stage: RAI ML0434400452004-12-30030 December 2004 RAI, Extended Power Uprate Project stage: RAI ML0500303612005-01-0606 January 2005 Ltr, Request for Information for Status of Amendment (Tac No. MC1330, MC1427, MC2305, MC3812, MC4070, MC4071, MC4072, MC4161, MC3743, MC3744) Project stage: RAI ML0501001802005-01-0707 January 2005 December 02, 2004 Browns Ferry Nuclear Plant, Units 1, 2, and 3, Summary of NRC Site Visit and Meeting Regarding Extended Power Uprate and License Renewal Applications Project stage: Meeting ML0503802832005-02-16016 February 2005 Summary of Conference Call with TVA Status of Amendments Using Method 3 Project stage: Other ML0505900362005-02-16016 February 2005 Enclosure 2, 02/01/2005 Conference Call with TVA Presentation Slides on TS Changes Using Method 3 for Interim Solution Project stage: Other ML0505601502005-02-23023 February 2005 Response to NRC Acceptance Review Letter and Request for Additional Information Related to Technical Specifications Change No. TS-431 - Request for Extended Power Uprate Operation Project stage: Request ML0505603372005-02-23023 February 2005 (BFN) - Response to NRCs Acceptance Review Letter and Request for Additional Information Related to Technical Specifications Change No. TS-418 - Request for Extended Power Uprate Operation (Tac Nos MC3743 and MC3744) Project stage: Request ML0607202932005-02-28028 February 2005 Hydrothermal Modeling of Browns Ferry Nuclear Plant with Units 1, 2, and 3 at Extended Power Uprate Project stage: Other ML0606805962005-02-28028 February 2005 Hydrothermal Modeling of Browns Ferry with Units 1, 2, and 3 at Extended Power Uprate Project stage: Other ML0508801572005-04-0101 April 2005 Summary of February 2005 Conference Calls Regarding Extended Power Uprate Acceptance Review Reply Project stage: Acceptance Review ML0509004212005-04-19019 April 2005 Ltr, Licensing Action, Dependencies Requests Project stage: Other ML0511501912005-04-19019 April 2005 Enclosure 3, Ltr, Licensing Action Status and Interdependencies Project stage: Other ML0511702442005-04-25025 April 2005 (BFN) - Unit 1 - Response to NRCs Request for Additional Information Related to Technical Specifications (TS) Change No. TS-431 - Request for Extended Power Uprate Operation Project stage: Request ML0511702422005-04-25025 April 2005 (BFN) - Units 2, and 3 - Response to NRCs Request for Additional Information Related to Technical Specifications (TS) Change No. TS-418 - Request for Extended Power Uprate Operation Project stage: Request ML0514300362005-05-20020 May 2005 Response to NRCs Letter on Licensing Action Status and Interdependencies, Project stage: Other ML0513201462005-05-27027 May 2005 EPU Acceptance Review Results to Increase Maximum Authorized Power Level (TAC No. MC3743, MC3744) (TS-418) Project stage: Acceptance Review ML0513201022005-05-27027 May 2005 Ltr., Extended Power Uprate Acceptance Review Results (Tac No. MC3812) (TS-431) Project stage: Acceptance Review ML0516403912005-06-0606 June 2005 Response to Technical Specifications (TS) Change No. TS-418 - Request for License Amendment - Extended Power Uprate (EPU) Operation Project stage: Request ML0515802492005-06-0606 June 2005 Response to NRCs Request for Additional Information Related to Technical Specifications (TS) Change No. TS - 431 - Request for License Amendment Extended Power Uprate (EPU) Operation Project stage: Request ML0515703812005-06-29029 June 2005 Fanp, Withholding Information from Public (TACs MC3743, MC3744) Project stage: Other ML0516606022005-06-29029 June 2005 Ltr., Withholding Public Disclosure for GE Company (TACs MC3743, MC3744) Project stage: Other ML0513201482005-06-29029 June 2005 Ltr., Ind FRN Facility Operating License for EPU and Opportunity for a Hearing Project stage: Other ML0511600362005-07-0101 July 2005 Notice of Consideration of Issuance of Amendment and Notice of Opportunity for a Hearing Regarding Extended Power Uprate (Tac No. MC3743, MC3744) Project stage: Other ML0518703902005-07-0707 July 2005 Meeting Summary with TVA and Framatome Regarding Fuel Analysis Methodology, Enclosure 2, Framatome Presentation Project stage: Meeting ML0520003282005-07-14014 July 2005 Surveillance Program for Channel-Control Blade Interference Project stage: Request ML0520706042005-07-26026 July 2005 Notice of Meeting with Tennessee Valley Authority (TVA) BFN Units 1, 2, and 3, and Sequoyah Units 1 and 2 on Resolution of Instrument Setpoint Concerns Project stage: Meeting ML0524204912005-08-23023 August 2005 Ltr., GE Request for Withholding Information from Public on Steam Dryer Analysis for EPU Conditions Project stage: Withholding Request Acceptance ML0522901442005-09-0202 September 2005 Summary of Meeting with the Tennessee Valley Authority Regarding Plant-Specific Resolution of Instrument Setpoint Concerns Project stage: Meeting ML0522903972005-09-0202 September 2005 TVA Handout Method 3 Issue BFN Proposed Resolution Project stage: Other ML0526600222005-09-30030 September 2005 Proprietary Information Review, Regarding GE Request for Withholding Information from Public Disclosure for Browns Ferry Unit 1, EPU Enclosure 4 Project stage: Withholding Request Acceptance ML0524303412005-10-0303 October 2005 RAI, Extended Power Uprate (TS-431) (Tac No. MC3812) Project stage: RAI ML0525104462005-10-0303 October 2005 Request for Additional Information Regarding Extended Power Uprate Project stage: RAI ML0535601862005-12-19019 December 2005 Response to NRC Round 2 Request for Additional Information Related to Technical Specifications Change No. TS-418-Request for Extended Power Uprate Operation Project stage: Request ML0535601942005-12-19019 December 2005 Response to NRC Round 2 Requests for Additional Information Related to Technical Specifications Change No. TS-431 - Request for Extended Power Uprate Operation Project stage: Request 05000296/LER-2005-003, Regarding Reactor Scram from Main Turbine Trip During Switching Operation2005-12-19019 December 2005 Regarding Reactor Scram from Main Turbine Trip During Switching Operation Project stage: Request ML0535601202005-12-22022 December 2005 Request for Additional Information, Information Concerning Extended Power Uprate Project stage: RAI ML0535601772005-12-22022 December 2005 Request for Additional Information, Concerning Extended Power Uprate Project stage: RAI ML0535703412006-01-19019 January 2006 Revised Schedule for Response to Extended Power Uprate Requests for Additional Information Project stage: RAI 2005-02-23
[Table View] |
Text
Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 Brian O'Grady Vice President, Browns Ferry Nuclear Plant March 9, 2006 TVA-BFN-TS-431 TVA-BFN-TS-418 U.S. Nuclear Regulatory Commission 10 CFR 50.90 ATTN:
Document Control Desk Mail Stop OWFN, P1-35 Washington, D. C. 20555-0001 Gentlemen:
In the Matter of
)
Docket Nos.50-259 Tennessee Valley Authority
)
50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) -
UNITS 1, 2, and 3 -
TECHNICAL SPECIFICATIONS (TS) CHANGES TS-431 AND TS-418 EXTENDED POWER UPRATE (EPU)
STEAM DRYER BENCHMARKING REPORT (TAC NOS.
- MC3812, MC3743, AND MC3744)
During a teleconference between NRC and TVA on February 13, 2006, it was agreed that TVA would provide NRC with benchmarking, scale model testing, and stress analysis reports for BFN steam dryer performance under EPU operating conditions.
Enclosed is "GENE-0000-0049-6652-01,General Electric Boiling Water Reactor Steam Dryer Scale Model Test Based Fluctuating Load Definition Methodology - March 2006 Benchmark Report."
The report version in Enclosure 1 contains information that the General Electric Company (GE) considers to be proprietary in nature and subsequently, pursuant to 10 CFR 9.17(a)(4), 2.790(a)(4) and 2.790(d)(1), requests that such information be withheld from public disclosure. contains an affidavit from GE supporting this request.
contains the redacted version of the report, with the GE proprietary material removed, which is suitable for public disclosure.
DUO3 Primed orn rc paper
U.S. Nuclear Regulatory Commission Page 2 March 9, 2006 Additionally, in letters to NRC on December 19, 2005 (ADAMS Accession Nos. ML053560186 and ML053560194) concerning TS-418 and TS-431, TVA stated that a status report providing additional steam dryer performance information would be provided to NRC by March 31, 2006.
In that regard, the steam dryer scale model testing (SMT) final report will be provided to the NRC by April 15, 2006, and the dryer stress analysis report will be provided to the NRC by May 5, 2006.
These dates correspond to the dates given in the enclosure to the March 1, 2006, letter from NRC to TVA on the revised schedule for review of TS-418 and TS-431.
There are no commitments contained in this letter.
If you have any questions regarding this letter, please contact William D. Crouch, Site Licensing Manager, at (256) 729-2636.
Sincerely, Brian O'Grady : GE-NE-0000-0049-6652-O1P (proprietary version) : GE-NE-0000-0049-6652-O1NP (non-proprietary version)
U.S. Nuclear Regulatory Commission Page 3 March 9, 2006 Enclosures cc (Enclosures):
U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-3415 Mr. Malcolm T. Widmann, Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-3415 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611-6970 Margaret Chernoff, Senior Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Eva A. Brown, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739