ML052310593

From kanterella
Jump to navigation Jump to search
IR 05000133-05-002 on 11/02/2004 for Pacific Gas and Electric Company; Humboldt Bay Power Plant (Hbpp) Unit 3 - NRC Special Inspection Final Report Completed on 06/20-24/2005
ML052310593
Person / Time
Site: Humboldt Bay
Issue date: 08/19/2005
From: Wert L
Division of Nuclear Materials Safety IV
To: Rueger G
Pacific Gas & Electric Co
References
EA-05-166, NMED 040585, NMED 050105 IR-05-002
Download: ML052310593 (62)


See also: IR 05000133/2005002

Text

August 19, 2005

EA-05-166

NMED Nos. 040585, 050105

Gregory M. Rueger, Senior Vice

President, Generation and Chief Nuclear Officer

Pacific Gas and Electric Company

Diablo Canyon Power Plant

P.O. Box 3

Avila Beach, CA 93424

SUBJECT: HUMBOLDT BAY POWER PLANT UNIT 3 - NRC SPECIAL INSPECTION

FINAL REPORT 050-00133/05-002

Dear Mr. Rueger:

This refers to the special inspection initiated on November 2, 2004, at the Humboldt Bay Power

Plant (HBPP) Unit 3 facility. The purpose of the special inspection was to review the

circumstances of the reported loss of three approximately 18-inch long spent fuel rod

segments, one intact incore detector, and parts of three other incore detectors all containing

special nuclear material (SNM). An interim inspection report was issued on April 5, 2005, that

described the inspection activities through March 31, 2005. On June 20-24, 2005, a team of

inspectors visited HBPP to complete the inspection. Subsequent to this site visit inspectors

interviewed personnel, and reviewed and evaluated licensee documents submitted after the

visit. The inspection activities were concluded on August 2, 2005. On August 16, 2005, a

telephonic exit interview was conducted with you and members of your staff to discuss the

inspection results.

This report documents the NRCs assessment of: Pacific Gas and Electrics (PG&E) current

control of SNM; accountability for the remainder of the SNM in the spent fuel pool; the

adequacy of PG&Es investigation into the circumstances that led to the loss of accountability of

the missing SNM; the potential radiological consequences of the postulated scenarios involving

the missing SNM; and compliance with applicable regulations.

The NRC special inspection team determined that your investigation was thorough and

complete, and the conclusions were reasonable and supportable. The NRC also found that

once these matters were identified by PG&E, you promptly and accurately notified the NRC and

kept it informed throughout the process of search and investigation.

The NRC staff concluded that the current material control and accounting program being

implemented at the Humboldt Bay Power Plant meets regulatory requirements. In addition, the

NRC team agreed with your conclusion that there is no evidence to support theft or diversion of

the missing SNM, and this is not a plausible scenario. The NRC teams conclusions differed

Pacific Gas and Electric Company -2-

from yours in one notable respect. The NRC team concluded that the most likely scenario for

the missing SNM is that it was inadvertently shipped to a low level waste burial site. While your

conclusions supported this as a possibility, your investigation concluded that the most likely

scenario for the missing spent fuel rod segments was that they are still in your spent fuel pool in

an altered condition.

Based on the results of this inspection, three apparent violations were identified and are being

considered for escalated enforcement action in accordance with the NRC Enforcement Policy.

The current Enforcement Policy is included on the NRCs Web site at www.nrc.gov; select

What We Do, Enforcement, then Enforcement Policy. The apparent violations involved

(1) the failure to keep records showing the inventory, transfer or disposal of the three 18-inch

segments of irradiated fuel and one complete and three partial incore detectors; (2) the failure

to establish, maintain, and follow adequate written material control and accounting procedures

sufficient to account for the SNM; and (3) the failure to conduct an accurate physical inventory

of all SNM in your possession at intervals not to exceed 12 months. The circumstances

surrounding these apparent violations, the significance of the issues, and the need for lasting

and effective corrective action were discussed with members of your staff at the inspection exit

meeting on August 16, 2005. As a result, it may not be necessary to conduct a predecisional

enforcement conference in order to enable the NRC to make an enforcement decision.

Before the NRC makes its enforcement decision, we are providing you an opportunity to either:

(1) respond to the apparent violations addressed in this inspection report within 30 days of the

date of this letter or (2) request a predecisional enforcement conference. If a conference is

held, it will be open for public observation. The NRC will also issue a Meeting Notice to

announce the conference. Please contact Dr. Blair Spiztberg, at (817) 860-8191 within 7 days

of the date of this letter to notify the NRC of your intended response.

If you choose to provide a written response, it should be clearly marked as a "Response to

Apparent Violations in Inspection Report No. 050-00133/05-002; EA-05-166, and should

include for each apparent violation: (1) the reason for the apparent violation, or, if contested,

the basis for disputing the apparent violation, (2) the corrective steps that have been taken and

the results achieved, (3) the corrective steps that will be taken to avoid further violations, and

(4) the date when full compliance will be achieved. Your response may reference or include

previous docketed correspondence, if the correspondence adequately addresses the required

response. If an adequate response is not received within the time specified or an extension of

time has not been granted by the NRC, the NRC will proceed with its enforcement decision.

In addition, please be advised that the number and characterization of apparent violations

described in the enclosed inspection report may change as a result of further NRC review. You

will be advised by separate correspondence of the results of our deliberations on this matter.

During a public meeting held in Eureka, California on September 29, 2004, to discuss the

missing spent fuel rod segments, the NRC indicated its intent to hold another public meeting in

the area at the conclusion of the special inspection to discuss the NRC findings. This public

meeting has been scheduled for the evening of September 15, 2005. A separate meeting

notice and agenda will be issued at least 10 days prior to this meeting.

Pacific Gas and Electric Company -3-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosures, and your response (if you choose to provide one) will be made available

electronically for public inspection in the NRC Public Document Room or from the NRCs

document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html. To the extent possible, your response should not include any personal privacy,

proprietary, or safeguards information so that it can be made available to the Public without

redaction.

Sincerely,

/RA/

Leonard D. Wert Jr., Director

Division of Nuclear Materials Safety

Docket No.: 050-00133

License No.: DPR-7

Enclosure:

1. NRC Special Inspection Report

050-00133/05-002

2. Special Inspection Charter (ML042990566)

cc w/enclosure:

Donna Jacobs, Vice President

Nuclear Services

Diablo Canyon Power Plant

P.O. Box 56

Avila Beach, CA 93424

Richard F. Locke, Esq.

Pacific Gas and Electric Company

P.O. Box 7442

San Francisco, CA 94120

Roy B. Willis, Plant Manager

Pacific Gas and Electric Company

Humboldt Bay Power Plant

1000 King Salmon Avenue

Eureka, CA 95503

Chairman

Humboldt County Board of Supervisors

County Courthouse

825 Fifth Street

Eureka, CA 95501

Pacific Gas and Electric Company -4-

Law Office of Linda J. Brown, Esq.

300 Drakes Landing Road, Suite 172

Greenbrae, CA 94904

Regional Radiation Representative

U. S. Environmental Protection Agency

Region IX Office

75 Hawthorne Street

San Francisco, CA 94105

Dr. Richard Ferguson, Energy Chair

Sierra Club California

1100 llth Street, Suite 311

Sacramento, CA 95814

Dr. James F. Davis, State Geologist

Department of Conservation

Division of Mines & Geology

801 K Street MS 12-30

Sacramento, CA 95814-3531

Ed Bailey, Chief

Radiologic Health Branch

State Department of Health Services

P.O. Box 997414 (MS 7610)

Sacramento, CA 95899-7414

Director

Energy Facilities Siting Division

Energy Resources Conservation &

Development Commission

1516 9th Street

Sacramento, CA 95814

Gretchen Dumas, Esq.

Public Utilities Commission

of the State of California

5066 State Building

San Francisco, CA 94102

Redwood Alliance

P.O. Box 293

Arcata, CA 95521

James D. Boyd, Commissioner

California Energy Commission

1516 Ninth Street (MS 34)

Sacramento, CA 95814

Pacific Gas and Electric Company -5-

bcc w/enclosure (via ADAMS distrib):

BSMallett

TPGwynn

J. Dixon-Herrity, OEDO RIV Coordinator (JLD)

LWCamper, NMSS/DWM

DMGillen, NMSS/DWM/DCD

CMCraig, NMSS/DWM/DCD

JBHickman, NMSS/DWM/DCD

LDWert

CLCain

DBSpitzberg

GFSanborn

EMGarcia

MCWilliams, NSIR/DNS/NSO/SOS

GWTuttle NSIR/DNS/NSO/SOS

RLKellar

TKMcLellan, NRR/ADPT/DE/EMCB

WCSifre

KEGardin

FCDB File

SISP Review Complete: EMG

ADAMS: X Yes Initials: emg

X Publicly Available X Non-Sensitive

DOCUMENT NAME: s:\dnms\!fcdb\emg\5050013302 Final: r:\_hb\5050013302

RIV:DNMS:FCDB RIV:DNMS:FCDB NRR:DE:EMCB

EMGarcia RLKellar TKMcLellan

/RA/ via e-mail /RA/ /RA/ via e-mail

08/16/2005 08/17/2005 08/16/2005

RIV:DRS:EB1 NSIR:DNS:SOS NSIR:DNS:SOS NMSS:DWMEP:DD:RDS

WCSifre GWTuttle MCWilliams JBHickman

/RA/ via e-mail /RA/ via e-mail /RA/ via e-mail /RA/ via e-mail

08/16/2005 08/18/2005 08/16/2005 08/16/2005

RIV:ACES C:FCDB D:DNMS

GFSanborn* DBSpitzberg* LDWert

/RA/ /RA/ /RA/

08/16/2005 08/17/2005 08/19/2005

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

  • Previous Concurrence

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.: 050-00133

License No.: DPR-7

Report No.: 050-00133/05-002

Licensee: Pacific Gas and Electric Company (PG&E)

Facility: Humboldt Bay Power Plant (HBPP), Unit 3

Location: 1000 King Salmon Avenue

Eureka, California 95503

Dates: November 2, 2004, through August 2, 2005

Inspectors: Emilio M. Garcia, Health Physicist, Team Leader

John B. Hickman, Project Manager, NMSS

Ray L. Kellar, P.E., Health Physicist

Thomas K. McLellan, Materials Inspector, NRR

Glenn W. Tuttle, MC&A Physical Scientist, NSIR

Wayne C. Sifre, Reactor Inspector

Martha C. Williams, Sr. MC&A Physical Scientist, NSIR

Approved By: D. Blair Spitzberg, Ph.D., Chief

Fuel Cycle and Decommissioning Branch

Attachment: Supplemental Inspection Information

ADAMS Entry:IR 05000133-05-02, on 11/02/2004-08/02/2005; Pacific Gas & Electric

Co.; Humboldt Bay, Unit 3. Special Inspection Final Report. Three

apparent violations.

-2-

TABLE OF CONTENTS

EXECUTIVE SUMMARY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

REPORT DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

2. Review of PG&Es SNM Control and Accountability Project . . . . . . . . . . . . . . . . . . . . . . 12

3. Material Control and Accounting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

4. Review of Scenario Involving Fuel Segments Shipped Offsite with Low Level

Radioactive Waste (LLRW) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

5. Review of Scenario Involving Fuel Segments Shipped Offsite In Other Direct

Shipments (ODS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

6. Review of Scenario Involving Incore Detectors Shipped Offsite with Low Level

Radioactive Waste (LLRW) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

7. Review of Scenario Involving Fuel Segments Stolen or Diverted . . . . . . . . . . . . . . . . . . 32

8. Review of Scenario Involving Fuel Segments Remaining in the SFP in an

Altered Condition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

9. Cause Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39

10. Health and Safety Consequences . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

11. Discussion of Previously Identified Unresolved Items and Apparent Violations . . . . . . . 43

12. Licensee Briefings and Exit Interview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46

ATTACHMENT - SUPPLEMENTAL INSPECTION INFORMATION:

PARTIAL LIST OF PERSONS CONTACTED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

INSPECTION PROCEDURES USED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . . . 1, 2 and 3

LIST OF ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

LIST (Partial) OF SIGNIFICANT DOCUMENTS REVIEWED . . . . . . . . . . . . . . . . . . . . 5

-3-

EXECUTIVE SUMMARY

Humboldt Bay Power Plant, Unit 3

NRC Inspection Report 050-00133/05-002

During the fall of 2003, staff from Pacific Gas and Electric (PG&E) Humboldt Bay Power Plant

were conducting an examination of the contents of its spent fuel pool (SFP). This examination

was in preparation for eventual removal of the fuel for placement into dry storage in an onsite

Independent Spent Fuel Storage Installation (ISFSI). During the sorting of materials in a

container in the SFP, licensee personnel discovered a fragment of a spent fuel rod

approximately 4-inches long. Licensee personnel located additional fuel fragments ranging in

length from 4 to 6 inches in subsequent sorting of materials in the SFP.

The discovery of fuel fragments indicated a potential problem with the Humboldt Bay material

control and accounting (MC&A) practices. In January 2004, during an NRC inspection, the

Plant Manager announced that due to the unexpected presence of the fuel fragments and other

uncertainties in the special nuclear material (SNM) inventory, the licensee initiated a

re-evaluation of the amount of SNM present in each assembly and in the SFP. The NRC

periodically monitored the licensees investigation. In addition, on March 25, 2004, the NRC

conducted a review of practices of spent fuel MC&A at HBPP in accordance with guidance

contained in Temporary Instruction 2515/154, Phases I and II. This Instruction was

implemented to determine if the MC&A issues at Millstone 1 regarding the loss of two spent fuel

rods, are applicable to other power reactors. Based on that review, the NRC decided that

Humboldt Bay required a Phase III inspection under Temporary Instruction 2515/154.

[Completion of Phase III of Temporary Instruction 2515/154 was documented in Inspection

Report Number 50-133/2005-01].

In late June 2004, the licensee found documentation indicating that in 1968 a stainless steel

clad fuel pin from assembly A-49 was segmented into three 18-inch sections. Other records

indicated that the complete A-49 assembly was later shipped offsite for reprocessing. The

licensee promptly informed the NRC of this discovery.

On July 16, 2004, the licensee made formal notification to the NRC pursuant to the

requirements of 10 CFR 20.2201(a)(1)(ii) of the discrepancy between inventory records and the

location of spent fuel pin segments. No records had been found indicating the location of the

fuel segments in the SFP. During July and August 2004, licensee personnel searched the most

likely and accessible locations within the SFP where the fuel segments could be. Region IV

NRC inspectors observed part of the search activities. On August 16, 2004, PG&E issued a 30-

day written followup report to its initial July 16, 2004, notification to the NRC, and the next day

the licensee made a 1-hour notification to the NRC pursuant to 10 CFR 74.11(a) that the

subject fuel pin segments were considered missing.

On September 29, 2004, the NRC held a meeting with licensee management and members of

the public in Eureka, California, to discuss the missing fuel and the licensees planned search

activities. During the public meeting, the NRC Region IV Regional Administrator announced

this special inspection and on October 25, 2004, Region IV established its charter (attached).

On February 22, 2005, the licensee issued their Special Nuclear Material Control and

-4-

Accountability Project Interim Reports (PG&E Interim Reports). On the same date, the licensee

notified NRC (Event Report 41340) and issued License Event Report 2005-01. This notification

and report informed NRC that PG&E was unable to locate one intact in-core detector and three

partial in-core detectors, amounting to less than a gram of SNM.

After the licensee had completed its major search activities for the missing SNM on April 5,

2005, NRC issued Inspection Report Number 50-133/2005-01. This report was an interim

report of the ongoing special inspection. The NRC interim report noted that the Material Control

and Accounting (MC&A) program in place as of November 4, 2004, met regulatory

requirements. However, the interim report also identified four apparent violations concerning

past licensee practices connected with the missing SNM. Three of these apparent violations

are discussed in Sections 3 and 11 of this report. The fourth apparent violation addressed the

possession of SNM in the form of remnants of fuel fragments when neither the license nor the

technical specifications authorized possession of SNM in this form. As noted in Section 11 of

this report, this apparent violation has been resolved and is no longer considered an apparent

violation. The NRC interim report also identified three unresolved items. The unresolved items

are discussed in Section 11 of this report and are considered resolved.

On May 27, 2005, PG&E issued their Special Nuclear Material Control and Accountability

Project Final Report. This report provided the results of the licensees investigation into the

location of the three 18-inch fuel rod segments and missing incore detectors, as well as the

overall control and accountability of SNM at the HBPP. On June 10, 2005, the license

submitted Revision 2 to LER 2004-01, regarding the three missing 18-inch fuel rod segments

and Revision 1 to LER 2005-01, regarding the missing incore detectors.

On June 20-24, 2005, a team of inspectors from NRC Headquarters and Region IV conducted

the final onsite portion of the special inspection to review the licensees efforts to locate the

missing SNM, the licensees scenarios as to the possible locations of the SNM and to complete

the review of current special nuclear material control and accounting practices.

Based on the findings of the special inspection, the inspection team concluded that:

  • The licensees current material control and accounting program meets regulatory

requirements. The program had undergone significant changes from that program

described in the interim special inspection report 05000133/2005-001. The changes

made to, and the implementation of procedures for the control and accountability of

SNM, physical inventory, and the use of tamper-indicating devices, had enhanced the

licensees MC&A program (Section 3).

  • The licensees SNM Control and Accountability Project which investigated the missing

SNM and the overall control and accountability of SNM at the HBPP was complete and

thorough in its search for the three 18-inch spent fuel segments and missing incore

detectors. The searches included all areas that were reasonable and practical to search

and that could accommodate the fuel segments. The licensee concluded, and the

inspectors agreed, that it is very improbable that the missing SNM could be in an area

not searched. The licensee expects that as the SFP contents are removed for dry fuel

storage, and plant decommissioning progresses, additional fuel fragments may be

found. However, it is very improbable that the intact missing 18-inch fuel segments

-5-

would be found. The inspectors agreed with this assessment (Section 2).

  • Although the SNM Control and Accountability Project documentation did not always

include the basis for their conclusions, no instances of erroneous or unreasonable

conclusions were identified (Section 2).

records during the period from August 6, 1969, to July 16, 2004, showing the inventory,

transfer or disposal of three approximately 18-inch segments of irradiated fuel

containing approximately 22.5 grams of SNM. Also from June 25, 1973, to February 4,

2005, the licensee failed to keep records, including location and unique identity, showing

the inventory, transfer or disposal of one complete and three partial incore detectors

containing SNM (Sections 3, 11).

maintain, and follow written material control and accounting procedures sufficient to

enable PG&E to account for the SNM in its possession. Specifically, PG&E failed to

account for the SNM contained in three approximately 18-inch segments of irradiated

fuel and one complete and three partial incore detectors (Sections 3, 11).

adequate physical inventories of all SNM in its possession at intervals not exceeding

12 months. Specifically, inventories performed by PG&E from June 4, 1971, to

February 4, 2005, with the exception of periods when the sealed SFP cover was in

place, did not include the three approximately 18-inch segments of irradiated fuel and

one complete and three partial incore detectors (Sections 3, 11).

  • The licensee evaluated 258 radioactive waste shipments made to low-level radioactive

waste (LLRW) disposal sites. The inspectors reviewed the screening criteria used by

the licensee and determined them to be reasonable. Of the 258 shipments, 249 were

screened out as implausible leaving 9 potential shipments to be further investigated.

Of the nine potential LLRW shipments, four had been made to Barnwell (South

Carolina) Waste Management Facility and five had been made to US Ecology, Inc.,

(Hanford, Washington) (Section 4).

  • The licensees records of LLRW shipments were remarkably thorough, considering the

lack of procedural guidance in effect at the time. The licensees loading procedures for

LLRW shipments lacked guidance for documentation and obtaining a dose rate of

individual items included in the shipments (Section 4).

  • The pipe container that had contained the fuel rod segments from assembly A-49 was

never located or described in any LLRW shipment records. In addition, the container

was unlikely to have completely dissolved in the SFP. The inspectors concluded that

the container was more than likely shipped to a LLRW site as irradiated material during

one of the spent fuel pool cleanup campaigns (Sections 4, 8).

-6-

  • Using the licensees terminology for the possibility of occurrence, the inspectors

concluded that it was Reasonably Possible that the pipe container along with the fuel

rod segments could have been inadvertently included in a LLRW shipment between

1968 and 1989. This conclusion differs from the licensee determination that it was

Possible, But Not Likely. The LLRW shipments to either Barnwell, South Carolina or

US Ecology in Richland, Washington could have contained the fuel rod segments.

However, the inspectors agreed with the licensees conclusion that the shipments to

Barnwell, South Carolina, that took place during 1983 and 1985, had the highest

probability of containing the fuel rod segments (Section 4).

  • The inspectors reviewed the screening criteria and process used by the licensee to

review the Other Direct Shipments (ODS) and determined it was reasonable. The

inspectors agreed with the licensee conclusion that it was Possible, But Not Likely that

the fuel rod segments had been included in an ODS (Section 5).

  • The licensee had located an extensive collection of records that documented the history

of the incore detectors at HBPP. A number of shipments of cutup incore segments and

intact incore detectors were documented. The inspectors agreed with the licensees

conclusions that the most likely locations for the missing full and three partial incore

detectors were either the Barnwell or Hanford LLRW disposal facility (Section 6).

  • The inspectors agreed with the licensees conclusion that theft or diversion of the three

18-inch fuel rod segments and incore detectors was highly unlikely (Section 7).

  • The inspectors concluded that the licensees consultant report performed by ATI to

evaluate the fuel fragments was based on sound engineering judgment and the

consultants were methodical in the process of determining the conditions of the fuel rod

fragments. However, the inspectors concluded that without substantial additional

testing, they could not agree with the ATI consultants conclusion that there was

reasonable evidence that the 18-inch segments maybe among the fragments found in

the SFP (Section 8).

  • The NRC teams conclusions differed from the licensees in one notable respect. The

NRC team concluded that the most likely scenario for the missing SNM was that it was

inadvertently shipped to a low level waste burial site. The licensees conclusions

supported this as a possibility, however, its investigation concluded that the most likely

scenario for the missing spent fuel rod segments was that they were still in the spent

fuel pool in an altered condition. The table below compares the inspection teams

conclusions with those of the licensee with respect to the possible scenarios regarding

the missing fuel rod segments and incore detectors:

-7-

Three 18 inch fuel rod segments Incore detectors

Scenario Licensee NRC Licensee NRC

Shipment to LLRW site possible but reasonably reasonably reasonably

not likely possible possible possible

Other Direct shipment possible but possible but highly unlikely highly unlikely

not likely not likely

Theft/Diversion highly unlikely highly unlikely highly unlikely highly unlikely

Still in SFP1 reasonably possible but highly unlikely highly unlikely

possible not likely

1

This scenario includes fuel fragments or incore detectors in the spent fuel pool in either an

altered configuration, or in a location that was not directly observable.

  • The cause analysis performed by the licensee followed the applicable procedure and

appeared to be through and adequate. Although the process used by the licensee was

not a root-cause analysis, but a less stringent cause analysis, the inspectors concluded

that the licensee considered all reasonable causes. The identified corrective actions

were complete and comprehensive. The inspectors identified several missed

opportunities to correct the MC&A program to address the three missing approximately

18-inch long fuel fragments and other SNM in its possession (Section 9).

  • The inspectors concluded that regardless of whether the missing fuel segments were

located in the SFP, had been shipped to NFS for reprocessing, or had been transferred

to a LLRW disposal facility, the overall risk from the 18-inch fuel rods segments was

minimal to the health and safety of the public, workers, or the environment. Based on

the extremely low risk that the 18-inch fuel rods segments posed, if they were at

Barnwell or Hanford, attempts to locate and retrieve the 18-inch fuel rods segments

would not be justified by arguments concerning public health and safety. The overall

risk from the missing incore detectors, if present (Section 10).

-8-

REPORT DETAILS

1. Introduction

Humboldt Bay Power Plant Unit 3 is currently in decommissioning SAFSTOR1 status. Unit 3

received an operating license from the Atomic Energy Commission2 on August 28, 1962. On

July 2, 1976, Unit 3 was shutdown for annual refueling and seismic modifications. This work

was suspended in December 1980, and in June 1983 PG&E announced its intention to

decommission the unit based on economic analyses that showed that completing the necessary

seismic upgrades would not be economical. Unit 3 has been essentially in SAFSTOR since

July 1985. On July 19, 1988, NRC approved the licensees SAFSTOR plan and amended the

license to a possess-but-not-operate status. The license expires on November 9, 2015. The

facility has undergone minimal decommissioning activity since shutdown.

During the fall of 2003, the licensee conducted an examination of the contents of its spent fuel

pool (SFP) in preparation for eventual removal of the remaining fuel assemblies3 to a dry

storage Independent Spent Fuel Storage Installation (ISFSI). On December 15, 2003, PG&E

applied for a license to build an onsite ISFSI.

On November 12, 2003, during sorting of materials in a container in the SFP, licensee

personnel discovered a fragment of a spent fuel rod4 approximately 4 inches long. During

subsequent sorting of materials in the SFP, licensee personnel located an additional eight fuel

fragments ranging in length from 4 to 6 inches. Through record reviews the licensee identified

additional fuel fragments, ranging in length from 1 to 30 inches, that were stored in

one container. These fuel fragments were in addition to those that had been found at that time.

On November 17, 2003, the licensee initially informed NRC personnel by telephone of these

findings. The licensee kept the NRC staff informed of subsequent findings as they arose. In

early December 2003, the licensee stopped additional work with containers in the SFP that

could potentially contain fuel pin fragments until a criticality evaluation could be completed.

The initial fuel assemblies used in 1963 during the first fuel loading were clad with stainless

steel. In 1965, cladding failure of stainless steel clad fuel was observed. In 1966, a fuel

washer was built and used to remove accumulated corrosion on the surface of the fuel pins.

During August through December 1966, fuel inspections identified at least three fuel

1

SAFSTOR is defined as a method of decommissioning in which the nuclear facility is placed and maintained in such

condition that the nuclear facility can be safely stored and subsequently decontaminated (deferred decontamination) to levels that

permit release for unrestricted use.

2

The Atomic Energy Commission was the predecessor to the Nuclear Regulatory Commission.

3

A fuel assembly is a cluster of fuel rods. The HBPP Unit 3 first fuel assemblies were General Electric Type I fuel with

stainless steel cladding and a 7 by 7 fuel rod array for 49 fuel rods per assembly. Forty-eight of the fuel rods had 79 inches active

fuel length and one had an active fuel length of approximately 78.5 inches. The segmented rod in assembly A-49 had an active

fuel length of 79 inches.

4

A fuel pin or fuel rod is a long slender thin walled metal tube that holds fissionable materia (fuel) for nuclear reactor use.

At HBPP Unit 3 the cladding was made of stainless steel or zirconium alloys. The terms pin and rod are used interchangeably.

-9-

assemblies with missing portions of pins. An undated Polaroid photograph of a video monitor

shows an additional assembly, different from those previously identified, with a missing portion

of a pin. Tests performed by licensee personnel demonstrated that all the spent fuel pin

fragments found in the SFP were from stainless steel clad fuel pins. Fuel used after the first

load was made with zirconium alloy. Zirconium alloy cladding was not subject to the same

failures experienced by the stainless steel clad fuel.

During an NRC inspection conducted during January 5-9, 2004, the licensee informed the

inspectors that it had found records that indicated that the stainless steel clad fuel assemblies

were transferred to Nuclear Fuel Services Corporation in West Valley, New York, during the late

1960's and early 1970's. Based on the information found as of the time of the inspection, it was

not clear to the inspectors that the reported transfer of special nuclear material (SNM) would

have accounted for the missing portions of pins. Some assemblies were shipped years after

being inspected and would have been inside containers that would have prevented the damage

from being easily seen. The licensees records indicated that a number of the assemblies in

the pool had pins removed in the 1970's time frame for evaluations by the fuel vendor. It was

not clear to the inspectors if the SNM inventory used by the licensee had accounted for the

removed pins.

On January 9, 2004, during the inspection, the plant manager decided to initiate a re-evaluation

of the amount of SNM present in each assembly and in the SFP. He took this action due to the

many uncertainties in the base inventory. The inspectors opened inspection followup items

(IFIs) 50-133/0304-01 and 50-133/0304-02 to track and review the licensees investigation of

the actions that were taken or should have been taken upon discovery of the fuel fragments;

and re-assessment of the SNM possessed under the license, including the accuracy of special

material status reports previously submitted. The discovery of fuel fragments indicated a

potential problem with the Humboldt Bay material control and accounting (MC&A) practices,

possibly extending as far back as the 1960 time-frame. However, the fuel fragments that were

discovered were contained within the licensees controlled area and did not constitute an

imminent reportability concern due to theft or loss of licensed material in accordance with

requirements of 10 CFR 20.2201 or 74.11.

On March 25, 2004, the NRC conducted a review of MC&A practices for spent fuel at Humboldt

Bay. The review was conducted in accordance with guidance contained in Temporary

Instruction 2515/154. This temporary instruction required the inspector to gather information in

answer to a series of questions about the licensees MC&A program. The questions covered

the following programmatic areas: physical inventory, tracking of individual rods that had been

separated from their assemblies, spent fuel pool practices, written procedures, accounting

records, and visual verification. Based on the responses to the questions, the NRC determined

that this site required additional inspection under the temporary instruction.

On June 29, 2004, the licensee informed NRC staff that it had recently found documentation

indicating that in 1968 a fuel pin was segmented into three 18-inch sections and that other

records indicated that the complete assembly was sent off site for reprocessing.

On June 30, 2004, the licensee convened a Technical Review Group to review the recently

found records. The minutes of an Onsite Review Committee (OSRC) meeting conducted on

October 2, 1968, noted that a fuel rod from assembly A-49 had been cut into three 18-inch long

-10-

segments. These three segments were intended to be sent to Battelle, Ohio, for an

experiment. The minutes indicated that prior to shipment of the rod segments the licensee

learned that the experiment had been canceled and the rod segments were placed in a

container in the pool. Another document from the September - October 1968 time frame

indicated that the rod that had been segmented had been previously damaged while in

operation. This document described a 1.5-inch diameter schedule 40 steel pipe that was used

as a container for the rod segments, which were to be shipped to Battelle. This document also

stated that if possible, the remains of the rod were to be placed in the "garbage can" in the pool.

The garbage can was an aluminum container originally intended for shipping damaged

stainless steel clad assemblies for reprocessing. This container was used for collection of small

irradiated components that were in the SFP. In more recent documents, PG&E has referred to

this container as the central storage container. None of the fuel pin fragments found in

November and December 2003 were 18 inches long.

Other records maintained by the licensee indicated that assembly A-49 was sent to Nuclear

Fuel Services, West Valley, New York, on August 6, 1969, for reprocessing. The record

indicated that the weight of the assembly shipped to Nuclear Fuel Services corresponded with

the weight of the assembly when it was received. Since the OSRC records indicated a fuel pin

had been removed from assembly A-49, the weight on receipt should not have agreed with the

weight on shipment. The licensee decided that this apparent discrepancy constituted a quality

problem related to their SNM records and issued a nonconformance report to address this

matter.

On July 16, 2004, PG&E notified the NRC pursuant to the requirements of

10 CFR 20.2201(a)(1)(ii) of the discrepancy between inventory records and the location of

spent fuel rod segments (Event Notification 40877). No records had been located indicating the

location of the fuel segments in the SFP.

During July and August 2004, licensee personnel searched the most likely and accessible

locations within the SFP where the fuel segments could be physically located. Region IV

inspectors observed part of the search activities, including the opening and removal of contents

from the assembly UD-006N box. On June 4, 1975, zirconium clad fuel assembly UD-006N

was dropped by an operator while being moved from one SFP location to another. As a result,

several rods became separated from the others in the fuel assembly. Subsequently, the

licensee stored all the rods from assembly UD-006N in a box. Some stainless steel clad fuel

fragments were also stored in the UD-006N box. The inspectors observed the search for

assembly A-49 segments in the UD-006 box. Several fragments were found in these searches

that at first appeared to have been cut as opposed to broken due to metal failure. A

metallurgist and a specialist in non-destructive examinations, both employed by the licensee at

their Diablo Canyon Nuclear Plant, examined video images of 12 fragments that initially

appeared to have been cut. The metallurgists opinion was that the video images suggested

that the fragments all exhibit the appearance of a fracture surface and are dark in color as if

oxidized to some degree. This appearance is more typical of inter-granular stress corrosion

cracks that occurred at operating temperature. The non-destructive examination specialist

concurred.

The metallurgist also stated that the schedule 40 steel pipe described in the 1968 records as

the shipping container for the 18-inch segments, could not have completely corroded away.

-11-

The metallurgist stated that even if the pipe container had been made from carbon steel, which

he believed it probably was since the material of construction was referred to simply as "steel

pipe," it would not have completely corroded away. He expected that if it was in the SFP it

would show signs of significant rust and corrosion, possibly even through the wall in localized

areas but it would still be easily recognizable.

On August 16, 2004, PG&E issued a 30-day written followup report to its initial July 16, 2004,

notification to the NRC (Event Notification 40877). This report was made pursuant to

10 CFR 20.2201(b)(2)(ii). The licensee reported implementation of an action plan that included

a detailed physical inspection of the SFP; documentation reviews of PG&E and vendor records;

and interviews with both employees and contractors who had been associated with the

Humboldt Bay SFP and radwaste operations.

On August 17, 2004, the Humboldt Bay Plant Staff Review Committee reviewed the results

from searching the most likely and accessible locations within the SFP where the fuel segments

could be located. During this phase of the search, the missing fuel was not located.

Consequently, the licensee made a 1-hour notification to the NRC pursuant to 10 CFR 74.11(a)

that the subject fuel rod segments were considered missing (Event Notification 40961).

On September 29, 2004, Region IV conducted a public meeting with the licensee in Eureka,

California, to discuss the current and planned search activities. During the public meeting, the

NRC Region IV Regional Administrator announced that a special inspection would be

conducted of the licensees material control and accountability program and that Region IV

would also continue to follow the licensees efforts to search for the missing fuel fragments. On

October 25, 2004, Region IV chartered this special inspection.

On February 22, 2005, the licensee issued their Special Nuclear Material Control and

Accountability Project Interim Reports (PG&E Interim Reports). On the same date the licensee

notified NRC (Event Report 41340) and issued License Event Report 2005-01. This notification

and report informed the NRC that PG&E was unable to locate one intact incore detector and

three partial incore detectors, amounting to less than a gram of SNM.

On April 8, 2005, PG&E submitted the revised ATI report. This licensee consultant report was

titled Evaluation of Nuclear Fuel Rod Fragments and Inference to Fuel Rod A-49 at Humboldt

Bay Power Plant. The executive summary to this report stated, in part, that it was the

judgement of the consultants that there was reasonable evidence that fragments from the three

missing 18-inch segments from assembly A-49 may be among the fuel fragments found in the

SFP.

On May 27, 2005, PG&E issued their Special Nuclear Material Control and Accountability

Project Final Report. This report provided the results of the investigation into the location of the

three 18-inch fuel rod segments and the location of the missing incore detectors, as well as the

overall control and accountability of SNM at HBPP.

On June 10, 2005, the license submitted Revision 2 to LER 2004-01, regarding the three

missing 18-inch fuel rod segments and Revision 1 to LER 2005-01, regarding the missing

incore detectors.

-12-

On June 20-24, 2005, a team of inspectors from NRC Headquarters and Region IV conducted

the final onsite portion of the special inspection to review the licensees efforts to locate the

missing SNM, the licensees scenarios as to the possible locations of the SNM and to complete

the review of current special nuclear material control and accounting practices. This report

documents that effort.

2. Review of PG&Es SNM Control and Accountability Project

2.1 Inspection Scope

The inspectors reviewed the licensees SNM Control and Accountability Project (the

Project) to evaluate the completeness and thoroughness of the search for the three

18-inch spent fuel segments. The review included the search in the SFP and

surrounding areas, the search of historical records, documentation of interviews

conducted with current and former employees and contractors, and the

characterizations of fuel fragments found. This review included project control

documents that consisted of the Project Plan and all Project Instructions, as well as

applicable records generated by the project, video documentation of the search and fuel

fragments characterizations, and the pertinent records obtained by the licensee from

outside PG&E. The inspectors also interviewed the project manager, other key project

personnel, and a former employee and a contractor who had been interviewed as part of

the project.

2.2 Observations and Findings

a. Project Management

The project guidance documents provided adequate and effective guidance for the

investigation process. The investigation method and approach was reasonable and

effective. The investigation had a logical division of investigation paths, inspections,

document reviews & interviews, coordinated with scenario and time line development.

However, although the guidance for control and retention of documents was adequate,

the guidance did not require specific documentation of the basis of decisions.

Consequently, some portions in the report did not have adequate documentation for the

basis of the licensee conclusions. This is discussed in more detail in paragraph f. of this

report section.

b. Records Review

The inspectors reviewed the project control documents including the physical search

data summary document (this document had no revision number or date). The

inspectors also reviewed records obtained from Nuclear Fuel Services (West Valley),

Battelle, and General Electric (GE). The licensees search for and review of records

was well organized, methodical and through. The licensee used a two step process

(designating documents first as applicable, then as relevant) which provided an

independent review. Additionally, the process included a second review audit of

documents determined applicable but then not relevant. This provided a necessary

independent verification of a key decision point. Searches and reviews were conducted

-13-

of both hard copy and electronic media. The documentation of the records review

process was particularly through and complete, including areas that were searched

without results. However, there were significant gaps in the documentation to be

reviewed. This was due to the unavailability of the documents due to their age rather

than a poor search process. Where inconsistencies were identified in the documents,

the SNM project staff resolved them adequately.

The search of records outside the company was adequate given the age of the issue

and the poor filing practices for documents during that time period. Although the

licensee relied on the personnel at the outside facility to conduct the search, there is no

indication the SNM project staff would have been more effective.

The inspectors also reviewed the training program and documentation for the document

readers. The training appeared to be comprehensive, sufficient, and well documented.

A training coordinator was designated and qualified personnel conducted the training on

each project instruction.

c. Physical Search

Inspection Report 05000133/2005-001 describes the observations made by the

inspectors during site visits in November and December 2004 and January 2005.

During these visits the inspectors observed ongoing search activities, including opening

of the UD006N assembly container and the vacuuming of the resin beds. The licensee

had experienced a number of problems that resulted in delays during the search for the

missing segments but the inspectors concluded that regardless of the difficulties

experienced the licensee had conducted a thorough search of the SFP and other areas

of the HBPP outside the SFP that could accommodate the fuel segments and were

probable, e.g. shielded containers or water-filled areas capable of accommodating the

fuel segments. These searches where conducted while maintaining effective personnel

safety. The licensee referred to the systematic searches performed during Phase 2 of

their project as Global Inspection Plan.

The searches did not find the three 18-inch fuel segments in their original form nor the

pipe container in which they were originally stored in 1968. The searches of locations

outside the SFP also did not locate the fuel rod segments, fuel fragments, or any other

irradiated SNM. The searches in the SFP did find fuel fragments, and other irradiated

SNM, including 175 fuel fragments amounting to 282.71 inches in length. The licensee

defined a fuel fragment as a clad or unclad portion of a fuel rod, including pellets or

portions of pellets that have a measurable dimension nominally greater than 1/4 inch.

Cladding without fuel was considered irradiated hardware, not a fuel fragment. The fuel

fragments contains SNM. The Global Inspection Plan also accounted for 50 incore

detectors and identified that one complete and three partial incore detectors were

missing.

The licensee searched all areas that were deemed practical to search and that could

reasonably contain or accommodate the fuel segments. However, these searches did

not include all areas of HBPP, for example the reactor vessel was not searched. The

licensee concluded, and the inspectors agreed, that based on available information it

-14-

was very improbable that the fuel rod segments or fuel fragments could be in any of the

locations not searched. It should be noted that the licensee expects that as the SFP

contents are removed to implement dry fuel storage and plant decommissioning,

additional fuel fragments maybe found. However, if this were to occur it is very

improbable that the intact missing 18-inch fuel segments would be found. The areas

that remain to be searched were too small to contain the intact 18-inch segments or

were recently developed. The area below where the fuel channels were stacked is such

a recently developed area. The channels were placed in their current location in the

year 2000 and no fuel segments or containers were observed when the channels were

stacked. The inspectors agreed that it is possible that additional fragments may be

found but it is very improbable that the intact missing 18-inch fuel segments or the

segments in their shipping container would be found.

d. Interviews

The inspectors reviewed applicable guidance documents including Project Instruction

04, Interviewing, and the results from the different interviews conducted by the

licensee. Additionally, the inspectors interviewed key project personnel. The project

instructions generally provided adequate guidance for an effective controlled interview

process. Although the Phase I interviews were conducted informally, the documentation

was adequate, allowing for the formal interviews to use the Phase I interviews as an

effective starting point. The documentation of the Phase II interviews that were

conducted was adequate. Documentation for why interviews had not been conducted

were not always available or easily recognizable. However, the inspectors determined

that the interviews that had not been conducted were generally not done for good

reasons, i.e. candidate deceased or unable to be located. Additionally, most of the

interviews were conducted by a single interviewer, which could have potentially reduced

the effectiveness of the interview process.

The inspectors conducted two independent interviews with Phase II interview subjects.

These interviews confirmed the records of the Phase II interview, although additional

information was obtained.

e. Fuel Fragment Characterizations

The licensee had used two types of fuels during their operation. The initial fuel load

consisted of fuel clad in stainless steel referred to as Type I. Subsequently, the licensee

used fuel clad with zirconium alloy or Type II fuel. Assembly A-49 from which the

segments were removed was Type I, stainless steel clad fuel. Differences in tube

external diameters, tube wall thickness, and magnetic properties would allow

differentiation between stainless steel and zirconium cladding. The licensee collected a

series of measurements from the fuel fragments with cladding to establish the type of

fuel involved, including external diameters, tube wall thickness, and magnetism. All clad

fuel fragments found were stainless steel clad. The licensee also characterized each

fragment found by measuring the length of fuel and the dose rates at nominal contact

(approximately 1 cm from center of detector) and at 6 inches. The inspectors observed

portions of the licensees activities to measure, identify, characterize, and store fuel

fragments.

-15-

Using information known about the missing 18-inch segments, the licensee calculated

the estimated dose rates and reported this information in Licensee Event Report

(LER) 2004-001, revisions 0 and 1. The NRCs Special Inspection Interim report

05000133/2005-001 noted that the calculated dose rates were at least 10 times greater

than the measured dose rates in fragments that had been found. The licensee agreed

to review their calculation for possible errors.

Revision 2 to LER 2004-001, issued on June 10, 2005, revised the calculated dose

rates. A footnote to Table 3, Calculated Dose Rates, of the revised LER stated that the

dose rates in this table were corrected from the previous LER revision, as described in

PG&E Calculation NX-289. Revision 3 to PG&E Calculation NX-289 noted that the

initial calculations were performed using the power level that corresponded to the power

generated in three segments (54 inches) of fuel rod. The revision used the power level

for one 18-inch segment. These calculated dose rates were still at least twice the

values measured.

To address this apparent discrepancy the licensee performed PG&E Calculation

NX-293. This calculation evaluated the underwater dose rates postulated from the A-49

18-inch segments, at multiple distance from the segment, including 1 centimeter and

6 inches. This calculation also estimated dose rates from fragments of 1, 2, 3, 6, 9, and

12 inches in length. The calculation also estimated dose rates for various burnup rates

of the fragments. The table below compares the measured dose rates for selected

fragments to the calculated values at 1 centimeter and 6 inches using the burnup rate of

13,000 megawatt-day per metric ton uranium (MWD/MTU). The calculated values at

1 centimeter range from two to four times the measured values. At 6 inches the values

are in better agreement ranging from comparable to three times the measured value.

The inspectors concluded that when comparing the calculated dose rates for the A-49

segments to the measured dose rates on the fuel fragments in the SFP it is not

reasonable to conclude that any of the fragments of interest originated from assembly

A-49.

-16-

Table 1

Humboldt Bay Power Plant Unit 3

Measure vs Calculated Dose Rate for Fuel Fragments

Fragment Fuel Length Measured Calculated Rate Approximate

in Inches Rate in R/hr in R/hri (NX-293) Ratios Calc/Meas

1 cm 6" 1 cm 6" 1 cm 6"

FF013 2e 230 9 701 10 3 1

FF021 13 d 198 10 776 29 4 3

FF026 10 209 7.5 774 25 4 3

FF027 6d 303 15 762 18 3 1

FF029 1 101 1.3 431 3 4 2

FF030 41/2 325 7 701 10 2 1

FF031 23/4 216 4.5 701 10 3 2

FF033 3.5 275 5 701 10 3 2

FFO34 3c 271 4 701 10 3 3

Ii

Calculation NX-293 calculated dose rates for fragments of 1, 2, 3, 6, 9, 12, and 18 inches in length. The recorded dose

rates are for the nearest calculated value to the measured fuel length, and for a burnup rate of 13000 MWD/MTU.

f. Documentation of Investigation

The inspectors reviewed the project documentation in support of the final report.

Although the documentation was generally adequate to support the conclusions of the

final report, one notable exception was the basis for decisions. Although the inspectors

were able to reconstruct the basis by examining supporting documentation, the basis for

some decisions was not explicitly provided in the report. Examples include:

  • No documentation was provided for the individuals listed on the proposed

interview list who were not interviewed, other than for those individuals who were

determined to be deceased. Although the basis could be determined by the

inspectors, it had not been documented by the SNM Project.

  • No documentation was provided for the basis of the Other Direct Shipments

which were excluded from further consideration. Again, the inspectors were able

to determine the basis and have no issues with the basis, but it was not provided

in the SNM Project documents.

  • Calculations were not performed to support the licensees conclusion that the

area radiation monitors (ARMs) would have alarmed if the rod segments had

been removed from the spent fuel pool. Although these calculations were

performed and provided during the course of the inspection, they were not

provided in the SNM Project documents.

-17-

Although the SNM Project documentation did not always document the basis of the

conclusions, no instances of erroneous or unreasonable conclusions were identified.

g. Adequacy of Interfaces with Government Agencies (NRC & States)

The inspectors reviewed the contact list for the fuel issue and interviewed key licensee

personnel. The contact list of government contacts was maintained current and tracked

for each notification. The notifications were timely. A weekly status call (subsequently

changed to bi-weekly at the participants request) was conducted with key stakeholders.

The contact list for significant updates was tracked by the licensees public affairs staff.

Additionally, the existing citizens advisory board, which includes local government

officials, was kept informed of the progress of the investigation.

2.3 Conclusions

The licensees SNM Control and Accountability Project was complete and thorough in its

search for the three 18-inch spent fuel segments and missing incore detectors. The

searches included all areas that were reasonable and practical to search and that could

accommodate the fuel segments. The licensee concluded and the inspectors agreed

that it is very improbable that the missing SNM could be in any of the locations not

searched (e.g. the reactor vessel). The licensee expects that as the SFP contents are

removed for fuel dry storage and plant decommissioning, additional fuel fragments may

be found, but that it is very improbable that the intact missing 18-inch fuel segments

would be found. The inspectors agreed with this assessment.

By comparing the measured dose rates on the fuel fragments in the spent fuel pool to

the calculated dose rates for the A-49 segments, the inspectors could not associate any

of the candidate fragments with those originating from assembly A-49.

Although the SNM Control and Accountability Project documentation did not always

document the basis for their conclusions, no instances of erroneous or unreasonable

conclusions were identified.

3. Material Control and Accounting

3.1 Inspection Scope

The inspectors reviewed changes made to the licensees Material Control and

Accounting (MC&A) program since the special inspection visit in November 2004 (see

inspection report 05000133/2005001). The inspectors reviewed the licensees written

MC&A procedures, which addressed control and accountability of SNM, physical

inventory, and the use of tamper-indicating devices. The inspectors interviewed

personnel on procedure implementation and examined records generated by the

procedures.

3.2 Observations and Findings

The over-arching material control and accounting procedure in force at the time of the

-18-

inspection was HBAP D-7, Control and Accountability of Special Nuclear Material and

Waste Shipment, Volume 1, Revision 11, dated May 2, 2005. The procedure defined

MC&A roles and responsibilities; provided instructions for identification, shipment, and

transfer of SNM; provided instructions concerning the discovery of SNM-containing

articles or SNM waste; and described the records and reports used to control and

account for SNM.

Several definitions were added to the procedure to better classify the various forms of

SNM in the SFP. New sections were added to provide more detail on SNM

Accountability Records and the discovery of SNM-containing articles or SNM waste.

The SNM Accountability Record form, SNM Movement Authorization form, and the SFP

map were revised to provide more thorough entries on the forms, to enhance

traceability, to provide better control of SNM moves, and to enhance the process of

updating records.

The inspectors reviewed the recently created accountability records for the new SNM

containers - SC1, FUEL FRAG, and UFFC. The forms included the serial number of the

Tamper Indicating Device (TID) installed and a reference to the container contents as

required by HBAP D-7. The inspectors also reviewed the accountability records for a

sample of assemblies and verified that attachments were added describing the history of

the assembly as specified in HBAP D-7.

The inspectors reviewed the licensees physical inventory procedure STP 3.6.6, SNM

Inventory, Volume 6, Revision 20, dated May 2, 2005. Steps were added to verify that

all SNM-containing items listed in the accountability records are found in the SFP and to

visually inspect the TID tags installed on the SNM storage containers. The inspectors

reviewed the SFP map from the most recent inventory conducted on May 5, 2005, and

reviewed a sample of 30 assembly accountability records to verify that the locations of

the assemblies as indicated on the SFP map matched the location in the accountability

records. The new SFP map and all reviewed accountability records were completed

according to procedure. The TID serial numbers for the SNM containers were verified

as required during the inventory.

The inspectors reviewed procedure HBAP D-8, SFP Cover Seals and SNM Container

TIDs, Volume 1, Revision 0, dated May 2, 2005. This new procedure included the

requirements for installation and removal of the SNM storage container TIDs. The

inspectors observed the new TIDs on the storage containers via underwater camera

while inspecting the SFP, and viewed video and photographs of the installation of the

TIDs. As mentioned above, the inspectors verified that the TID serial numbers were

recorded on the accountability records for the storage containers, and were verified at

the most recent inventory, as required.

On August 6, 1969, assembly A-49 was shipped off site for reprocessing, from that date

forward, PG&E failed to maintain records indicating whether the three approximately

1-inch long segments of irradiated fuel were in their inventory, had been transferred or

had been disposed. Calculations made by the licensee indicate the three segments

contained approximately 22.5 grams of SNM.

-19-

Site records indicated that during the period of June 21 to 25, 1973, some incore strings

were cut to remove the incore detectors . The incore detectors from three selected

incore strings were then transferred to another licensee on June 25, 1973. An additional

nine incore strings were presumed to have been cut and segmented during this same

time frame, based on plant documentation. Evidence indicated that several segments

from the incore cutup operations conducted during 1973 were approximately 30 inches

in length. The three partial incore detectors were found in segments that were also

approximately 30 inches long. June 1973 is the most likely period when control and

accounting of the SNM in the incore detectors was lost, since the licensee did not know

which lengths of incore string tubing contained SNM and which were just irradiated

hardware. The inspectors concluded that this is when the licensee lost control of the

accounting for the SNM in the incore detectors.

Records maintained by the licensee indicated that on June 4, 1971, the last shipment of

fuel with stainless steel cladding, also known as Type 1 fuel, was made. At that point

the licensee removed all the associated SNM contained in the Type 1 fuel from their

inventory. However, as noted on the licensees calculation NX-288, over the last year

and half, the licensee has found 175 Type 1 fuel fragments. These fuel fragments are

the equivalent to more than 280 inches of fuel or more than the equivalent of three fuel

rods. In calculation NX-290, the licensee calculated that as of September 30, 2004, this

amounted to 97 grams of uranium-235 and 22 grams of plutonium. Additionally,

licensees calculation NX-290 also estimated that there was 10 grams of uranium-235

and 5 grams of plutonium as SNM waste in the SFP. Regulations in effect during these

time frames required that inventories account for all SNM, including the amount

contained in the fuel fragments.

Even though the presence of Type 1 fuel fragments was noted during the 1976 and the

mid-1980's pool clean up campaigns and the licensee conducted SNM inventories at the

required intervals, these inventories failed to account for the SNM in the fuel fragments

and SNM waste. Inventories of all SNM have been required by applicable regulations

throughout this time.

These failures in the SNM control and accountability program were noted in the interim

inspection report and are identified as apparent violations on Section 11 of this report.

3.3 Conclusions

The inspectors concluded that the licensees current material control and accounting

program meets regulatory requirements. The program has undergone significant

changes from that program described in the special inspection report

05000133/2005-001. The changes made to, and the implementation of, procedures for

the control and accountability of SNM, physical inventory, and the use of tamper-

indicating devices, have enhanced the licensees MC&A program.

-20-

4. Review of Scenario Involving Fuel Segments Shipped Offsite with Low Level

Radioactive Waste (LLRW)

4.1 Inspection Scope

The inspectors reviewed the licensee screening process that was used to evaluate the

potential inclusion of the three fuel rod segments in LLRW shipments. Supporting

shipment records and plant procedures that were used for LLRW shipments were also

reviewed.

4.2 Observations and Findings

This scenario evaluated the possibility that the three missing spent fuel rod segments

were inadvertently included in a LLRW shipment, that would have originated from HBPP

between September 1968 and July 1989. This scenario assumed that the three 18-inch

fuel rod segments would not have been recognized as spent fuel and were either

individually or collectively included with other radioactive waste and shipped offsite.

Portions of the screening process used by the licensee for LLRW also evaluated the

potential that the three fuel rod segments were included in what the licensee termed

Other Direct Shipments (ODS). A separate scenario will be evaluated for ODS.

The licensee investigation for the both the LLRW and ODS scenarios started with a

record review to locate all the radioactive material shipment records. After the

radioactive material shipment records were located, they were screened for applicability

and relevancy by the licensee using instructions contained in procedure Special

Nuclear Material (SNM) Inventory, Inspection & Control Project, Project Instruction

Documentation Investigation SAP8065936 - PI - 03, Revision 5, dated March 18, 2005.

The licensee then evaluated all of the 490 radioactive material shipment records that

had been determined to be applicable and relevant by using the Screening Tool for

Fuel Rod Segments in Offsite Shipments, approved May 24, 2005. This screening tool

provided detailed criteria for evaluation of the potential inclusion of the spent fuel rod

segment(s) in either LLRW shipments or in ODS.

The Screening Tool for Fuel Rod Segments included potential scenarios explaining how

the fuel rod segments could have been inadvertently shipped from the site along with

evaluation criteria to determine if the fuel rod segment(s) were contained within a

shipment. Each shipment was conservatively evaluated using the radiological dose

profile from a single fuel rod segment. Table 3.1-1 of the Screening Tool for Fuel Rod

Segments provided a summary of the evaluation criteria that was used by the licensee

to determine whether the shipment could contain the missing fuel segments. The

criteria from Table 3.1-1 utilized to evaluate the shipping records consisted of:

5. The first screening criteria that was considered in the process determined if the

shipment of radioactive material had been receipt inspected upon arrival at the

final destination. The licensee evaluated the plausibility of a material recipient

inspection occurring that would have recognized the presence of the fuel rod

segments as an anomaly and contacted HBPP personnel. Material contained in

-21-

LLRW shipments were not individually receipt inspected and therefore received

further consideration.

6. The second screening criteria considered the dose rate of the package. If the

shipment had a high dose rate, the presence of the fuel rod segments were

more plausible. A dose rate tool contained in Humboldt Bay Power Plant

Calculation No. NX-292, Revision 1, provided several dose rate versus decay

time curves for different types and sizes of transportation packages. The

package types evaluated by the curves included large Low Specific Activity

(LSA) boxes, small LSA boxes, steel drums and cardboard boxes. The dose

rate associated with a single 18-inch segment was conservatively applied in each

of the curves. If the dose rate of the individual package was above the

calculated dose rate curve from Calculation No. NX-292, the package would be

further evaluated.

7. The third screening criteria determined if the shipment used a shielded cask.

The shielding provided by the cask made it more plausible that the presence of a

fuel rod segment would be undetected during radiation surveys. A package that

was shielded would receive additional evaluation. Even if the package was not

shielded, it was still evaluated utilizing the dose rate versus decay time curves

from Calculation No. NX-292.

8. The forth screening criteria examined the contents and details of the shipping

manifest. The shipping records were reviewed to determine if the description of

the package contents described items with a similar appearance and/or

configuration to the fuel rod segments or pipe container.

9. The fifth screening criteria determined if the material originated from the spent

fuel pool. Due to the extremely high dose rates emitted from the fuel rod

segments, their most probable storage location would be under water in the

spent fuel pool, where they were initially placed in 1968. It was considered

highly unlikely that the fuel rod segments would have been moved from the spent

fuel pool during the course of normal operations, due to the extremely high dose

rates involved with their movement. A planned movement of the fuel rod

segments should have required additional documentation and procedures, which

were not located during the record search.

10. The sixth screening criteria considered whether the package involved the

solidification of an ion exchange resin or a concentrated liquid. Requirements for

processing a liquid or a resin for waste shipment were considerably different

than those associated with preparing a solid item for shipment, such as a pipe.

Regulations also prohibited mixing waste forms and therefore, packages that

contained resin or liquids were not evaluated further.

11. The seventh and final screening criteria confirmed that the date associated with

the shipment record occurred after the segments had last been documented to

be located in the spent fuel pool in 1968 and before the pool cover was installed

in 1989. The segments could not have been shipped offsite prior to their initial

-22-

placement in the spent fuel pool in September 1968 and there were no

shipments that originated from the spent fuel pool, exceeding the dose rate

screening criteria contained in Calculation No. NX-292, after the pool cover had

been installed in July 1989.

The licensee utilized the screening criteria listed above, although not necessarily in the

order listed, to examine and evaluate if the fuel rod segments and/or the pipe container

could have been removed and shipped from the site to a LLRW or ODS facility.

The inspectors concurred that the Screening Tool for Fuel Rod Segments and the

screening process utilized by the licensee to evaluate LLRW shipments and ODS was

appropriate.

The inspectors selected 30 of the ODS and LLRW shipments that had been screened

by the licensee for an independent review. Selected records of shipments to General

Electric Co. Vallecitos, CA; Nuclear Fuel Services; Nuclear Engineering Co., Richland,

WA; Nuclear Engineering Co., Beatty, NV; Southwest Radiological Health Lab and

US Ecology were compared to the screening results obtained by the licensee using the

Screening Tool for Fuel Rod Segments in Offsite Shipments. No deficiencies of the

licensee screening results were identified.

Utilizing the Screening Tool for Fuel Rod Segments, the licensee evaluated 258

radioactive shipments made to LLRW facilities. Of these 258 shipments, 249 were

screened out as implausible based on the criteria mentioned above. There were nine

potential LLRW shipments that were determined to be candidates for the inadvertent

shipment of the fuel rod segments. The potential LLRW shipments included four to

Barnwell Waste Management Facility located in Barnwell, South Carolina and five to

US Ecology, Inc., located in Richland, Washington. The LLRW shipments were made in

two phases. The initial phase consisted of three shipments to Barnwell Waste

Management Facility during 1983. The second phase consisted of one shipment to

Barnwell and five shipments to US Ecology, Inc., during 1985 and 1986.

The first three shipments to Barnwell Waste Management Facility occurred during

October and November 1983. The first shipment record was dated October 11, 1983,

and described the waste contents as reactor control rods, control rod followers and

poison curtains.

description of small material or miscellaneous parts was not included with the first

shipment record. This could mean that no additional material was necessary to stabilize

the shipment or that a detailed list of the items had been omitted. The second shipment

record dated October 24, 1983, and the third shipment record dated November 16,

1983, described the waste contents as reactor control rods, control rod followers,

poison curtains, fuel channels & misc. parts. Handwritten descriptions of the items

included in the waste shipments as shoring or misc. parts along with sketches of the

articles were located with the records for both the second and third shipments. None of

the items that were described or sketched included with the second or third shipments

resembled the fuel rod segment pipe container or the fuel rod segments. Dose rate

surveys had not been performed on the individual items included as shoring in the

-23-

shipments. Dose rate readings were performed after all the waste had been placed in

the liners for shipment, while still underwater in the spent fuel pool. Due to the highly

radiated components that were included in the waste shipments, the dose rate readings

measured underwater for the three Barnwell shipments varied from 600 to 2,200 Rem

per hour. Therefore, final dose rate surveys performed for these shipment packages to

Barnwell would have masked the presence of the fuel rod segments, if they had been

present.

The loading of the radioactive material into the LLRW shipment casks for the 1983

Barnwell shipments was reported to have been performed by HBPP personnel. Chem-

Nuclear Systems, Inc., personnel provided the personnel and equipment to ship the

transportation packages from HBPP to the LLRW disposal site. Temporary Procedure

No. 10/04/83, Loading the Shipping Cask Liner, Revision 100-10/83, had been utilized

to perform the loading operations for the cask liners. Procedure step number 10.f.

stated, Load any more items that will fit in the available space. Load items in the

remaining space in the top of the liner as directed. Therefore, the temporary procedure

directed the loading personnel to place as many items as possible into the available

spaces in the transportation cask. The temporary procedure did not require individual

items be listed or surveyed as they were incorporated into the waste shipments.

A major change to the regulations for radiological waste shipments occurred in

December 1983. This was when the requirements of 10 CFR Part 61, Licensing

Requirements for Land Disposal of Radioactive Waste became effective.

10 CFR Part 61 required, in part, that the waste be properly classified and packaged in

such a manner to provide structural stability of the waste at the disposal site. Prior to

implementation of this regulation, the requirements for classification of items included in

a waste shipment were less stringent.

The second phase of LLRW shipments consisted of one shipment to Barnwell Waste

Management during the last quarter of 1985 and five shipments to US Ecology during

the first quarter of 1986. These shipments were all made after 10 CFR Part 61

regulations went into effect. In contrast to the earlier LLRW shipments made during

1983, Chem-Nuclear Systems, Inc., personnel loaded all the shipments.

The fourth LLRW shipment to Barnwell Waste Management Facility occurred on

December 15, 1985. The radioactive waste shipment manifest described the waste as

activated metal. A handwritten spreadsheet included with the records listed the

dimensions, weight and average dose rates for each individual item. The item

descriptions did not resemble the fuel rod segment pipe container or the fuel rod

segments. Dose rate information was provided for the individual items, but high dose

rate readings would have masked the presence of the fuel rod segments. The

radioactive waste shipment record reported that 1,520 linear inches of cutup incore tube

string pieces or processed incores were included. The average radiological dose rates

for the processed incores were recorded as 69.3, 218.83 and 145.36 Rem per hour.

The processed incores were reported to consist of various lengths of incore pieces,

that were composed of stainless steel tubes with a diameter of 0.75 inches. The

missing fuel rod segments also consisted of stainless steel tubes, approximately

18 inches long and were 0.50 inches in diameter. It is not known whether the missing

-24-

fuel rod segments were ever removed from the pipe container. A HBPP Memorandum

to File, dated February 24, 1986, stated that additional pieces of the cutup incore tubes

had been located during subsequent pool cleanup work. From this statement, it could

be concluded that during previous incore tube cut-up campaigns, portions of the tubes

had been misplaced in the spent fuel pool and later recovered. It is reasonable to

assume that if the fuel rod segments had become separated from the pipe container,

they could have been mistaken as previously cut-up incore tubes. The small difference

in stainless steel tube diameters between the fuel rod segments and the incore tubes

would have been difficult to differentiate underwater in the spent fuel pool. However, the

inclusion of the fuel rod segments was believed to be highly unlikely due to

documentation included in the HBPP Memorandum to File, dated February 24, 1986.

Information in the memorandum indicated that only the incore segments that had been

cut up during the year 1985 were included in the shipment. Therefore, only a small

potential for the inclusion of miscellaneous incore pieces found on the bottom of the

spent fuel pool would have existed.

five shipments to US Ecology in Richland, Washington occurred on January 20,

1986; January 28, 1986; February 5, 1986; February 18, 1986 and March 4, 1986. Each

of the five shipment manifest records described the waste as metal oxides and

plastic/cellulose filter media, stabilized/encapsulated in cement. A separate

handwritten sheet of paper found with each of the 5 waste shipments provided a

description for each item that had been included in the shipment. Additionally, the

weights and average dose rates for each item were also included on the handwritten

sheets of paper. The descriptions of the items included in the shipments did not

resemble the fuel rod segment container nor the fuel rod segments, however some of

the item descriptions were of 55 gallon drums that could have contained the missing

items. An example of such a container would be the shipment that occurred on

January 28, 1996, that included a drum containing compacted spent fuel pool trash.

Dose rate information was provided for the individual items in the radwaste shipment,

but high dose rate readings of the packages varied from 13 to 30 Rem per hour and

would have masked the presence of the fuel rod segments.

Instructions for loading the radioactive waste shipment liners during the 1985 and 1986

shipment campaigns were included in Temporary Procedure No. 12/26/85 No. 2,

Loading SFP Hardware into Chem-Nuclear Systems CNS 8-120 Liner and Cask,

Revision 146-12/85. Step 8 of the Temporary Procedure stated, Liner is now ready to

be loaded with hardware as approved by Chem-Nuclear personnel with the concurrence

of the PGandE Chemical/Radiation Protection Engineer. The step is very vague by

todays standards and does not preclude the undocumented introduction of additional

items into the liner nor does the procedure require that each item receive a dose rate

survey. However, a dose rate survey of each major item was located with the records

for each shipment. Figure 1 of the Temporary Procedure contained the only

procedurally required dose rate readings, that specified final dose rate readings be

taken and recorded at 32 separate locations on the liner after loading operations had

been completed.

The inspectors conducted a telephonic interview with an individual that had served in a

supervisory capacity with Chem-Nuclear Systems, Inc., during the LLRW shipments

-25-

conducted during the years 1985 and 1986. The individual described the process of

documenting and obtaining a dose rate survey for each item included in the LLRW

shipment. The process details described by the individual closely aligned with the

details contained in the LLRW shipment records, recovered by the licensee.

The licensees records of LLRW shipments were remarkably thorough, considering the

lack of procedural guidance and regulatory requirements. The licensees loading

procedures for LLRW shipments lacked guidance for documentation and obtaining a

dose rate of individual items in the shipment. The licensee procedures did not require

that a closed container, such as a pipe, be opened to evaluate the container contents.

The licensee did not have a current procedure that could be used to ship LLRW in a

shielded cask that originated from the spent fuel pool.

There were no items discovered during the licensees review of LLRW shipment records

that matched or resembled the pipe container that had contained the fuel rod segments.

Unfortunately, the only record located by the licensee described the pipe container as

1 1/2" schedule 40 steel pipe. Regardless of whether the pipe was made from carbon

steel or stainless steel, a substantial portion of the pipe along with the pipe caps were

expected to have remained intact in the spent fuel pool. Since the pipe container was

not located in the spent fuel pool and no records exist that indicated a planned or

procedural approved movement of the pipe container with the fuel rod segments ever

occurred, it is possible that the pipe was disposed of as radwaste with or without the fuel

rod segments inside.

4.3 Conclusions

The inspectors reviewed the screening criteria used by the licensee and determined that

the process utilized to evaluate and screen the LLRW shipments was reasonable.

The licensee evaluated 258 radioactive waste shipments made to low-level radioactive

waste (LLRW) disposal sites utilizing the Screening Tool for Fuel Rod Segments. Of

these 258 shipments, 249 were screened out as implausible leaving 9 potential

shipments to be further investigated. Of the nine potential LLRW shipments, four had

been made to Barnwell (South Carolina) Waste Management Facility and five had been

made to US Ecology, Inc., (Hanford, Washington).

The first three shipments to Barnwell had been loaded by Humboldt Bay personnel

during 1983. Handwritten records provided descriptions of the small items included in

the last two radwaste shipments, but a description was missing from the first radwaste

shipment. Site procedures governing loading activities lacked instructions to describe

and document items included in the radwaste shipment and specifically directed loading

personnel to fill available spaces in the liner with waste items.

The fourth Barnwell shipment had been loaded by Chem-Nuclear personnel during the

1985 time frame. A handwritten record confirmed that the shipment contained

processed incores. The fuel rod segments could have been mistaken as cutup incore

-26-

string tubes and included in the shipment. However, this was believed to be highly

unlikely. The high dose rates associated with the incore string tubes would have

masked the missing fuel rod segments, if they had been present.

The five shipments to US Ecology in Richland, Washington were loaded and shipped by

Chem-Nuclear personnel during the 1986 time frame. Handwritten records were

available that provided descriptions of items included with the shipment together with

dose rates for the individual items. The procedural instructions to document individual

items placed in the radwaste shipments were vague.

The licensees records of LLRW shipments were remarkably thorough, considering the

lack of procedural guidance and regulatory requirements. The licensees loading

procedures for LLRW shipments lacked guidance for documentation and obtaining a

dose rate of individual items included in the shipments.

The pipe that had contained the fuel rod segments was never located or described in

any LLRW shipment records. Since the pipe container was never located, it was

plausible that it had been shipped from the site as radwaste during one of the spent fuel

pool cleanup campaigns.

Using the licensees terminology for the possibility of occurrence, the inspectors

concluded that it was Reasonably Possible that the pipe container along with the fuel

rod segments could have been inadvertently included in a LLRW shipment between

1968 and 1989. This conclusion differs from the licensee determination that it was

Possible, But Not Likely. The LLRW shipments to either Barnwell, South Carolina or

US Ecology in Richland, Washington, could have contained the fuel rod segments.

However, the inspectors agreed with the licensees conclusion that the shipments to

Barnwell, South Carolina, that took place during 1983 and 1985 had the highest

probability of containing the fuel rod segments.

5. Review of Scenario Involving Fuel Segments Shipped Offsite In Other Direct

Shipments (ODS)

5.1 Inspection Scope

The inspectors reviewed the license screening process used to evaluate the potential

inclusion of the three spent fuel rod segments in Other Direct Shipments (ODS) that

contained radioactive material. Shipment records and other supporting documentation

for the ODS were also reviewed.

5.2 Observations and Findings

This scenario evaluated the inadvertent inclusion of the three missing spent fuel rod

segments in a shipment classified as ODS. An ODS is defined as a radioactive

materials shipment that was made from HBPP to another licensee authorized to receive

the shipment. The ODS shipments differed from LLRW shipments in that the

radioactive material that was shipped was not waste. The radioactive material would be

utilized or processed by the licensee, normally expected to include unpacking, receipt

-27-

inspection and handling of the material. This scenario assumed that the three 18-inch

fuel rod segments would have been recognized as an anomaly and the licensee would

have then contacted HBPP personnel.

The licensee used several of the same processes to evaluate this scenario that were

used to determine if the segments were contained in a LLRW shipment. The

radioactive shipment records were screened for applicability and relevancy. The

licensee then applied the screening criteria from Table 3.1-1 of the Screening Tool for

Fuel Rod Segments to evaluate the potential for inadvertent inclusion of the fuel rod

segments into one of the ODS.

The inspectors selected and reviewed 30 of the ODS and LLRW shipments that had

been screened by the licensee. No deficiencies of the licensee screening results were

identified.

Utilizing the Screening Tool for Fuel Rod Segments, the licensee evaluated 232

radioactive ODS. Of these 232 shipments, 217 were screened out as implausible.

The 15 ODS that were screened in as potential candidates for receipt of the fuel rod

segments were the shipments of fuel for reprocessing to Nuclear Fuel Services (NFS) at

West Valley, New York.

The 15 ODS shipments of irradiated spent fuel assemblies were made to NFS between

May 14, 1969, and June 3, 1971. Each of the shipments were reported to contain 18

fuel assemblies. Interviews with plant personnel indicated that it would have been

possible to include the fuel rod segments and pipe container in the fuel shipment cask.

However, due to the level of difficulty necessary to accomplish this task, documentation

would most likely have included in a plant record. A record that indicated the fuel rod

segments had been placed in a shipping cask with the fuel assemblies was never

located.

The spent fuel reprocessing activities at NFS were described in a report by Nuclear

Audit and Testing Company entitled, Surveillance of Humboldt Bay Spent Fuel During

Reprocessing at the NFS at West Valley, New York, dated October 25, 1971.

The focus of the report was on accounting for the percentages of uranium and

plutonium that had been recovered during fuel reprocessing. The radionuclides from the

assemblies were reclaimed in batches of 11 fuel assemblies. The report specified that

fuel assembly A-49 had been included in Dissolver Batch number 8 and Tank 3D-1

batch number 13. The report documented the variance between the recorded weights

of the uranium and plutonium that were recovered from the batch of fuel assemblies that

contained assembly A-49, as well as the other batches of fuel assemblies received from

HBPP. The nuclide variances of the individual batches far exceeded the radionuclide

weights reported in the three fuel rod segments by the licensee in Licensee Event

Report 2004-001-002. Therefore, accounting records of reclaimed radionuclides, that

could have indirectly substantiated the presence or absence of the missing fuel rod

segments were inconclusive due to large variances.

The licensee requested three of the most likely ODS recipients to perform a search to

determine if their records indicated receipt of the fuel rod segments or the pipe

-28-

container. Responses were received from New York State Energy Research and

Development Authority (formerly NFS), dated September 10, 2004; Battelle, dated

September 8, 2004; and General Electric, Vallecitos Nuclear Center, dated October 14,

2004. New York State Energy Research and Development Authority responded that a

review of available records did not disclose any information of the receipt of a small

shipping container with fuel rods or of the disposition of the three rod segments.

Battelle reviewed its records and confirmed that the planned shipment of the three

irradiated fuel rod segments from HBPP to Battelles West Jefferson, Ohio facility did

not take place. General Electric responded that after an extensive review of available

General Electric records, they did not identify any information to support a finding that

the three unaccounted for Humboldt Bay fuel rod segments were ever received at the

GE Vallecitos Nuclear Center or the GE San Jose facilities.

The shipment records reviewed by the inspectors normally contained detailed

descriptions of the individual items included in the shipments. Based on a review of the

available information, the inspectors agreed with the licensee conclusion that it was

Possible, But Not Likely that the fuel rod segments had been included in an ODS.

5.3 Conclusions

The inspectors reviewed the screening criteria used by the licensee and determined that

the process utilized to evaluate and screen the Other Direct Shipments (ODS) was

reasonable.

The licensee evaluated 232 radioactive ODS made to other licensees using the

Screening Tool for Fuel Rod Segments. Of these 232 shipments, 217 were screened

out as implausible leaving 15 potential shipments of irradiated fuel to NFS for

reprocessing to be further investigated.

No conclusive or circumstantial evidence was found to support the premise that the fuel

rod segments were included in an ODS.

The inspectors agreed with the licensee conclusion that it was Possible, But Not Likely

that the fuel rod segments had been included in an ODS.

6. Review of Scenario Involving Incore Detectors Shipped Offsite with Low Level

Radioactive Waste (LLRW)

6.1 Inspection Scope

The inspectors reviewed licensee documents consisting of incore accountability records,

shipment records, procedures and miscellaneous correspondence to determine if the

incore detectors had been shipped offsite with a LLRW shipment.

6.2 Observations and Findings

This scenario evaluated the possibility that the one full and three partial missing incore

detectors, also called ion chambers, were included with a LLRW shipment. The

-29-

licensee reported their belief that the missing incore detectors had been erroneously

included with irradiated hardware and shipped to a LLRW facility at Hanford or Barnwell,

in Licensee Event Report 2005-001-01. The inspectors independently reviewed

available documents to determine the most likely location of the missing incore

detectors including the accounting of the incore detector string segments. This scenario

concentrated on the incore detector strings that had been placed in the spent fuel pool

and later cutup and was not concerned with the intact incore detector strings that have

not been irradiated.

A brief description of the incore detector string composition and the process used to

cutup the incore detector strings for shipment follows. Each incore detector string,

hereafter referred to as simply an incore, consisted of a stainless steel tube

approximately 16-feet long with three incore detectors, also called ion chambers. Each

incore detector contained a small amount of Special Nuclear Material (SNM), which the

licensee was required to account for. The incore detectors were located at regularly

spaced intervals near one end of the incore detector string. When the incore detectors

no longer functioned correctly, the entire incore detector string would be removed from

the reactor and stored underwater in the spent fuel pool, due to the high radiation dose

rates emanating from the irradiated incores. The incore detector strings would

periodically be disposed of as waste to provide additional space in the spent fuel pool.

To dispose of the incores, the personnel would remove sections from the incore that

contained the incore detectors and store these sections separately. The remaining

pieces of the incores, that did not contain the incore detectors, would be cut up into

lengths that could be easily handled and were either stored in the spent fuel pool or

shipped offsite.

The licensee had located an extensive collection of records that documented the history

of the incores at HBPP. The Special Nuclear Material Accountability Record had been

located for each incore that had been used at HBPP. The SNM Accountability Records

documented the movements of each incore from the warehouse to disposal, along with

associated dates. The inspectors reviewed the SNM Accountability Records along with

records of radioactive material shipments, procedures used to cutup the incores and

other miscellaneous correspondence that related to the missing incore detectors.

The first planned shipment of incore detectors and incores for disposal occurred on

December 12, 1968. The HBPP On-site Review Committee Minutes of Regular

Meeting, dated December 3, 1968, discussed a proposal to remove the incore detectors

from the six defective incores that were located in the spent fuel pool and cutup the

remaining sections into approximately four foot lengths to fit into an available cask for

shipment offsite. The Radioactive Materials Shipment Record, dated December 12,

1968 and the SNM Material Accountability Records for incore detector serial numbers

5451136, 5451137, 5451138, 5451140, 5451141, 5451142 confirmed that both the

incore detectors and the cutup incores had been shipped offsite to Nuclear Engineering

Co., Beatty, Nevada, for disposal.

The second planned shipment consisted of nine incore detectors removed from three

selected incores that were located in the spent fuel pool. Documentation indicated that

the left over incore pieces had been stored in the spent fuel pool. A letter from General

-30-

Electric Co., San Jose, California, dated May 7, 1973, documented plans for GE

personnel to remove the incore detectors from incore serial numbers 5451154, 5808867

and 5808868. The incore detectors or elements were then planned to be returned to

General Electric Co., Vallecitos, California, for examination. HBPP Radioactive

Materials Shipment Record No. 215, dated June 25, 1973, confirmed the shipment of

the nine incore fission chambers from strings, Serial Nos. 5451154, 5808867, &

5808868," which indicated that only the incore detectors had been shipped. A typed

record of the events that occurred on June 21, 1973, documented that the incore

detectors had been cutup into two foot sections and stored in a separate compartment

of GEs cask liner for shipment, while the other short pieces were to be placed in one

of the storage cans prepared for plant use. This record also supported that only the

nine incore detectors had been shipped leaving approximately 400 inches of incores in

one of the storage cans presumably in the spent fuel pool.

At the time of the segmenting of the incore detectors for General Electric in 1973 there

were nine additional incores in the spent fuel pool. Although detailed records or copies

of the procedure used to cutup these nine incore detectors strings were never located, it

appeared that this operation occurred at approximately the same time as the

segmenting of the incore detectors for GE. A handwritten note from the April 1973 time

frame indicated that we might as well cut them all up while we are at it. The incores

were most likely cutup between June 22 and 25, 1973. A HBPP Memorandum to File,

dated February 24, 1986, documented that the remnants of nine incores cutup in earlier

years were located in the spent fuel pool.

In December 1985, HBPP Temporary Procedure 11/25/85 No. 2, Revision 146-12/85

was used to cut the incore detectors from nine intact incores located in the spent fuel

pool. The procedure provided specific directions and diagrams for removing the incore

detectors. Additionally, the presence of the incore detectors were determined by

changes in dose rate readings as detailed in Supplement to T.P.11/25/85 No. 2. The

HBPP Memorandum to File, dated February 24, 1986, documented that nine incores

were cut and 27 incore detectors were removed. By procedure, the cutup sections that

contained the incore detectors would be either 10 or 11 inches long. The remaining

pieces of incores cutup by use of the procedure were reported to have been included in

shipment number 473, to Barnwell, South Carolina that occurred on December 15,

1985. This shipment listed three barrels that contained a total length of 1520 inches of

processed incores, corresponding to the expected amount of waste from the nine

cutup incore pieces, minus the 27 incore detector segments.

Soon after the cutup and shipment of the nine incore waste pieces that occurred in

December 1985, HBPP personnel attempted to account for all the incore detectors.

They found cutup incore remnants that consisted of 49 pieces approximately 25 to

30 inches in length and 5 pieces approximately 18 inches in length. The total length of

the incores evaluated by HBPP personnel (including the 27 incore detectors from the

nine detector strings cutup in 1973) was estimated between 1315 to 1560 inches. This

total did not include the incore detectors recently cutup in December 1985 of

approximately 400 inches. A dose rate survey of the incore pieces was conducted to

locate the missing incore detectors. The results of the dose rate surveys were

inconclusive. The Memorandum noted that due to variations in activation of the fission

-31-

chambers and decay times, positive identification of the fission chambers was not

possible. However, based on the total length of the incores and the dose rate

measurements, the licensee concluded that all fission chambers were accounted for.

As part of the effort to positively account for all SNM at HBPP, the licensee performed

an inventory of all the incore detectors onsite. HBPP procedure TP 2004-10, Incore

Detector Evaluation and Container Loading, Revision 5 provided instructions to

determine if the incore segments contained an incore detector. The procedure required

measurement of the individual incore piece lengths and positive verification of the

presence of an incore detector. The results of this inventory was reported to the NRC

on February 22, 2005, which concluded that one full and three partial incore detectors

were not in the spent fuel pool as previously believed. The three partial incore

detectors, located by the licensee, were found in incore segments approximately

30 inches in length. The licensee reported that the total length of the incores (including

incore detectors) that remained in the spent fuel pool was 2,046 inches. This reported

length of incore detectors and incore pieces closely matched the total length of incores

documented in the HBPP Memorandum to File, dated February 24, 1986. The single

exception was an equivalent length of approximately 400 inches of cutup incore pieces

from the 1973 time period.

The precise location of the missing segments from the full and partial length incore

detectors can not be determined. Approximately 400 inches of incore segments,

including the missing incore detectors, cannot be located or accurately accounted for.

The missing incore detectors were most likely included in a LLRW shipment along with

portions of other incore segments from the 1973 cutup campaign. Evidence exists that

the 1973 cutup campaign produced segments of 25 to 30 inches in length. The

inspectors concluded that the documented shipments of incores would not have

included the missing full or partial incore detector segments for the following reasons:

  • The shipment in 1968 included all the components (both strings and incore

detectors) from the six incores that existed in the spent fuel pool. No incore

detector pieces were reported to have been left in the spent fuel pool.

  • According to available records the shipment to GE in 1973, only included the

incore detectors. Evidence suggested that approximately 400 inches of cutup

incores were stored from the campaign at HBPP. No shipment records or other

documentation to account for the 400 inches of cutup incores from this shipment

were located.

  • The three partial incore detectors were located by the licensee in incore

segments that were approximately 30 inches in length.

  • Records related to the shipment made in 1985 indicated that only the recently

cutup incore segments from the campaign conducted several weeks prior to the

shipment were included. Documentation indicated that the incore detector

segments stored in the HBPP spent fuel pool from the 1985 cutting operation

-32-

contained incore detectors between 10 and 11 inches long. Therefore, the

probability that a 30-inch segment remained at HBPP from the cutting

operation/shipment conducted in 1985 is very small.

  • HBPP personnel noted that 49 incore pieces that were 25 to 30 inches in length

were in the spent fuel pool in 1986, presumably from the 1973 cutup campaign.

  • The licensee performed a comprehensive search that determined the number of

incore detectors that are currently in the spent fuel pool. Based on the HBPP

Memorandum to File, dated February 24, 1986, the amount of material that

existed in the spent fuel pool in 1886 closely matched the amount recently

reported by the licensee.

The licensee records were inconclusive as to the possible location for approximately

400 inches of incore detector strings, presumably cutup in 1973. Based on a review of

the available information, the inspectors agreed with the licensee conclusion that the

missing incore detectors were most likely located at a licensed LLRW disposal facility.

Since the incore detectors would have been highly radioactive and therefore stored in

the spent fuel pool, the most likely LLRW disposal sites were determined to be either

Barnwell or Hanford. The suspect LLRW shipments mirror those considered for the

missing fuel rod segments that would have occurred between 1983 and 1986.

6.3 Conclusions

The licensee had located an extensive collection of records that documented the history

of the incore detectors at HBPP. A number of shipments of cutup incore segments and

intact incore detectors were documented.

Records were inconclusive as to the whereabouts of approximately 400 inches of cutup

incores, presumably from the campaign performed during June of 1973. Documentation

indicated that the partial incore detectors found by the licensee had been cutup during

this campaign.

The inspectors agreed with the licensees conclusions that the most likely locations for

the missing full and three partial incore detectors were either the Barnwell or Hanford

LLRW disposal facility.

7. Review of Scenario Involving Fuel Segments Stolen or Diverted

7.1 Inspection Scope

The inspectors reviewed the licensee interim and final reports sections related to the

theft and diversion scenario, interviewed personnel involved in the development of this

portions of the licensee reports, examined supporting documentation and reviewed

special evaluations and calculations.

7.2 Observations and Findings

-33-

The licensee identified three alternatives for this scenario:

7. Theft by an External Entity

8. Theft by an Insider

9. Unauthorized Disposal

The licensee analysis involved a defense-in-depth approach meaning that for a

successful theft or diversion to have occurred, multiple barriers in place to prevent such

an occurrence would have to have failed. In addition to the analysis performed by the

licensee, the inspectors requested that the licensee conduct some additional evaluations

not detailed in the licensees report. The inspectors requested that the licensee perform

a calculation to demonstrate that the plant radiological monitoring system could have

detected and would have generated an alarm if one unshielded 18-inch segment would

had been removed from the SFP. The inspectors also requested the licensee evaluate

available records of unexpected alarms and determined if plant personnel had

responded. The licensee evaluations demonstrated that a single unshielded 18-inch

segment would have generated an alarm and that for unexpected alarms the licensee

personnel responded to evaluate the cause. The licensee evaluations and the

inspectors independent review support the conclusions listed in Section 4.5.6 of the

licensees Final Report. These conclusions include:

  • Few individuals knew of the existence of the three 18-inch fuel segments
  • Theft of unshielded fuel segments in the 1968 through 1974 period would have

presented significant health risks due to radiation exposure.

  • Theft of fuel segments using a shielded container would have required

knowledge of a large number of plant employees and the use and manipulation

of major plant equipment that would not have gone on unobserved. No evidence

of such use has been found.

  • There is very limited economic or strategic value to the fuel rod segments or the

incore detectors.

  • No group or individuals have claimed to have stolen or diverted the fuel rod

segments or incore detectors.

7.3 Conclusions

The inspectors agreed with the licensees conclusion that theft or diversion of the three

18-inch fuel rod segments and incore detectors was highly unlikely.

8. Review of Scenario Involving Fuel Segments Remaining in the SFP in an Altered

Condition

8.1 Inspection Scope

The inspectors reviewed the ATI Consulting report Evaluation of Nuclear Fuel Rod

Fragments and Inference to Fuel Rod A-49 at Humboldt Bay Power Plant (ATI report)

dated March 31, 2005, and other related documents and procedures, and reviewed

video and still images of the fuel fragments found.

-34-

8.2 Observations and Findings

In a meeting held on September 17, 1968, by the HBPP On-site Review Committee

(OSRC) led by W. A. Raymond (Acting Chairman), the committee decided that a fuel

segment will be removed from a corner rod of bundle A-49. This fuel segment would

then be cut in three 18 inch segments from this irradiated fuel rod and shipped to

Battelle Memorial Institute in Columbus (BMI). The top and end pieces of the fuel rod

were to remain in the SFP. The three rod segments were to be used in a study

regarding Type 1 fuel rods and were to be shipped in a specially made shipping

container. The study by BMI was canceled prior to shipment and the three 18-inch fuel

rod segments and pipe container were placed back in the SFP.

During the fall of 2003, Pacific Gas and Electric (the licensee) conducted an

examination of the contents of its SFP in preparation for removal of the fuel for

placement into dry storage in an onsite Independent Spent Fuel Storage Installation.

Subsequently, on June 23, 2004, the licensee discovered a discrepancy in the plant

records related to the three 18-inch rod segments such that there was no accounting for

the removed fuel rod or segments from Assembly A-49. The licensee contracted with

ATI Consulting to review digital video and photographs of the inventoried fuel rod

fragments to determine if they may be part of the remnants and cut segments from the

fuel rod fragments of Assembly A-49.

The inspectors reviewed each section of the ATI report and repeated the visual

assessment of each fuel fragment that the consultants performed in the ATI report. The

inspectors also reviewed each document used by the consultants listed in the Sources

of Data Evaluated Section of the ATI report. Each of the documents are listed in the

attachment to this inspection report. The ATI report was divided into seven sections that

included: 1) Executive Summary; 2) Background; 3) the Sources of Data Evaluated; 4)

General Assessment; 5) Evaluation Criteria; 6) Data and Discussion; and

7) Conclusions.

In the General Assessment Section of the ATI report, the consultants discussed the

history of the GE Type 1 fuel with Type 304 stainless steel cladding regarding failures

due to intergranular stress corrosion cracking (IGSCC). The report also described the

dimensions of a typical Type 1 fuel rod that is representative of the stainless steel clad

fuel rods in Assembly A-49 and the cutting plan for the subject fuel rod.

The inspectors reviewed a paper by R. N. Duncan, et al, in titled Stainless-Steel-Clad

Fuel Rod Failures, and General Electric Company (GE), Nuclear Applications Vol.1

(pp 413-418), dated October 1965 which discussed the failure of the Type-304 stainless

steel fuel rods by IGSCC. The inspectors reviewed this paper in order to determine if the

ATI consultants were accurate in explaining the cause of the fragmentation of the

subject fuel rod. The inspectors were also aware of substantial efforts in research and

development that had been sponsored by the BWR (Boiling Water Reactor) Owners

Group for IGSCC Research. The results of this program, along with other related work

by vendors, consulting firms, and confirmatory research sponsored by the NRC allowed

the NRC staff to development positions regarding the IGSCC problems in BWRs. The

technical bases for these positions were detailed in NUREG-0313, Revision. 2

-35-

"Technical Report on Material Selection and Process Guidelines for BWR Coolant

Pressure Boundary Piping." Based on these studies, the inspectors determined that the

ATI consultants were correct in their assessment that the subject rods fragmentation

was caused by IGSCC.

The ATI consultants noted that the axial dimension, not including the endplug shanks at

the top and bottom ends of the rod, was approximately 83 inches. The consultants

further noted that the top endplug shank was slightly longer than one inch, while the

bottom endplug shank was slightly longer than 0.5 inches. Additionally, each fuel rod

had an identification stamp at the bottom end of the rod above the endplug shank. The

inspectors reviewed General Electric Drawing Number 932C653, Titled ASM Fuel Rod

and verified that the consultants were accurate in their description of the subject fuel rod

in the ATI report.

The inspectors also reviewed the licensees cutting plan and the ATI consultants

evaluation of the licensees cutting plan of the subject fuel rod. The cutting plan was

contained in the OSRC meeting notes dated September 17, 1968, along with a sketch

showing the A-49 corner rod and a second cutting plan that would require five cuts to

produce the three 18-inch segments. The consultants in their report termed this

drawing as the alternate cutting plan. The inspectors found that the ATI consultants

were methodical and sound in their engineering judgement in determining the process

the licensee used in the cutting plan of the subject fuel rod.

In the Evaluation Criteria Section of the ATI report, the consultants developed a basis

for the assessment of the fuel rod segments that consisted of five criteria: (1) planarity/

perpendicularity of the end surfaces of the individual fuel rod fragments, relative to their

axial orientation; (2) appearance of the separated surfaces of the cladding, when viewed

normal to the separated surface; (3) flushness of the separated surfaces of the fuel

pellets with the separated surfaces of the cladding; (4) appearance of the separated

surfaces of the fuel pellets, when viewed normal to the separated surface; and

(5) degree of associated intergranular stress corrosion cracking adjacent to the

separated surface. The ATI consultants also developed criteria to identify the deference

between ends of broken segments produced by cutting, verses ends of broken

segments produced by other failure mechanisms, e.g, IGSCC or tearing. The

inspectors found that when they repeated the visual assessment of each fuel rod

fragment utilizing the five criteria developed by the ATI consultants, the criteria were of

sound engineering judgement and provided a useful tool in determinating the end

conditions of the subject fragments.

In the Data and Discussion Section of the ATI report, the consultants listed the fuel

fragments and findings of their assessment for each fuel rod fragment. The inspectors

repeated the visual assessment of each fuel fragment that the ATI consultants

performed. These fragments are listed in Table 2 of this report along with the

inspectors findings.

-36-

Prior to their visual assessment of the subject fragments, the inspectors reviewed the

licencees procedure TP 2400-08 Fuel Fragment Evaluation and Container Loading,

dated May 12, 2005. Procedure TP 2400-08 was used by the licensee to evaluate the

fuel fragments and to determine their physical characteristics. It also provided

instructions for loading fuel fragments into compartmental container trays or unclad fuel

fragment container boxes. In TP 2400-08 the licensee characterized the different types

of fuel fragments e.g., Type I (304 stainless steel clad), Type II (zircaloy clad), and Type

III and Type IV (both are zircaloy clad and are of a larger diameter). According to the

procedure, three tests were performed by the licensee on each of the fragments to

determine their characteristics. For example, 1.) a go/no-go test was performed to

determine if the fragment was of a smaller diameter Type 1 or Type II fuel rod verses

the larger diameter Type III and IV fuel rods; 2.) a magnetic test was performed to

distinguish the Type I and the other types of fuel rods (a stainless steel clad fuel rod is

slightly magnetic whereas the zircaloy clad fuel is non-magnetic); and 3) an ultrasonic

examination was performed on the fragments to determined the wall thickness of each

fragments to distinguish the different fuel types since there is a difference in thickness

for various fuel types. The licensee also measured the does rate of each fragment and

the length of the fuel segment. The inspectors determined that the licensees procedure

TP 2400-08 was a sound engineering approach to distinguish the different types of fuel

rods.

The licensee recorded and documented its data by video camera and on a fuel fragment

evaluation data sheet. The video camera was a Remote Ocean Systems (ROS) CE-X

Miniature Environmental Color Zoom Camera Serial Number 1090. The NRC had

authorized alternatives to the American Society of Mechanical Engineers Boiler and

Pressure Vessel Code (ASME Code),Section XI, Rules for Inservice Inspection of

Nuclear Power Plant Components allowing licensees to perform an enhanced VT-1

visual examination with a high resolution camera that can be calibrated to focus on a

.001 inch wire in lieu of ASME Code surface nondestructive examinations e.g., dye-

penetrans or magnetic particle examination.

The inspectors were able to visually identify the measurement line increments of the

ruler used by the licensee to measure the fuel fragments. The inspectors judged the

line increments of the ruler to be 1/64 inch or .016 inches wide. The inspectors

compared the specifications of the licensees camera to one that was evaluated in

NRCs NUREG/CR-6860, An Assessment of Visual Testing and found that the

licenseess camera was comparable to one listed in the NUREG. The inspectors were

aware that the licensee did not calibrate its camera to focus on a .001 inch wire;

however, the inspectors did determine that the licensees camera imaging did have the

capability to distinguish between a mechanical cut and fracture of a fuel fragment by

IGSCC or other means.

The inspectors repeated the visual examinations described in the ATI report. Using the

ATI consultants five criteria basis for the assessment of the fuel rod fragments, the

inspectors found that all the fragments as shown in Table 2 match the ATI report

description. The inspectors also inspected two additional fragments FF-001 and

FF-020. Fragment FF-001 was a top end fuel assembly segment with one end that

appeared to have been fractured by IGSCC. Fragment FF-020 was identified as a

-37-

bottom end fuel assembly fragment with a serial number of PH-5177. Both FF-001 and

FF-020 fragments were not considered part of fuel assembly A-49 in the ATI report.

Table 2

Humboldt Bay Power Plant Unit 3 - Fuel Rod Fragments Examined From ATI Report

Fuel Rod Length Match ATI End Fragment? End Condition Rad Dose on Rad Dose 6 Remarks

Fragment (Inches) Report of Fragments Contact (R/hr) Inches From

No. Description Fragment

Surface (R/hr)

FF009 30.25 Yes Top End fuel One end is 183 15 None

rod fragment jagged and no

sign of cutting

FF013 4 Yes No Fractures on 230 9 Partial cut mark on surface

both ends of of fuel rod fragment and

fuel rod could be considered as

fragment part of

A-49

FF021 14 Yes Bottom End of One end split 198 10 ID Pin Number PH-5155

fuel rod and folded

fragment back across

fuel rod

FF026 11 Yes Top End of fuel One end is cut 209 7.5 Fuel rod fragment meets 5

rod fragment point ATI Report Criteria

FF027 6.25 Yes No One end of fuel 303 15 None

fragment

appears cut

and the other

end is bent

FF028 1 Yes No Fractures on 136 1.5 None

both ends of

the fuel rod

fragment

FF029 1 Yes No Fractures on 101 1.3 None

both ends of

the fuel rod

fragment

FF030 4.5 Yes No Fractures on 325 7.0 None

both ends of

the fuel rod

fragment

FF031 2.75 Yes No Fractures on 216 4.5 None

both ends of

the fuel rod

fragment

FF032 4.5 Yes No Fractures on 328 5 None

both ends of

the fuel rod

fragment

FF033 3.625 Yes No One end 275 5 None

appears cut

and other end

is fractured

FF034 3.25 Yes No Fractures on 271 12 None

both ends of

the fuel rod

fragment

FF020 16.5 N/A Bottom End of Fractured on 225 12 This fragment was not

fuel rod end of fuel rod considered as part of A-49

fragment fragment in the ATI Report. ID as

PH 5177

FF001 52 N/A Top End of fuel Fractured on 250 116 This fragment was not

rod fragment end of fuel rod considered as part of A-49

fragment in the ATI Report.

-38-

Fragment FF-021 was a bottom end fragment and had the serial number PH-5155

stamped on it. The ATI consultants considered this fragment as part of the A-49 fuel

rod. Neither the licensee nor GE could produce records to confirm whether fuel rod

Serial Number PH-5155 was part of fuel assembly A-49. The inspectors determined

that for positive identification, the serial number for FF-021 needed to be confirmed. The

opposite end of the pin end was spilt and folded back toward the pin end.

The ATI consultants also identified fragments FF-026, and FF-013 as potential portions

of A-49. The inspectors found that fragment FF-026 was a top end and the opposite

end appeared to have been cut by mechanical means. However, the inspectors did not

agree with the ATI consultants that FF-026 may have been part of A-49, without

additional examination either by chemical analysis or microscopic examination.

However, the inspectors realized that it was not practical to perform these tests due to

the high radiation doses that would be encountered. Furthermore, the individual fuel rod

manufacturer specifications were not available and without these specifications the

results of these tests would not produce meaningful data. The inspectors also found

that for fragment FF-013, it was approximately 4 inches long and both ends were

fragmented by what appeared to be IGSCC. The inspectors identified an aborted partial

mechanical cut on fragment FF-013 as did the ATI consultants. The inspectors

determined that fragment FF-013 could be a fragment of A-49. The inspectors findings

regarding all other fuel fragments were similar to the findings of the of the ATI

consultants with the exception that the inspectors did not agree that FF-021 was part of

A-49 without further testing.

The inspectors also identified that some of the fragments appeared to be bent as if a

dynamic load had been placed on the rods. In discussions with the licensee, review of

spent fuel pool handling procedures, and observation of the spent fuel pool, the

inspectors determined that it was unlikely that dynamic loading caused the bending of

the fragments. The inspectors determined that more than likely IGSCC weakened the

fuel rod fragments and the weight of the fuel rod itself and the repositioning of the fuel

assemblies in the spent fuel pool caused the bending of the fuel rod fragments.

The inspectors evaluated the possibility that the missing pipe container in which the

licensee had placed the three A-49 18-inch long fuel segments could have dissolved in

the SFP. The container was a carbon or stainless steel 11/2 Schedule 40 pipe capped at

both ends, with a welded hook on one end of the container. The outside diameter was

1.90 inches and wall thickness 0.145 inches. The licensee believed that the container

was shipped with other contaminated waste material or it was on the bottom on the fuel

pool in fragments. There had been discussion by the licensee that the pipe container

had dissolved in the SFP. The inspectors reviewed SFP water quality data sheets and

found that the chemistry of the SFP water was fairly constant and had only experienced

a high acid content for a couple of short periods. The inspectors also reviewed the

monthly spent fuel pool water quality check procedure and found it an acceptable

procedure to insure he SFP water quality. The inspectors determined that if the

container had corroded into fragments there should be remnants left in the SFP. The

licensee did a search for the pipe container and did not find any remains in the SFP.

Therefore, the inspectors determined that the container was not in the SFP and that it

more than likely was shipped offsite as contaminated waste.

-39-

8.3 Conclusions

The inspectors concluded that the ATI report was based on sound engineering judgment

and the ATI consultants were methodical in the process of determining the conditions of

the fuel rod fragments. However, the inspectors concluded that without substantial

additional test, they could not agree the ATI consultants conclusion that there was

reasonable evidence that the 18-inch segments maybe among the fragments found in

the SFP.

The inspectors concluded that the cause of the bent fragments was most likely

Intergranular Stress Corrosion Cracking (IGSCC), that weakened the fuel rods with the

weight of the fuel rod itself causing the bending. In addition, the inspectors concluded

that the repositioning of the fuel assemblies in the spent fuel pool also may have

contributed to the bending of the fuel rods.

The pipe container for the missing segments was unlikely to have dissolved in the SFP.

If the pipe container corroded into fragments there would have been remnants of it in

the SFP. The inspectors further concluded that the container was more than likely

shipped to a LLRW site as irradiated material.

9. Cause Analysis

9.1 Inspection Scope

The inspectors reviewed licensee reports, records, procedures, and interviewed

personnel to determine whether the cause analysis performed was thorough and well

documented.

9.2 Observations and Findings

The inspectors reviewed HBPP Procedure Number HBAP C-12 #2, Revision 7, 2/14/05,

Technical Review Group and Nonconformances, and Application of HBAP C-12 #2

Cause Analysis Guidelines to SNM Control and Accountability Issues at HBPP, dated

4/14/05, by Roger Johnson, and interviewed key licensee personnel.

The cause analysis was conducted by Project personnel who were contractors and

independent from the organizations responsible for the activities evaluated. The cause

analysis utilized a barrier analysis and an simplified event-cause tree analysis. These

are two tools often used in root cause analysis. The licensee was not committed and

was not required to perform a root-cause analysis. Although the process used by the

licensee was not a root-cause analysis, but a less stringent cause analysis, the

inspectors concluded that the licensee considered all reasonable causes. No alternative

causes were identified by the inspectors.

As previously noted in Section 2.f, although the SNM Control and Accountability Project

documentation did not always include the basis for the conclusions, no instances of

erroneous or unreasonable conclusions were identified.

-40-

The licensees process identified causes, characterized barriers, and recommended

immediate corrective actions (ICA) and corrective actions to prevent recurrence (CAPR).

Further, the licensee determined potential causes associated with the loss of control of

fuel fragments, the missing fuel rod segments and the missing incore detectors. The

causes, barrier analysis and ICA and CAPR are summarized in Section 6 the licensees

Final Report.

Once the licensee recognized that it was likely that SNM was missing, they promptly

notified the NRC and initiated a search for the missing SNM and any other SNM

fragments. The corrective actions included revising procedures, cataloging and

characterization the fuel fragments and SNM waste found to ensure a complete and

accurate accounting and tracking of all SNM in PG&Es possession at HBPP, down to

the fragment level. The corrective actions also included developing a program to ensure

that SNM Custodians are appropriately trained and qualified. The inspectors concluded

that the corrective actions taken and proposed by the licensee where through, complete

and comprehensive.

The licensee missed several opportunities to correct their MC&A program to address the

three missing approximately 18-inch long fuel fragments and other SNM in its

possession. Four of the more significant opportunities were:

6. On August 3, 1966, an internal memorandum directed plant staff to keep track of

fuel rod pieces and to make entries on the control operators log regarding fuel

rod pieces that were found. The memorandum included the following statement:

In those cases where portions of fuel rods are broken off of the bundle, the

inspector should estimate as accurately as possible, the total number of rods (or

portions of rods) which are missing. We are required to account for all of the

uranium that we possess, and so we will have to estimate as accurately as

possible the amount of fuel which ends up in the pellet catcher. (Bold font

added for emphasis). Although the licensee recognized the need to maintain

control of SNM and to account for it accurately, no specific actions to maintain

accounting and control appear to have been taken.

7. On October 22, 1974, ANSI Standard N15.8-1974 was approved and on June

1975 this standard was endorsed by NRC Regulatory Guide 5.29. In Section

6.1, Internal Control, the ANSI Standard described the unit of control as

follows: "The basic unit of control for nuclear material shall be the nuclear fuel

assembly. Each nuclear fuel assembly shall be identified in the material control

records by its serial number and location. Nuclear material contained in fuel

elements, not part of an assembly, shall be separately identified on all

material control records." (Bold font added for emphasis). In this statement,

the standard and the endorsing regulatory guidance identified to all licensees the

need to account for and control nuclear fuel that had become separated from its

assembly, but no action appears to have been taken by the licensee.

8. The licensees November 14, 2003, response to NRC Bulletin 2003-004, which

requested that licensees perform a one-time reporting of SNM quantities of 1

gram or more of contained uranium-235, was based on the September 2003

-41-

inventory that did not include the fuel fragments present in the spent fuel pool.

Opportunities to acknowledge and include fuel fragments in the SNM reported

quantities included a recent discovery of a fuel fragment on November 12, 2003,

only days before the licensee submitted their response to NRC Bulletin 2003-

004. No action was taken by the licensee to adjust their accounting records to

account for the found fragment or other fragments that existed in the spent fuel

pool.

9. During the physical inventories performed annually from 1971 through 2003

(except for those years when the pool was covered and the licensee was given

an exemption from the requirement to perform inventory), the presence of fuel

fragments should have been identified and the SNM inventory records updated

to account for them. The licensee missed multiple opportunities to identify that

the segments were missing and to account for the rod pieces in the spent fuel

pool. Comparison of the book inventory with the results of the physical inventory

would have shown that the book inventory was incorrect, but the licensee did not

appear to have made this comparison.

The licensee missed all of the opportunities described above and did not initiate a

reevaluation of the SNM inventory until January 2004. This reevaluation was

undertaken partially in response to concerns expressed by the inspectors about the

accuracy of the existing book inventory in light of the six fuel fragments that were found

in containers in the SFP during November and December 2003, and uncertainty about

the inventory of zirconium clad assemblies from which rods had been removed.

9.3 Conclusions

The cause analysis performed by the licensee followed the applicable procedure and

appeared to be through and adequate. Although the process used by the licensee was

not a root-cause analysis, but a less stringent cause analysis, the inspectors concluded

that the licensee considered all reasonable causes. The identified corrective actions

were complete and comprehensive. The inspectors identified several missed

opportunities to correct the MC&A program to address the three missing approximately

18-inch long fuel fragments and other SNM in its possession.

10. Health and Safety Consequences

10.1 Inspection Scope

The inspectors reviewed the licensees evaluation of consequences to public health and

safety as well as to the environment due the loss of the 18-inch fuel segments and

incore detectors. The inspectors also evaluated the safety analysis performed for the

Millstone missing fuel rods for its applicability to the missing SNM from HBPP.

10.2 Observations and Findings

Section 5.2 of the licensees Final Report titled Health and Safety, described the

evaluation the licensee performed for the potential consequences to the public health

-42-

and safety or to the environment due the loss of the 18-inch long fuel segments.

Section 3.3.1 of the Final Report addressed potential consequences to the public health

and safety or to the environment due to the loss of the incore detectors.

The licensee evaluated three possible locations for the 18-inch long fuel rod segments:

  • They were still in the SFP
  • They were shipped to NFS for reprocessing, or
  • They were shipped to Barnwell or Hanford LLRW sites

The licensee concluded that if the fuel rod segments are in the SFP, they are in a safe

location and there is no increased risk to the health and safety of the public, workers, or

the environment. If the fuel rod segments were shipped to NFS, the shipping and

processing was in accordance with approved methods and there was no increased risk

to the health and safety of the public, workers, or the environment.

The licensee also concluded that if the fuel rod segments were shipped to either

Barnwell or Hanford, the shipment process did not pose a significantly increased risk to

the health and safety of the public, the workers, or the environment. Also the potential

burial of the fuel rod segments at either of these LLRW facilities would not increase the

risk to the health and safety of the public, site workers, or the environment. Both of the

LLRW facilities were designed and licensed to safely dispose of all radionuclides

contained in the three fuel rod segments, and all of the radionuclides contained in the

three fuel rod segments were already present in the inventories of those facilities at

amounts that far exceeded the contents of fuel rod segments. The fuel rod segments

would add only a very small amount to the radionuclide inventories at these LLRW

disposal facilities.

On April 14, 2004, NRC released the safety analysis reports of the long-term hazard of

Millstone Unit 1s missing spent fuel rods potentially disposed of at the Barnwell and

Hanford commercial LLRW disposal facilities. These reports noted that the inventory in

the Millstone Unit 1s two missing spent fuel rods was a very small fraction of the

radionuclide inventories already present at these two LLRW disposal facilities.

Millstones two missing rods contained SNM in a quantity of 132 grams of uranium-235,

27 grams of plutonium, and a total of 518 curies of activity. The HBPP three 18-inch

missing rods segments contained SNM in an approximate quantity of 17 grams of

Uranium-235, 5 grams of plutonium, and a total of 80 curies of activity. The radionuclide

contents of the three 18-inch missing rods segments were only a fraction of the

inventory in the Millstone Unit 1s two missing spent fuel rods.

The NRC safety analyses concluded that although the LLRW sites are not licensed for

disposal of nuclear fuel, the overall risk due to the potential presence of the Millstone

fuel rods at either Barnwell or Hanford, was minimal to both the present workers and

future generations of the public. The risks associated with locating and retrieving them

would likely result in more actual dose being delivered to the workers than the potential

dose future generations could receive if the rods were not retrieved. Based on the

extremely low risk that the fuel rods posed, if they were at Barnwell or Hanford, retrieval

of the rods would not be justified by arguments concerning public health and safety.

-43-

Considering that the radionuclide inventory for the HBPP missing fuel segments was a

fraction of the inventory of Millstones two missing spent fuel rods, the inspectors

concluded that if 18-inch fuel rod segments were at either site, the risk is minimal to

both the present workers and future generations of the public. Additional efforts to

locate and retrieve the missing 18-inch fuel rod segments would not be warranted. The

overall risk from 18-inch fuel rods segments, if present, would be minimal to the health

and safety of the public, workers, or the environment.

Since the SNM inventory from the missing incore detectors was considerably less than

the 18-inch fuel rod segments (estimated at 0.035 grams of uranium-235), it is evident

that the overall risk from the missing incore detectors, if presence at either Barnwell or

Hanford, would also be minimal to the health and safety of the public, workers, or the

environment.

10.3 Conclusions

The inspectors concluded that regardless of whether the missing fuel segments were

located in the SFP, had been shipped to NFS for reprocessing, or had been transferred

to a LLRW disposal facility, the overall risk from the 18-inch fuel rods segments was

minimal to the health and safety of the public, workers, or the environment. Based on

the extremely low risk that the 18-inch fuel rods segments posed, if they were at

Barnwell or Hanford, attempts to locate and retrieve the 18-inch fuel rods segments

would not be justified by arguments concerning public health and safety. The overall

risk from the missing incore detectors, if present at either Barnwell or Hanford, would

also be minimal.

11. Discussion of Apparent Violations and Previously Identified Unresolved Items

11.1 Apparent Violations

In NRC Interim Inspection Report 05000133/2005001, the inspectors identified and

documented four apparent violations and three unresolved items. As noted in the

report, the licensee identified the missing 18-inch irradiated fuel segments and the

missing one complete and three partial incore detectors; promptly notified the NRC

when it determined that the material was missing and promptly initiated a search,

evaluation of the problems and corrective actions. As a result of the Special Inspection

chartered to review all information related to the missing SNM, the inspectors identified

the following apparent violations:

A. 10 CFR 74.19(a)(1), formerly 10 CFR 70.51(a)(1), requires, in part, that the

licensee shall keep records showing the receipt, inventory (including location and

unique identity), acquisition, transfer, and disposal of all SNM in its possession

regardless of its origin or method of acquisition.

1. Contrary to the above from August 6, 1969 (date when assembly A-49

was shipped off site) to July 16, 2004 (date when PG&E determined that

the segments were missing), PG&E, failed to keep records showing the

-44-

inventory, transfer or disposal of three approximately 18-inch segments of

irradiated fuel containing approximately 22.5 grams of SNM.

2. Contrary to the above from June 25, 1973 to February 4, 2005, the

licensee failed to keep records including location and unique identity

showing the inventory, transfer or disposal of one complete and three

partial incore detectors containing a total of approximately 0.035 grams of

SNM.

These failures are an apparent violation of 10 CFR 74.19(a)(1)

(APV 50-133/0501-03).

B. 10 CFR 74.19(b), formerly 10 CFR 70.51(b), requires that each licensee that is

authorized to possess SNM in a quantity exceeding one effective kilogram at any

one time shall establish, maintain, and follow written material control and

accounting procedures that are sufficient to enable the licensee to account for

the SNM in its possession under license. The licensee shall retain these

procedures until the Commission terminates the license that authorizes

possession of the material and retain any superceded portion of the procedures

for 3 years after the portion is superceded.

Contrary to the above, from June 4, 1971 (date when last Type 1 fuel assembly

was shipped off site) to July 16, 2004 (date when PG&E determined that the

segments were missing), PG&E, a licensee authorized by NRC License DPR-7

to possess SNM in a quantity exceeding one effective kilogram, failed to

establish, maintain, and follow written material control and accounting

procedures sufficient to enable PG&E to account for the SNM in its possession

under license DPR-7. Specifically, PG&E failed to account for SNM located in

the HBPP SFP consisting of a quantity of 111 grams of uranium-235, 27 grams

of plutonium contained in the remnants from Type 1 damaged fuel assemblies

(fuel fragments and SNM waste), and incore detectors.

This failure is an apparent violation of 10 CFR 74.19(b) (APV 50-133/0501-04).

C. 10 CFR 74.19(c), formerly 10 CFR 70.51(c), requires each licensee who is

authorized to possess SNM, at any one time and site location, in a quantity

greater than 350 grams of contained uranium-235, uranium-233, or plutonium, or

any combination thereof, shall conduct a physical inventory of all SNM in its

possession under license at intervals not to exceed 12 months.

Contrary to the above, PG&E, a licensee authorized to possess SNM at the

HBPP in quantities greater than 350 grams of contained uranium-235, uranium-

233, or plutonium failed to conduct a physical inventory of all SNM in its

possession at intervals not to exceed 12 months. Specifically, inventories

performed by PG&E from June 4, 1971 (date when last Type 1 fuel assembly

-45-

was shipped off site), to February 4, 2005, with the exception of periods when

the sealed SFP cover was in place, did not include fuel fragments and other

SNM remnants from Type 1 damaged fuel assemblies and all incore detectors.

This failure is an apparent violation of 10 CFR 74.19(c) (APV 50-133/0501-05).

Based on information provided by the licensee and upon further evaluation, the

inspectors concluded that the previously identified apparent violation related to the form

that the licensee was authorized to possess SNM is controlled by the conditions of the

license and not technical specification 4.2. License Condition B.2(d) states that the

licensee is authorized to possessed 1000 kilograms of contained uranium-235 at any

one time. This condition does not specify the form of the uranium, therefore this matter

is no longer considered an apparent violation.

11.2 Unresolved Items

(Closed) URI 50-133/0501-01. As of January 31, 2005, the current location and

reportability of an unspecified number of fuel pellets last accounted for on June 7, 1976,

as stored in a vacuum bag hung from the side of SFP had not been determined.

The licensee determined based on interviews and other records reviewed that the June

1976 records of an unspecified number of fuel pellets that had been collected and

stored in a vacuum cleaner bag in the SFP was incorrect and that fuel pellets were not

stored in vacuum bags. After review of the licensees evaluation and as a result of an

independent interview conducted by the inspectors with the individual that lead the clean

up campaign in 1976, the inspectors agree with the licensees conclusion.

(Closed) URI 50-133/0501-02. As of January 31, 2005, the current location of the three

18-inch segments from irradiated fuel Assembly A-49, that was first reported missing by

Pacific Gas & Electric on July 16, 2004, had not been determined.

The licensee has completed their investigation and concluded that the location of the

missing 18-inch fuel segments can not be conclusively be determined. The licensee

believes that the most likely possibilities is that the fuel segments remain in the SFP but

in broken fragments or they were shipped to a low level waste site or NFS. The

inspectors concluded that the most likely location is at a low level waste site, but since

the actual location cannot be determined this matter is consider closed.

(Closed) URI 50-133/0501-06. The conditions that resulted in the loss of one complete

incore detector and parts of three others, their fate, and the consequences associated

with their loss has not been reviewed by the NRC.

The inspectors have concluded that the lost of the incore detectors constitute another

example of the three apparent violations identified above and would be so noted,

therefore this item is considered closed.

-46-

12. Licensee Briefings and Exit Interview

The inspectors conducted briefings of preliminary inspection findings with licensee

senior plant managers at the conclusion of each site visit. On August 16, 2005, a

telephonic exit interview was conducted with senior licensee managers at the

conclusion of the NRC Special Inspection.

ATTACHMENT

SUPPLEMENTAL INSPECTION INFORMATION

PARTIAL LIST OF PERSONS CONTACTED

J. Albers, Radiation Protection Manager

M. Anthony, Decontamination Specialist

W. Barkhuff, Metallurgist Diablo Canyon

G. Bierbaum, Engineer

J. Brimble, Supervisor of Maintenance

T. Carraher, Data Logger

J. Galle, Sr. Design Engineer Manager

S. Gardner, Former Supervisor, Chem Nuclear

J. Hill, Inservice Inspectors Diablo Canyon

R. Johnson,

V. Jensen, Nuclear Quality Services Supervisor

P. Kapus, Document Reader

C. Kudla, SNM Control and Accountability Project

G. McKinnon, Control Operator

P. Narbut, Nuclear Quality Services Inspectors

B. Norton, Project Manager SNM Control and Accountability Project

R. Parker, Senior Radiation Protection Engineer

J. Rasmussen, Senior Control Operator

D. Swanson, Shift Foreman

M. Smith, Engineering Manager

D. Sokolsky, Supervisor of Licensing

S. Stevens, Document Reader

I. Tsosie, Radiation Protection Dosimetry Analyst

R. Willis, Plant Manager

INSPECTION PROCEDURES USED

IP 93812 Special Inspection

TI 2515/154 Spent Fuel Material Control and Accounting at Nuclear Power Plants

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

None

Discussed

50-133/0501-03 APV Contrary to the requirements of 10 CFR 74.19(a)(1), formerly 10

CFR 70.51(a)(1), from August 6, 1969 (date when assembly A-49

was shipped off site) to July 16, 2004 (date when PG&E

determined that the segments were missing), PG&E, failed to

keep records showing the inventory, transfer or disposal of three

approximately 18-inch segments of irradiated fuel containing

-2-

approximately 22.5 grams of SNM. Also from June 25, 1973 to

February 4, 2005, the licensee failed to keep records including

location and unique identity showing the inventory, transfer or

disposal of one complete and three partial incore detectors

containing a total of approximately 0.035 grams of SNM.

50-133/0501-04 APV Contrary to the requirements of 10 CFR 74.19(b), formerly 10

CFR 70.51(b), from June 4, 1971 (date when last Type 1 fuel

assembly was shipped off site) to July 16, 2004 (date when PG&E

determined that the segments were missing), PG&E, a licensee

authorized by NRC License DPR-7 to possess SNM in a quantity

exceeding one effective kilogram, failed to establish, maintain,

and follow written material control and accounting procedures

sufficient to enable PG&E to account for the SNM in its

possession under license DPR-7. Specifically, PG&E failed to

account for SNM in a quantity of 111 grams of uranium-235,

27 grams of plutonium contained in remnants from Type 1

damaged fuel assemblies (fuel fragments and SNM waste), and

incore detectors.

50-133/0501-05 APV Contrary to the requirements of 10 CFR 74.19(c), formerly 10

CFR 70.51(c), Pacific Gas and Electric Company, failed to

conduct a physical inventory of all SNM in its possession at

intervals not to exceed 12 months. Specifically, inventories

performed by PG&E from June 4, 1971 (date when last Type 1

fuel assembly was shipped off site), to February 4, 2005, with the

exception of periods when the sealed SFP cover was in place, did

not include fuel fragments and other SNM remnants from Type 1

damaged fuel assemblies and all incore detectors.

Closed

50-133/0501-01 URI As of January 31, 2005, the current location and reportability of an

unspecified number of fuel pellets last accounted for on June 7,

1976, as stored in a vacuum bag hung from the side of SFP had

not been determined.

50-133/0501-02 URI As of January 31, 2005, the current location of the three 18-inch

segments from irradiated fuel Assembly A-49, that was first

reported missing by Pacific Gas & Electric on July 16, 2004, had

not been determined.

50-133/0501-06 URI The conditions that resulted in the loss of one complete incore

detector and parts of three others, their fate, and the

consequences associated with their loss has not been reviewed

by the NRC.

-3-

50-133/0501-07 APV From November 18, 2002, through September 10, 2004, the

licensee possessed SNM in the form of fuel fragments and was

not authorized by the technical specifications in effect at that time

to possess SNM in this form.

-4-

LIST OF ACRONYMS

BMI Battelle Memorial Institute

BWR Boiling Water Reactor

CFR Code of Federal Regulations

GE General Electric Company

HBPP Humboldt Bay Power Plant

IFI Inspection Followup Item

IP Inspection Procedure

IGSCC Intergranular Stress Corrosion Cracking

LER Licensee Event Report

LLRW Low Level Radioactive Waste

LSA Low Specific Activity

MC&A Material Control and Accounting

NRC Nuclear Regulatory Commission

NFS Nuclear Fuel Services

PG&E Pacific Gas and Electric Company

ODS Other Direct Shipment

R Roentgen

SFP Spent Fuel Pool

SNM Special Nuclear Material

TI Temporary Instruction

TID Tamper Indicating Device

URI Unresolved Item

APV Apparent Violation

-5-

LIST OF SIGNIFICANT DOCUMENTS REVIEWED

Document Title Document Date

PG&E HBPP Visual Inspection Record of Type I (304 Stainless Clad) Nuclear Fuel September 7, 1966

Minutes of HBPP On-Site Review Committee of Special Meeting of September 17, 1968. September 17, 1968

(PG&E Record Locator No. 0210-4610)

PG&E General Computation Sheet Subject: Inner Can for fuel shipping Cask Sample to (Undated) Circa

Battelle Columbus (Undated)(PG&E Record Locator No. 3601-2912) September 17, 1968

Minutes of HBPP On-Site Review Committee of Special Meeting of October 2, 1968. October 2, 1968

(PG&E Record Locator No. 0210-4607)

PG&E General Computation Sheet Subject: NFS Shipping Cask (PG&E Record Locator August 5, 1969

No. 3612-2856)

HBPP Calculation NX-265, Evaluate Fuel Criticality with Assemblies Removed from Boral July 1, 2004

Cans, Revision 1

Event Notification No. 40877, Report of Missing Special Nuclear Material (Three Missing July 16, 2004

Fuel Rod Segments)

Event Notification No. 40961, Report of Missing Special Nuclear Material (Three Missing August 16, 2004

Fuel Rod Segments)

PG&E Letter HBL-04-020, Licensee Event Report (LER) 2004-001-00, Three Missing Fuel August 16, 2004

Rod Segments

PG&E Letter HBL-04-026, LER 2004-001-01, Three Missing Fuel Rod Segments, Rev. 1 November 19, 2004

PG&E Letter HBL-05-001, Special Nuclear Material Control and Accountability Project February 22, 2005

Interim Reports

PG&E Letter HBL-05-002, LER 2005-001-01, Missing Incore Detectors February 22, 2005

Event Notification No. 41430, Report of Missing Special Nuclear Material (Missing Incore February 22, 2005

Detectors)

HBPP Calculation NX-291, Estimation of SNM waste at HBPP, Revision 2 March 14, 2005

HBPP Calculation NX-287, SNM Re-verification, Revision 2 March 29, 2005

ATI Report Evaluation of Nuclear Fuel Rod Fragments and Inference to Fuel Rod A-49 at March 31, 2005

Humboldt Bay Power Plant

HBPP Calculation NX-288, Documentation of Spent Fuel Fragments and Debris, Rev. 6 April 21, 2005

HBPP Calculation NX-292, Develop Radioactive Waste Shipping Package Screening Tool April 29, 2005

for Possible Identification of Location of 18" Fuel Rod Segments from Fuel Assembly A-

49, Revision 1

HBPP Calculation NX-293, Evaluation of Underwater Dose Rates Associated with A-49 April 30, 2005

HBPP Calculation NX-290, To calculate and record the SNM Inventory, Revision 3 May 3, 2005

HBPP Calculation NX-289, Evaluate 18" Fuel Rod Segments from Fuel Assembly A-49, May 11, 2005

Revision 4

-6-

LIST OF SIGNIFICANT DOCUMENTS REVIEWED

PG&E Letter HBL-05-017, Special Nuclear Material Control and Accountability Project May 27, 2005

Final Report

PG&E Letter HBL-05-019, LER 2005-001-01, Missing Incore Detectors, Revision 1 June 10, 2005

PG&E Letter HBL-05-020, LER 2004-001-02, Three Missing Fuel Rod Segments, Rev. 2 June 10, 2005

October 25, 2004 Enclosure 2 (ML042990566)

MEMORANDUM TO: D. Blair Spitzberg, Ph.D., Chief

Fuel Cycle Decommissioning Branch

Emilio M. Garcia, Health Physicist

Fuel Cycle Decommissioning Branch

FROM: Mark A. Satorius, Director /RA/

Division of Nuclear Materials Safety

SUBJECT: SPECIAL INSPECTION CHARTER - THREE SPENT FUEL ROD

SEGMENTS MISSING IN THE HUMBOLDT BAY SPENT FUEL

POOL

A NRC special inspection has been established in response to information received from PG&E

that three spent fuel rod segments are missing in the Humboldt Bay spent fuel pool. On

August 17, 2004, PG&E Humboldt Bay Power Plant informed the NRC Operations Center that

three spent fuel rod segments (approximately 18 inches in length) could not be located within

Humboldt Bays spent fuel pool in accordance with 10 CFR 74.11. PG&E also issued a press

release of the event on the same date. Personnel at Humboldt Bay Power Plant continue to

search the spent fuel pool for the missing segments and the licensee has begun an

investigation to determine what happened to them.

The NRC decided, based on a number of factors, that it is appropriate to charter a special

inspection to assess the key elements of PG&Es investigation effort. Key factors in this NRC

decision included the large scope and complexity of the licensees investigation, the need for

focused specialist oversight by NRC, and the need to evaluate potential generic implications.

The NRC decision recognizes that it is highly unlikely that the material is in the public domain.

The inspection will review the results of PG&Es investigation, assess PG&Es determination of

the root cause, determine whether PG&E was in compliance with applicable regulations,

complete Phase III of TI 2515/154, Spent Fuel Material Control and Accounting at Nuclear

Power Plants, and identify which findings or observations may have generic implications.

Focused oversight of the licensees investigation and search efforts for the missing fuel

fragments began on July 12, 2004. Additional inspector site visits occurred during the weeks of

August 9 and September 13, 2004. Results of these focused inspection visits will be issued as

a separate inspection report no later than early November 2004.

The special inspection is expected to be conducted during several weeks of onsite inspection to

review focused areas within the overall scope of the inspection and to continue to observe

licensee search activities. The special inspection will primarily consist of onsite activities but

may include some in-office activities. Each week of onsite inspection should utilize only the

inspector resources assigned to the areas to be- 7 reviewed

- during that weeks inspection. The

Memorandum to Various -2-

overall duration of the inspection will depend on PG&Es schedule for completion of its

investigation but it is currently anticipated that it could extend into 2005. For planning purposes,

it is expected that the onsite portion of the special inspection will be completed 30 days after the

issuance of PG&Es report documenting its investigation.

A draft of the inspection plan should be available for approval prior to the first onsite inspection

activity. Major revisions of the inspection plan should be discussed with me prior to

implementing the changes. An exit meeting, that is open for public observation, will be held

after the onsite and in-office inspection activities are completed. An inspection report will be

issued within 45 days following the exit meeting for the inspection.

The members of the special inspection team are:

Manager: Blair Spitzberg, Chief, FCDB

Leader: Emilio Garcia, Region IV

Members: Ray Kellar, Region IV

Martha Williams, NSIR

Glenn Tuttle, NSIR

Other members will be assigned as needed.

The charter for the special inspection and details of the inspection scope are attached. The

special inspection shall be conducted in accordance with the applicable sections of Inspection

Procedure 93812, Special Inspection, and this memorandum.

Attachment: Special Inspection Charter

ATTACHMENT

CHARTER FOR HUMBOLDT BAY SPECIAL INSPECTION

BACKGROUND:

Humboldt Bay Power Plant Unit 3 is a shutdown 200-megawatt (thermal) (65-megawatt electric)

General Electric designed boiling water commercial nuclear power reactor. This reactor is

owned and was previously operated by Pacific Gas and Electric Company.

During the fall of 2003, Pacific Gas and Electric Company (PG&E) personnel at the Humboldt

Bay Power Plant Unit 3, were conducting an examination of the contents of the spent fuel pool

in preparation for dry storage operations. On November 12, 2003, Humboldt Bay personnel

discovered a fragment of a spent fuel pin approximately 4 inches long. Subsequent detailed

investigations identified additional fuel pin fragments in various spent fuel pool locations.

Humboldt Bay personnel informed the NRC via telephone of the discovery of the fuel

fragments.

In early December 2003, Humboldt Bay halted additional work in the spent fuel pool until a

criticality evaluation could be completed. Based on an NRC inspection performed during

January 2004, the Humboldt Bay Plant Manager initiated an evaluation of the amount of special

nuclear material present in each assembly and in the spent fuel pool.

On June 29, 2004, the licensee informed NRC staff that it had recently found documentation

indicating that in 1968, a fuel pin was segmented into three 18-inch sections intended to be sent

offsite for an experiment. Documentation also indicated that the three segments had been

placed into a 1.5-inch diameter pipe and subsequently returned to the spent fuel pool after the

intended experiment had been canceled. Humboldt Bay personnel started a search of the

spent fuel pool for the three fuel rod segments on July 9, 2004.

On July 16, 2004, PG&E notified the NRC of a discrepancy between inventory records and the

location of the three missing spent fuel rod segments (Event Notification #40877). The licensee

continued to perform a search for the fuel pin segments in the most likely and accessible

locations in the spent fuel pool and perform a search of documents that could provide

information as to the whereabouts of the fuel segments. Interviews were conducted with

personnel that worked at the plant during the time frame when the fuel pin was segmented.

On August 16, 2004, PG&E issued a 30-day written followup report to the initial July 16, 2004,

notification. This report was made pursuant to 10 CFR 20.2201(b)(2)(ii).

On August 17, 2004, the licensee Plant Staff Review Committee determined that the fuel

segments were not in the most likely and accessible locations within the spent fuel pool.

Consequently, PG&E made a 1-hour notification to the NRC pursuant to 10 CFR 74.11(a) that

the missing fuel rod segments were considered lost.

PG&E personnel have entered into Phase II of the search for the missing fuel rod segments.

The Phase II search includes additional searches of the spent fuel pool in less accessible

locations, additional document searches and personnel interviews. NRC inspectors continue to

provide periodic oversight of the investigation process. The licensee still believes that the most

likely location of the missing fuel rod segments is in the spent fuel pool. The licensees

-2-

investigation team will evaluate the potential for offsite disposal of the fuel segments and

complete a root cause analysis including documentation of the team findings in a final report.

PG&E expects to complete the search for the missing fuel rod segments and root cause

investigation during the first quarter of 2005.

On September 29, 2004, a Category 1 Public Meeting was held with Pacific Gas and Electric

Company. The purpose of this meeting was to discuss licensed radioactive material control

and accountability at Humboldt Bay Power Plant.

SPECIAL INSPECTION CHARTER

A special inspection will evaluate PG&Es investigation and conclusions regarding the potential

location of the missing fuel rod segments. The special inspection may consist of several

inspections that occur during the course of PG&Es investigation. The special inspection should:

13. Conduct a thorough and systematic review of PG&Es investigation into the

circumstances that led to the loss of accountability of the three missing fuel rod

segments and other special nuclear material (SNM). Determine the adequacy of

PG&Es investigation and conclusions regarding the location of the three missing fuel

rod segments, based upon its completeness and thoroughness of fuel pool inspections,

records reviews, and interviews.

14. Assess the adequacy of PG&Es control of SNM and non-SNM radiological materials.

15. Assess the determination of root cause performed by PG&E. Identify alternative causes

if appropriate. Develop independent conclusions regarding the causes(s) of the loss of

accountability of the special nuclear material.

16. Assess the adequacy of PG&Es investigation regarding its conclusion on the accuracy

of the accountability for the remainder of the special nuclear material in the spent fuel

pool.

17. Independently verify selected sets of records and interviews.

18. Determine whether PG&E was in compliance with applicable regulations.

19. Assess the adequacy of PG&Es radiological characterization of each missing fuel rod

segment.

20. Complete Phase III of TI2515/154, Spent Fuel Material Control and Accounting at

Nuclear Power Plants.

21. Conduct regular briefings for NRC internal stakeholders to allow the appropriate NRC

internal stakeholders to brief external stakeholders.

22. Identify those findings or observations that may have generic implications.

-3-

23. Document the inspection findings, observations and conclusions in a special inspection

report in accordance with the applicable sections of IP 93812 within 45 days of the exit

meeting.

24. Conduct an inspection exit that is open for public observations.