TAC:MC1330, (Open) TAC:MC1427, (Approved, Closed) TAC:MC2305, (Approved, Closed) TAC:MC3743, Revise Containment Requirements During Handling Irradiated Fuel and Core Alterations (Approved, Closed) TAC:MC3744, (Approved, Closed) TAC:MC3812, Revise Containment Requirements During Handling Irradiated Fuel and Core Alterations (Approved, Closed) TAC:MC4070, (Open) TAC:MC4071, (Open) TAC:MC4072, (Open) TAC:MC4161, (Open) |
|
MONTHYEARML0606805861975-05-23023 May 1975 May 23, 1975 - Final Summary Report Startup, Enclosure 4 Project stage: Other ML0607202531975-05-23023 May 1975 May 23, 1975 - Final Summary Report Unit 2 Startup Project stage: Other ML0606805901977-05-0909 May 1977 May 9, 1977 - Final Summary Report Startup, Enclosure 5 Project stage: Other ML0607202721977-05-0909 May 1977 May 9, 1977 - Final Summary Report Unit 3 Startup Project stage: Other ML0607202731992-11-30030 November 1992 A Guide for Environmental and Best Management Practices for Tennessee Valley Authority Transmission Construction and Maintenance Activities Project stage: Other ML0607202982001-03-13013 March 2001 Environmental Assessment Bear Creek Reservoirs Land Management Plan Project stage: Other ML0606805992001-03-31031 March 2001 Bear Creek Reservoirs Land Management Plan Project stage: Other ML0607202952001-03-31031 March 2001 Bear Creek Reservoirs Land Management Plan, Resource Stewardship Bear Creek Watershed Project stage: Other L-80-017, (Bfn), Unit 1 - Technical Specifications (TS) Change 437 - Scram Discharge Volume Water Level Setpoint2003-11-0303 November 2003 (Bfn), Unit 1 - Technical Specifications (TS) Change 437 - Scram Discharge Volume Water Level Setpoint Project stage: Request ML0411106652004-04-16016 April 2004 Brown Ferry, Unit 1, Request for Additional Information, Scram Discharge Volume Water Level Setpoint Project stage: RAI ML0412803272004-05-0606 May 2004 Technical Specifications (TS) Change 437 - Response to Request for Additional Information Regarding Scram Discharge Volume Water Level Setpoint Project stage: Response to RAI ML0423707612004-08-16016 August 2004 Technical Specifications Change TS-447 - Extension of Channel Calibration Surveillance Requirement Performance Frequency and Allowable Value Revision Project stage: Other ML0423701002004-08-23023 August 2004 Ltr, Framatome Proprietary Review Project stage: Other ML0425702122004-09-13013 September 2004 RAI, Allowable Value for Reactor Vessel Water Level Project stage: RAI ML0429403302004-10-19019 October 2004 RAI, Power Range Neutron Monitor Upgrade Project stage: RAI ML0431303662004-11-0808 November 2004 Technical Specifications (TS) Change 430 - Response to Request for Additional Information Regarding Power Range Neutron Monitor Upgrade with Implementation of Average Power Range Monitor and Rod Block Monitor Project stage: Response to RAI ML0431004762004-11-18018 November 2004 Ltr, Results of Acceptance Review for EPU Project stage: Acceptance Review ML0429202832004-11-18018 November 2004 Ltr, Results of Acceptance Review for Extended Power Uprate Project stage: Acceptance Review ML0433701792004-12-29029 December 2004 RAI Re Extended Power Uprate Project stage: RAI ML0434400452004-12-30030 December 2004 RAI, Extended Power Uprate Project stage: RAI ML0500303612005-01-0606 January 2005 Ltr, Request for Information for Status of Amendment (Tac No. MC1330, MC1427, MC2305, MC3812, MC4070, MC4071, MC4072, MC4161, MC3743, MC3744) Project stage: RAI ML0501001802005-01-0707 January 2005 December 02, 2004 Browns Ferry Nuclear Plant, Units 1, 2, and 3, Summary of NRC Site Visit and Meeting Regarding Extended Power Uprate and License Renewal Applications Project stage: Meeting ML0436405562005-01-10010 January 2005 Ltr, Acceptance Review to Extend Technical Specification (TAC No. MC4070, MC4071, MC4072) (TS-447) Project stage: Acceptance Review ML0505900362005-02-16016 February 2005 Enclosure 2, 02/01/2005 Conference Call with TVA Presentation Slides on TS Changes Using Method 3 for Interim Solution Project stage: Other ML0503802832005-02-16016 February 2005 Summary of Conference Call with TVA Status of Amendments Using Method 3 Project stage: Other ML0505601502005-02-23023 February 2005 Response to NRC Acceptance Review Letter and Request for Additional Information Related to Technical Specifications Change No. TS-431 - Request for Extended Power Uprate Operation Project stage: Request ML0505603372005-02-23023 February 2005 (BFN) - Response to NRCs Acceptance Review Letter and Request for Additional Information Related to Technical Specifications Change No. TS-418 - Request for Extended Power Uprate Operation (Tac Nos MC3743 and MC3744) Project stage: Request ML0606805962005-02-28028 February 2005 Hydrothermal Modeling of Browns Ferry with Units 1, 2, and 3 at Extended Power Uprate Project stage: Other ML0607202932005-02-28028 February 2005 Hydrothermal Modeling of Browns Ferry Nuclear Plant with Units 1, 2, and 3 at Extended Power Uprate Project stage: Other ML0507703702005-03-11011 March 2005 Technical Specifications (TS) Change TS-447, Request for Additional Information (RAI) - Extension of Channel Calibration Surveillance Requirement Performance Frequency and Allowable Value Revision Project stage: Request ML0508801572005-04-0101 April 2005 Summary of February 2005 Conference Calls Regarding Extended Power Uprate Acceptance Review Reply Project stage: Acceptance Review ML0511501912005-04-19019 April 2005 Enclosure 3, Ltr, Licensing Action Status and Interdependencies Project stage: Other ML0509004212005-04-19019 April 2005 Ltr, Licensing Action, Dependencies Requests Project stage: Other ML0511702422005-04-25025 April 2005 (BFN) - Units 2, and 3 - Response to NRCs Request for Additional Information Related to Technical Specifications (TS) Change No. TS-418 - Request for Extended Power Uprate Operation Project stage: Request ML0511702442005-04-25025 April 2005 (BFN) - Unit 1 - Response to NRCs Request for Additional Information Related to Technical Specifications (TS) Change No. TS-431 - Request for Extended Power Uprate Operation Project stage: Request ML0514300362005-05-20020 May 2005 Response to NRCs Letter on Licensing Action Status and Interdependencies, Project stage: Other ML0513201022005-05-27027 May 2005 Ltr., Extended Power Uprate Acceptance Review Results (Tac No. MC3812) (TS-431) Project stage: Acceptance Review ML0513201462005-05-27027 May 2005 EPU Acceptance Review Results to Increase Maximum Authorized Power Level (TAC No. MC3743, MC3744) (TS-418) Project stage: Acceptance Review ML0515802492005-06-0606 June 2005 Response to NRCs Request for Additional Information Related to Technical Specifications (TS) Change No. TS - 431 - Request for License Amendment Extended Power Uprate (EPU) Operation Project stage: Request ML0516403912005-06-0606 June 2005 Response to Technical Specifications (TS) Change No. TS-418 - Request for License Amendment - Extended Power Uprate (EPU) Operation Project stage: Request ML0516606022005-06-29029 June 2005 Ltr., Withholding Public Disclosure for GE Company (TACs MC3743, MC3744) Project stage: Other ML0515703812005-06-29029 June 2005 Fanp, Withholding Information from Public (TACs MC3743, MC3744) Project stage: Other ML0513201482005-06-29029 June 2005 Ltr., Ind FRN Facility Operating License for EPU and Opportunity for a Hearing Project stage: Other ML0511600362005-07-0101 July 2005 Notice of Consideration of Issuance of Amendment and Notice of Opportunity for a Hearing Regarding Extended Power Uprate (Tac No. MC3743, MC3744) Project stage: Other ML0518703902005-07-0707 July 2005 Meeting Summary with TVA and Framatome Regarding Fuel Analysis Methodology, Enclosure 2, Framatome Presentation Project stage: Meeting ML0520003282005-07-14014 July 2005 Surveillance Program for Channel-Control Blade Interference Project stage: Request ML0520706042005-07-26026 July 2005 Notice of Meeting with Tennessee Valley Authority (TVA) BFN Units 1, 2, and 3, and Sequoyah Units 1 and 2 on Resolution of Instrument Setpoint Concerns Project stage: Meeting ML0521301352005-08-15015 August 2005 RAI, Regarding Channel Calibration Test Interval (TS-447) (Tac Nos. MC4070, MC4071, MC4072) Project stage: RAI ML0524204912005-08-23023 August 2005 Ltr., GE Request for Withholding Information from Public on Steam Dryer Analysis for EPU Conditions Project stage: Withholding Request Acceptance ML0522901442005-09-0202 September 2005 Summary of Meeting with the Tennessee Valley Authority Regarding Plant-Specific Resolution of Instrument Setpoint Concerns Project stage: Meeting 2005-01-07
[Table View] |
Summary of Conference Call with TVA Status of Amendments Using Method 3| ML050380283 |
| Person / Time |
|---|
| Site: |
Browns Ferry  |
|---|
| Issue date: |
02/16/2005 |
|---|
| From: |
Chernoff M NRC/NRR/DLPM/LPD2 |
|---|
| To: |
Singer K Tennessee Valley Authority |
|---|
| Chernoff, M H, NRR/DLPM, 301-415-4041 |
| Shared Package |
|---|
| ML050480652 |
List: |
|---|
| References |
|---|
| ISA-S67.04-1994, ML041690604, TAC MC1330, TAC MC1427, TAC MC2305, TAC MC3743, TAC MC3744, TAC MC3812, TAC MC4070, TAC MC4071, TAC MC4072, TAC MC4161 10 CFR 50.36, 10 CFR 50.59, TS-418, TS-431, TS-434, TS-437, TS-443, TS-447 |
| Download: ML050380283 (5) |
|
Text
February 16, 2005 LICENSEE:
Tennessee Valley Authority FACILITIES:
Browns Ferry Units 1, 2 and 3
SUBJECT:
SUMMARY
OF FEBRUARY 1, 2005, CONFERENCE CALL REGARDING REQUEST FOR INFORMATION REGARDING STATUS OF AMENDMENTS USING METHOD 3 (TAC NOS. MC1330, MC1427, MC2305, MC3812, MC4070, MC4071, MC4072, MC4161, MC3743, MC3744)
On February 1, 2005, the U.S. Nuclear Regulatory Commission (NRC) staff conducted a conference call with the Tennessee Valley Authority (TVA, the licensee) representatives. The call was conducted at the licensees request and served as the licensees response to the Nuclear Regulatory Commission (NRC) staffs January 6, 2005, letter, which discussed six amendments proposed by TVA. These proposed amendments involved setpoints calculated using Instrumentation, Systems and Automation Society of America (ISA) Standard, ISA-S67.04-1994, Setpoints for Nuclear Safety-Related Instrumentation, Method 3. is a list of attendees and Enclosure 2 is a copy of TVA viewgraphs presented during the meeting.
BACKGROUND TVA submitted six license amendment requests (TS-418, TS-431, TS-434, TS-437, TS-443, TS-447) using instrumentation setpoints established using a methodology about which the NRC staff has concerns. The NRC staff has identified that the methodology does not provide adequate assurance that a plant will operate in accordance with the assumptions upon which the plant safety analyses have been based under certain conditions. The NRC staffs safety concerns were described in a letter from Mr. Ledyard Marsh to Mr. Alex Marion of the Nuclear Energy Institute [ADAMS Accession Number ML041690604]. The issue was also discussed in various public meetings held in June and July 2004.
TVA calculated multiple setpoint Allowable Values (AVs) by means of ISA Standard, ISA-S67.04-1994, Setpoints for Nuclear Safety-Related Instrumentation. The NRC staff determined that setpoint AVs established by means of ISA 67.04 Part 2 Method 3 (Method 3) may not be calculated conservatively enough to ensure that instrument uncertainty and routine drift will not result in challenging the analytical limits. Since the six amendments were based on a methodology about which the NRC staff has concerns, the NRC issued a letter dated January 6, 2005, requesting TVA to address how they wanted to proceed. The letter requested that TVA either revise the applications to address the NRC staffs safety concerns and provide a schedule for submittal of the revised applications, or withdraw the requests and resubmit when the generic issue has been resolved.
2 DISCUSSION The NRC staff described ongoing efforts to resolve concerns with Method 3. The staff is developing a generic resolution that will be presented to NRR senior management by March 31, 2005. The focal point of the NRC staffs proposed resolution is the issue of re-setting instruments to the calculated Trip Setpoint following periodic Channel Operational Testing. This aspect is of particular concern to the staff when Method 3 is employed due to the less conservative nature of the definition of the AV as the operability limit and potential challenges that could result in transgressing Analytical Limits as a result of loop uncertainty and instrument drift. The NRC staff agrees that ISA Method 3 is an acceptable method for determination of instrument setpoints, provided that the trip setpoint and the AV are set appropriately and reset of the instrument to the calculated trip setpoint is accomplished at the completion of surveillance testing. The difference between the licensees proposed solution and the NRC staffs position involves the mechanism of regulatory controls over the practice of resetting the instrument at the conclusion of surveillance testing (i.e., the as-left value) and the regulatory controls needed to determine instrument technical specification (TS) operability.
The NRC staff indicated to the licensee that the requirement for re-set needs to be reflected in the plant TSs in accordance with Title 10, Code of Federal Regulations (10 CFR) Section 50.36.
Recognizing that the re-set is currently captured in TS Bases and plant procedures for a significant number of affected plants, the NRC staff is considering development of a Consolidated Line Item Improvement Process to insert regulatory controls over a requirement to re-set the instruments after surveillance testing into the TSs. The NRC staffs proposed solution would not require any licensee to recalculate/revise the setpoints or to change setpoint calculation methodology. However, it would provide a regulatory control that ensures equipment would be capable of performing its intended safety function.
The licensee provided a history of the correspondence surrounding the generic review of this concern and then presented an interim plant-specific solution. TVA 's proposed interim plant-specific solution is the addition of statements to the applicable TS Bases section clarifying what constitutes instrument operability, and stating that setpoints should be adjusted to within the established calibration tolerance band at the completion of testing. Deviations from the process would constitute a change to the approved methodology and, therefore, would require review and approval by the NRC staff. The licensee provided assurances that appropriate control of the practice can be performed through 10 CFR 50.59.
The NRC staff did not agree with the licensees rationale that 10 CFR 50.59 would be adequate to ensure compliance with the requirements nor did the staff agree that a change to information in the TS Bases would require NRC staff review per 10 CFR 50.59. The NRC staff reiterated that reliance on settings or practices outside the TS, and not mandated by the TS, is not consistent with 10 CFR 50.36.
3 The licensee indicated their intent to delay revision of these submittals until the generic issue is resolved, and that the delay would not adversely affect site scheduled activities.
The NRC staff considered this conference call as the licensees response to the January 6, 2005, letter. No commitments were made by the licensee and no regulatory decisions were made by the NRC staff during the proceedings of this conference call.
/RA/
Margaret H. Chernoff, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260 and 50-296
Enclosures:
- 1. List of Participants
- 2. TVA Presentation Slides w/ enclosures: See next page
ML050380283 Enclosure No.: ML050590036 NRC-001 OFFICE PDII-2/PM PDII-2/PM PDII-2/LA PDII-2/SC PDII-1/SC NAME EBrown MChernoff BClayton MMarshall JNakoski DATE 2/ 16 /05 2/ 16 /05 2/ 16 /05 2/ 16 /05 2/ 10 /05
Participant List Conference Call FEBRUARY 1, 2005 NRC TENNESSEE VALLEY AUTHORITY Paul Rebstock Rich DeLong Ed Hackett Tony Langley John Nakoski Dave Burrell Tom Boyce Jim Ballard Carl Shulten Bert Morris Bob Clark Tim Abney Michael Marshall Chris Gratton Hukam Garg Steve Cahill Margaret Chernoff Eva Brown